Table of Content
1.4 Summary of Construction Works
1.5 Summary of EM&A Programme Requirements
2.......... AIR QUALITY MONITORING
2.4 Monitoring Parameters, Frequency and Duration
2.6 Monitoring Schedule for the Reporting Month
3.4 Monitoring Parameters, Frequency and Duration
3.6 Monitoring Schedule for the Reporting Month
4.......... ENVIRONMENTAL SITE INSPECTION AND AUDIT
4.2 Advice on the Solid and Liquid Waste Management Status
4.3 Environmental Licenses and Permits
4.4 Implementation Status of Environmental Mitigation Measures
4.5 Summary of Exceedances of the Environmental Quality Performance Limit
4.6 Summary of Complaints, Notification of Summons and Successful Prosecutions
5.1 Construction Programme for the Coming Two Months
5.2 Key Issues for the Coming Two Months
5.3 Monitoring Schedule for the Coming Month
6.......... ConclusionS AND RECOMMENDATIONS
List of Tables
Table 1.1 Contact
Information of Key Personnel
Table 2.1 Air
Quality Monitoring Equipment
Table 2.2 Locations
of Air Quality Monitoring Stations
Table 2.3 Air
Quality Monitoring Parameters, Frequency and Duration
Table 2.4 Summary
of 1-hour TSP Monitoring Results in the Reporting Period
Table 2.5 Summary
of 24-hour TSP Monitoring Results in the Reporting Period
Table 3.1 Noise
Monitoring Equipment
Table 3.2 Locations
of Impact Noise Monitoring Stations
Table 3.3 Noise
Monitoring Parameters, Frequency and Duration
Table 3.4 Summary
of Impact Noise Monitoring Results in the Reporting Period
Table 4.1 Summary
of Environmental Licensing and Permit Status
List of Figures
Figure 1.1 General Layout Plan
Figure 2.1 Monitoring Locations
List of
Appendices
Appendix
A Project Organization Structure
Appendix B Implementation Schedule of Environmental
Mitigation Measures
Appendix C Summary of Action and Limit Levels
Appendix D Calibration Certificates of Equipments
Appendix
E EM&A Monitoring Schedules
Appendix F Air Quality Monitoring Results and their
Graphical Presentations
Appendix
G Noise Monitoring Results and their
Graphical Presentations
Appendix H Meteorological Data for January 2014
The Project “Development at
(hereafter called “the Project”) is proposed to form platforms for
housing development and associated
uses in area of about 20 hectares, and to carry out necessary
infrastructural upgrading or improvement works to
cater for the proposed development.
China State Construction Engineering (
The impact EM&A for the Project includes air quality and noise
monitoring. The EM&A programme for Sau Ming Primary School (ID 4) and Sau
Mau Ping Catholic Primary School (ID 5) commenced on 1 May 2008, while for Kwun
Tong Government Secondary School (ID
The monitoring stations ID 4 & ID 5 will serve both the entire
Development of Anderson Road
(Schedule 3 Designated Project (DP)) project as well as the Widening of
Po Lam Road (Schedule 2 DP) project.
The construction for the Widening of Po Lam Road (Schedule 2 DP)
project was commenced on 21
September 2011.
This report documents the findings of EM&A
works for ID
l Site
clearance
l Establishment
of temporary access road and temporary drainage
l Condition
survey
l Slope
stabilization and upgrading works
l Tree
transplanting and protection
l Excavation
work at portions A, B, C, J4, S
l Ground
investigation and instrumentation
l Trial
pit excavation
l Temporary
traffic arrangement and road work at J/O Po Lam Road & Sau Mau Ping Road,
Sau Fung Street, J2
l Bridge
prestressing work
l Toe
/ Berm planter and platform drainage construction
l Maintenance
Work
l Bridge
structural works at Bridge A, B and D
l Retaining
wall structural works
l Blasting
l Trench
excavation and pipe laying
l Erection
and maintenance of Blasting Cages & Fencing
l RE
wall panel installation and backfilling
l Permanent
backfilling at portion S
l Erection
and maintenance of hoarding
l Box
culvert construction
l Construction
of pedestrian subway
l Erection
of panel wall at R15
l Stormwater
tank construction
l Box
culvert construction
l Excavation
of footbridge A, B,C
l Mini-pile
construction of footbridge
l Structural
works at Footbridge A, B and C
l Pipe
Jacking at Hiu Kwong Street
Breaches of Action and Limit
Levels for Air Quality
All 1-Hour TSP results were below the Action
and Limit Level in the reporting month. Three (3) exceedances of Action Level
and one (1) exceedance of Limit Level were recorded in 20 January 2014 for
24-hour TSP monitoring at ID2, 3, 4 and 5 respectively. Exceedances were not
related to project.
Breaches of Action and Limit
Levels for Noise
According to the information provided by the
Contractor, no Action Level exceedance was recorded since no noise related
complaint was received in the reporting month.
No exceedance of Limit
Level of noise was recorded in the reporting month.
Complaint, Notification of
Summons and Successful Prosecution
According to the information provided by the Contractor on 17 February 2014, dust related complaint
which dated on 30 December 2013 was confirmed to be recorded as enquiry. The
cumulative statistics on complaints is updated in Appendix J.
No environmental complaint and no notification of summons and successful prosecution were received in the reporting month.
Reporting Changes
There was no reporting
change in the reporting month.
Future Key Issues
-
Properly store and label oil drums and chemical
containers placed on site;
-
Proper chemicals, chemical wastes and wastes
management;
-
Maintenance works should be carried out within
roofed, paved areas with proper drainage system to handle run-off from
maintenance works;
-
Collection and segregation of construction waste
and general refuse should be carried out properly and regularly;
-
Site runoff should be properly collected and
treated prior to discharge;
-
Regular review and maintenance of drainage
systems and desilting facilities;
-
Exposed slopes/soil stockpiles should be properly
treated to avoid generation of silty surface run-off during rainstorm;
-
Proper mitigation measures should be provided to
avoid relocation of treated contaminated soil;
-
Regular review and maintenance of wheel washing
facilities provided at all site entrances/exits;
-
Suppress dust generated from work processes with
use of bagged cements, earth movements, drilling works, breaking works,
excavation activities, exposed areas/slopes/soil stockpiles and haul road
traffic;
-
Conduct regular inspection of the working
machineries within works area to avoid any dark smoke emission and oil leakage;
-
Quieter powered mechanical equipment should be
used;
-
Provision of proper and effective noise control
measures, such as erection of movable noise barriers during blasting, breaking
and drilling works and at crushing plant works area and provision of acoustic
material wrapping to breaking tips of breakers; and
-
Proper protection and regular inspection of
existing trees, transplanted/retained trees.
Table 1.1 Contact Information of Key Personnel
Party |
Position |
Name |
Telephone |
Fax |
ER (Ove
Arup) |
Chief Resident Engineer |
Dennis Leung |
3656 3000 |
3656 3100 |
Senior Resident
Engineer |
Michael Wright |
3656 3000 |
3656 3100 |
|
Resident Engineer (Safety and Environmental) |
Kenneth Lee |
3656 3000 |
3656 3100 |
|
IEC (ENVIRON) |
Independent Environmental Checker |
David Yeung |
3465 2888 |
3465 2899 |
Contractor (CSCE) |
Site Agent |
Wilson Lau |
2704 2095 |
2702 6553 |
Environmental Manager |
Leo Chung |
2704 2095 |
2702 6553 |
|
ET (AECOM) |
ET Leader |
Yiu Wah Fung |
3922 9366 |
2317 7609 |
l Site
clearance
l Establishment
of temporary access road and temporary drainage
l Condition
survey
l Slope
stabilization and upgrading works
l Tree
transplanting and protection
l Excavation
work at portions A, B, C, J4, S
l Ground
investigation and instrumentation
l Trial
pit excavation
l Temporary
traffic arrangement and road work at J/O Po Lam Road & Sau Mau Ping Road,
Sau Fung Street, J2
l Bridge
prestressing work
l Toe
/ Berm planter and platform drainage construction
l Maintenance
Work
l Bridge
structural works at Bridge A, B and D
l Retaining
wall structural works
l Blasting
l Trench
excavation and pipe laying
l Erection
and maintenance of Blasting Cages & Fencing
l RE
wall panel installation and backfilling
l Permanent
backfilling at portion S
l Erection
and maintenance of hoarding
l Box
culvert construction
l Construction
of pedestrian subway
l Erection
of panel wall at R15
l Stormwater
tank construction
l Box
culvert construction
l Excavation
of footbridge A, B,C
l Mini-pile
construction of footbridge
l Structural
works at Footbridge A, B and C
l Pipe
Jacking at Hiu Kwong Street.
- All monitoring parameters;
- Monitoring schedules for the reporting month and
forthcoming months;
- Action and Limit levels for all environmental
parameters;
- Event / Action Plan;
- Environmental mitigation measures, as recommended in
the Project EIA study final report; and
- Environmental requirement in contract documents.
Table
2.1 Air Quality Monitoring Equipment
Equipment |
Brand and Model |
Portable direct
reading dust meter (1-hour TSP) |
Sibata Digital Dust
Monitor (Model No. LD-3 and LD-3B) |
High Volume Sampler
|
Tisch Total
Suspended Particulate Mass Flow Controlled High Volume Air Sampler (Model No.
TE-5170 & GMW-2310) |
Table 2.2 Locations of Air Quality Monitoring
Stations
ID |
Location |
Monitoring Station |
|
|
Roof top of the premises
facing |
2 |
On Yat House |
Roof top of the
premises facing Lee On Road |
3 |
Sau Nga House |
Roof top of the premises facing |
4 |
|
Roof top of the premises |
5 |
|
Roof top of the premises |
Table 2.3 Air Quality Monitoring Parameters,
Frequency and Duration
Monitoring Station |
Parameter |
Frequency and Duration |
ID |
1-hour TSP |
At least 3 times every 6 days |
24-hour TSP |
At least once every 6 days |
(a)
The HVS was installed in
the vicinity of the air sensitive receivers.
The following criteria were considered in the installation of the HVS:-
(i)
A horizontal platform with appropriate
support to secure the sampler against gusty wind was provided.
(ii)
The distance between the HVS and any
obstacles, such as buildings, was at least twice the height that the obstacle
protrudes above the HVS.
(iii)
A minimum of 2 meters separation from walls,
parapets and penthouse for rooftop sampler.
(iv)
A minimum of 2 meters separation from any
supporting structure, measured horizontally is required.
(v)
No furnace or incinerator flues nearby.
(vi)
Airflow around the sampler was unrestricted.
(vii)
Permission was obtained to set up the
samplers and access to the monitoring stations.
(viii)
A secured supply of electricity was obtained
to operate the samplers.
(ix)
The sampler was located more than 20 meters
from any dripline.
(x)
Any wire fence and gate, required to protect
the sampler, did not obstruct the monitoring process.
(xi)
Flow control accuracy was kept within ±2.5%
deviation over 24-hour sampling period.
(b)
Preparation of Filter
Papers
(i)
Glass fibre filters, G810 were labelled and
sufficient filters that were clean and without pinholes were selected.
(ii)
All filters were equilibrated in the
conditioning environment for 24 hours before weighing. The conditioning
environment temperature was around
(iii)
All filter papers were prepared and analysed
by ALS Technichem (HK) Pty Ltd., which is a HOKLAS
accredited laboratory and has comprehensive quality assurance and
quality control programmes.
(c)
Field Monitoring
(i)
The power supply
was checked to ensure the HVS works properly.
(ii)
The filter holder and the area surrounding
the filter were cleaned.
(iii)
The filter holder was removed by loosening
the four bolts and a new filter, with stamped number upward, on a supporting
screen was aligned carefully.
(iv)
The filter was properly aligned on the screen
so that the gasket formed an airtight seal on the outer edges of the filter.
(v)
The swing bolts were fastened to hold the
filter holder down to the frame. The
pressure applied was sufficient to avoid air leakage at the edges.
(vi)
Then the shelter lid was closed and was
secured with the aluminium strip.
(vii)
The HVS was warmed-up for about 5 minutes to
establish run-temperature conditions.
(viii)
A new flow rate record sheet was set into the
flow recorder.
(ix)
On site temperature and atmospheric pressure
readings were taken and the flow rate of the HVS was checked and adjusted at
around
(x)
The programmable digital timer was set for a
sampling period of 24 hrs, and the starting time, weather condition and the
filter number were recorded.
(xi)
The initial elapsed time was recorded.
(xii)
At the end of sampling, on site temperature
and atmospheric pressure readings were taken and the final flow rate of the HVS
was checked and recorded.
(xiii)
The final elapsed time was recorded.
(xiv)
The sampled filter was removed carefully and folded
in half length so that only surfaces with collected particulate matter were in
contact.
(xv)
It was then placed in a clean plastic
envelope and sealed.
(xvi)
All monitoring information was recorded on a
standard data sheet.
(xvii)
Filters were then sent to ALS Technichem (HK) Pty Ltd. for analysis.
(d)
Maintenance and Calibration
(i)
The HVS and
its accessories were maintained in good working condition, such as replacing
motor brushes routinely and checking electrical wiring to ensure a continuous
power supply.
(ii)
HVSs were calibrated using TE
(iii)
Calibration certificate of the TE
(a)
Measuring Procedures
The measuring procedures of the 1-hour dust
meter were in accordance with the Manufacturer’s Instruction Manual as
follows:-
(i)
Turn the power on.
(ii)
Close the air collecting opening cover.
(iii)
Push the “TIME SETTING” switch to [BG].
(iv)
Push “START/STOP”
switch to perform background measurement for 6 seconds.
(v)
Turn the knob at SENSI ADJ position to insert
the light scattering plate.
(vi)
Leave the equipment for 1 minute upon “SPAN
CHECK” is indicated in the display.
(vii)
Push “START/STOP” switch to perform automatic
sensitivity adjustment. This measurement takes 1 minute.
(viii)
Pull out the knob and return it to MEASURE
position.
(ix)
Push the “TIME SETTING” switch the time set
in the display to 3 hours.
(x)
Lower down the air collection opening cover.
(xi)
Push “START/STOP” switch to start measurement.
(b)
Maintenance and Calibration
(i)
The 1-hour TSP meter was
calibrated at 1-year intervals against a continuous particulate TEOM Monitor,
Series 1400ab. Calibration certificates of the Laser Dust Monitors are provided in Appendix D.
|
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
ID |
81.7 |
73.6 – 90.3 |
201.5 |
500 |
ID 2 |
82.2 |
73.9 – 90.0 |
197.0 |
500 |
ID 3 |
81.9 |
74.9 – 89.3 |
203.7 |
500 |
ID 4 |
82.1 |
75.5 – 90.5 |
264.6 |
500 |
ID 5 |
82.5 |
74.9 – 90.3 |
267.4 |
500 |
Table 2.5 Summary of 24-hour TSP Monitoring
Results in the Reporting Period
|
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
ID |
44.6 |
30.9 – 69.9 |
170.2 |
260 |
ID 2 |
88.0 |
41.5 – 209.2 |
200.0 |
260 |
ID 3 |
112.2 |
52.0 – 282.6 |
200.0 |
260 |
ID 4 |
104.0 |
55.4 – 213.6 |
181.3 |
260 |
ID 5 |
84.8 |
26.4 – 237.6 |
180.8 |
260 |
1.
Main haul road were regularly watering by water
trucks to maintain the surface wet;
2.
Continuous water spraying and tarpaulin sheet
coverage was applied during excavation;
3.
Exposed slope surface should be either hydroseeded,
shotcreted or covered up by tarpaulin;
4.
Vehicle washing facility was provided at vehicle
exit points, and vehicle was washed to remove any dusty materials from its body
and wheels before leaving.
1.
Main haul road were regularly watering by water
trucks to maintain the surface wet;
2.
Continuous water spraying and tarpaulin sheet
coverage was applied during excavation;
3.
Exposed slope surface should be either hydroseeded,
shotcreted or covered up by tarpaulin;
4.
Vehicle washing facility was provided at vehicle
exit points, and vehicle was washed to remove any dusty materials from its body
and wheels before leaving.
Table 3.1 Noise Monitoring Equipment
Equipment |
Brand and Model |
Integrated Sound Level Meter |
|
Acoustic Calibrator |
Rion (Model No. NC-73) |
Table 3.2 Locations of Impact Noise Monitoring
Stations
ID |
Location |
Monitoring Station |
|
|
|
2 |
On Yat House |
|
3 |
Sau Nga House |
|
4 |
|
|
5 |
|
|
Table 3.3 Noise
Monitoring Parameters, Frequency and Duration
Monitoring Station |
Parameter and Duration |
Frequency |
ID |
30-mins measurement at each monitoring
station between 0700 and 1900 on normal weekdays. Leq, L10
and L90 would be recorded. |
At least once per week |
(a)
The sound level meter was set on a tripod at a height of
(b)
Façade measurements were made at all
monitoring locations.
(c)
The battery condition was checked to ensure the correct functioning of the meter.
(d)
Parameters such as frequency weighting, the
time weighting and the measurement time were set as follows:
(i)
frequency weighting: A
(ii)
time weighting: Fast
(iii)
time measurement: Leq(30-minutes)
during non-restricted hours i.e. 07:00 – 1900 on normal weekdays; Leq(5-minutes)
during restricted hours i.e. 19:00 – 23:00 and 23:00 – 07:00 of normal weekdays, whole day of Sundays
and Public Holidays
(e)
Prior to and after each noise measurement,
the meter was calibrated using the acoustic calibrator for 94dB(A) at 1000
Hz. If the difference in the calibration
level before and after measurement was more than 1 dB(A), the measurement would
be considered invalid and repeat of noise measurement would be required after
re-calibration or repair of the equipment.
(f)
During the monitoring period, the Leq,
L10 and L90 were recorded. In addition, site conditions and noise
sources were recorded on a standard record sheet.
(g)
Noise measurement was paused during periods
of high intrusive noise (e.g. dog barking, helicopter noise) if possible.
Observations were recorded when intrusive noise was unavoidable.
(h)
Noise monitoring was cancelled in the
presence of fog, rain, wind with a steady speed exceeding
(a)
The microphone head of the sound level meter was
cleaned with soft cloth at regular intervals.
(b)
The meter and calibrator
were sent to the supplier or HOKLAS laboratory to check and calibrate at yearly
intervals.
(c)
Calibration certificates of
the sound level meters and acoustic calibrators are
provided in Appendix D.
Table 3.4 Summary of
Impact Noise Monitoring Results in
the Reporting Period
|
Average, dB(A), Leq (30 mins) |
Range, dB(A), Leq (30 mins) |
Limit Level, dB(A), Leq (30 mins) |
ID |
59.7 |
51.9 – 64.4 |
*65/70 |
ID 2 |
63.7 |
61.1 – 65.3 |
75 |
ID 3 |
63.7 |
58.2 – 67.0 |
75 |
ID 4 |
63.5 |
59.3 – 65.3 |
*65/70 |
ID 5 |
60.9 |
57.8 – 64.1 |
*65/70 |
Note:
*Daytime noise Limit Level of 70dB(A) applies to education institutions while 65dB(A) applies during school examination period.
4
ENVIRONMENTAL SITE INSPECTION AND AUDIT
Table 4.1 Summary of Environmental
Licensing and Permit Status
Description |
Permit
No. |
Valid
Period |
Remarks |
||
From |
To |
||||
EIAO |
Environmental Permit |
EP-140/2002 |
-- |
-- |
- Widening of a
section of Po Lam Road - Improvement
works to existing roads |
APCO |
NA notification |
-- |
16/04/09 |
-- |
-
Whole Construction Site |
WPCO |
Discharge License |
WT0002558-2009 |
|
|
-
Discharge of Construction Runoff |
Discharge License |
EP670/I/C0613/293 |
02/02/12 |
28/02/17 |
- Discharge from Road L6 |
|
WDO |
Chemical Waste Producer Registration |
5213-292-C3249-32 |
|
-- |
-
Whole Construction Site |
Waste Charges Account |
7006839 |
12/03/08 |
-- |
-
Whole Construction Site |
|
Construction Noise
Permit |
GW-RE0750-13 |
17/07/13 |
10/01/14 |
- Whole Construction Site |
|
GW-RE0982-13 |
20/09/13 |
03/02/14 |
- Hiu Kwong Street Works |
l Log complaint and date of receipt onto the
complaint database and inform the IC(E) immediately;
l Investigate the complaint to determine its
validity, and assess whether the source of the problem is due to works
activities;
l Identify mitigation measures in consultation
with the IC(E) if a complaint is valid and due to works;
l Advise the Contractor if additional mitigation measures are required;
l Review the Contractor’s response to identified
mitigation measures, and the updated situation;
l If the complaint is transferred from EPD,
submit interim report to EPD on status of the complaint investigation and
follow-up action within the time frame assigned by EPD;
l Undertake additional monitoring and audit to
verify the situation if necessary, and review that circumstances leading to the
complaint to not recur;
l Report investigation results and subsequent
actions to complainant (if the source of complaint is EPD, the results should
be reported within the time frame assigned by EPD); and
l Record the complaint, investigation, the
subsequent actions and the results in the monthly EM&A reports.
l Site clearance
l Establishment of temporary access road and
temporary drainage
l Condition survey
l Slope stabilization and upgrading works
l Tree transplanting and protection
l Excavation work at portions A, B, C, J4, S
l Ground investigation and instrumentation
l Trial pit excavation
l Temporary traffic arrangement and road work at
J/O Po Lam Road & Sau Mau Ping Road, Sau Fung Street, J2
l Bridge prestressing work
l Toe / Berm planter and platform drainage
construction
l Maintenance Work
l Bridge structural works at Bridge A, B and D
l Retaining wall structural works
l Blasting
l Trench excavation and pipe laying
l Erection and maintenance of Blasting Cages
& Fencing
l RE wall panel installation and backfilling
l Permanent backfilling at portion S
l Erection and maintenance of hoarding
l Box culvert construction
l Construction of pedestrian subway
l Erection of panel wall at R15
l Stormwater tank construction
l Construction of retaining wall at R15b, R16a
and R16b
l Excavation of footbridge A, B,C
l Construction of footbridge A, B, C
l Structural works at Footbridge A, B and C
l Pipe jacking at Hiu Kwong Street.
-
Properly store and label oil drums and chemical
containers placed on site;
-
Proper chemicals, chemical wastes and wastes management;
-
Maintenance works should be carried out within
roofed, paved areas with proper drainage system to handle run-off from
maintenance works;
-
Collection and segregation of construction waste
and general refuse should be carried out properly and regularly;
-
Site runoff should be properly collected and
treated prior to discharge;
-
Regular review and maintenance of drainage
systems and desilting facilities;
-
Exposed slopes/soil stockpiles should be
properly treated to avoid generation of silty surface run-off during rainstorm;
-
Proper mitigation measures should be provided to
avoid relocation of treated contaminated soil;
-
Regular review and maintenance of wheel washing
facilities provided at all site entrances/exits;
-
Suppress dust generated from work processes with
use of bagged cements, earth movements, drilling works, breaking works,
excavation activities, exposed areas/slopes/soil stockpiles and haul road traffic;
-
Conduct regular inspection of the working machineries within
works area to avoid any dark smoke emission and oil leakage;
-
Quieter powered mechanical equipment should be
used;
-
Provision of proper and effective noise control
measures, such as erection of movable noise barriers during blasting, breaking
and drilling works and at crushing
plant works area and provision of acoustic material wrapping to
breaking tips of breakers; and
-
Proper protection and regular inspection of
existing trees, transplanted/retained trees.
6
ConclusionS AND RECOMMENDATIONS