Contract No: CV/2012/07 Development at Anderson road - Footbridge D and Associated works AREA Monthly
Environmental Monitoring & Audit Report
- june 2017 -
|
CLIENTS: |
|
Lam-Po Wing Joint Venture |
Lam Environmental Services Limited 11/F
Centre Point 181-185
Gloucester Road, Wanchai,
H.K. Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail: info@lamenviro.com Website:
http://www.lamenviro.com |
|
|
|
|
|
Certified
by: |
|
Derek Lo Environmental Team Leader |
|
DATE: |
|
July 2017 |
2.2 Scope
of the Project and Site Description
2.3 Project
Organization and Contact Personnel
3. Status
of Regulatory Compliance
3.1 Status
of Environmental Licensing and Permitting under the Project
6.3 Review
of the Reasons for and the Implications of Non-compliance
6.4 Summary
of action taken in the event of and follow-up on non-compliance
8. Complaints,
Notification of Summons and Prosecution
lIST OF TABLES
Table 2.1 Contact Details of Key Personnel
Table
4.1 Noise Monitoring Stations
Table
4.2 Air Monitoring Station
Table
5.1 Summary of Noise Monitoring Results at NM1
and NM2
Table
5.2 Summary of Air Monitoring Results at AQM1 -
24 hr TSP Monitoring
Table
5.3 Summary of Air Monitoring Results at AQM1 -
1 hr TSP Monitoring
Table
5.4 Details of Waste Disposal for Contract no.
CV/2012/07
Table
7.1 Summary of Environmental Inspections for
Contract no. CV/2012/07
Table
8.1 Cumulative Statistics on Complaints
Table
8.2 Cumulative Statistics on Successful
Prosecutions
lIST OF FIGUREs
Figure
2.1 Project Layout
Figure 2.2 Project Organization Chart
Figure 4.1 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix 5.1 Monitoring Schedule for Reporting Month and Coming
month
Appendix 5.2 Noise Monitoring Results and
Graphical Presentations
Appendix 5.3 Air Quality
Monitoring Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Summary for Notification of Exceedance_Air
and Noise
Appendix
8.1 Complaint Log
Appendix 9.1 Construction Programme
Construction Activities for the Reporting Period
¡P
Site Clearance
Noise Monitoring
Air Quality Monitoring
Complaints, Notifications of Summons and Successful
Prosecutions
Site Inspections and Audit
Reporting Change
vii. There are no reporting
changes in this Reporting Period.
1.1.1. Lam
Environmental Services Limited (LES) has been appointed to work as the
Environmental Team (ET) to implement the Environmental Monitoring and Audit
(EM&A) programme as stipulated in the EM&A Manual of the approved
Environmental Impact Assessment (EIA) Report for Development of Anderson Road.
1.1.2. This
report presents the environmental monitoring and auditing work carried out in
accordance to the Section 1.4 of EM&A Manual and ¡§Environmental
Monitoring and Audit Requirements¡¨ under Particular Specification Section
25.
1.1.3. The
construction works of this project was commenced on 20 July 2013. This report
documents the finding of EM&A works for this Project and during the period
of 1 June 2017 to 21 June 2017. The cut-off date of reporting is at the end
of each reporting month.
Section 1 Introduction ¡V details the scope and structure of the report.
Section 2 Project
Background ¡V summarizes background and
scope of the project, site description, project organization and contact
details of key personnel during the reporting period.
Section 3 Status of Regulatory Compliance ¡V summarizes the status of valid Environmental Permits /
Licenses during the reporting period.
Section 4 Monitoring
Requirements ¡V summarizes all monitoring
parameters, monitoring methodology and equipment, monitoring locations,
monitoring frequency, criteria and respective event and action plan and
monitoring programmes.
Section 5 Monitoring
Results ¡V summarizes the monitoring
results obtained in the reporting period.
Section 6 Compliance Audit ¡V summarizes
the auditing of monitoring results, all exceedances environmental
parameters.
Section 7 Cumulative Construction Impact due
to the Concurrent Projects ¡V summarizes the relevant cumulative
construction impact due to the concurrent activities of the concurrent Projects.
Section 8 Site Inspection ¡V summarizes the findings of weekly site inspections
undertaken within the reporting period, with a review of any relevant follow-up actions within the reporting period.
Section 9 Complaints, Notification of
summons and Prosecution ¡V summarizes the cumulative statistics on
complaints, notification of summons and prosecution
Section 10 Conclusion
2.1.1. The main
objective of the project ¡§Development at Anderson Road ¡V Footbridge D and
Associated Works Area¡¨ (Hereafter called ¡§this Project¡¨) is to construct a footbridge, Footbridge D,
and associated lift towers across Shun On Road between the existing Shun Tin
Estate and the future development platform.
2.1.2. For this
project, Tin Wan House (NM1) and Ning Po No.2 College (NM2 and AQM1) are the
designated monitoring station during the construction period. Owing to this
contract is under the master project and on the other hand, the construction
area is vicinity to the monitoring station (On Yat House) ID2 and (Sau Nga
House) ID3 of the master project, so that the baseline noise and air quality
monitoring will adopt the baseline data from those stations instead of
conducting baseline monitoring. All the baseline data are referred to the
baseline report from the public domain web site (www.anderson-road.com/main.htm).
2.1.3. The construction works of this project was commenced on 20 July 2013.
During the construction phase of the project, air quality (dust) and noise
impacts from the development site itself and the adjacent Anderson Road Quarry
and other nearby construction sites are identified as the major environmental
issues of concern. Besides, waste management is also identified in the EIA
study as another environmental issue during the construction phase of the
project that requires mitigation measures.
2.2.1. The
Project is located mainly near Shun Tin Estate and Ning Po No.2 College, as shown in Figure 2.1.
2.2.2. The scope of the Project comprises:
Construction of footbridge and
associated lift towers between Shun On Road and future platform at +152mPD and
across Shun On Road. In Conjunction with these footbridge works are the
associated furniture, drainage system, irrigation system and traffic signs.
Construction
of drainage system for diversion of an existing stream on the slope adjoining
Footbridge D.
Site
formation and associated slope works for Footbridge D adjacent to Shun On Road.
2.3.1. Civil Engineering
and Development Department is the overall project controllers for this project.
For the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.3.2. The
proposed project organization and lines of communication with respect to
environmental protection works are shown in Figure 2.2. Key
personnel and contact particulars are summarized in Table 2.1.
Table 2.1 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
Ove
Arup |
Engineer
|
Chief
Resident Engineer |
Dennis
Leung |
2407
0300 |
2407 8382 |
|
Resident
Engineer |
Brian
Wan |
3656
3000 |
3656 1000 |
|
Lam-Po
Wing Joint Venture |
Contractor
under Contract no. CV/2012/07 |
Project Manager |
K.C.
Wong |
2318
0281 |
3171 7222 |
Site Agent |
T.L.
Lo |
2318
0281 |
|||
Safety Officer |
K.W. Lau |
2318
0281 |
|||
Environmental Officer |
K.I.
Ip |
2318
0281 |
|||
Ramboll
Environ Hong Kong
Limited |
Independent Environmental
Checker (IEC) |
Independent Environmental
Checker (IEC) |
Mr.
David Yeung |
3465
2888 |
3465 2899 |
Lam Environmental
Services
Limited |
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr.
Derek Lo |
2882
3939 |
2882 3331 |
2.3.3. For
Contract no. CV/2012/07, the principal work activities in this reporting month
included:
¡P
Site Clearance
3.1.1. A summary
of the current status on licences and/or permits on environmental protection
pertinent to the Project is shown in Table 3.1.
Permits
and/or Licences |
Reference
No. |
Issued
Date |
Valid Period/ Expiry Date |
Status |
Discharge Licence |
WT00015447-2013 |
27 March 2013 |
31 March 2018 |
Valid |
Billing Account under Waste Disposal Ordinance |
7017083 |
15 March 2013 |
N/A |
Valid |
The Air Pollution Control (Construction Dust)
Regulation |
355705 |
14 February 2013 |
N/A |
Valid |
Form A ¡V Application for Water Pollution Control
Licence |
355706 |
14 February 2013 |
N/A |
Valid |
Application for Registration as a Chemical Waste
Producer |
WPN5213-292-L2825-01 |
28 November 2013 |
N/A |
Valid |
Application for
Construction Noise Permit |
GW-RE0694-16 |
24 July 2016 |
14 August 2016 |
Expired |
Noise Monitoring Stations
4.1.1. The noise
monitoring has been undertaken at the designated locations Tin Wan House (NM1)
and Ning Po No.2 College (NM2). The detailed information of monitoring stations
for the Project are listed and shown in Table 4.1 and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.1 Noise
Monitoring Stations
Station ID |
Monitoring Location |
NM1 |
G/F of Tin Wan House |
NM2 |
G/F of Ning Po No.2 College |
Noise Monitoring Parameters,
Frequency and Duration
4.1.2. The construction noise level shall be measured in
terms of the A-weighted equivalent continuous sound pressure level (Leq).
Leq (30 minutes) shall be used as the monitoring parameter for the
time period between 0700 and 1900 hours on normal weekdays. For all other time
periods, Leq (5 minutes) shall be employed for comparison with the
Noise Control Ordinance (NCO) criteria.
Supplementary information for data auditing, statistical results such as L10
and L90 shall also be obtained for reference.
4.1.3. Noise
monitoring shall be carried out at all the designated monitoring stations. The
monitoring frequency shall depend on the scale of the construction activities.
The following is an initial guide on the regular monitoring frequency for each
station on a weekly basis when noise generating activities are underway:
¡P
one
set of measurements between 0700 and 1900 hours on normal weekdays.
4.1.4. If
construction works are extended to include works during the hours of 1900 ¡V
0700 as well as public holidays and Sundays, additional weekly impact
monitoring shall be carried out during respective restricted hours periods.
Applicable permits under NCO shall be obtained by the Contractor.
Monitoring Equipment
4.1.5. As
referred to in the Technical Memorandum (TM) issued under the NCO, sound level
meters in compliance with the International Electrotechnical Commission
Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be
used for carrying out the noise monitoring. Immediately prior to and following
each noise measurement the accuracy of the sound level meter shall be checked
using an acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted as valid only if the calibration level
from before and after the noise measurement agree to within 1.0 dB.
4.1.6. Noise
measurements shall not be made in fog, rain, wind with a steady speed exceeding
5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with
a portable wind speed meter capable of measuring the wind speed in m/s.
Air Quality Monitoring
Stations
4.2.1. The air
monitoring has been conducted at the designated location Ning Po No.2 College
(AQM1).The air monitoring stations for the Project are listed and shown in Table
4.2 and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.2 Air Monitoring
Station
Station ID |
Monitoring Location |
AQM1 |
Roof Top of Ning Po No.2 College |
Air Monitoring Parameters,
Frequency and Duration
4.2.2. One-hour
and 24-hour TSP levels should be measured to indicate the impacts of
construction dust on air quality. The 24-hour TSP levels shall be measured by
following the standard high volume sampling method as set out in the Title 40
of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.
4.2.3. All
relevant data including temperature, pressure, weather conditions, elapsed-time
meter reading for the start and stop of the sampler, identification and weight
of the filter paper, and any other local atmospheric factors affecting or
affected by site conditions, etc., shall be recorded down in detail.
4.2.4. For
regular impact monitoring, the sampling frequency of at least once in every
six-days, shall be strictly observed at all the monitoring stations for 24-hour
TSP monitoring. For 1-hour TSP monitoring, the sampling frequency of at least
three times in every six-days should be undertaken when the highest dust impact
occurs.
Sampling Procedure and
Monitoring Equipment
4.2.5. High
volume samplers (HVSs) in compliance with the following specifications shall be
used for carrying out the 1-hour and 24-hour TSP monitoring:
¡P
0.6
- 1.7 m3 per minute adjustable flow range;
¡P
equipped
with a timing / control device with +/- 5 minutes accuracy for 24 hours
operation;
¡P
installed
with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
¡P
capable
of providing a minimum exposed area of 406 cm2;
¡P
flow
control accuracy: +/- 2.5% deviation over 24-hour sampling period;
¡P
equipped
with a shelter to protect the filter and sampler;
¡P
incorporated
with an electronic mass flow rate controller or other equivalent devices;
¡P
equipped
with a flow recorder for continuous monitoring;
¡P
provided
with a peaked roof inlet;
¡P
incorporated
with a manometer;
¡P
able
to hold and seal the filter paper to the sampler housing at horizontal
position;
¡P
easily
changeable filter; and
¡P
capable
of operating continuously for a 24-hour period.
4.2.6. Initial
calibration of dust monitoring equipment shall be conducted upon installation
and thereafter at bi-monthly intervals. The transfer standard shall be
traceable to the internationally recognized primary standard and be calibrated
annually. The calibration data shall be properly documented for future
reference by concerned parties such as the IEC. All the data should be
converted into standard temperature and pressure equivalents.
Laboratory Measurement /
Analysis
4.2.7. A clean
laboratory with constant temperature and humidity control, and equipped with
necessary measuring and conditioning instruments to handle the dust samples
collected, shall be available for sample analysis, and equipment calibration
and maintenance. The laboratory should be HOKLAS accredited.
4.2.8. If a site
laboratory is set up or a non-HOKLAS accredited laboratory is retained for
analysis, laboratory equipment shall be provided by the ER in consultation with
the IC(E). Measurement performed by the laboratory shall be demonstrated to the
satisfaction of the ER and the IC(E). The IC(E) shall conduct regular audit to
the measurement performed by the laboratory to ensure the accuracy of
measurement results. The ET leader shall provide the ER with one copy of the
Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), and Appendix
B for his reference.
4.2.9. Filter
paper of size 8" x 10" shall be labelled before sampling. It shall be
a clean filter paper with no pinholes, and shall be conditioned in a humidity-controlled
chamber for over 24-hours and be pre-weighed before use for the sampling.
4.2.10. After
sampling, the filter paper loaded with dust shall be kept in a clean and
tightly sealed plastic bag. The filter paper shall then be returned to the
laboratory for reconditioning in the humidity controlled chamber followed by
accurate weighing by an electronic balance with readout down to 0.1 mg. The
balance shall be regularly calibrated against a traceable standard.
4.2.11. All the
collected samples shall be kept in a good condition for 6 months prior to
disposal.
5.0.1. The
environmental monitoring will be implemented based on the sensitive receivers
which would be mostly affected. Overall layout showing the work area, latest
status of work commencement and monitoring stations are shown in Figure
2.1 and Figure 4.1.
5.0.2. The
environment monitoring schedules for reporting month and coming month are
presented in Appendix 5.1.
5.1.1. The noise
monitoring results for Contract no. CV/2012/07 are summarized in Table
5.1 below:
Table 5.1 Summary of Noise Monitoring Results at
NM1 and NM2
Date |
Time |
Location |
Leq (dB) |
Limit Level |
3-Jun-17 |
10:35 |
NM1 |
68.5 |
75 |
11:30 |
NM2 |
62.0 |
70 |
|
9-Jun-17 |
10:30 |
NM1 |
67.0 |
75 |
11:30 |
NM2 |
62.5 |
70 |
|
15-Jun-17 |
13:02 |
NM1 |
64.9 |
75 |
14:02 |
NM2 |
68.0 |
70 |
|
20-Jun-17 |
15:45 |
NM1 |
65.1 |
75 |
15:10 |
NM2 |
66.5 |
70 |
|
Limit Level |
65 / 70 /75* |
|
Note :
-
70dB(A)
and 65 dB(A) for schools during normal teaching periods and school examination
periods, respectively.
5.1.2. Day time
period noise monitoring was conducted at the Tin Wan House (NM1) and Ning Po
No.2 College (NM2).
5.1.3. Noise
monitoring results measured in this reporting period are reviewed and
summarized. No exceedance was recorded in reporting month. Details of noise
monitoring results and graphical presentation can be referred in Appendix 5.2.
5.2.1. The air
monitoring results are summarized in Table 5.2 and Table
5.3 below. No exceedance was recorded in the reporting
month.
Table 5.2 Summary of Air Monitoring Results at
AQM1 - 24 hr TSP Monitoring
Time |
TSP
Level, (mg
/m3) |
|
2-Jun-17 |
8:00 |
62 |
8-Jun-17 |
8:00 |
30 |
14-Jun-17 |
8:00 |
46 |
20-Jun-17 |
8:00 |
32 |
Action Level |
200 |
|
Limit Level: |
260 |
Table 5.3 Summary of Air
Monitoring Results at AQM1 - 1 hr TSP Monitoring
Date |
Time |
TSP
Level, (mg
/m3) |
3-Jun-17 |
9:08 |
82 |
3-Jun-17 |
10:10 |
34 |
3-Jun-17 |
13:00 |
34 |
9-Jun-17 |
9:15 |
21 |
9-Jun-17 |
10:17 |
67 |
9-Jun-17 |
13:00 |
37 |
15-Jun-17 |
13:00 |
84 |
15-Jun-17 |
14:05 |
69 |
15-Jun-17 |
15:07 |
31 |
21-Jun-17 |
13:00 |
64 |
21-Jun-17 |
14:02 |
27 |
21-Jun-17 |
15:05 |
31 |
Action Level |
197 |
|
Limit Level: |
500 |
5.2.2.
Air monitoring results measured in this reporting
period are reviewed and summarized. No exceedance was recorded in reporting
month. Details of air monitoring results can be referred in Appendix 5.3.
5.3.1. Inert
C&D waste and general refuse were disposed in this reporting month. Details
of the waste flow table are summarized in Table 5.4.
Table 5.4 Details of
Waste Disposal for Contract no. CV/2012/07
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
0.010578 |
12.3112 |
TKO137 |
Inert C&D materials recycled, m3 |
0 |
0 |
N/A |
Non-inert C&D materials disposed, m3 |
0 |
0 |
N/A |
Non-inert C&D materials recycled, kg |
0 |
34.5436 |
N/A |
Chemical waste disposed, kg |
0 |
0 |
N/A |
General refuse,m3 |
0.011375 |
0.98557 |
NENT |
6.0.1. The Event
Action Plan for construction noise, air quality and water quality are presented
in Appendix
6.1.
6.1.1.
No exceedance was recorded in the reporting
month.
6.2.1. No
exceedance was recorded in the TSP monitoring in the reporting month.
6.3.1. There was
no non-compliance from the site audits in the reporting period. The
observations and recommendations made in each individual site audit session
were presented in Section 7.
6.4.1. There was
no particular action taken since no project-related non-compliance was recorded
from the site audits and environmental monitoring in the reporting period.
7.0.1. According
to EM&A Manual stipulation, the regular weekly site inspections on 06, 13 and 20
June 2017 were carried out by ET, IEC, the Contractor and
ARUP for Contracts no. CV/2012/07 to ensure the environmental performance.
Observations and findings are summarized in Table 7.1.
Table 7.1 Summary of
Environmental Inspections for Contract no. CV/2012/07
Date |
Observations |
Follow-Up |
06 - June - 2017 |
l
No finding. |
NA |
13 ¡V June - 2017 |
l
No finding |
NA |
20 ¡V June ¡V 2017 |
l
No finding. |
NA |
8.0.1. No complaint and notification of
summons or successful prosecutions were recorded in this reporting month.
8.0.2. The
details of cumulative complaint log and updated summary of complaints are
presented in Appendix 8.1.
8.0.3. Cumulative
statistic on complaints and successful prosecutions are summarized in Table
8.1 and Table 8.2 respectively.
Table 8.1 Cumulative
Statistics on Complaints
Reporting
Period |
No.
of Complaints |
June
2017 |
0 |
Project-to-Date |
1 |
Table 8.2 Cumulative
Statistics on Successful Prosecutions
Environmental
Parameters |
Cumulative
No. Brought Forward |
No.
of Successful Prosecutions this month (Offence Date) |
Cumulative
No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
9.0.1. The
EM&A programme was carried out in accordance with the EM&A Manual
requirements, minor alterations to the programme proposed were made in response
to changing circumstances.
9.0.2. No
construction air and noise monitoring results that triggered the Action and
Limit Level was recorded. No complaint of air and noise were received by the
ARUP and the contractor. Furthermore, no notification of summons or successful
prosecution was received in this reporting month.
9.0.3. Dismantling
and paving were the key works of the current construction works. Vehicle loads
transport should
be the potential construction dust and noise impact since the construction site
located nearby residential area of Shun Tin Estate. It is reminded that
mitigation measures for dust and noise should be properly implemented.