Project Title: Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities

 

Reference of the Approved EIA Report in the Register : AEIAR-145/2009

Conditions of Approval under Section 8(3) of the EIA Ordinance (the Ordinance)

 

 

The EIA Report as exhibited under Section 7(1) of the Ordinance is approved by the Director on the following conditions:

 

 

1.                          The project proponent shall advance the preparation works for the designation of the marine park in the Brothers Islands, including a study on the details of the designation and consultation with stakeholders, on the understanding that designation of the marine park would immediately follow the completion of the project;

 

2.                          The project proponent shall submit the proposal and detailed plan, including the proposed size and management plan, of the proposed marine park in the Brothers Islands, in consultation with the Agriculture, Fisheries and Conservation Department, to the Advisory Council on the Environment for comments and advice before the commencement of construction works; and

 

3.                          The project proponent shall not use underwater percussive piling for the project.

 

 

 

 

Environmental Protection Department