Environmental Management Plan

for

 

Proposed Headquarters and Bus Maintenance Depot in Chai Wan

 

 

 

Reference :

 

R0474-3.01

 

Date :

 

June 2001

 
 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


Client :

 

Citybus Limited

 
 


 

Project Consultancy Team:

Ling Chan + Partners Limited

in association with

CH2M HILL (China) Limited

Wong Pak Lam & Associates Limited

Thomas Anderson & Partners Limited

LLA Consultancy Limited

MDA Hong Kong Limited

Edaw Earthasia Limited

 

 
 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


TABLE OF CONTENTS

1.            Introduction

1.1      Background

2.            Environmental monitoring and Audit Requirements

2.1      Objectives of the EM&A Programme

2.2      Content of the EM&A Manual

2.3      Project Description

2.4      Sensitive Receivers

2.5      Project Organisation

2.6      Construction Dust Monitoring

2.7      Construction Noise Monitoring

2.8      Event and Action Plan for Construction Noise

2.9      Noise Mitigation Measures

2.10       Construction Waste Management

2.11       Landscape and Visual Issues

2.12       Site Environmental Audit

2.13       Reporting

3.            Environmental Management System

3.1      Introduction

3.2      Identification of Key Environmental Factors

3.3      Time Schedule for Setting Up the EMS

 

 

 LIST OF FIGURES

Figure 1-1     Location of Proposed Headquarters and Bus Maintenance Depot in Chai Wan

Figure 2‑1    Outline Zoning Plan No. S/H20/11 (Extract)

Figure 2‑2    Preliminary Construction Programme

Figure 2‑3    Air Quality Monitoring Field Record Sheet

Figure 2‑4    Location of the Proposed Air Quality Monitoring Station

Figure 2‑5    Noise Monitoring Field Record Sheet

Figure 2‑6    Location of the Proposed Noise Monitoring Stations

Figure 2‑7    Complaint - Response Procedures

Figure 2‑8    Sample Template for Interim Notifications of Environmental Quality Limits Exceedances

 

 

LIST OF TABLES

Table 2‑1     Action and Limit Levels for Air Quality

Table 2‑2     Event/Action Plan for Air Quality

Table 2‑3     Action and Limit Levels for Construction Noise

Table 2‑4     Event and Action Plan for Construction Noise Monitoring

Table 3‑1     Summary of Key Environmental Factors and Environmental Mitigation Strategy to be included in the EMS

 

LIST OF APPENDICES

Appendix I   Environmental Mitigation Measures Implementation Schedule

Appendix II  Record Forms (1, 2, 3, 4, 5, 6, 7, 8, 9)


1.                   Introduction

1.1                Background

1.1.1             An Environmental Impact Assessment (EIA) has been conducted for the proposed Headquarters and Bus Maintenance Depot at Chai Wan East Industrial Area, Chai Wan. Figure 1-1 shows the location of the development site. 

1.1.2             Based on the assessment results, a number of mitigation measures have been recommended if necessary for implementation during the construction phase of the bus depot development.  In accordance with the requirements under Sections 4 to 6 of the EIA Study Brief, this Environmental Management Plan (EMP) has been prepared to cover the Environmental Monitoring and Audit (EM&A) requirements and Environmental Management System (EMS).

1.1.3            As part of the EIA study, this EMP was prepared by CH2M HILL (China) Limited, formerly named as EHS Consultants Limited. The first section of this EMP describes the EM&A activities recommended to be carried out during the construction phase of the development project in accordance with the requirements under Section 6 of the EIA Study Brief.  The second part of this EMP presents the project proponent’s proposal on the setting up of an Environmental Management System (EMS).

1.1.4            The EM&A programme will be useful in providing a means to verify the effectiveness and adequacy of the mitigation measures recommended in the EIA such that additional mitigation measures or remedial action, if deemed necessary, can be formulated during the construction phase of the development. The recommended EM&A programme is to be carried out by an Environmental Team (ET) formed before the commencement of the construction works.

1.1.5            The EM&A requirements presented in this EMP provide systematic procedures for the carrying out of recommended monitoring and auditing works for checking of potential environmental impacts which may arise from the implementation of the project.  Mitigation measures recommended in the EIA Report for each key environmental aspect during the construction phase are also summarised and presented in this Manual.  Operational phase environmental control or mitigation measures are also included in the Implementation Schedule presented in Appendix I. 

1.1.6            To ensure that the relevant environmental issues are taken into account during the operational phase of the development, an EMS is proposed for implementation.

1.1.7            Environmental regulations currently enforced in Hong Kong pertaining to air quality, noise and waste, etc. and the recommendations given in the EIA report have been observed in the preparation of this EMP.


 


2.                   Environmental monitoring and Audit Requirements

2.1                Objectives of the EM&A Programme

2.1.1            The main objectives of the EM&A programme include:

(i)           to provide a database on baseline environmental quality for subsequent checking of any environmental impacts arising from the implementation of the project;

(ii)         to provide information at an early stage for identification of potential problem areas and formulation of additional environmental mitigation measures where necessary should any of the environmental control measures or practices fail to achieve the target standards;

(iii)        to monitor the performance of the project from an environmental viewpoint and the sufficiency and effectiveness of the implemented mitigation measures;

(iv)        to verify the environmental impacts predicted in the EIA for the bus depot;

(v)         to determine project compliance with relevant regulatory standards, requirements and guidelines;

(vi)        to take remedial action should unexpected problems or unacceptable impacts are identified;

(vii)      to provide baseline and compliance monitoring data to assist the carrying out of effective environmental audits.

 

2.2                Content of the EM&A Manual

2.2.1            The recommended EM&A programme in Section 2 of this EMP, referred to as the EM&A Manual, contains the following information:

(i)           duties of the Environmental Team (ET) in the environmental monitoring and audit programme;

(ii)         information on project organisation, construction schedule and activities;

(iii)        information on the preliminary construction programme and the necessary environmental monitoring and audit programme to track the varying environmental impacts;

(iv)        definition of Action and Limit levels, and establishment of Event and Action Plans;

(v)         requirements of reviewing pollution sources and work procedures in the event of non-compliance of the environmental criteria;

(vi)        requirements in presentation of EM&A data and appropriate reporting procedures;

(vii)      an Implementation Schedule (Appendix I) of the environmental mitigation measures recommended in the EIA report;

(viii)     record forms (Appendix II) to be adopted where applicable during the construction phase of the project.

2.2.2            The EM&A Manual shall be regarded as an evolving document that should be updated when necessary in order to maintain its relevance during the detailed design stage and/or the construction phase (e.g. when alternative monitoring locations are proposed).  The updated EM&A Manual shall be submitted to the ER and EPD for agreement.


2.3                Project Description

The Subject Site and Its Environs

2.3.1            The proposed bus depot will be constructed on an approximately 1 hectare site located in the Chai Wan East Industrial Area. Figure 1-1 shows the location of the site.

2.3.2            The site was reclaimed and is zoned for industrial use (“I”) similar to its surrounding reclaimed area as shown in the Outline Zoning Plan (OZP) No. S/H20/11.  According to the Notes of the OZP, “Bus Depot” is a column 1 use that no planning permission from the Town Planning Board is required.  Figure 2-1 presents an Extract of the OZP. 

2.3.3            Located at an approximate minimum distance of 80m to the North-west of the future bus depot is Hong Kong Institute of Vocational Education (IVE) (Chai Wan).  Lying between the college and the bus depot site are the MTR railway tracks leading to the Chai Wan Station to the south and Shing Tai Road. To the immediate North of IVE is its associated Staff Quarters.  The nearest residential block at Tsui Wan Estate is situated at more than 165m to the South-west of the site. The nearest residential block at Heng Fa Chuen is located at approximately 390m to the north of the site. 

2.3.4            Planning Department (PlanD) has advised that in addition to the proposed bus depot, the Chai Wan East Industrial Area is also planned to accommodate an Open Space, a Joint Government Departmental Depot, Lorry Park & Motor Vehicle Repair Workshop, New World First Bus Depot, LPG/ Petrol Filling Station and Hong Kong Post Super Centre.  The northern side of the site is planned by the Government for the development of a LPG/ petrol filling station, while the southern side of the site would be HK Post Supercentre.  Only the NWFB depot situated near Chong Fu Road and located at about 135m from the proposed bus depot is under active construction and is expected to be completed by year 2002. According to PlanD, all other proposed developments in the area are currently still at a planning stage without a concrete development programme.

2.3.5            The proposed Citybus depot will be bound by a future local road – Road 20/4 to the East and Shing Tai Road to the west.  Other future new roads in the Chai Wan East Industrial Area include Road 20/6 and Road 20/10 as shown in Figure 1-1.  Highways Department (HyD) has advised that the three new roads – 20/4, 20/6 and 20/10 are expected to be completed in December 2002.

 

Bus Depot Design & Construction Programme

2.3.6            The proposed bus depot will be in form of a low-rise building occupying a site area of approximately 1 hectare.  The bus depot will occupy the G/F to 3/F of the development.  4/F and 5/F will be office areas and constructed as an extension on the side of the site facing Road 20/4. The development will provide spaces for bus parking, maintenance and office areas.  Architectural design of the development have been developed by the Project Architect – LCP, with input on the engineering, traffic and environmental aspects provided by the sub-consultants. 

2.3.7            To meet the urgent bus depot demand, construction works are planned to commence near end of 2001 to have the bus depot ready for operation in mid-2003.  Figure 2-2 presents a tentative construction programme of the depot development. The Environmental Team (ET) Leader shall make reference to the actual works programme make available by the appointed Contractor in scheduling the EM&A works. 

 


2.4                Sensitive Receivers

2.4.1            Existing sensitive receivers located in the vicinity of the project site that might be potentially affected by the construction works of the site formation project were identified and described in the EIA Report.  These sensitive receivers include:

§        Hong Kong Institute of Vocational Education (IVE) (Chai Wan);

§        Staff Quarters of IVE (Chai Wan);

§        Tsui Wan Estate – nearest block is Tsui Sau House;

§        Heng Fa Chuen – nearest block is Block 50 

 

2.5                Project Organisation

2.5.1            The key parties in an EM&A programme include the Contractor, the Engineer[1] or the Engineer’s representative (ER)1, the Environmental Team (ET), the Independent Checker (Environment) (IC(E)) and Environmental Protection Department (EPD).

 

Environmental Team

2.5.2            An ET shall be appointed to carry out the EM&A works of the site formation project. The ET shall not be an associated company of the Contractor.  The ET leader[2] shall plan, organise and manage the implementation of the EM&A programme, and to ensure that the EM&A works are undertaken to the required standards.  The ET leader shall have relevant professional qualification and sufficient experience in carrying out the EM&A works.

2.5.3            Appropriately qualified staff shall be included in the ET.  The ET shall be under the supervision of the ET Leader in fulfilling the EM&A duties specified in this Manual. The board categories of woks of the ET comprise the followings:

(a)    sampling, analysis and statistical evaluation of monitoring parameters with reference to the EIA/EA study recommendations and requirements;

(b)   environmental site surveillance;

(c)    audit of compliance with environmental protection, and pollution prevention and control regulations;

(d)   monitor the implementation of environmental mitigation measures;

(e)    monitor compliance with the environmental protection clauses/specifications in the Contract;

(f)    review construction programme and comment as necessary;

(g)    review construction methodology and comment as necessary;

(h)   complaint investigation, evaluation and identification of corrective measures;

(i)     liaison with IC(E) on all environmental performance matters, and timely submission of all relevant EM&A proforma for IC(E)’s approval;

(j)     advice to the Contractor on environmental improvement, awareness, enhancement matters, etc., on site; and

(k)   timely submission of the EM&A report to the Project Proponent and the Director of Environmental Protection.

 

2.5.4            In the event of an exceedance in action/ limit levels, the ET shall immediately inform the IC(E) and Engineer/ ER so that appropriate remedial action can be undertaken by the Contractor promptly notified by ER. The ET is also responsible for the preparation of the monthly EM&A reports for submission to the IC(E), the Contractor and the Engineer/ ER, and through the Engineer/ ER to EPD.  The ET shall assist the Contractor and the Engineer/ ER in formulating any necessary corrective actions and/ or additional mitigation measures, and liasing with relevant Government Departments where necessary.

 

Independent Checker (Environment)

2.5.5            The Independent Checker (Environment) (IC(E)) shall advise the ER on environmental issues related the project. The role of the Checker shall be independent from the management of construction works; but the Checker shall be empowered to audit the environmental performance of construction. The Checker shall have project management experience in addition to the requirements of the ET leader. The appointment of the Checker is subject to the approval of the ER.

2.5.6            The main duty of the IC(E) is to carry out environmental audit of the construction project; this shall include, inter alia, the followings:

(a) review and audit all aspects of the EM&A programme;

(b) validate and confirm the accuracy of monitoring results; monitoring equipment, monitoring locations, monitoring procedures and locations of sensitive receivers;

(c) carry out random sample check and audit on monitoring data and sampling procedures, etc;

(d) conduct random site inspection;

(e) audit the EIA recommendations and requirements against the status of implementation of environmental protection measures on site;

(f) review the effectiveness of environmental mitigation measures and project environmental performance;

(g) on a needs basis, audit the Contractor’s construction methodology and agree the least impact alternative in consultation with the ET leader and the Contractor;

(h) check complaint cases and the effectiveness of corrective measures;

(i) review EM&A report submitted by the ET leader; and

(j) feedback audit results to ET by signing off relevant EM&A proformas.   

 


The Contractor

2.5.7            The Contractor is responsible for providing requested information to the ET in the event of any exceedance in the environmental criteria specified in this Manual or other current environmental standards, and to rectify unacceptable practices. The Contractor shall also discuss with the ET, IC(E) and ER on any additional mitigation measures identified to be required by the ET and implement the agreed measures to alleviate any identified environmental impact to acceptable levels.  The Contractor shall submit proposals for remedial actions to IC(E), and report to the ET on the actions taken targeting at environmental protection for inclusion in the monthly report to be prepared by the ET.

 

The Engineer or the Engineer’s Representative

2.5.8            The Engineer, or the ER shall be responsible for overseeing the operations of the Contractor and the ET.  He shall advise, co-ordinate and give instruction when appropriate for efficient implementation of any specific environmental mitigation measures identified to be required by the contractor, and/or outstanding EM&A works required to be carried out by ET in consultation with IC(E).

 

2.6                Construction Dust Monitoring

Air Quality Parameters

2.6.1            Monitoring and audit of Total Suspended Particulate (TSP) levels shall be carried out by the ET during the proposed site formation activities to ensure that deterioration of air quality could be detected and timely action taken to rectify the situation.

2.6.2            24-hour and 1-hour Total Suspended Particulate (TSP) levels shall be measured according to the recommended programme.  24-hour and 1-hour TSP levels shall be measured by following the standard high volume sampling method as set out in Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B. 

2.6.3            Upon approval of the ER on the advice of EPD, 1-hour TSP levels can alternatively be measured by direct reading methods which are capable of producing comparable results as that by the high volume sampling method, to indicate short event impacts. However, the ET should submit sufficient information to the IC(E) to prove that the instrument is capable of achieving a comparable result as that the HVS and maybe used for 1-hr sampling.

2.6.4            All relevant data including temperature, pressure, weather conditions, elapsed-time meter reading for the start and stop of the sampler, identification and weight of the filter paper, and other special phenomena and work progress of the concerned site etc. shall be recorded down in details, where appropriate.  A sample data sheet is shown in Figure 2-3.

 


Monitoring Equipment

2.6.5            Regarding the high volume sampling method, high volume sampler (HVS) in compliance with the following specifications or equivalence shall be used :

a)           0.6-1.7 m3/min. (20-60 SCFM) adjustable flow range;

b)          equipped with a timing/control device with +/- 5 minutes accuracy for 24 hours operation;

c)           installed with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;

d)          capable of providing a minimum exposed area of 406 cm2 (63 in2);

e)           flow control accuracy: +/- 2.5% deviation over 24-hr sampling period;

f)           equipped with a shelter to protect the filter and sampler;

g)           incorporated with an electronic mass flow rate controller or other equivalent devices;

h)          equipped with a flow recorder for continuous monitoring;

i)            provided with a peaked roof inlet;

j)            incorporated with a manometer;

k)          able to hold and seal the filter paper to the sampler housing at horizontal position;

l)            easy to change the filter; and

m)         capable of operating continuously for 24-hr period.

2.6.6            A direct reading dust meter capable of achieving results comparable to a HVS for 1-hr sampling with reading in the range of 0.1 - 100 mg/m3 can also be used for 1-hr sampling provided that the instrument is to be calibrated against a traceable primary standard at regular intervals.  Sufficient information on the direct reading dust meter shall be submitted to the ER to verify that the instrument is suitable for the 1-hr sampling.

2.6.7            During execution of the construction works, the ET is responsible for provision of the monitoring equipment. He shall ensure that sufficient number of HVSs with an appropriate calibration kit, and direct reading dust meters are available for the carrying out of baseline monitoring, regular impact monitoring and ad hoc monitoring. 

2.6.8            The HVSs shall be equipped with an electronic mass flow controller and be calibrated against a traceable standard at regular intervals.  All the equipment, calibration kit, filter papers, etc. shall be clearly labelled.

2.6.9            Initial calibration of HVSs shall be conducted upon installation and thereafter at bi-monthly intervals.  The transfer standard shall be traceable to the internationally recognised primary standard and be calibrated annually.  The calibration data shall be properly documented for future reference by the concerned parties such as the IC(E).  All data should be converted into standard temperature and pressure condition.

2.6.10         The flow-rate of the sampler before and after the sampling exercise with the filter in position shall be verified to be constant and be recorded down in the data sheet given in Figure 2-3.

2.6.11         Wind data monitoring equipment shall also be provided and set up at a conspicuous location for logging wind speed and wind direction near to the dust monitoring locations.  The location for equipment installation shall be proposed by the ET and agreed with the ER.  For installation and operation of wind data monitoring equipment, the following points shall be observed:

a)           the wind sensors should be installed on masts at an elevated level 10m above ground so that they are clear of obstructions or turbulence caused by the buildings;

b)          the wind data should be captured by a data logger and to be downloaded for processing at least once a month;

c)           the wind data monitoring equipment should be re-calibrated at least once every six months; and

d)          wind direction should be divided into 16 sectors of 22.5 degrees each.

2.6.12         In exceptional situations, the ET may propose alternative methods to obtain representative wind data upon approval from the ER and agreement from the IC(E).

 

Laboratory Measurement / Analysis

2.6.13         A clean laboratory with constant temperature and humidity control, and equipped with necessary measuring and conditioning instruments, to handle the dust samples collected, shall be available for sample analysis, and equipment calibration and maintenance.  The laboratory should be HOKLAS accredited.

2.6.14         If a site laboratory is set up or a non-HOKLAS accredited laboratory is hired for carrying out the laboratory analysis, the laboratory equipment shall be approved by the ER in consultation with the IC(E) and the measurement procedures shall be witnessed by the IC(E) and the ER.  The ET shall provide the ER with one copy of the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B for his reference.

2.6.15         Filter paper of size 8”x10” shall be labelled before sampling.  It shall be a clean filter paper with no pin holes, and shall be conditioned in a humidity controlled chamber for over 24-hr and be pre-weighed before use for the sampling.

2.6.16         After sampling, the filter paper loaded with dust shall be kept in a clean and tightly sealed plastic bag.  The filter paper is then returned to the laboratory for reconditioning in the humidity controlled chamber followed by accurate weighing by an electronic balance with a readout down to 0.1 mg.  The balance shall be regularly calibrated against a traceable standard.

2.6.17         All the collected samples shall be kept in a good condition for 6 months before disposal.

 

Proposed Monitoring Location

2.6.18         The dust emission impact assessment presented in the EIA report indicated that the nearby air sensitive receivers (ASRs) will not be subject to adverse dust impact from the construction of the depot.  Nevertheless, dust mitigation measures have been recommended and shall be implemented by the Contractor in accordance with the requirements under the Air Pollution Control (Construction Dust) Regulation.  The contractor shall be responsible for the design and implementation of the dust mitigation measures.

2.6.19         Figure 2-4 shows the location of the proposed dust monitoring station (at IVE – Chai Wan) recommended to check the implementation of the required dust control measures by the Contractor. The Institute was identified to be the nearest sensitive receiver situated in the vicinity of the development site. The appointed ET may like to propose alternative monitoring location taking into consideration the latest status, availability and/or accessibility of the station. The alternative monitoring location proposed by the ET shall be approved by the ER and agreed by IC(E).

2.6.20         When an alternative monitoring location is proposed, the following criteria should be followed as far as practicable:

a)           at the site boundary or such locations close to the major dust emission sources;

b)          close to the sensitive receptors; and

c)           take into account the prevailing meteorological conditions.

 

2.6.21         The ET shall agree with the ER in consultation with the IC(E) on the position of the HVS for installation of the monitoring equipment. When positioning the sampler, the following points shall be noted:

a)           a horizontal platform with appropriate support to secure the samplers against gusty wind should be provided;

b)          the distance between the sampler and an obstacle, such as buildings, must be at least twice the height that the obstacle protrudes above the sampler;

c)           a minimum of 2 metres of separation from walls, parapets and penthouses is required for rooftop samplers;

d)          a minimum of 2 metres separation from any supporting structure, measured horizontally is required;

e)           no furnace or incinerator flue is nearby;

f)           airflow around the sampler is unrestricted;

g)           the sampler is more than 20 metres from the dripline;

h)          any wire fence and gate, to protect the sampler, should not cause any obstruction during monitoring;

i)            permission must be obtained to set up the samplers and to obtain access to the monitoring stations; and;

j)            a secured supply of electricity is needed to operate the samplers.

 

Baseline Monitoring

2.6.22         Baseline monitoring shall be carried out by the appointed ET at the recommended monitoring station for at least 14 consecutive days to obtain daily 24-hr TSP samples before the commencement of any dusty construction activities.  1-hr sampling shall also be done at least 3 times per day during daytime when there are planned construction activities. The ET should inform the IC(E) of the baseline monitoring programme before commencement such that the IC(E) can conduct on-site audit to ensure accuracy of the baseline monitoring results.

2.6.23         During the baseline monitoring, there should not be any dust generating construction activities in the vicinity of the monitoring station arising from the subject development site. 

2.6.24         In case the baseline monitoring cannot be carried out at the designated monitoring location during the baseline monitoring period, the ET Leader shall carry out the monitoring at alternative location which can effectively represent the baseline conditions at the impact monitoring location.  The alternative baseline monitoring locations shall be approved by the ER and agreed with IC(E).

2.6.25         If the ET considers that the ambient conditions have been changed and a repeat of the baseline monitoring is required to be carried out for obtaining the updated baseline levels, the monitoring should be carried out at times when the contractor’s activities are not generating dust in the proximity of the monitoring stations.  Should change in ambient conditions be determined, the baseline levels and, in turn, the air quality criteria, should be revised.  The revised baseline levels and air quality criteria should be agreed with the IC(E) and EPD.

 


Impact Monitoring

2.6.26         The ET shall carry out impact monitoring during the course of the construction works at the recommended dust monitoring station.  For regular impact monitoring, a sampling frequency of at least one in every six-days shall be followed at the selected monitoring station for 24-hr TSP monitoring. The specific time to start and stop the 24-hr TSP monitoring shall be clearly defined and be strictly followed by the operator. Before commencement, the ET leader shall inform the IC(E) of the impact monitoring programme such that the IC(E) can conduct on-site audit to ensure accuracy of the impact monitoring results.

2.6.27         For 1-hr TSP monitoring, a sampling frequency of at least three times per day in every six-days should be undertaken during the hours when active construction activities are taking place.  The 1-hr TSP monitoring can be undertaken on the same day as the 24-hr TSP monitoring. 

2.6.28         In case of non-compliance with the air quality criteria, more frequent monitoring exercise, as specified in the following section, shall be conducted within 24 hours after the result is obtained.  This additional monitoring shall be continued until the excessive dust emission or the deterioration in air quality is rectified.

 

Event and Action Plan for Air Quality

2.6.29         The baseline monitoring results form the basis for determining the air quality criteria for the impact monitoring.  The ET shall compare the impact monitoring results with air quality criteria set up for 24-hour TSP and 1-hour TSP.  Table 2‑1 shows the air quality criteria, namely Action and Limit levels to be used.  Should non-compliance of the air quality criteria occurs, the ET shall undertake the relevant action in accordance with the Action Plan in Table 2‑2.

 

Table 21                   Action and Limit Levels for Air Quality

Parameters

            Action

Limit

24 Hour TSP Level in mg/m³

For baseline level £ 200 mg/m³, Action level = (Baseline level * 1.3 + Limit level)/2;

For baseline level > 200 mg /m³, Action level = Limit level

260 mg/m³

1 Hour TSP Level in mg/m³

For baseline level £ 384mg /m³, Action level = (Baseline level * 1.3 + Limit level)/2;

For baseline level > 384mg/m³, Action level = Limit level

500mg/m³

 


Table 22                   Event/Action Plan for Air Quality

 

ACTION

EVENT

ET Leader

IC (E)

ER

CONTRACTOR

ACTION LEVEL

1.Exceedance for one sample

    

1.     Identify source

2.     Inform IC(E) and ER

3.     Repeat measurement to confirm finding

4.     Increase monitoring frequency to daily

1.     Check monitoring data submitted by ET

2.     Check Contractor’s working method

1.     Notify Contractor

1.  Rectify any unacceptable practice

2.  Amend working methods if appropriate

2.Exceedance for two or more consecutive samples

i.      Identify source

ii.     Inform IC(E) and ER

iii.    Repeat measurements to confirm findings

iv.    Increase monitoring frequency to daily

v.     Discuss with IC(E) and Contractor on remedial actions

vi.    If exceedance continues, arrange meeting with IC(E) and ER

vii.   If exceedance stops, cease additional monitoring

i.      Checking monitoring data submitted by ET

ii.     Check Contractor’s working method

iii.    Discuss with ET and Contractor on possible remedial measures

iv.    Advise the ER on the effectiveness of the proposed remedial measures

v.     Supervisor implementation of remedial measures

i.      Confirm receipt of notification of failure in writing

ii.     Notify Contractor

iii.    Ensure remedial measures properly implemented

i.   Submit proposals for remedial actions to IC(E) within 3 working days of notification

ii.  Implement the agreed proposals

iii. Amend proposal if appropriate

LIMIT LEVEL

1.Exceedance for one sample

               

1.     Identify source

2.     Inform ER and EPD

3.     Repeat measurement to confirm finding

4.     Increase monitoring frequency to daily

5.     Assess effectiveness of Contractor's remedial actions and keep IC(E), EPD and ER informed of the results

1.    Checking monitoring data submitted by ET

2.    Check Contractor’s working method

3.    Discuss with ET and Contractor on possible remedial measures

4.    Advise the ER on the effectiveness of the proposed remedial measures

5.    Supervisor implementation of remedial measures

1.    Confirm receipt of notification of failure in writing

2.    Notify Contractor

3.    Ensure remedial measures properly implemented

1.     Take immediate action to avoid further exceedance

2.     Submit proposals for remedial actions to IC(E) within 3 working days of notification

3.     Implement the agreed proposals

4.     Amend proposal if appropriate

2.Exceedance for two or more consecutive samples

i.      Notify IC(E), ER, Contractor and EPD

ii.     Identify source

iii.    Repeat measurement to confirm findings

iv.    Increase monitoring frequency to daily

v.     Carry out analysis of Contractor’s working procedures to determine possible mitigation to be implemented

vi.    Arrange meeting with IC(E) and ER to discuss the remedial actions to be taken

vii.   Assess effectiveness of Contractor's remedial actions and keep IC(E), EPD and ER informed of the results

viii.  If exceedance stops, cease additional monitoring

i.      Discuss amongst ER, ET and Contractor on the potential remedial actions

ii.     Review Contractor’s remedial actions whenever necessary to assure their effectiveness and advise the ER accordingly

iii.    Supervise the implementation of remedial measures

i.      Confirm receipt of notification of failure in writing

ii.     Notify Contractor

iii.    In consultation with the IC(E), agree with the Contractor on the remedial measures to be implemented

iv.    Ensure remedial measures properly implemented

v.     If exceedance continues, consider what portion of the work is responsible and instruct the Contractor to stop that portion of work until the exceedance is abated remedial actions

i.      Take immediate action to avoid further exceedance

ii.     Submit proposals for remedial actions to IC(E) within 3 working days of notification

iii.    Implement the agreed proposals

iv.    Resubmit proposals if problem still not under control

v.     Stop the relevant portion of works as determined by the ER until the exceedance is abated

 


Dust Mitigation Measures

2.6.30         The EIA report has recommended various dust control and mitigation measures. The following measures are specifically recommended for implementation together with those presented in the Air Pollution Control (Construction Dust) Regulation.

 

General Site Management

2.6.31         Appropriate working methods should be devised and arranged to minimise dust emissions and to ensure any installed air pollution control system and measures are operated and/or implemented in accordance with their design merits.  In the event of malfunctioning of any control system or equipment, the relevant dusty activities shall stop until the relevant control system or equipment are restored to proper functioning.

2.6.32         Frequent mist spraying should be applied on dusty areas.  The frequency of spraying required will depend upon local meteorological conditions such as rainfall, temperature, wind speed and humidity.  The amount of mist spraying should be just enough to dampen the material without over-watering, which could result in unnecessary surface water runoff.

2.6.33         No free falling of construction debris shall be allowed at the site.

 

Vehicles and Site Haul Road

2.6.34         Dust emission from unpaved roads comes predominantly from travelling of vehicles. Areas within the site where there are regular vehicle movements should have an approved hard surface.  Speed controls at an upper limit of 10 to 15 kph should be imposed and their movements should be confined to designed roadways within the site.  All dusty vehicle loads should have side and tail boards and should be covered by tarpaulin extending at least 300 mm over the edges of the side and tail boards.  Wheel-wash troughs and hoses should be provided at exit points of the site.

 

Material Stockpiling and Handling

2.6.35         The amount of stockpiling should be minimised as far as practicable. The surface of the stockpile should be kept wet by spraying with water.  Dust emission during loading of fill material to dump trucks should be mitigated by spraying to sufficiently damp the material prior to any loading or unloading operation. Dusty construction debris should be covered or stored inside enclosed areas where practicable to avoid dust generation. 

2.6.36         Watering is an effective dust control measure commonly employed in storage piles and handling operations and should be implemented where appropriate. Other control measures such as enclosed or semi-enclosed windboard should be used, where applicable, to minimise dust emission.


2.7                Construction Noise Monitoring

Noise Parameters

2.7.1            The construction noise level shall be measured in terms of the A-weighted equivalent continuous sound pressure level (LAeq).  LAeq(30 min.) shall be used as the monitoring parameter for the time period between 0700-1900 hours on normal weekdays. For all other time periods, LAeq(5 min) shall be employed for comparison with the NCO criteria.

2.7.2            As supplementary information for data auditing, statistical results such as L10 and L90 shall also be obtained for reference. A sample data record sheet is shown in Figure 2-5 for reference.

 

Monitoring Equipment

2.7.3            As referred to in the Technical Memorandum issued under the Noise Control Ordinance (NCO), sound level meters in compliance with the International Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for carrying out the noise monitoring. Immediately prior to and following each noise measurement, the accuracy of the sound level meter shall be checked using an acoustic calibrator generating a known sound pressure level at a known frequency.  Measurements may be accepted as valid only if the calibration level from before and after the noise measurement agree to within 1.0dB.

2.7.4            Noise measurements should not be made in the presence of fog, rain, wind with a steady speed exceeding 5m/s or wind with gusts exceeding 10m/s. The wind speed shall be checked with a portable wind speed meter capable of measuring the wind speed in m/s.

2.7.5            The ET is responsible for the provision of the monitoring equipment.  He shall ensure that sufficient noise measuring equipment and associated instrumentation are available for carrying out the baseline monitoring, regular impact monitoring and ad hoc monitoring. All the equipment and associated instrumentation shall be clearly labelled.

 

Monitoring Locations

2.7.6            The proposed locations (M1 to M4) for noise monitoring during construction works are shown in Figure 2-6. The appointed ET may like to propose alternative monitoring locations based on consideration of the latest status, availability and/or accessibility of the various possible monitoring locations. Alternative monitoring locations proposed by the ET shall be approved by the ER and agreed by EPD and the IC(E).

2.7.7            When alternative monitoring locations are proposed, the monitoring locations should be chosen based on the following criteria:

a)           at locations close to the major site activities which are likely to have noise impacts;

b)          close to the noise sensitive receivers; and

c)           for monitoring locations located in the vicinity of the sensitive receivers, care should be taken to cause minimal disturbance to the occupants during monitoring.


2.7.8            The monitoring station shall normally be at a point 1m from the exterior of the sensitive receivers building facade and be at a position 1.2m above ground.  If there is problem with access to the normal monitoring position, an alternative position may be chosen, and a correction to the measurements shall be made.  For reference, a correction of +3dB(A) shall be made to free field measurement data. The ET shall agree with the IC(E) on the monitoring position and the corrections adopted. Once the positions for the monitoring stations are chosen, the baseline monitoring and the impact monitoring shall be carried out at the same positions.

 

Baseline Monitoring

2.7.9            A schedule on the baseline monitoring shall be submitted to the ER for approval before the start of the monitoring.

2.7.10         In exceptional cases, when insufficient baseline monitoring data or questionable results are obtained, the ET shall liaise with EPD to agree on an appropriate set of data to be used as a baseline reference and submit to the ER for approval.

 

Impact Monitoring

2.7.11         Noise monitoring shall be carried out by the ET at the selected representative noise monitoring stations.  The following is an initial guide on the regular monitoring frequency for each station on a per week basis when noise generating activities are underway.

(i)       One set of measurement shall be monitored between 0700-1900 hours on normal working days (i.e. Monday to Saturday).  LAeq(30min.) noise levels shall be monitored at the selected representative monitoring stations in the vicinity of work areas.

2.7.12         The monitoring programme shall cover noise monitoring at IVE-Chai Wan (M3) during the school examination periods.  The ET Leader shall liaise with the Institute’s representative and the Examination Authority to ascertain the exact time periods of all examination periods during the construction works contract. 

2.7.13         In case of non-compliance with the construction noise criteria, more frequent monitoring as specified in the Action Plan shall be carried out. This additional monitoring shall be continued until the recorded noise levels are rectified or proved to be irrelevant to the construction activities.

 

2.8                Event and Action Plan for Construction Noise

2.8.1            The Action and Limit levels for construction noise are defined in Table 2‑3. Should non-compliance of the criteria occurs, action in accordance with the Action Plan in Table 2-4, shall be carried out.

Table 23                   Action and Limit Levels for Construction Noise

Time Period

Action

Limit

0700-1900 hrs on normal weekdays

When one documented complaint is received

75 dB(A)*

* reduce to 70dB(A) for IVE- Chai Wan (and 65dB(A) during the Institute’s examination period.)


Table 24                   Event and Action Plan for Construction Noise Monitoring

EVENT

ACTION

ET Leader

IC(E)

ER

Contractor

Action Level

1. Notify IC(E) and Contractor

2. Carry out investigation

3. Report the results of investigation to the IC(E) and Contractor

4. Discuss with the Contractor and formulate remedial measures

5. Increase monitoring frequency to check mitigation effectiveness

1. Review the analysed results submitted by the ET

2. Review the proposed remedial measures by the Contractor and advise the ER accordingly

3. Supervise the implementation of remedial measures

1. Confirm receipt of notification of failure in writing

2. Notify Contractor

3. Require Contractor to propose remedial measures fro the analysed noise problem

4. Ensure remedial measures are properly implemented

1. Submit noise mitigation proposals to IC(E)

2. Implement noise mitigation proposals

Limit Level

1. Notify IC(E), ER, EPD and Contractor

2. Identify source

3. Repeat measurement to confirm findings

4. Increase monitoring frequency

5. Carry out analysis of Contractor’s working procedures to determine possible mitigation to be implemented

6. Inform IC(E), ER and EPD the causes & actions taken for the exceedances

7. Assess effectiveness of Contractor’s remedial actions and keep IC(E), EPD and ER informed of the results

8. If exceedance stops, cease additional monitoring

1. Discuss amongst ER, ET, and Contractor on the potential remedial actions

2. Review Contractor’s remedial actions whenever necessary to assure their effectiveness and advise the ER accordingly

3. Supervise the implementation of remedial measures

1. Confirm receipt of notification of failure in writing

2. Notify Contractor

3. Require Contractor to propose remedial measures for the analysed noise problem

4. Ensure remedial measures are properly implemented

5. If exceedance continues, consider what portion of the work is responsible and instruct the Contractor to stop that portion of work until the exceedance is abated

1. Take immediate action to avoid further exceedance

2. Submit proposals for remedial actions to IC(E) within 3 working days of notification

3. Implement the agreed proposals

4. Resubmit proposals if problem still not under control

5. Stop the relevant portion of works as determined by the ER until the exceedance is abated

 

2.9                Noise Mitigation Measures

2.9.1            The EIA report has recommended various construction noise mitigation measures. These are summarised below for easy reference.  The Contractor shall be responsible for the design and implementation of these recommended measures.

2.9.2            Noise emissions from the construction site can be minimised by adopting a number of practicable noise mitigation options, including:

§        Use of quiet PME;

§        Phasing of construction activities to minimise concurrent operation of PME; and

§        Minimise number of PME working concurrently;

§        Good site practice and noise management;

§        Erect temporary noise barrier and provision of machinery enclosure

 

 


Selecting Quiet PME

2.9.3            Silenced types of equipment for use in construction activities are available in Hong Kong.  The contractor should diligently seek equivalent models of silenced PME that are quieter than the standard types given in the Technical Memorandum on Noise from Construction Works Other than Percussive Piling” (TM). Plants with lower noise levels than those given in the TM should be used wherever possible.

 

Phasing of Construction Activities & Reduce No. of Equipment working concurrently

2.9.4            As recommended in the EIA report, phasing of construction activities such that equipment servicing different purpose would not be operating concurrently shall be introduced as work procedure as far as practicable for noise mitigation purpose. Under certain work situations, the number of PME working concurrently shall also be reduced to minimize the cumulative noise impact.

 

Use of Temporary Noise Barriers and Machinery Enclosures

2.9.5            The erection of noise barriers between noise sources and the NSRs will be effective in reducing the noise impact.  Barriers should have no openings or gaps, and preferably have a superficial surface density of at least 7 kg/m2.  As recommended in the EIA report, a 6m high vertical noise barrier (or equivalent, if a cantilever type noise barrier is adopted) is recommended to be erected at the western site boundary along Shing Tai Road to shield the noise generated from noise activities generated behind the barrier.  The noise barrier can be incorporated into the design of the site hoarding along Shing Tai Road.  For maintaining the acoustic shielding effectiveness of the temporary noise barrier proposed, vehicular access to the construction site shall not be positioned at Shing Tai Road as far as practicable. 

2.9.6            If required, additional movable noise barriers can be temporarily erected at specific locations within the site in the proximity of noisy work areas, when generation of high noise levels is expected to be associated with certain construction activities, or identified through the Environmental Monitoring and Audit (EM&A) progamme.

 

Other Recommended Noise Mitigation Measures

2.9.7            To be prudent in the construction noise management, the following additional noise mitigation and good site practices are also recommended for implementation.

·        the Contractor shall comply with and observe the Noise Control Ordinance (NCO) and its current subsidiary regulations;

·        before the commencement of any work, the Contractor shall submit to the Engineer for approval the method of working, equipment and sound-reducing measures intended to be used at the site;

·        the Contractor shall devise and execute working methods that will minimise the noise impact on the surrounding environment; and shall provide experienced personnel with suitable training to ensure that these methods are implemented;

·        only well-maintained plants should be operated on-site;

·        plants should be serviced regularly during the construction programme;

·        machines that may be in intermittent use should be shut down or throttled down to a minimum between work periods;

·        silencer and mufflers on construction equipment should be utilised and should be properly maintained during the construction programme;

·        noisy activities can be scheduled to minimise exposure of nearby NSRs to high levels of construction noise. For example, noisy activities can be scheduled for midday or at times coinciding with periods of high background noise (such as during peak traffic hours);

·        noisy equipment such as emergency generators shall always be sited as far away as possible from noise sensitive receivers;

·        mobile plants should be sited as far away from NSRs as possible; and

·        material stockpiles and other structures should be effectively utilised as noise barrier, where practicable.

 

2.10             Construction Waste Management

Introduction

2.10.1         The Contractor is responsible for proper handling of excavated material, construction and demolition material (C&DM), chemical waste and general refuse within the construction site, for disposal offsite, and to implement measures to minimise waste generation.

2.10.2         The construction waste management measures recommended in the EIA report are summarized below.

 

Mitigation Measures

2.10.3         The overall construction management strategy shall be minimisation of waste generation, coupled with maximum reuse and recycling of construction and demolition materials onsite or offsite as far as practicable.  Contract requirements should include the responsibilities of the Contractor for waste collection and disposal.  The following measures are recommended at this planning stage for proper handling of waste material during the construction phase of the site formation works.

 

Waste Management Plan

2.10.4         To ensure the appropriate handling of different construction waste types, it is recommended that the contractor shall be required to implement the recommended waste management measures through establishing a waste management plan. The WMP shall be submitted to the Project Engineer at the commencement of the construction works for approval on the advice of DEP.

 

Overall Waste Management

2.10.5         Storage areas for different waste types - different types of waste should be segregated and stored in different containers, skips or stockpiles to enhance reuse or recycling of materials and their proper disposal.  An on-site temporary storage area equipped with required control measures (e.g. dust) should be provided;

2.10.6         Trip-ticket system - in order to monitor the disposal of inert C&DM at public filling facilities and the remaining C&D waste to landfills, and control fly-topping, a trip-ticket system should be included as a contractual requirements and audited by the Environmental Team;

2.10.7         Records of Wastes - a recording system for the amount of wastes generated, recycled and disposed (including the disposal sites) should be proposed;

2.10.8         Training - training should be provided to workers in respect of site cleanliness and appropriate waste management procedure, including waste reduction, reuse and recycling, and avoid contamination of reusable C&DM.

 

Construction & Demolition Material

2.10.9         A “selective demolition” approach is recommended for avoiding the mixing of reusable/ recyclable material with waste requiring disposal.

2.10.10      Surplus construction material, which may arise from construction preparatory works and actual construction activities, shall be minimised, reused or recycled as far as practicable.  These material may include:

·        Wood from formwork;

·        Surplus concrete or grouting mixes;

·        Damaged or contaminated construction materials;

·        Equipment and vehicle maintenance parts; and

·        Materials and equipment wrappings, etc.

 

2.10.11      Wherever practicable, the production of construction waste should be minimised by the contractor through careful design, planning, good site management, control of ordering procedures, segregation and reuse of materials.  These measures will also assist in minimising costs associated with the construction works.  For examples, wooden boards can be reused on-site or off-site, though the reusability and quantity of final waste will depend on the quality, size and shape of the boards.  Those timber which cannot be reused again shall be sorted and stored separate from all inert waste before disposed of in landfill. Arrangement could be made for private contractors to collect used formwork materials for reuse. On-site incineration of wooden waste is prohibited.

2.10.12      If feasible, noise enclosure or barriers used on-site should be designed so that they are reusable after they have been dismantled and removed.  Should construction site hoarding be erected, metal fencing or building panels, which are more durable than wooden panels, are recommended to be used where practicable.  Opportunity shall also be sought to re-use any wooden boards used in site fencing on-site or off-site.  Concrete and masonry can be crushed and used as fill material if practicable.

 

Chemical Waste

2.10.13      As defined under the Waste Disposal (Chemical Waste) (General) Regulation, chemical waste includes any substance being scrap material or unwanted substances specified under Schedule 1 of the Regulation.  Chemical waste could be generated from operation and maintenance of on-site equipment.  Chemicals generated from daily operation of the construction works shall be recycled/ reused on-site as far as practicable.

2.10.14      The amount of chemical waste that will be generated from the construction work will depend on the contractor’s on-site maintenance intention, age and number of plant and vehicles used.  Chemical wastes such as lubricating oil or solvent generated by workers are not expected to be in large quantity, given the nature of the construction activities involved.  The chemical waste types are expected to be readily accepted by licensed contractors in Hong Kong. 

2.10.15      If off-site disposal of chemical waste is required, they should be collected by licensed contractors for proper disposal in accordance with the Waste Disposal (Chemical Waste) (General) Regulation. Contractors shall register with EPD as chemical waste producers when disposal of chemical waste is anticipated to be required.  Chemical waste materials have to be stored on-site with suitable containers so that leakage or spillage is prevented during the handling, storage, and subsequent transportation.

2.10.16      Provided that the handling, storage and disposal of chemical wastes are in accordance with the Waste Disposal (Chemical Waste) (General) Regulation and the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes, it will not cause an unacceptable environmental impact.

General Refuse

2.10.17      Throughout the construction phase, the workforce on the construction site would likely generate a variety of general refuse requiring disposal.  These refuse will mainly consist of food wastes, aluminium cans, and waste paper, etc.  No information regarding the number of workers on-site is available at this feasibility study stage.  Assuming that 100 workers are working together at any one time, and a waste generation rate of about 0.6 kg per person, it is estimated that the amount of general refuse that would be generated is in the order of 60 kg per day.

2.10.18      General refuse generated at the construction site shall be stored separated from construction and chemical wastes to avoid cross contamination.  A reliable waste collector shall be employed by the Contractor to remove general refuse from the construction site on a daily basis where appropriate to minimise the potential odour, pest and litter impacts.  The segregation of aluminum cans or other recyclable material for recycling should be considered as far as practicable.

2.10.19      Wastewater effluent generated from the construction works shall be managed in accordance with the requirements under ProPECC Note PN1/94 “Construction Site Drainage”.  No effluent discharge shall be made into the embayed water of the Cargo Handling Basin, or stormwater drains at road carriageways and other public areas.

 

2.11             Landscape and Visual Issues

2.11.1         To mitigate the potential landscape impact, the carrying out of tree transplanting has been recommended in the study.  The tree transplanting works shall be carried out strictly according to the Transplanting Specification (Appendix D of the Tree Survey Report) under the close monitoring by a qualified architect or an arboriculturist. 

2.11.2         The qualified architect shall also monitor the planting of heavy standard Delonix regia recommended along the footpath of Road 20/4 and Shing Tai Road and the recommended compensatory planting with the site boundary taking into account the design of the building layout.

2.11.3         To ensure the visual compatibility with the surrounding environmental context, the Project Architect shall take into account in the building design the façade treatment required.  Strategies to be considered shall include the use of recessed grove lines to divide the wall into panels, so as to reduce its massive scale.  Colours will also be used to further break down the scale by means of spray-painting on plaster.  In addition to spray-painting, metal cladding, tiling will also be used for the main elevations facing Road 20/4 and Shing Tai Road, in order to add richness in texture and colour, so as to create an environmental in harmony with the surroundings.

 


2.12             Site Environmental Audit

Site Surveillance

2.12.1         Site surveillance provides a direct means to trigger and ensure the specified environmental protection and pollution control measures are in compliance with the contract specifications.  They shall be undertaken regularly and routinely by the ET to inspect the construction activities in order to ensure that appropriate environmental protection and pollution control mitigation measures are properly implemented by the Contractor in accordance with EM&A recommendations.  With well defined pollution control and mitigation specifications and a well established site inspection, deficiency and action reporting system, the site inspection is one of the most effective tools to enforce the environmental protection requirements on the construction site.

2.12.2         The ET leader is responsible for formulation of the environmental site inspection, deficiency and action reporting system, and for carrying out the site inspections under the EM&A works.  He shall, in consultation with the IC(E), prepare and submit a proposal on the site inspection, deficiency and action reporting procedures within 21 days of the construction contract commencement to the Contractor for agreement and to the ER for approval. 

2.12.3         Regular site inspections shall be carried out at least once per week.  The areas of inspection shall cover the environmental situation, pollution control and mitigation measures within the site, it should also review the environmental situation outside the site area which is likely to be affected, directly or indirectly, by the site activities.  The ET leader shall make reference to the following information in conducting the inspection:

a)           the EIA recommendations on environmental protection and pollution control mitigation measures with respect to air quality, noise, waste management and water quality, etc.;

b)           works progress and programme;

c)           individual works methodology proposals (which shall include proposal on associated pollution control measures);

d)           the contract specifications on environmental protection and pollution prevention control;

e)           the relevant environmental protection and pollution control laws; and

f)            previous site inspection results.

 

2.12.4         The satisfactory implementation of relevant recommended mitigation measures during the construction phase shall be checked during the ET’s regular site inspections during the relevant phases of construction works.

2.12.5         The Contractor shall update the ET on all relevant information of the construction contract for him to carry out the site inspections.  The inspection results and its associated recommendations on improvements to the environmental protection and pollution control works shall be submitted to the IC(E) and the Contractor in a site inspection proforma within 24 hours, for reference and for taking immediate action. The Contractor shall follow the procedures and time-frame as stipulated in the environmental site inspection, deficiency and action reporting system formulated by the ET to report on any remedial measures subsequent to the site inspections.

2.12.6         Ad hoc site inspections shall also be carried out by the ET and/or IC(E) if significant environmental problems are identified.  Inspections may also be required subsequent to receipt of an environmental complaint, or as part of the investigation work, as specified in the Action Plan for environmental monitoring and audit.

 


Compliance with Legal and Contractual Requirements

2.12.7         There are contractual environmental protection and pollution control requirements as well as environmental protection and pollution control laws in Hong Kong which the construction activities shall comply with.

2.12.8         The ET shall review the progress and programme of the works to check that relevant environmental laws have not been violated, and that any foreseeable potential for violating the laws can be prevented. 

2.12.9         The Contractor shall regularly copy relevant documents to the ET so that the checking work can be carried out.  The document shall at least include the updated Work Progress Reports, the updated Works Programme, the application letters for different licence/permits under the environmental protection laws, and all the valid licence/permit.  The site diary shall also be available for the ET’s inspection upon his request.

2.12.10      After reviewing the document, the ET shall advise the ER and the Contractor of any non-compliance with the contractual and legislative requirements on environmental protection and pollution control for them to take follow-up actions.  If the ET's review concludes that the current status on licence/permit application and any environmental protection and pollution control preparation works may not cope with the works programme or may result in potential violation of environmental protection and pollution control requirements by the works in due course, he shall also advise the Contractor and the ER accordingly. The review shall be copied to IC(E) for any follow-up action.

2.12.11      Upon receipt of the advice, the Contractor shall undertake immediate action to remedy the situation.  The ER shall check that appropriate action has been taken by the Contractor in order that the environmental protection and pollution control requirements are fulfilled.

 

Environmental Complaints

2.12.12      Complaints received on environmental issues shall be referred to the ET leader for carrying out complaint investigation procedures. The ET leader shall undertake the steps given below in a) to i) upon receipt of the complaints.  The complaint investigation procedures are also presented in form of a flow chart in Figure 2-7 for ease of reference.

a)           log complaint and date of receipt onto the complaint database and inform the IC(E) immediately;

b)          investigate the complaint to determine its validity, and to assess whether the source of the problem is due to works activities;

c)           if a complaint is valid and due to project works, identify mitigation measures in consultation with the IC(E);

d)          if mitigation measures are required, advise the Contractor accordingly;

e)           review the Contractor's implementation of the identified and required mitigation measures, and the current situation;

f)           if the complaint is transferred from EPD, submit interim report to EPD on status of the complaint investigation and follow-up action within the time frame assigned by EPD;

g)           undertake additional monitoring and audit to verify the complaint if necessary, and ensure that any valid reason for complaint does not recur through proposed amendments to work methods, procedures, machines and/or equipment, etc.;

h)          report the investigation results and the subsequent actions to the complainant (If the source of complaint is identified through EPD, the results should be reported within the time frame assigned by EPD); and

i)            log a record of the complaint, investigation, the subsequent actions and the results in the monthly EM&A reports.

2.12.13      During the complaint investigation work, the Contractor and ER shall co-operate with the ET leader in providing all the necessary information and assistance for completion of the investigation.  If mitigation measures (in consultation with the IC(E)) are required following the investigation, the Contractor shall promptly carry out the mitigation.  The ER shall check that the measures have been carried out by the Contractor.

 

Documentation

2.12.14      All documentation is required to be filed in a traceable and systematically manner and ready for inspection upon request. All Construction Phase EM&A results and findings shall be documented in the Construction Phase EM&A report prepared by the ET and endorsed by IC(E) prior to disseminate to the Contractor, ER and EPD.

 

2.13             Reporting

General

2.13.1         The following reporting requirements based upon a paper documentation approach.  However, the same information can be provided in an electronic medium upon agreeing the format with the ER and EPD. All the monitoring data (baseline and impact) shall also be submitted in diskettes in an agreed format.  This would enable a transition from a paper/historic and reactive approach to an electronic/real time proactive approach.

 

Baseline Monitoring Report

2.13.2         The ET Leader shall prepare and submit a Baseline Environmental Monitoring Report within 10 working days of completion of the baseline monitoring. Copies of the Baseline Environmental Monitoring Report shall be submitted to each of the four parties: the Contractor, the IC(E), the ER and EPD. The ET Leader shall liaise with the relevant parties on the exact number of copies needed.  The form and content of the report, and the representation of the baseline monitoring data to be submitted to EPD shall be agreed with EPD.

2.13.3          The baseline monitoring report shall include at least the following:

a)           up to half a page executive summary;

b)          brief project background information;

c)           drawings showing locations of the baseline monitoring stations;

d)          an updated construction programme with milestones of environmental protection/mitigation activities annotated;

e)           monitoring results (in both hard and diskette copies) together with the following  information:

-           monitoring methodology;

-           name of laboratory and types of equipment used and calibration details;

-           parameters monitored;

-           monitoring locations (and depth);

-           monitoring date, time, frequency and duration;

-           QA/QC results and detection limits.

f)           details on influencing factors, including:

-           major activities, if any, being carried out on the Site during the period;

-           weather conditions during the period;

-           other factors which might affect the results;

g)           determination of the Action and Limit Levels (AL levels) for each monitoring parameter and statistical analysis of the baseline data, the analysis shall conclude if there is any significant difference between control and impact stations for the parameters monitored;

h)          revisions for inclusion in the EM&A Manual; and

i)            comments and conclusions.

 

Monthly EM&A Reports

2.13.4         The results and findings of all EM&A work required in the Manual shall be recorded and submitted to the ET Leader. Based on these information a monthly EM&A reports shall be prepared by the ET Leader.  The EM&A report shall be prepared by A/ER and endorsed by IC(E) and submitted to EPD within 10 working days of the end of each reporting month, with the first report due in the month after construction commences.  A maximum of 4 copies of each monthly EM&A report shall be submitted to each of the four parties : the Contractor, the IC(E), the ER and EPD.  Before submission of the first EM&A report, the ET Leader shall liaise with the parties on the exact number of copies and format of the monthly reports in both hard copy and electronic medium required.

2.13.5         The ET Leader shall review the number and location of monitoring stations and parameters to monitor every 6 months or on as needed basis in order to cater for the changes in surrounding environment and nature of works in progress.

 

First Monthly EM&A Report

2.13.6         The first monthly EM&A report shall include at least the following :

a)           1-2 pages executive summary; 

- Breaches of AL levels;

- Complaint Log;

- Notifications of any summons and successful prosecutions;

- Reporting Changes;

- Future key issues.

b)          Basic Project Information

- Project organisation including key personnel contact names and telephone numbers;

- Construction Programme with fine tuning of construction activities showing the inter-relationship with environmental protection/mitigation measures for the month;

- Management structure;

- Works undertaken during the month.

c)           Environmental Status

- Works undertaken during the month with illustrations (such as location of works, daily

dredging/filling rates, percentage fines in the fill material used);

- Drawing showing the project area, any environmental sensitive receivers and the locations of the monitoring and control stations.

d)          Summary of EM&A requirements including:

- All monitoring parameters;

- Environmental quality performance limits (Action and Limit levels);

- Event-Action Plans;

- Environmental mitigation measures, as recommended in the project EIA study final report;

- Environmental requirements in contract documents;

e)           Implementation Status

- Advice on the implementation status of environmental protection and pollution control/mitigation measures including measures for ecological and visual impacts, as recommended in the project EIA study report, summarised in the updated implementation schedule.

f)           Monitoring Results (in both hard and diskette copies) together with the following information;

- Monitoring methodology;

- Name of laboratory and types of equipment used and calibration details;

- Parameters monitored;

- Monitoring locations (and depth);

- Monitoring date, time, frequency, and duration;

- Weather conditions during the period;

- Graphical plots of the monitored parameters in the month annotated against:

- Major activities being carried out on site during the period;

- Weather conditions that may affect the results;

- Any other factors which might affect the monitoring results;

- QA/QC results and detection limits.

g)           Report on Non-compliance, Complaints, Notifications of Summons and Successful Prosecutions

- Record of all noncompliance (exceedances) of the environmental quality performance limits (Action and Limit levels);

- Record of all complaints received (written or verbal) for each media, including locations and nature of complaints investigation, liaison and consultation undertaken, actions and follow-up procedures taken, results and summary;

- Record of all notifications of summons and successful prosecutions for breaches of the current environmental protection/pollution control legislations, including locations and nature of the breaches, investigation, follow-up actions taken, result and summary;

- Review of the reasons for and the implications of non-compliance, complaints, summons and prosecutions including review of pollution sources and working procedures;

- Description of the actions taken in the event of non-compliance and deficiency reporting and any follow-up procedures related to earlier non-compliance;

h)          Others

- An account of the future key issues reviewed from the works programme and work method statements;

- Advice on the solid and liquid waste management status;

- Submission of implementation status proforma, proactive environmental protection proforma, regulatory compliance proforma, site inspection proforma, data recovery schedule and complaint log summarizing the EM&A of the period.

 

Subsequent EM&A Reports

2.13.7         The subsequent monthly EM&A reports shall include the following :

a)           Executive Summary (1-2 pages)

- Breaches of AL levels

- Complaint Log

- Notifications of any summons and successful prosecutions;

- Reporting Changes

- Future key issues

b)          Environmental Status

- Construction Programme with fine tuning of construction activities showing the inter-relationship with environmental protection/mitigation measures for the month;

- Works undertaken during the month with illustrations including key personnel contact names and telephone numbers;

- Drawing showing the project area, any environmental sensitive receivers and the locations of the monitoring and control stations

c)           Implementation Status

- Advice on the implementation status of environmental protection and pollution control/mitigation measures including measures for ecological and visual impacts, as recommended in the project HA study report, summarised in the updated implementation schedule.

d)          Monitoring Results to provide monitoring results (in both hard and diskette copies) together with the following information

- Monitoring methodology

- Name of laboratory and types of equipment used and calibration details

- Parameters monitored

- Monitoring locations (and depth);

- Monitoring date, time, frequency, and duration;

- Weather conditions during the period;

- Graphical plots of the monitored parameters in the month annotated against:

- Major activities being carried out on site during the period;

- Weather conditions that may affect the results;

- Any other factors which might affect the monitoring results;

- QA/QC results and detection limits.

e)           Report on Non-compliance, Complaints, Notifications of Summons and Successful Prosecutions

- Record of all noncompliance (exceedances) of the environmental quality performance limits (Action and Limit levels);

- Record of all complaints received (written or verbal) for each media, including locations and nature of complaints investigation, liaison and consultation undertaken, actions and follow-up procedures taken, results and summary;

- Record of all notifications of summons and successful prosecutions for breaches of the current environmental protection/pollution control legislations, including locations and nature of the breaches, investigation, follow-up actions taken, result and summary;

- Review of the reasons for and the implications of non-compliance, complaints, summons and prosecutions including review of pollution sources and working procedures;

- Description of the actions taken in the event of non-compliance and deficiency reporting and any follow-up procedures related to earlier non-compliance.

f)           Others

- An account of the future key issues reviewed from the works programme and work method statements;

- Advice on the solid and liquid waste management status

- Submission of implementation status proforma, proactive environmental protection proforma, regulatory compliance proforma, site inspection proforma, data recovery schedule and complaint log summarizing the EM&A of the period.

g)           Appendix

- AL levels

- Graphical plots of trends of monitored parameters at key stations over the past four reporting periods for representative monitoring stations annotated against the following:

i) major activities being carried out on Site during the period;

ii) weather conditions during the period;

iii) any other factors which might affect the monitoring results

§        Monitoring schedule for the present and next reporting period

§        Cumulative statistics on complaints, notifications of summons and successful prosecutions

§        Outstanding issues and deficiencies

 


Quarterly EM&A Summary Reports

2.13.8         The quarterly EM&A summary report which should generally be around 5 pages (including about 3 of text and tables and 2 of figures) should contain at least the following listed information. Apart from these, the first quarterly summary report should also confirm that the monitoring work is proving effective and that it is generating data with the necessary statistical power to categorically identify or confirm the absence of impact attributable to the works

a)           up to half a page executive summary;

b)          basic project information including a synopsis of the project organisation, programme, contacts of key management, and a synopsis of work undertaken during the quarter;

c)           a brief summary of EM&A requirements including:

·      monitoring parameters;

·      environmental quality performance limits (Action and Limit levels); and

·      environmental mitigation measures, as recommended in the project EIA study final report;

d)          advice on the implementation status of environmental protection and pollution control/mitigation measures, as recommended in the project EIA study report, summarised in the updated implementation schedule;

e)           drawings showing the project area, any environmental sensitive receivers and the locations of the monitoring and control stations;

f)           graphical plots of the trends of monitored parameters over the past 4 months (the last month of the previous quarter and the present quarter) for representative monitoring stations annotated against;

·      the major activities being carried out on site during the period;

·      weather conditions during the period; and

·      any other factors which might affect the monitoring results;

g)           advice on the solid and liquid waste management status;

h)          a summary of non-compliance (exceedances) of the environmental quality performance limits (Action and Limit levels);

i)            a brief review of the reasons for and the implications of non-compliance including review of pollution sources and working procedures;

j)            for project where measurement of suspended solids is required, quarterly assessment of construction impacts on suspended solids at the project site, including, but not limited to, a comparison of the difference between the quarterly mean and 1.3 times of the ambient mean, which is defined as 30% increase of the baseline data or EPD data, of the related parameters by using appropriate statistical procedures. Suggestion of appropriate mitigation measures if the quarterly assessment analytical results demonstrate that the quarterly mean is significantly higher than the 1.3 on water quality times of the ambient mean (p < 0.05);

k)          a summary description of the actions taken in the event of non-compliance and any follow-up procedures related to earlier non-compliance;

l)            a summary record of all complaints received (written or verbal) for each media, liaison and consultation undertaken, actions and follow-up procedures taken;

m)         a summary record of all notifications of summons and successful prosecutions for breaches of the current environmental protection/pollution control legislations, locations and nature of the breaches, investigation, follow-up actions taken and results;

n)          comments (e.g. effectiveness and efficiency of the mitigation measures), recommendations (e.g. any improvement in the EM&A programme) and conclusions  for the quarter; and

o)          proponents' contacts and any hotline telephone number for the public to make enquiries.

 

Final EM&A Summary Reports

2.13.9         The final EM&A summary report shall include the following:

a)           an executive summary;

b)          basic project information including a synopsis of the project organisation, programme, contacts of key management, and a synopsis of work undertaken during the entire construction period;

c)           a brief summary of EM&A requirements including:

·      monitoring parameters;

·      environmental quality performance limits (Action and Limit levels); and

·      environmental mitigation measures, as recommended in the project EIA study final report;

d)          advice on the implementation status of environmental protection and pollution control/mitigation measures, as recommended in the project EIA study report, summarised in the updated implementation status proforma;

e)           drawings showing the project area, any environmental sensitive receivers and the locations of the monitoring and control stations;

f)           graphical plots of the trends of monitored parameters over the construction period for representative monitoring stations annotated against;

·      the major activities being carried out on site during the period;

·      weather conditions during the period; and

·      any other factors which might affect the monitoring results;

·      the return of ambient environmental conditions in comparison with baseline data.

g)           compare and contrast the EM&A data with the EIA predictions and annotate with explanation for any discrepancies;

h)          provide clear-cut decisions on the environmental acceptability of the project with reference to the specific impact hypothesis;

i)            advice on the solid and liquid waste management status;

j)            a summary of non-compliance (exceedances) of the environmental quality performance limits (Action and Limit levels);

k)          a brief review of the reasons for and the implications of non-compliance including review of pollution sources and working procedures;

l)            a summary description of the actions taken in the event of non-compliance and any follow-up procedures related to earlier non-compliance;

m)         a summary record of all complaints received (written or verbal) for each media, liaison and consultation undertaken, actions and follow-up procedures taken;

n)          review the monitoring methodology adopted and with the benefit of hindsight, comment on its effectiveness (including cost effectiveness);

o)          a summary record of all notifications of summons and successful prosecutions for breaches of the current environmental protection/pollution control legislations, locations and nature of the breaches, investigation, follow-up actions taken and results;

p)          review the practicality and effectiveness of the EIA princess and EM&A programme (e.g. effectiveness and efficiency of the mitigation measures), recommend any improvement in the EM&A programme;

q)          a conclusion to state the return of ambient and/or the predicted scenario as per EIA findings.

 

Forms to be Adopted

2.13.10      To facilitate the management of the EM&A programme for the construction works, the record forms presented in Appendix II (including those presented in the preceding section) should be adopted where applicable during the construction phase of the Project. These forms are listed as follows :

·        Implementation Schedule;

·        Implementation Status Proforma;

·        Data Recovery Schedule;

·        Site Inspection Proforma;

·        Proactive Environmental Protection Proforma;

·        Regulatory Compliance Proforma;

·        Compliant Log;

·        Sample Template for Interim Notifications of Environmental Quality Limited Exceedance;

·        Data Sheet for TSP Monitoring;

·        Noise Monitoring Field Record Sheet.

 

Data Keeping

2.13.11      The site document such as the monitoring field records, laboratory analysis records, site inspection forms, etc. are not required to be included in the monthly EM&A reports for submission.  However, the document shall be well kept by the ET and be ready for inspection upon request.  All relevant information shall be clearly and systematically recorded in the document.  The monitoring data shall also be recorded in magnetic media form, and the software copy can be available upon request.  All the documents and data shall be kept for at least one year after completion of the construction contract.

 

Interim Notifications of Environmental Quality Limit Exceedances

2.13.12      With reference to Event/Action Plans in previous sections, when the environmental quality limits are exceeded, the ET shall immediately notify the ER & EPD, as appropriate.  The notification shall be followed up with advice to EPD on the results of the investigation, proposed action and success of the action taken, with any necessary follow-up proposals.  A sample template for the interim notifications is shown in Figure 2-8.



3.                   Environmental Management System

3.1                Introduction

3.1.1            Section 5 of the EIA Study Brief requires the project proponent to describe an appropriate Environmental Management System (EMS) to be implemented for managing the environmental impacts that may arise from the proposed bus depot development.

3.1.2            The appointed Contractor will be required under the requirements of the Contract Specification to implement the environmental control/ mitigation measures recommended in the EIA during the construction phase of the project.  The implementation of sufficient mitigation measures will be checked by the Environmental Monitoring and Audit (EM&A) requirements as set out in the preceding section.  The further establishing of an EMS during the construction phase is not considered necessary for ensuring compliance with the relevant environmental standards and guidelines. 

3.1.3            The EMS presented here relates to the operational phase of the proposed bus depot.  The purpose of setting up this EMS is to achieve that the long-term operation of the bus depot will not only satisfy the relevant environmental legislation and regulations currently enforced in Hong Kong, but also conform to the Environmental Policy to be established by the project proponent.  The establishment of this Environmental Policy is not a statutory requirement but reflects the project proponent’s commitment to taking the relevant environmental factors into consideration as appropriate in the operation of the bus depot development.

 

3.2                Identification of Key Environmental Factors

3.2.1            The key environmental issues associated with the operation of the bus depot have been assessed in the EIA study.  These environmental issues and the key findings of the assessments are summarized below:

§             Vehicular Emissions from Buses Operation

The findings of the EIA study revealed that bus operation within the depot and in the vicinity road carriageways will not pose any significant cumulative air quality impact on the surrounding air sensitive receivers.  Taking into account the background air pollutant concentrations, the modeling results show the relevant Air Quality Objectives are well satisfied.

 

§             Traffic Noise from Buses Operation  

The findings of the EIA study revealed that with appropriate consideration on the bus routes entering/ leaving the bus depot, future bus operation will not pose any significant contribution to the overall traffic noise levels on the nearby Noise Sensitive Receivers (NSRs).

 

§             Noise from fixed noise sources at the Bus Depot  

In the presence of other planned future landuses, the building façade on the north-eastern and south-western sides of the bus depot building (G/F and 1/F) will be constructed in form of a solid wall.  This will help to prevent the generation of any unacceptable noise impact from the depot providing shielding to noise sensitive receivers situated to the north-east (Heng Fa Chuen) and south-west (Tsui Wan Estate) of the site. The findings of the assessment presented in the EIA report revealed that fixed plant noise generated from the operation of the bus depot will unlikely exceed the relevant noise limits.

 

§             Waste Management

Chemical waste generation and disposal was identified to be the key interest.  Unacceptable impact is not expected provided that the chemical wastes are managed in accordance with the requirements under the Waste Disposal (Chemical Waste) (General) Regulation and Code of Practice on the Packaging, Labelling ad Storage of Chemical Waste published by EPD.

 

§             Land Contamination Prevention

Proper design, use, and maintenance of the onsite diesel fuel tanks and associated pipelines, training of staff engaged in bus refueling activities, and proper management of chemicals used on site will significantly minimize the land contamination potential caused by the operation of the bus depot.

 

§             Wastewater Treatment and Disposal

Sewage generated from designated bus washing areas will be properly pretreated by petrol interceptors or by grease traps for kitchen areas before discharged into government sewers.  Stormwater collected at the roof floor level with bus parkings will also be diverted to petrol interceptors before discharge.  With the appropriate design, provision and maintenance of these sewage and drainage facilities, operation of the bus depot will unlikely pose any unacceptable water quality impact.

3.2.2            It can be noted that the identified potential environmental impacts associated with the operation of the bus depot are either identified to be within acceptable (and with a significant margin between the predicted impact levels and the relevant acceptable standards specified in the EIAO-TM), or there exists reliable (standard) control/ mitigation measures to prevent the occurrence of any unacceptable environmental impact. 

3.2.3            The implementation of the required mitigation measures will be controlled by the Environmental Permit system under the EIA Ordinance.  The setting up of an “impact-mitigation oriented” EMS to be established by the project proponent during the operational phase will give added benefits to achieve effective implementation of sufficient control/ mitigation measures target to achieve not only compliance with the relevant regulatory environmental requirements, but also continual improvements with respect to the implementation of the recommended control/ mitigation measures.

3.2.4            It is considered that the setting up of a full EMS programme to also cover other environmental aspects (e.g. energy consumption, use of natural resources, etc.) to allow the EMS to be possibly certified to an International Standard by a third party is not considered necessary, as the implementation of the recommended mitigation measures/ control measures recommended in the EIA report will be controlled by the environmental permit conditions and facilitated by this impact-mitigation oriented EMS.

3.2.5            Table 3-1 summarises the key environmental factors and the associated environmental mitigation strategy recommended to be included in establishing the EMS as appropriate.  It is recommended that the exact environmental issues to be covered in the EMS shall be reviewed at the detailed design stage and operational phase by the project proponent to maintain their relevance, practicability and effectiveness in achieving the Environmental Policy in addition to the relevant current environmental legislation and regulations.


Table 31       Summary of Key Environmental Factors and Environmental Mitigation Strategy to be included in the EMS

Key Environmental Factors

Environmental Mitigation Strategy

Air Quality – Bus Emission

§     Implement a maintenance programme to ensure that the bus engines are performing within acceptable standards

§     Implement a fleet rejuventation programme by regularly introduce new and environmentally friendly buses;

§     Introduce use of Euro III engines for new buses;

§     Ensure that by upgrading if necessary all existing buses have engines that can meet the Euro standards;

§     Installation of catalytic converters for buses to enable a further reduction in exhaust emissions;

§     Introduce the use of ultra-low sulphur diesel (with the sulphur content reduced from the normal statutory requirement of 0.035% to 0.005% for all operating buses.

 

Air Quality – Depot Emission

§     Idling emissions should be minimized by requiring all drivers to switch off the bus engines while waiting;

§     Mechanical ventilation required at specific locations shall be properly designed.  Exhaust air outlets shall be located away from nearby air sensitive receivers to avoid causing any unacceptable nuisance;

§     Fresh air inlets should be located so that they can capture fresh air comparable to the ambient air quality levels.  The fresh air inlet louvers shall be located away from major air emission sources including exhaust air outlets;

§     The mechanical ventilation system shall be regularly inspected and maintained to ensure proper operation and minimize breakdown time to ensure the keeping of an acceptable air quality within the bus depot;

 

Noise – Traffic Noise

§     Buses drives will be required to strictly follow the bus route plan agreed with TD in approaching/ leaving the bus depot;

§     Bus drivers arriving the depot from Siu Sai Wan or leaving for Siu Sai Wan will be required to route through the future Sheung On Street Extension and Road 20/4 at all time periods during normal operation, instead of the existing Wing Tai Road and Shing Tai Road; 

§     Bus drivers will be required to avoid generation of excessive noise when approaching or leaving the bus depot by driving in a proper speed in a steady manner, and avoid unnecessary acceleration and resultant use of brakes as far as practicable especially during early morning hours and at midnight peak hours;

 

 

Noise – Fixed Plant Noise

§     Brake testing and engine testing activities shall be scheduled to operate mainly during daytime and evening as far as practicable.  Activities during the nighttime period should be minimised;

 

 

Chemical Waste Management

§     Minimise generation of chemical waste through reducing the quantity in use and maximize reuse and recovery of used material as far as practicable.

 

Diesel Fuel or Chemical Spillage

§     Adopt best practices and comprehensive training to the relevant staff engaged in the works to minimize the chance of spillage.

 

 

3.3                Time Schedule for Setting Up the EMS

3.3.1            Development of an EMS prior to commencement of operational activities at the bus depot is considered unusual.  The EMS, environmental policy and environmental factors and the programme are recommended to be reviewed during the detailed design stage and then further developed during the operational phase.  This will allow a practicable, reasonable and effective system be gradually evolved and that new or revised environmental factors be incorporated into the plan to effect the achievement of the environmental policy, and continuous improvement.  The prime objectives are to ensure that the relevant control measures recommended in the EIA in relation to the operational phase of the development can be effectively implemented to further ensure that no unacceptable environmental impacts will be generated during the operational phase of the bus depot.

 

 

 

 


 



[1] For the purpose of this manual, the “Engineer” shall refer to the Engineer as defined in the Contract and the Engineer's Representative (ER), in cases where the Engineer's powers have been delegated to the ER, in accordance with the Contract. 

[2] The Environmental Team (ET) leader, who shall be responsible for and in charge of the ET, refers to the person delegated the role of executing the environmental monitoring and audit requirements.