Drainage
Services Department
Consultants
Management Division
42/F,
Wanchai,
Agreement No. CE 80/2001(DS)
Drainage Improvement in
Tsuen Wan and Kwai Chung –
Tsuen Wan Drainage Tunnel
Environmental Impact
Assessment - Executive Summary
Document No. 204417/18/B
June 2005
Mott
Connell Limited
40/F,
183
Queen’s Road East
Wan
Chai,
This
document has been prepared for the titled project or named part thereof and
should not be relied upon or used for any other project without an independent
check being carried out as to its suitability and prior written authority of
Mott Connell Ltd being obtained. Mott
Connell Ltd accepts no responsibility or liability for the consequence of this
document being used for a purpose other than the purposes for which it was
commissioned. Any person using or
relying on the document for such other purpose agrees, and will by such use or
reliance be taken to confirm his agreement to indemnify Mott Connell Ltd for
all loss or damage resulting therefrom. Mott Connell Ltd accepts no
responsibility or liability for this document to any party other than the
person by whom it was commissioned.
Chapters
E.3 Intake/Outfall
Locations and Tunnel Alignment
E.13 Environmental
Monitoring and Audit
Figures
Figure 1 Proposed Drainage Tunnel General Layout
Figure 2 Proposed Intake I-1 Layout Plan
Figure 3 Proposed Intake I-2 Layout Plan
The Drainage
Services Department (DSD) completed the “Stormwater Drainage Master Plan (DMP)
Study in Tsuen Wan, Kwai Chung and Tsing Yi” in July 1999. In that Study it was
identified that the drainage systems in Tsing Yi could meet the current flood
protection standard in general, but not the drainage systems in Tsuen Wan and
Kwai Chung. A series of drainage
improvement works including the “Drainage Improvement in Tsuen Wan and Kwai
Chung – Tsuen Wan Drainage Tunnel” (The Project) and the “Drainage Improvement
in Tsuen Wan and Kwai Chung – Urban Drainage Improvement Works” were proposed,
and subsequently DSD commissioned a Preliminary Project Feasibility Study
(PPFS) for “Drainage Improvement in Tsuen Wan and Kwai Chung – Package A, Tsuen
Wan Drainage Tunnel” which was completed in April 2000.
The PPFS concluded
that the construction of a tunnel of an internal diameter of 6.5m and length
5.35km should be implemented to alleviate the flooding risk in Tsuen Wan and
Kwai Chung. At the end of October 2002,
Mott Connell Limited (MCL) was commissioned by the Drainage Services Department
under Agreement No. CE 80/2001 (DS) to carry out the investigation and preliminary
design for the “Drainage Improvement in Tsuen Wan and Kwai Chung – Tsuen Wan
Drainage Tunnel” (The Project).
The primary
objective of the Project is to develop an optimum preliminary design of the
proposed tunnel and associated drainage structures based on the recommendations
of the Preliminary Project Feasibility Study Report (PPFS), the Stormwater
Drainage Master Plan Study in Tsuen Wan, Kwai Chung and Tsing Yi (DMP) and the
results of the various investigations to be carried out under this Assignment. This Environmental Impact Assessment (EIA) is
a key submission of the project and has been prepared in conjunction with other
design teams including the drainage, geotechnical and landscape teams.
The proposed
drainage improvement works comprise a tunnel and associated intakes and outfall
structures (shown in Figures 1-5).
The scope of
construction works for the tunnel development comprises:
·
5.13km drainage tunnel system between Kwai Chung
and Yau Kom Tau (reduced from 5.35km during preliminary design);
·
provision of three Intake locations:
i. Intake
I-1: Kwai Chung, adjacent to the junction of
ii Intake
I-2: At Lo Wai, adjacent to
iii Intake
I-3: At Tso Kung Tam, about 350m off Route Twist.
·
provision of Outfall O-1: Yau Kom Tau,
underneath the existing
·
provision of associated environmental mitigation
measures.
In October 2002,
DSD appointed Mott Connell Limited (MCL) to carry out the investigation, preliminary
design and Environmental Impact Assessment (EIA) for the Project. This report
presents the findings of the EIA which was carried out as an integral part of
the Project and makes reference to other related documents and reports which
were also prepared under the auspices of this Project.
Throughout the
development of the project various alignments and intake/outfall locations have
been considered. Final options selection report for intake/outfall locations
and tunnel alignment was completed in June 2003. This detailed environmental
impact assessment has been examined the impacts associated with the preferred
scheme from the Options Selection Report. The conclusions of the individual
assessments, which have been carried out in accordance with the Study Brief,
are given in the following paragraphs.
Tunnel and Underground Structures
The main tunnel
will be constructed using a Tunnel Boring Machine (TBM). The direction of drive
of the TBM excavation will be from outfall O-1 to Intake I-1. Other than the
main tunnel, there are other ancillary underground structures including man access vertical shaft and storm water drop shaft
which need to be constructed.
Intake I-1
Most of the works
at Intake I-1 including the construction of maintenance works area and spiral
access ramp will be undertaken on sloping area which mainly involve slope
cutting works, installation of soil nails, construction of retaining walls,
site formation and excavation, and pilings.
Intake I-2
The construction
activities in Intake I-2 will mainly involve the channel modification works,
construction of retaining wall on the western side of the channel, vortex
chamber and its associated on-line approach channel, the drop shaft and
underground de-aeration chamber, the man access shaft and connecting tunnel.
Intake I-3
Intake I-3 mainly
involves the construction of the vortex chamber and its associated on-line
approach channel, drop shaft, aeration chamber and audit tunnel, access road
and slope works.
Outfall O-1
The works at
Outfall O-1 will include the construction of tunnel portal, cascade, box
culvert underneath the improved
The construction
of the Project may lead to dust generation. It is predicted that various
construction activities associated with the earthworks, material handling and
tunnel construction would cause temporary minor impacts. “Best practice measures” are recommended to
suppress dust emissions from construction activities through good site
practice.
The construction
of the Project may lead to noise generation if noise mitigation measures are
not undertaken. It is predicted that
various construction activities associated with the earthworks, excavation and
construction may cause temporary impacts without mitigation. “Best practice
measures”, quiet plant and mobile noise barriers are recommended to suppress
noise emissions from construction activities where noise exceedance is
anticipated.
With appropriate
mitigation and precautions measures in place during construction there should
be relatively minor impacts associated with this project during or following
construction. In the operational phase, the impacts from stormwater discharge
are anticipated to be negligible.
The potential
environmental impacts with the handling and disposal of waste arising from the
construction the Tsuen Wan Drainage Tunnel have been assessed. Operational impacts on the proposed route are
not expected to be a key concern and no detailed assessment will be
required. Key issues include the need
for effective waste management planning during the construction phase. The assessment has concluded that the
potential environmental impacts associated with the handling, storage,
treatment and disposal of waste arising for the construction of the Tsuen Wan
Drainage Tunnel meet the requirements of the Technical Memorandum on
Environmental Impact Assessment Process.
The ecological
resources recorded within the Study Area included woodland, plantation,
grassland, village-orchard, stream channel, intertidal habitat
(artificial/disturbed seashore) and disturbed/urbanized, as well as the
associated wildlife. Of these habitats,
woodland and stream habitat (Sam Dip Tam Stream and Tso Kung Tam Stream) have
moderate ecological value. The remaining
habitats are of low to moderate ecological value. With the exception of low to
moderate impact to the middle course of Sam Dip Tam Stream (location of Intake
I-2) and Tso Kung Tam Stream (location of Intake I-3), the direct ecological
impact due to the construction and operation of the drainage channel is
expected to be low. No rare or protected
species near the works areas are affected by the proposed works. The loss of
stream sections of natural bottom and bank and hydrological disruption to the
natural stream habitats downstream to the intake structures, particularly
Intakes I-2 and I-3, have been minimised and properly mitigated. No adverse
residual impact is expected after the implementation of the recommended
mitigation measures. Since the affected sections of Sam Dip Tam Stream and Tso
Kung Tam Stream (location of Intakes I-2 and I-3) are partially disturbed (with
relatively less aquatic faunal diversity) due to the residential sewage and the
intake structures have been appropriately designed to minimise habitat loss,
the impacts due to the land take for the surface structures and hydrological
disruption are considered acceptable. Adverse ecological impacts on the
proposed
A
literature review supplemented by an archaeological investigation identified no
sites of archaeological significance in the Study Area. No mitigation measures for archaeological
resources are considered necessary.
One Grade III
building (Po Kwong Yuen Monastery at Lo Wai) and 86 historical buildings and
structures were identified within the Study Area during the built heritage
survey. Most of the identified sites
except a few sites at Lo Wai, Sam Dip Tam and Yau Kom Tau settlement areas are
located over 70 m from the Preferred Option of the drainage tunnel alignment
and the associated Intakes/Outfall construction activities.
Potential
vibration impact on a number of historical buildings and structures at Lo Wai, Sam
Dip Tam and Yau Kom Tau has been identified and appropriate mitigation measures
have been recommended including the adoption of construction methods that
minimises generation of excessive vibration, a pre-construction survey to
establish the existing condition of the potentially affected buildings and
vibration monitoring as part of the Environmental Monitoring and Audit
programme.
According to the
EIA Study Brief, evaluation of Hazard to Life as the criteria specified is
considered not necessary since no overnight storage of explosives is
anticipated for this project. In addition, with the stringent control and
monitoring procedures in place, adverse impact on populated area or on
Potential Hazardous Installations nearby due to the blasting operation is
unlikely.
Reviews of
existing information on commercial fisheries resources and fishing operations
located within the Study Area have been undertaken. Information from a study on fishing
operations in
The construction
and operation of the Project will not give rise to impacts to fisheries, as
there is no predicted adverse impact to water quality or habitat loss.
No special
mitigation measures are required for fisheries resources, mitigation measures
recommended to reduce impacts to water quality are also expected to mitigate
any impacts to fisheries resources. The availability of literature on the
fisheries resources of the Study Area comes mainly from the AFCD.
Environmental
monitoring and audit procedures have been identified for the specific
confirmation of the mitigation and protection measures proposed with emphasis
being placed on air quality, noise, vibration, water quality and
ecology. Routine monitoring is also recommended for confirming the
mitigation measures are being implemented correctly and as effectively as
predicted.
The EIA has been completed in accordance with the
requirements of the EPD Study Brief No. ESB-069/2001. A tunnel alignment
between Tsuen Wan and Kwai Chung has been proposed which has least impact on
the environment while avoidance or minimisation of environmental aspects
underpinning the entire process of options selection. In keeping with the basic
tenets of the DSD’s Environmental Policy and the principle of avoidance or
minimisation, the Drainage Tunnel has been designed to minimise environmental
and ecological impacts and minimise waste generation.
The EIA has surmised that provided the recommended
mitigation measures are implemented, there will be no significant impacts of
the construction or operation of the Tsuen Wan drainage tunnel on the alignment
between Tsuen Wan and Kwai Chung or at the intake/outfall locations. Assuming
the mitigation proposed within this EIA the drainage tunnel can be constructed
and operated within acceptable standards.
Early discussions have been held with relevant Government Departments to consider the views and opinions on the intake/outfall locations and the alignment. The feedback has been used in the assessment of the Project and has allowed design principles to be developed and avoidance of conflicts where possible.