TABLE OF CONTENTS
1. INTRODUCTION.. 1
1.1 Background. 1
1.2 Project Objectives. 1
1.3 Nature of the Project 1
1.4 Purpose of EIA Study. 1
1.5 The Approach. 1
1.6 Mitigation Measures. 2
1.7 Reference to Relevant
Study. 2
1.8 Scope of Key Environmental
Issues. 2
2. description of the project.. 4
2.1 Location and Description
of the Project 4
2.2 Identification of the
Project Need. 4
2.3 Considerations for Design
Options. 5
2.4 Alternative Options for
Entrance and Subway Alignment 9
2.5 Considerations of Alternative
Construction Methods. 10
2.6 The Preferred Scheme. 10
2.7 Implementation and
Planning of the Proposed Project 13
3. construction air quality impact.. 14
3.1 Introduction. 14
3.2 Environmental
Legislation, Standards and Guidelines. 14
3.3 Description of the
Environment 15
3.4 Air Sensitive Receivers. 15
3.5 Identification of
Pollutant Sources. 16
3.6 Assessment Methodology. 17
3.7 TSP Daily Concentration. 19
3.8 Evaluation of Impacts. 19
3.9 Cumulative Impacts. 20
3.10 Mitigation of Adverse Environmental
Impacts. 20
3.11 Evaluation of Residual Impacts. 21
3.12 Environmental Monitoring and Audit 21
4. NOISE IMPACT.. 22
4.1 Introduction. 22
4.2 Environmental
Legislation, Policies, Plans, Standards and Criteria. 22
4.3 Construction Noise –
General Construction Works. 22
4.4 Fixed Noise in Operation
Phase. 24
4.5 Noise Sensitive Receivers. 24
4.6 Assessment Methodology. 26
4.7 Identification of
Environmental Impacts. 29
4.8 Prediction and Evaluation
of Environmental Impacts. 29
4.9 Mitigation of Adverse
Environmental Impacts. 31
4.10 Evaluation of Residual Impacts. 34
4.11 Environmental Monitoring and Audit 37
4.12 Conclusion. 37
5. construction water quality impact.. 39
5.1 General 39
5.2 Environmental Legislation
and Standards. 39
5.3 Environmental Impact
Assessment Ordinance (EIAO), Cap. 499, S.16. 39
5.4 Water Pollution Control
Ordinance (WPCO) 39
5.5 Technical Memorandum.. 40
5.6 Practice Notes. 41
5.7 Baseline Condition. 41
5.8 Assessment Methodology. 42
5.9 Identification of Water
Sensitive Receivers. 42
5.10 Potential Sources from Construction
Activities. 42
5.11 Evaluation of Potential Water Quality
Impacts. 43
5.12 General Construction Site Activities. 44
5.13 Mitigation Measures. 44
5.14 General Construction Site Activities. 46
5.15 Evaluation of Residual Impacts. 46
5.16 Environmental Monitoring and Audit 46
5.17 Conclusions. 46
6. waste management.. 47
6.1 Introduction. 47
6.2 Environmental Legislation
and Standards. 47
6.3 Waste Management 47
6.4 Construction and
Demolition (C&D) Materials. 48
6.5 Assessment Methodology. 48
6.6 Prediction and Evaluation
of Environmental Impacts. 48
6.7 Mitigation Measures. 51
6.8 Evaluation of Residual
Impacts. 52
6.9 Environmental Audit 53
6.10 Conclusion. 53
7. Landscape and Visual Impact assessment.. 54
7.1 Introduction. 54
7.2 Environmental
Legislation, Standards and Guidelines. 54
7.3 Assessment Methodology. 55
7.4 Scope and Content of the
Study. 59
7.5 Review of Planning and
Development Control Framework. 59
7.6 Baseline Study. 60
7.7 Landscape Impact
Assessment 64
7.8 Visual Impact Assessment 71
7.9 Conclusion. 77
8. BUILT HERITAGE IMPACT ASSESSMENT.. 78
8.1 Introduction. 78
8.2 Environmental Legislation
and Standards. 78
8.3 Assessment Methodology. 79
8.4 Results of the Desk Based
Study. 80
8.5 Results of the Field
Survey. 82
8.6 Prediction and
Identification of Impacts. 82
8.7 Evaluation of Impacts. 83
8.8 Mitigation
Recommendations. 85
8.9 Conclusions. 85
9. environmental monitoring and audit (EM&A)
Requirements.. 86
9.1 Introduction. 86
9.2 Construction Air Quality
Impact 86
9.3 Noise Impact 86
9.4 Construction Water
Quality Impact 87
9.5 Waste Management 87
9.6 Landscape and Visual
Impact 87
9.7 Built Heritage Impact 88
10. ConclUsions And rEcommendations.. 89
LIST OF TABLES
Table 2.1 Summary
of the Preferred Scheme
Table 2.2 Preliminary
Construction Programme
Table 3.1 Hong Kong Air Quality Objectives
Table 3.2 Annual
Average TSP Concentration in the Latest Five Years (Year 2002 – 2006) for Urban
Development
Table 3.3 Details
of Representative Air Sensitive Receivers
Table 3.4 Emission
Factors for Construction Activities
Table 3.5 Predicted
Maximum 1 - hour Average TSP Concentrations
Table 3.6 Predicted
Maximum 24 - hour Average TSP Concentrations
Table 4.1 Daytime
Construction Noise Criteria
Table 4.2 Acceptable
Noise Levels
Table 4.3 Acceptable
Noise Level for Fixed Plant Noise
Table 4.4 Summary
of Representative Noise Sensitive Receivers
Table 4.5 Construction
Tasks Involved
Table 4.6 Ventilation
Shafts for the Proposed Project
Table 4.7 Summary
of Unmitigated Construction Noise Levels at Representative NSRs During Normal Daytime Working Hours
Table 4.8 Summary
of Max SWL for Each Ventilation Shaft
Table 4.9 Summary
of Max SWL for Each Ventilation Shaft with Consideration of Cumulative Effect
Table 4.10 Quieter
PME Recommended for Adoption during Construction Phase
Table 4.11 Noise
Mitigation Measures for Certain PME during Construction Phase
Table 4.12 Mitigated
Construction Noise Levels
Table 4.13 Construction
Noise Residual Impacts
Table 4.14 Durations
of Construction Noise Residual Impacts
Table 4.15 Construction
Noise Residual Impacts at NSR N5
Table 5.1 Summary
of Water Quality Objectives for Victoria Harbour WCZ
Table 5.2 Marine
Water Quality of Victoria Harbour WCZ at
the Selected Monitoring Station in 2006
Table 6.1 Estimated
Quantities of C&D Materials
Table 7.1 Relationship
between Receptor Sensitivity and Impact Magnitude in Defining Impact
Significance
Table 7.2 List
of the Landscape Resources and Their Sensitivity to Change
Table 7.3 Visual
Sensitive Receivers (VSRs) and Their Sensitivity to Change
Table 7.4 Significant
Landscape Impacts of the Proposed Works during Construction Phase
Table 7.5 Proposed
Construction Phase Landscape Mitigation Measures
Table 7.6 Proposed
Operation Phase Landscape Mitigation Measures
Table 7.7 Significance
of Landscape Impacts in the Construction and Operation Phases
Table 7.8 Significance
of Visual Impacts in the Construction and Operation Phases
Table 8.1 Distance
of the Identified Resources in the Project Study Area from the Proposed Works
Table 10.1 Summary
of Key Environmental Outcomes
LIST OF FIGURES
Figure 1.1 Site
Layout Plan
Figure 1.2 Section
A-A
Figure 1.3 Section
B-B
Figure 1.4 Section
C-C
Figure 1.5 Study
Boundary for Air Quality, Noise and Water Quality Assessment
Figure 2.1 Construction
Sequence – Plant Basement
Figure 2.2 Construction
Sequence – Satellite Concourse
Figure 3.1 Locations
of Representative Air Sensitive Receivers
Figure 3.2 Contours
of Maximum 1-Hour Average TSP Concentration at 1.5m Above Ground
Figure 3.3 Contours
of Maximum 24-Hour Average TSP Concentration at 1.5m Above Ground
Figure 4.1 Locations
of Representative Noise Sensitive Receivers
Figure 4.2 Schematic
Diagram Showing Typical Site Arrangement
Figure 4.3 Schematic
Diagram Showing Typical Site Arrangement
Figure 4.4 Assumed
Worst Locations of Ventilation Shaft Openings
Figure 5.1 Locations
of Marine Water Quality Monitoring Stations in Victoria Harbour WCZ (VM5 &
VM6)
Figure 7.1 Landscape
and Visual Impact Study Area
Figure 7.2 Baseline
Landscape Resources
Figure 7.2.1 Baseline
Landscape Resources Photos
Figure 7.2.2 Baseline
Landscape Resources Photos
Figure 7.2.3 Baseline
Landscape Resources Photos
Figure 7.2A Aerial
Photograph Showing Baseline Landscape Characters and Resources
Figure 7.3 Key
VSRs and Zone of Visual Influence During Construction and Operation
Figure 7.3.1 Baseline
VSRs Photos
Figure 7.3.2 Baseline
VSRs Photos
Figure 7.4 Propose
Landscape Mitigation Measure
Figure 7.4.1 Photomontage
A
Figure 7.4.2 Photomontage
B
Figure 7.4.3 Photomontage
C
Figure 8.1 Enhanced
Entrance A1
Figure 8.2 Enhanced
Entrance A1 (View from NE Corner)
LIST OF APPENDICES
Appendix 3.1 Construction
Dust Emission Factors
Appendix 4.1 Photographs of Representative Noise Sensitive Receivers
Appendix
4.2 Plant
Inventory for Construction Noise Assessment (Unmitigated)
Appendix 4.3 Calculation
of Construction Noise Levels at Representative Noise Sensitive Receivers During
Normal Daytime Working Hours (Unmitigated Scenario)
Appendix 4.4 Plant
Inventory for Construction Noise Assessment (Mitigated)
Appendix 4.5 Calculation
of Construction Noise Levels at Representative Noise Sensitive Receivers During
Normal Daytime Working Hours (Mitigated Scenario)
Appendix 8.1 Figures
of Built Heritage Impact Assessment
Appendix 8.2 Catalogue
of the resources surveyed for the Project
Appendix 8.3 Photographs of the
existing environment
Appendix 10.1 Implementation
Schedule of the Proposed Mitigation Measures
Hayes, J 1966 Old
British Kowloon, Journal of the Hong Kong Royal Asiatic Society, Vol VI
pp.120-137
1.1.1
The title of this project is known as “Tsim Sha Tsui Station Northern Subway”
(TNS) (hereafter known as the Project). The Project Proponent is MTR Corporation
Limited (MTRCL). ENSR Asia (HK)
Limited has been commissioned to carry out an Environmental Impact Assessment
Study for the Project.
1.2.1
The
objectives of this Project are to
provide passengers with a direct and accessible safe pedestrian subway in
addition to the existing entrances and to relieve the existing busy northern
concourse and platform areas of Tsim Sha Tsui (TST) Station by providing a new
direct high-capacity corridor for effective passenger access. The location of the proposed Project is shown in Figure 1.1. Three cross sections of the Project are
shown in Figures 1.2 to 1.4.
1.3.1
The Project is classified as a
Designated Project under Category A.2 (A railway and its associated stations)
of Part 1, Schedule 2 of the EIAO.
1.3.2
The Project involves construction and operation of (i) An
underground pedestrian subway link that connects the north end of the TST
Station platform with integrated entrances in the basements of the Tung Ying Building Redevelopment, Miramar Hotel and
Miramar Shopping Centre; (ii) An underground satellite concourse underneath
Nathan Road located adjacent to Tung Ying
Building and the Miramar Hotel; and (iii) A new plant basement near existing
Entrance A1 to house the station equipment relocated from the north end of TST
Station for accommodating the TNS connection.
1.4
Purpose of EIA Study
1.4.1
The purpose of this EIA Study
is to provide information on the nature and extent of environmental impacts
arising from the construction and operation of the proposed subway works, and
to contribute to decisions on the overall acceptability of the Project, after
the implementation of proposed mitigation measures.
1.5.1
The EIA study has been prepared
in accordance to the EIA Study Brief (No. ESB-168/2007) and the guidelines
provided in Annex 11 of the Technical Memorandum on Environmental Impact
Assessment Process (EIAO-TM) for the report contents and Annexes 12 to 19 for
the impact assessments of various environmental issues. The general approaches and methodologies
adopted for this EIA study are described below.
Existing
Environment Condition
1.5.2
The characteristics of the
existing environment were reviewed for identification and prediction of
environmental impacts. The baseline
conditions of the key issues as identified in the EIA Study Brief including
landscape & visual, noise, construction air and water quality and built
heritage are described in the assessment.
Impacts
Prediction
1.5.3
The EIA Study was undertaken in
accordance with the guidelines on assessment methodologies given in Annexes 12
to 19 of the EIAO-TM.
1.5.4
Quantitative approach was adopted
for assessing the construction noise impacts. The predictions were conducted
based on well-proven, internationally accepted methods.
1.5.5
The applied methodologies for
the Project had previously been adopted in other EIA studies. They have been generally accepted for
use in predicting environmental impacts and for comparison of assessment
results with the EIAO-TM requirements.
Limitations are however envisaged of these methodologies. The accuracy
of the prediction result will be affected by uncertainty in input data such as
sound power levels of construction plants to be used on-site. The most realistic data have been used
in the prediction in order to provide a result with the lowest practicable
quantitative uncertainty.
1.6.1
Mitigation measures are
proposed to alleviate the potential impacts predicted. The proposed mitigation
measures have previously been adopted in other environmental assessment studies
with similar construction works. An
Environmental Monitoring and Audit programme is recommended to ensure that the
recommended mitigation measures can effectively mitigate the impacts so as to
comply with the corresponding criteria.
1.7.1
The EIA Study was made
reference to the approved relevant EIA Study Modifications to MTRCL Tsim Sha Tsui Station, Mass Transit Railway Corporation Limited
(EIAO Register No.: AEIAR-043/2001).
1.8.1
The identified key
environmental issues regarding the construction of the proposed Project are
listed as below:
·
potential construction dust impacts to nearby
sensitive receivers from the Project;
·
potential construction and operation noise impacts
to nearby sensitive receivers from the Project;
·
potential construction water quality impacts to
nearby sensitive receivers, as well as waste management implications, from the
Project;
·
potential landscape and visual impacts to nearby
sensitive receivers from the Project during its construction and operation
stages;
·
potential impacts to nearby identified heritage resources from the Project during its construction and
operation stages; and
·
potential cumulative impacts to nearby sensitive
receivers for the above key issues, taking into account the existing
construction works is discussed in Section 2.
1.8.2
The assessments of these key
environmental issues are to be discussed in the following chapters of this
Report. The study boundaries of construction air quality, noise and
construction water quality impacts are shown in Figure 1.5.
1.8.3
The Project is within a developed urban area,
there are no ecological sensitive receivers, such as
Sites of Special Scientific Interest (SSSIs), Fish Culture Zones and Marine Parks
and/or Reserves and other areas of ecological importance or conservation
interest, within or in the immediate vicinity of the site area. Ecological impacts are, therefore, not
expected during the construction and operation phases of the proposed
Project. Accordingly ecological impact assessment is not required
in this EIA Study.
2.1.1
The Project is located in Tsim
Sha Tsui district which is an urban area with mixture of commercial and
residential developments. The
proposed works lie along Nathan
Road from Cameron Road junction to Miramar Shopping
Centre near Kimberley Road. The proposed new plant basement will be
located under the existing Entrance A1 of the TST Station.
2.1.2
The project includes the
following:
·
A
subway (Subway TST) from the north end of TST Station, running approximate 85m
under Nathan Road
to a Satellite Concourse;
·
A
satellite concourse (45m approx) underneath Nathan Road located adjacent to Tung Ying
Building and the Miramar
Hotel;
·
A
subway (Subway MSC) from the north end of the Satellite Concourse, running
approximate 80m under Nathan Road
to the Miramar Shopping Centre (MSC).
2.2
Identification of the
Project Need
2.2.1
The passenger forecast study
has established that the north of TST Station is under the most pressure and is
now already approaching capacity.
This is because the station catchment areas of the northern section are
relatively more developed and will have more re-development. The northern section of the station is
already and is expected to continue to be overloaded, especially at the
vertical links between concourse and street at Entrances A1 (to Nathan Road and Haiphong Road), B1
and B2 (to Nathan Road
and Cameron Road). Without any modification works, the
north end of the station concourse will become significantly overloaded in the
next few years.
2.2.2
The proposed subway will
provide a direct link for passengers between the platform at the north end of
the TST Station to a satellite concourse with access to street level via subway
connections to the Tung Ying
Building Redevelopment, Miramar Hotel, and Miramar Shopping Centre. Passengers
can access the development areas north-east of TST, thus avoiding congestion
and a number of signalled pedestrian crossings at street level.
2.2.3
TNS will provide an attractive
route for existing and future passengers as it will enhance the walking
quality, and provide a fast, safe, air-conditioned and weather proof route
between the station and the catchment north of Tsim Sha Tsui avoiding Entrances
A1, B1 and B2 of TST Station and traffic and pedestrian congestion at street
level.
2.2.4
In the absence of the project,
in the longer term the TST Station would remain busy and its congested sections
would remain saturated. This
strongly implies that the station is in need of a significant operational
relief in its northern section, despite the launching of the Kowloon Southern
Link (KSL) in year 2009, and the passenger diversion that it may cause.
2.2.5
The TNS scheme is also
complementary with a number of pedestrian schemes and traffic calming measures
implemented by the Government of the HKSAR in the area west of Nathan Road to
improve the whole pedestrian environment.
These include Haiphong Road,
Canton Road, Peking Road, Hankow Road, Lock Road and Ashley Road modification schemes. As these schemes have been well received
by the public, further schemes are in progress to implement even more
comprehensive measures to regulate both vehicular and pedestrian traffic to
achieve a better environment in the whole Tsim Sha Tsui area.
·
Those
projects include:
·
Greening
Master Plan (GMP) for TST Area by Civil Engineering Development Department
(CEDD); and
·
Area
Improvement Plan (AIP) for TST Area by Transport Department (TD).
2.2.6
Since the opening of East Tsim
Sha Tsui (ETS) Station and the new pedestrian connections to TST Station, it
has provided rail and non rail users a direct and convenient interchange
to/from MTR stations, relieving congestion at the busy street level and
enhancing the walking environment in Tsim Sha Tsui. In the next few years, this subway
network is to be expanded to include the Middle Road Subway Extension to Peking Road
extending the railway catchment to the south west of Tsim Sha Tsui. With both the ETS related pedestrian
links in TST south and the TNS scheme in TST north completed, the TST District
can be comprehensively served with good pedestrian connectivity and
accessibility along both sides of Nathan
Road.
2.2.7
To conclude, this station
improvement scheme would provide much-needed relief to the currently congested
Entrances A1 (to Haiphong Road)
and B1 & B2 (to Cameron Road). Without such relief, these two northern
entrances would continue to suffer from heavy operational pressure, especially
with the continuous TST catchment growth following the airport relocation and
the subsequent relaxation of building height/massing constraints in south Kowloon.
2.3
Considerations for Design Options
2.3.1
In 2006, MTRCL commenced the
planning of a new capacity enhancement scheme to relieve the northern section
of the TST Station. This is known
as the Tsim Sha Tsui Station Northern Subway (TNS) and is the subject of this
submission. This scheme consists of
an underground pedestrian subway link (TNS) that connects the northern end of
the TST Station platform, via the modified concourse plant room area, with
integrated entrances in the basements of Tung Ying
Building Redevelopment, Miramar Hotel and the Miramar Shopping Centre together
with an underground satellite concourse (the Satellite Concourse) in the middle
of the subway.
Considerations
for TNS Subway Alignment
2.3.2
The two prime objectives to be
achieved in the planning of the TNS subway include:
·
to
provide a direct pedestrian subway link between the TST Station and the Tung Ying Building Redevelopment, Hotel Miramar and
Miramar Shopping Centre;
·
to
accommodate the existing plant rooms displaced from the TST Station by the TNS
subway link.
2.3.3
The key objective is to
minimise the walking distance as far as practicable. Obviously, if the
alignment of the pedestrian subway is not attractive to the passengers, the
purpose of building it will be defeated.
In planning the subway alignment, there are several key considerations
for its layout and the form that it might take. The major constraints on the design and
construction of the proposed subway identified are as follows:
·
Clearance
requirements to the Tsuen Wan Line (TWL) Tunnels and structures;
·
Minimum disturbances to the existing water mains,
utilities and drainage systems;
·
Interface with the redevelopment works of Tung Ying Building (TYB);
·
Interfaces with Hotel Miramar (HM) and Miramar
Shopping Centre (MSC), both in use during construction;
·
Interface with MTR TST Station and the need to
minimise any impacts on the functionality of key public and plant room areas;
·
Limited works area and construction access;
·
Land availability and projections from buildings;
·
Vehicular and Pedestrian Traffic Management during
construction;
·
Landscape and visual impacts for any above ground
structures;
·
Minimal disturbance to Old and Valuable Trees
(OVTs) and trees of landscape value; and
·
Minimum noise and dust nuisance to the public and
residents during construction.
TNS
Subway Alignment
2.3.4
In identifying the above
constraints, the preferred alignment of the subway has been developed to
provide:
·
a shallow and broad subway;
·
a vertical alignment that is as flat as possible,
the ideal conditions for pedestrians comfort and convenience;
·
Travelators to further enhance passenger convenience.
2.3.5
As the vertical alignment of
the subway is controlled by the need to connect into the TST Station and the
basement of Tung Ying Building
Redevelopment, Miramar Hotel and Miramar Shopping Centre, there is limited
flexibility in adjusting the vertical alignment.
2.3.6
The subway connects into the
section north end wall at approximately 1m above existing concourse level to provide
sufficient cover to the existing MTR running tunnels underneath. To overcome any artificial obstructions,
in the form of left-in-place temporary piles and grout injection tubes, a
Connection Chamber is located here to be built by cut-and-cover method. The Connection Chamber is a buried
underground structure with no permanent impacts at ground or above-ground
level.
2.3.7
The north end of the existing
TST Station is to be modified to accommodate the passageway to Subway TST (the
southern section of the subway between the Satellite Concourse and TST
Station).
New
Plant Basement Options
2.3.8
The connection between the
Subway MSC (the northern section of the subway between Satellite Concourse and
the Miramar Shopping Centre) and TST Station requires that the existing station
E&M equipment from north-end plant rooms be re-located to provide a clear
passageway to the platform. There
is no space in the existing station for the relocated E&M equipment. By inspection of the surrounding area,
the only vacant space near the station in which to construct a new Plant
Basement to contain the displaced equipment from TST Station is in the vicinity
of Entrance A1.
2.3.9
In physical terms, the new
plant basement is contained within a zone around Entrance A1 with the following
structures and features surrounding it:
·
Heritage building, known as the Health Education
Exhibition and Resource Centre (HEER) located north;
·
the old retaining wall at Haiphong Road;
·
existing TST Station Entrance A1 Adit and
Ventilation Shaft Z located east;
·
the western wall of the TST Station and Nathan Road to the
west; and
·
existing Entrance A2 Adit and Haiphong Road to the south.
2.3.10
The dimensions of the Plant
Basement are constrained by the site environs (see above). Options have been considered for both
single-level and two-level basements.
The single level basement extended beyond the footpath of Haiphong Road was
rejected based on unacceptable impacts to the existing structures nearby and
the traffic on Haiphong Road. A two-level basement was preferred as
the layout was more compact and minimised impacts to the surrounding vehicular
traffic and the existing structures including the heritage building nearby.
2.3.11
The plant basement will be
ventilated through to the existing exhaust stack in Vent Shaft ‘Z’, in
preference to constructing new ventilation shafts which would cause operational
noise, visual and landscape impacts.
Entrance
Options
General
2.3.12
In general, the above-ground
entrances have the most potential impacts on noise, dust, visual and landscape
to the public. The entrance options
discussed in the following section have different impacts on the immediate
surrounding areas as follows:
Entrances Q1, Q2 and Q3
2.3.13
The three integrated entrances
to the east of the satellite concourse (namely, Entrances Q1, Q2 and Q3) will
have no permanent environmental impacts at ground and above-ground levels, with
the only impacts being the underground connections to the basement levels of
the adjoining buildings, namely, Tung Ying
Building Redevelopment and the two existing Miramar Developments, Miramar Hotel
and Miramar Shopping Centre.
2.3.14
As far as these buildings and
their integrated MTR entrances are concerned, appropriate interior layout will
be arranged such that any pedestrians can be fed to/from the respective
buildings, and any by-passing passengers can walk effectively through these
buildings for:
·
comfort of weather proof environment; and
·
convenient and direct access to the station’s
platform avoiding the congested northern section at the station’s concourse
level.
Entrances Q4 and Q5 on Park Lane Shopper’s Boulevard
2.3.15
To comply with statutory
requirements for the emergency escape requirements from the subway. It has been established that one
emergency exit is required at the Satellite Concourse, the mid-point between
the two subways. A second emergency
exit is required at the end of Subway MSC.
As emergency escapes routes can be upgraded to form entrances, a review
of entrance options was undertaken on the western footpath of Nathan Road. These entrances are all located in order
to:
·
facilitate public accessibility to the station, the
Kowloon Park or as a means of crossing Nathan Road; and
·
assist in evacuation from the underground subway.
2.3.16
The environmental
considerations include the need to:
·
minimise noise and dust impacts during
construction;
·
minimise the visual and landscape impacts during
construction and operation;
·
minimise the nuisance to pedestrians during
construction; and
·
avoid the large OVTs, and the assumed extent of
their tree roots and tree canopies.
2.3.17
The entrance locations
identified on the western footpath of Nathan
Road include:
a)
An entrance located at the Kowloon Park
entrance between the north and south blocks of Park Lane Shopper’s Boulevard;
b)
An entrance opposite the Miramar Shopping Centre;
and
c)
An entrance opposite the proposed Satellite
Concourse.
No further entrance options were identified, given the constraints found
on the footpaths of Nathan Road.
2.3.18
The entrance scheme at Kowloon Park
was not considered further due to construction impacts on the existing Kowloon Park stair structure where the electric
equipment supporting the Park Lane Boulevard shops could not be temporarily
re-provided during construction.
2.3.19
Substantial discussions had been
held with Leisure and Cultural Services Department (LCSD) regarding the
entrance options proposed on the footpath of Park Lane Boulevard opposite the
Miramar Shopping Centre and the proposed Satellite Concourse. Though due considerations have been given
in the design and construction methodology of the entrances, it is concluded
that the two entrance options on the footpath of Park Lane Boulevard were
inappropriate in view of the potential impacts to the OVTs on the west side of
Nathan Road and were not further pursued.
2.3.20
The ventilation shaft
originally proposed to be integrated with one of the entrance on the footpath
of Park Lane Boulevard will be incorporated with the Tung Ying Redevelopment and Hotel Miramar.
Emergency Exits
2.3.21
As mentioned earlier, two
emergency exit points are required for the scheme, and as no entrances would be
provided to street, the proposed emergency exits are dedicated escape routes
only and not for public access. Two
locations identified are at the satellite concourse and at the end of the
Subway MSC.
Emergency Exit at the Satellite Concourse
2.3.22
The emergency exit at the
Satellite Concourse exits via the Tung Ying
Building Redevelopment in a dedicated emergency corridor to street level. The exit location to street is under
study by the Tung
Ying
Building developer.
Emergency Exit at Subway MSC
2.3.23
The emergency exit is situated
in the east footpath and planter of Nathan
Road. It was placed well away from the OVT in the
roadside planter in front of the Miramar Shopping Centre. The footprint of the emergency exit was
minimized to fit into the space at present occupied by young Ficus microcarpa (non-OVTs). No other feasible locations have been
identified due to the sever constraints found in the area. To minimise any sight line problems and
visual impacts, the above-ground structure is level with the existing planter
and finished with materials to the adjacent planter to provide total
integration.
Entrance A1 Upgrade
2.3.24
The existing canopy structure
for Entrance A1 is approximately twenty-six years old.
2.3.25
The existing Entrance A1 canopy
will be demolished during construction of the Plant Basement. It will be replaced with an iconic
transparent glass box, a distinctive station entrance that reinforces the
Corporate image in Tsim Sha Tsui District.
The new Entrance A1 will improve access to the station with a disabled
lift serving the Kowloon
Park entrance, street
level and the TST concourse level, a staircase and escalators from street level
to the existing Entrance A1/A2 adit.
2.3.26
The transparent structure is
intended to allow the new structure to blend in with the surrounding
environment and minimise any landscape and visual impacts.
2.4.1
Alternative entrance locations
and subway alignment are studied under the following constraints placed on this
Project:
a)
Location of large OVTs and their assumed extend of
root system near the project boundary;
b)
Requirement of an emergency escape/exit at the
subway northern end;
c)
Requirement of an emergency escape/exit located at
the mid-point between the existing TST station box and the northern end of the
subway extension; and
d)
With the objective to minimise the walking distance
as much as practicable; hence the shortest construction duration and the
minimal environmental impacts.
2.4.2
Alternative location for
Entrance Q3 (proposed at the footpath of Park Lane Boulevard) has been
reviewed. Nevertheless, in view of
the potential impacts to the OVTs on the west side of Nathan Road, it is
concluded that lesser degree of environmental impact cannot be provided from
any alternative due to the location constraint and thus not pursued further.
2.4.3
For the subway alignment, the
current alignment provides the shortest and the most direct connection between
the existing TST Station & Satellite Concourse and between Satellite
Concourse and the Miramar Shopping Centre, such that the environmental impact will
be minimised.
Other alignment alternatives have been considered but all present
additional environmental burdens from noise and dust due to longer or deeper
subway alignment hence were not further pursued.
2.5.1
The construction of the TNS
subway and associated structures is expected to be difficult, given the obvious
need to minimise any environmental disturbance and impacts on the OVTs, traffic
and pedestrian, residents, existing MTRCL Tsuen Wan Line (TWL) tunnels, TST Station and the nearby building
structures. Tunneling by mining
method and cut-and-cover method are the available techniques to select from. Based on the study, large proportion of
the works under this project are to be constructed using tunneling by mining
method, in which environmental impact will be minimised, only small proportion
of works, where above ground construction works are inevitable are to be
constructed by cut-and-cover method.
2.5.2
In order to minimise the
environmental impacts and disturbance to the existing utilities and traffic
along Nathan Road,
the subway tunnels, which comprise a large proportion of the project, are to be
constructed by using tunneling
by mining method.
The alignment of the tunnels and ground conditions found in the project
area are considered suitable for using tunneling by mining method based on the
geological information provided by the geotechnical investigation carried out
for this Project.
2.5.3
For the small remaining
proportion of works of this project, where above ground construction works are
inevitable (such as area with limited soil cover and the need for access point
for the works), the cut-and-cover method are to be adopted. Nevertheless, cut-and-cover elements of
the work have been limited as far as practicable to the Satellite Concourse,
Connection Chamber, Plant Basement and the Emergency Exit stair.
2.5.4
Whenever cut-and-cover method is adopted,
majority of construction works will be decked to reduce
airborne noise, dust, visual and minimise traffic
impacts which allow traffic to be diverted back over the excavation on Nathan Road.
2.5.5
Other alternative construction
method including open-cut excavation method has been reviewed. Nevertheless, in view of large
environmental impact will be created as compare with tunneling by mining method
and cut-and-cover method, it is not recommended and thus not further pursued.
2.6.1
The site constraints,
environmental factors and options available for the selection of the preferred
scheme have been discussed in the above sections and are summarised below in Table
2.1:
Table 2.1 Summary of the Preferred
Scheme
TNS Component
|
Scheme and Environmental Factors Considered
|
Subway Tunnels
-
Subway TST
-
Subway MSC
|
·
The TNS subway is the most direct and shortest link to the proposed
entrances, i.e. minimise the extent of the construction works area and limit
the works area to the section of Nathan
Road that are mostly surrounded by hotels and
commercial buildings provided with central air conditioning systems and do
not rely upon openable windows for ventilation.
·
The subway tunnels which form of a large proportion of the project are
to be constructed using tunneling by mining method. The environmental benefits include:
- minimal
airborne noise and dust impacts on nearby sensitive receivers;
- minimal
impact on the traffic and pedestrians at street level during construction to
reduce the chance noise generated from possible traffic back up.
·
The subway alignment shifts towards the east side of Nathan Road away
from the row of OVTs on west footpath of Nathan Road.
|
Cut-and-Cover Components –
Satellite Concourse, Connection
Chamber, Plant Basement and Emergency Exit
|
·
Above ground
construction work are inevitable.
Nevertheless, they are limited as far as practicable to:
- Satellite
Concourse;
- Plant
Basement;
- Connection
Chamber; and
- Emergency
Exit Stair.
Moreover, cut and cover
method is adopted, i.e. majority of construction works would be carried out
under road deck. Dust and airborne noise emission
during construction, would be screened off by the road deck from the nearby
receivers.
|
Plant Basement and Entrance A1 Upgrade
|
·
The two-level plant
basement located near Entrance A1 is compact to minimise environmental impacts during the construction phase.
Comparing to the single-level scheme, the works area would be largely
reduced, the associated impacts, particularly construction noise and fugitive
dust impacts are substantially reduced.
·
Relocation of the
plant basement near Entrance A1 provides an opportunity to upgrade the
entrance. The old entrance is over 26 years
old.
The new entrance with use of transparent glass would reduce bulk
effect and be in compatible with the adjacent urban setting. The new facilities for the entrance
include a disabled lift serving the station, street level and Kowloon Park. The accessibility/connectivity
of Kowloon Park,
a recreational/ leisure resource in urban Hong Kong,
is effectively enhanced with the Entrance A1 upgrade in place as it
significantly improves the pedestrian and disabled access to the park from
the station with insubstantial level of visual impact.
·
Ventilation at the
plant basement utilises the existing exhaust shaft that could avoid
environmental impacts arising from construction of a new vent shaft.
|
Emergency Exit
|
·
The emergency exits are a statutory requirement for the TNS
scheme. The emergency exits are
located at the Satellite Concourse and at the end of Subway MSC.
·
The emergency exit at the Satellite Concourse is routed via the Tung Ying Building Redevelopment in a dedicated route
to street level.
·
The emergency exit at Subway MSC is situated in the planter along the east footpath at Nathan Road. The above ground structure is level with the
existing planter and finished with materials similar to the
adjacent planter to provide total integration. Moreover it is well
away from the OVT. As such visual and landscape impacts
are minimised.
|
2.6.2
Following review of the scheme
options, construction methods and environmental factors, the preferred scheme
for the Tsim Sha Tsui Station Northern Subway consist of :
a)
A subway (Subway TST) from the
north end of TST Station, running approximate 85m under Nathan Road to a Satellite Concourse;
b)
A satellite concourse (the
Satellite Concourse) approximate 45m underneath Nathan Road, containing ticket gates
(reversible type), ticket issuing machines (TIMs), self service points,
help-lines, etc. It has direct
underground connections to the basements of the Miramar Hotel and of the
development on the site of the former Tung Ying Building - these integrated entrances
are designated Q2 and Q1 respectively.
A mezzanine level in the Satellite Concourse contains electrical and
ventilation plantrooms for the subway;
c)
A subway (Subway MSC) from the
north end of the Satellite Concourse, running approximate 80m under Nathan Road to the
Miramar Shopping Centre (MSC), where an underground link connects to its
basement. This integrated entrance
is designated Q3;
d)
An Emergency Exit situated in
the east footpath and planter of Nathan
Road, outside the Miramar Shopping Centre;
e)
The fresh, ventilation and smoke exhaust ducts for
TNS are integrated with the Tung Ying
Redevelopment and Hotel Miramar;
f)
A two-level plant basement (Plant Basement) located
below and in front of Entrance A1 to house the displaced E&M equipment from
the north end of TST Station; and
g)
Entrance A1 upgrade to replace the existing
concrete structure with a new transparent box reconstructed on the same site
with a improved access to the station with new disabled lift serving TST
concourse level, street and Kowloon Park; and escalators serving street and the
existing Entrance A1 Adit.
2.7
Implementation and Planning
of the Proposed Project
2.7.1
The proposed works are
scheduled to commence in June 2009 with duration of approximately 35 months.
The entire project is scheduled to be completed in May 2012. The preliminary
construction programme for the Project is shown in Table 2.2.
Table 2.2 Preliminary
Construction Programme
Activity
|
Time
period
|
Site clearance and set up
|
Jun
2009 to Jul 2009
|
Tree Protection
|
Jun
2009 to Jan 2012
|
Plant Basement and
Entrance A1 construction
|
Jul
2009 to Dec 2010 and Nov 2010 to Nov 2011
|
Satellite
Concourse and Entrances Q1 and Q2 construction
|
Nov
2009 to Jan 2012
|
Subway to TST
Station
|
Mar
2011 to Dec 2011
|
Subway to Miramar
Shopping Centre and Entrance Q3 construction
|
Feb
2011 to Dec 2011
|
Emergency Exit at Miramar Shopping Centre
|
Jul 2009
to Aug 2009, Nov 2011 to Feb 2012
|
TST Connection Chamber
|
Jul
2009 to Mar 2010
|
TST North End modification
|
Jun
2011 to Mar 2012
|
Landscaping works
|
Oct
2011 to Jan 2012
|
Site reinstatement works
|
Jan
2012 to May 2012
|
2.7.2
The construction of the
proposed Plant Basement and Satellite Concourse are divided into six stages to
adopt temporary pedestrian flow and traffic diversion. The construction
sequence of the Plant Basement and Satellite Concourse are shown in Figures
2.1 and 2.2 respectively.
2.7.3
Based on the tentative
construction programme, the Project will be carried out concurrently with the
adjacent Tung Ying Building
Redevelopment, which is under construction. It is expected that the foundation and
infrastructure works of the Tung Ying
Building Redevelopment will be completed at the time of the commencement of
this Project. Consequently,
cumulative environmental impacts from the Tung Ying
Building Redevelopment are envisaged to be insignificant.
3.
construction air quality impact
3.1.1
This section presents air
quality impact assessment during construction phases of the Tsim Sha Tsui
Station Northern Subway (TNS) Project.
Representative Air Sensitive Receivers (ASRs) and the potential air quality
impact on these receivers associated with the Project has been identified and
assessed. Appropriate mitigation
measures would be proposed if necessary.
3.2.1
The criteria for evaluating air
quality impacts and the guidelines for air quality assessment are set out in
Annex 4 and Annex 12 of the Technical Memorandum on Environmental Impact
Assessment Process (EIAO-TM).
Air Quality Objective &
EIAO-TM
3.2.2
The Air Pollution Control
Ordinance (APCO) provides the statutory authority for controlling air
pollutants from a variety of sources.
The Hong Kong Air Quality Objectives (AQOs), which must be satisfied,
stipulate the maximum allowable concentrations of certain pollutants over
specific periods. The relevant AQOs
are listed in Table 3.1.
Table 3.1 Hong Kong Air Quality Objectives
|
Maximum Concentration (µg m-3) (1)
|
Pollutant
|
Averaging Time
|
|
1 hour (2)
|
8 hour (3)
|
24 hour (3)
|
Annual (4)
|
Total Suspended Particulates (TSP)
|
-
|
-
|
260
|
80
|
Respirable Suspended Particulates
(RSP) (5)
|
-
|
-
|
180
|
55
|
Sulphur Dioxide (SO2)
|
800
|
-
|
350
|
80
|
Nitrogen Dioxide (NO2)
|
300
|
-
|
150
|
80
|
Carbon Monoxide (CO)
|
30,000
|
10,000
|
-
|
-
|
Photochemical Oxidants
(as Ozone, O3) (6)
|
240
|
-
|
-
|
-
|
Notes:
(1)
Measured at 298 K and
101.325 kPa.
(2)
Not to be exceeded more than
three times per year.
(3)
Not to be exceeded more than
once per year.
(4)
Arithmetic mean.
(5)
Suspended particulates in
air with a nominal aerodynamic diameter of 10 mm or smaller.
(6)
Photochemical oxidants are
determined by measurement of ozone only.
Air Pollution Control
(Construction Dust) Regulation
3.2.4
Notifiable and regulatory works
are under the control of the Air Pollution Control (Construction Dust)
Regulation. Notifiable works are
site formation, reclamation, demolition, foundation and superstructure construction
for buildings and road construction.
Regulatory works are building renovation, road opening and resurfacing
slope stabilisation, and other activities including stockpiling, dusty material
handling, excavation, concrete production etc. This Project is expected to include both
notifiable and regulatory works.
Contractors and site agents are required to inform the Environmental
Protection Department (EPD) on carrying out construction works and to adopt
dust reduction measures to reduce dust emission to the acceptable level.
3.3.1
The Project is located in Tsim
Sha Tsui district which is an urban area with mixture of commercial and
residential developments. The
proposed works lie along Nathan
Road from Cameron Road junction to Miramar Shopping
Centre near Kimberley Road. The proposed new plant basement is
located under the existing Entrance A1 of the TST Station.
3.3.2
There is no EPD air quality
monitoring station at Tsim Sha Tsui.
The background pollutant values adopted for assessment are based on the
EPD “Guideline on Assessing the ‘TOTAL’ Air Quality Impacts”. In the categorisation of monitoring air
quality data, Tsim Sha Tsui is categorised as urban development. The latest five years (2002-2006)
average monitoring data for urban development would be adopted as the background
concentrations. These urban
monitoring stations considered in this assessment include: Central/Western,
Kwun Tong and Sham Shui Po. Table
3.2 summarizes the annual average TSP concentrations adopted as background
concentrations for this air impact assessment.
Table 3.2 Annual
Average TSP Concentration in the Latest Five Years (Year 2002 - 2006) for Urban
Development
Pollutant
|
Annual Average Concentration in the Latest Five Years (mg m-3)
|
TSP
|
78
|
3.4.1
In accordance with the Annex 12
of the EIAO-TM, any domestic premises, hotel, hostel, hospital, clinic,
nursery, school, educational institution, office, factory, shop, shopping
centre, place of public worship, library, court of law, sports stadium or
performing arts centre are considered to be an ASR. Any other place with which, in terms of
duration or number of people affected, has a similar sensitivity to the air
pollutants as the aforelisted places are also be considered to be a sensitive
receiver, for example, playground, sitting area of parks/promenade.
3.4.2
No planned ASRs are located in
vicinity of the Project. The
identified representative ASRs are listed in Table 3.3 and the
corresponding locations are shown in Figure 3.1.
Table 3.3 Details of Representative Air Sensitive
Receivers
ASR
|
Description
|
*Current
Use
|
Distance
from nearest emission sources (m)
|
A1
|
Parmanand House
|
Commercial
|
40
|
A2
|
Hai Phong
Mansion
|
Residential and commercial
|
20
|
A3
|
Health Education Exhibition and Resource
Centre
|
G/IC
|
35
|
A4
|
Health Education Exhibition and Resource
Centre
|
G/IC
|
5
|
A5
|
Kowloon Mosque and Islamic Centre
|
Religionary
|
25
|
A6
|
Park
Lane Shopper's Boulevard
|
Shop
|
20
|
A7
|
Park
Lane Shopper's Boulevard
|
Shop
|
30
|
A8
|
Park
Lane Shopper's Boulevard
|
Shop
|
25
|
A9
|
Park
Lane Shopper's Boulevard
|
Shop
|
30
|
A10
|
Park
Lane Shopper's Boulevard
|
Shop
|
55
|
A11
|
Cheong Hing
Building
|
Residential and commercial
|
35
|
A12
|
Manson House
|
Service Apartment
|
25
|
A13
|
Majestic House
|
Residential and commercial
|
30
|
A14
|
Comfort Building
|
Residential and commercial
|
10
|
A15
|
Burlington Arcade
|
Residential and commercial
|
35
|
A16
|
Milton Mansion
|
Commercial
|
20
|
A17
|
Hotel Miramar
|
Hotel and Shop
|
10
|
A18
|
Miramar Shopping Centre
|
Commercial and Shop
|
5
|
A19
|
Antiquities & Monuments Office Antiquities
Advisory Board Secretariat
|
G/IC
|
60
|
Note: (*) G/IC: Government, institution or community
use. The permitted uses of the
premise A16 are both residential and commercial
3.4.3
As the construction activities
are to be undertaken at and
below ground level, the worst dust impact on the ASRs
will be at the ground floor of the ASRs.
The height of 1.5m
above ground, which is the breathing level of human, was adopted for the
construction dust impact assessment.
In addition, 5m and 10m above local ground level were also
selected to show the vertical variation of the pollutant concentrations.
3.5.1
The plant basement and modification
works at the existing entrance A1, connection chamber, satellite concourse, two
subways and emergency exit are to be constructed at
five works areas. The
construction period for the TNS Project is tentatively scheduled from June 2009
to early 2012. According to the
construction programme, the major dusty construction activities at the five works areas will
not be overlapped. However, the
construction works at different areas are assumed to be undertaken simultaneously in the
assessment as the worst case scenario.
3.5.2
Cut-and-cover method would be
adopted for the construction of the plant basement, connection chamber,
satellite concourse and emergency exit.
Construction would be conducted initially above ground for installation
of traffic deck. Once the decking
is completed, majority of the construction activities would be underground
below the deck. Aboveground
construction works including excavation, material handling, loading and
unloading of fill materials may pose potential dust impacts to ASRs in the
vicinity of the site area of the proposed Project.
3.5.3
For the construction of the
subways connecting the new entrances and concourses, tunneling by mining method
would be considered. With the works
conducted underground, no dust impact is expected.
3.5.4
Based on the tentative
construction programme, the proposed Project will be carried out concurrently
with the Tung Ying Building
Redevelopment adjacent to TNS Project Site, which is under construction. However, it is expected that the
foundation and infrastructure works of the Tung Ying
Building Redevelopment will be complete at the time of the commencement of this
Project i.e. June 2009 Cumulative
environmental impacts from the Tung Ying
Building Redevelopment are thus envisaged to be insignificant.
3.6.1
The principal source of air
pollution during the construction phase will be dust from the dusty activities
as mentioned in Section 3.5.2. The impact of fugitive dust sources on
air quality depends upon the quantity as well as the drift potential of the
dust particles emitted into the atmosphere. Large dust particles (i.e. over 100 mm in diameter) will settle out near the source and particles that
are between 30 and 100 mm in diameter are likely to undergo
impeded settling. The main dust
impacts are likely to arise from particles less than 30 mm in diameter, which have a greater potential to disperse over
greater distances.
3.6.2
According to the USEPA AP-42,
construction dust particles may be grouped into nine particle size
classes. Their size ranges are 0 - 1 mm, 1 - 2 mm, 2 - 2.5 mm, 2.5 - 3 mm, 3 - 4 mm, 4 - 5 mm, 5 - 6 mm, 6 - 10 mm and 10 - 30 mm, and the percentage of particles in each class was estimated to be
4%, 7%, 4%, 3%, 7%, 5%, 4%, 17% and 49%, respectively.
3.6.3
The emission rates adopted in
the TNS project assessment for different construction activities are based on
the USEPA Compilation of Air Pollutant Emission Factors (AP-42), 5th
edition. The four major
construction sources including:
·
Plant Basement;
·
TST Connection Chamber;
·
Satellite Concourse; and
·
Emergency Stair at MSC.
3.6.4
Table 3.4 gives the relevant clauses for emission factors used in this
assessment in AP-42. Detailed
calculation of emission rate is presented in Appendix 3.1.
Table 3.4 Emission Factors for Construction
Activities
Emission Sources
|
Construction
Activities
|
Emission
Rate [2,3](g/m2/s)
|
Remark
[1]
|
Plant Basement
|
Heavy Construction Activities
|
E = 7.394E-05
|
- 47.5%
work area
- 50% reduction by water suppression (watering twice a day)
- USEPA AP-42 5th ED., S.13.2.3.3
|
TST Connection Chamber
|
Heavy Construction Activities
|
E = 2.179E-05
|
- 14.0% work area
- 50% reduction by water suppression (watering twice a day)
- USEPA AP-42 5th ED., S.13.2.3.3
|
Satellite Concourse
|
Heavy Construction Activities
|
E = 4.76354E-05
|
- 30.6% work area
- 50% reduction by water suppression (watering twice a day)
- USEPA AP-42 5th ED., S.13.2.3.3
|
Emergency Stair at MSC
|
Heavy Construction Activities
|
E = 6.6005E-05
|
- 42.4% work area
- 50% reduction by water suppression (watering twice a day)
- USEPA AP-42 5th ED., S.13.2.3.3
|
All Emission Sources
|
Wind Erosion
|
E = 2.6953E-06
|
- USEPA AP-42 5th ED., S.11.9, Table 11.9.4
|
Note:
-
[1] The percentage area under active operation has
reconfirmed with Engineer. The
percentage active area is estimated based on the actual construction programme
and the availability of plant equipment
-
[2] Only unit conversion has been conducted in the
emission factors in accordance with AP-42.
-
[3] Assume 30 working days per month and 8 working hours
per day.
3.6.5
The Air Pollution Control
(Construction Dust) Regulation specifies that dust suppression measures such as
watering shall be applied for the construction site. Dust emission from the site will be
reduced by 50% if watering with complete coverage of active construction area
twice a day. This assumption was
considered in the construction dust impact assessment.
3.6.6
Fugitive Dust Model (FDM) (1993
version) was used to assess potential dust impact from the construction
works. The worst case meteorological
data was used to predict the 1-hour and 24-hour average TSP concentrations at
representative discrete ASRs close to the construction works. As mentioned in Section 3.4.3,
assessment level at 1.5m,
5m and 10m are included in the assessment.
3.6.7
The meteorological data used in
the model are:
·
Wind
speed: 1 m/s
·
Wind
direction: 360
wind direction
·
Stability
class: D (daytime) & F (night time)
·
Surface
roughness: 1m
·
Mixing
height: 500 m
3.7.1
Daily TSP concentrations were
calculated as follows:
Daily TSP concentration =
(working hour)/24 ´ (1-hour average maximum TSP concentration during working hours) +
(non-working hour)/24 ´ (1-hour average maximum TSP concentration during non-working hours)
+ Background.
3.7.2
As mentioned in Section 3.3.2, the background TSP of 78 mg/m3 was adopted as an indication of the future TSP
background concentration.
3.8
Evaluation of Impacts
3.8.1
The predicted maximum 1-hour
and 24-hour average TSP during construction are shown in Tables 3.5 and
3.6, respectively.
Table 3.5
Predicted Maximum 1-hour Average TSP Concentrations
ASR
|
1.5m above ground
|
5m above ground
|
10m above ground
|
A1
|
186
|
147
|
95
|
A2
|
350
|
161
|
90
|
A3
|
203
|
152
|
93
|
A4
|
484
|
118
|
89
|
A5
|
247
|
160
|
93
|
A6
|
145
|
129
|
99
|
A7
|
182
|
137
|
94
|
A8
|
202
|
125
|
89
|
A9
|
108
|
105
|
96
|
A10
|
99
|
97
|
92
|
A11
|
206
|
153
|
93
|
A12
|
268
|
160
|
89
|
A13
|
224
|
156
|
91
|
A14
|
149
|
131
|
98
|
A15
|
163
|
136
|
97
|
A16
|
260
|
154
|
94
|
A17
|
365
|
158
|
94
|
A18
|
168
|
112
|
100
|
A19
|
103
|
100
|
93
|
Notes: (1) Background concentration is
included.
(2) 1-hour TSP criterion of 500mg/m3 is stipulated in the EIAO-TM.
Table 3.6 Predicted
Maximum 24-hour Average TSP Concentrations
ASR
|
1.5m above ground
|
5m above ground
|
10m above ground
|
A1
|
120
|
102
|
84
|
A2
|
179
|
107
|
82
|
A3
|
126
|
104
|
83
|
A4
|
223
|
92
|
82
|
A5
|
142
|
107
|
83
|
A6
|
105
|
97
|
85
|
A7
|
120
|
99
|
84
|
A8
|
126
|
94
|
82
|
A9
|
91
|
89
|
84
|
A10
|
87
|
86
|
83
|
A11
|
127
|
104
|
83
|
A12
|
150
|
107
|
82
|
A13
|
134
|
106
|
83
|
A14
|
106
|
98
|
85
|
A15
|
115
|
99
|
84
|
A16
|
153
|
105
|
84
|
A17
|
191
|
106
|
84
|
A18
|
112
|
92
|
86
|
A19
|
89
|
87
|
84
|
Notes: (1) Background concentration is
included.
(2) 24-hour TSP criterion of
260mg/m3 is stipulated in the EIAO-TM.
3.8.2
Based on the above prediction,
no exceedance of 1-hour and 24-hour average TSP objective will occur at any
representative ASR in the Study Area.
From the results, it is found that the maximum 1-hour and 24-hour
average TSP concentrations will occur at 1.5m above ground (484mg/m3
and 223mg/m3,
respectively). Contours of the maximum predicted 1-hour and 24-hour average TSP
concentrations at 1.5m above
ground are shown in Figures 3.2 and 3.3 respectively.
3.9.1
As mentioned in Section 3.5.4, it is expected that
the foundation and infrastructure works of the Tung Ying
Building Redevelopment would be completed at the time of the commencement of
this Project. Another new commercial development (iSquare) is found at 63 Nathan Road
(ex-Hyatt Regency Hong Kong Hotel at the
junction of Peking Road
and Nathan Road)
which is about 95m to the south of the new plant basement works area of the
Project. The commercial development
is scheduled to open in 2009 and all infrastructure construction works are
expected to be completed by July 2009 when this Project start. Thus, cumulative environmental impacts
would not be expected.
3.10.1
To ensure compliance with the
relevant standards, dust mitigation measures stipulated in the Air Pollution
Control (Construction Dust) Regulation and good site practices shall be
incorporated in the contract document to control potential dust emission from
the site. The major dust
suppression measures include:
watering of active construction works area twice a
day.
skip hoist for material
transport shall be totally enclosed by impervious sheeting.
every vehicle shall be
washed to remove any dusty materials from its body and wheels before leaving a
construction site.
the area where vehicle
washing takes place and the section of the road between the washing facilities
and the exit point shall be paved with concrete, bituminous materials or
hardcores.
where a site boundary
adjoins a road, streets or other accessible to the public, hoarding of not less
than 2.4m high
from ground level shall be provided along the entire length except for a site
entrance or exit.
every stack of more than 20
bags of cement shall be covered entirely by impervious sheeting places in an
area sheltered on the top and the 3 sides.
all dusty materials shall
be sprayed with water prior to any loading, unloading or transfer operation so
as to maintain the dusty materials wet.
the height from which
excavated materials are dropped shall be controlled to a minimum practical
height to limit fugitive dust generation from unloading.
stockpile of excavated or
dusty materials shall be covered entirely by clean impervious sheeting.
the load of dusty materials
carried by vehicle leaving a construction site shall be covered entirely by
clean impervious sheeting to ensure dust materials do not leak from the
vehicle.
instigation of an
environmental monitoring and auditing program to monitor the construction
process in order to enforce controls and modify method of work if dusty
conditions arise.
3.11
Evaluation of Residual Impacts
3.11.1
With the implementation of dust
suppression measures stipulated in Air Pollution control (Construction Dust)
Regulation and
watering of active construction works area twice a day during
construction, no exceedance of AQO within the Study Area is predicted. Therefore, no adverse residual dust
impact is expected.
3.12.1
With the implementation of the
proposed dust suppression measures, good site practices and dust monitoring and
audit programme, acceptable dust impact are expected at the ASRs. Details of the monitoring requirements
such as monitoring locations, frequency of baseline and impact monitoring are
presented in the stand-alone EM&A Manual.
4.
NOISE IMPACT
4.1.1
This section presents the
potential noise impacts arising from the proposed Project during construction
and operation phases. It is
expected that construction and operation noise impact will arise from the
proposed Project. Potential construction and operation noise impacts are
evaluated in this study.
General
4.2.1
Noise impacts generated by the
construction of this Project have been assessed in accordance with the criteria
and methodology given in the Technical Memoranda (TMs) under the Noise Control
Ordinance (NCO), and the Technical Memorandum on Environmental Impact
Assessment Process (EIAO-TM).
4.2.2
The NCO and EIAO provide the
statutory framework for noise control.
Applicable assessment procedures and standards are set out in three TMs
listed below:
·
EIAO-TM
·
TM
on Noise from Construction Work other than Percussive Piling (GW-TM)
·
TM
on Noise from Construction Work in Designated Areas (DA-TM)
·
TM
on Noise from Places other than Domestic Premises, Public Places or
Construction Sites (IND-TM)
4.3.1
The NCO provides the statutory
framework for noise control of construction work, other than percussive piling,
using powered mechanical equipment (PME) between the hours of 1900 and 0700
hours or at any time on Sundays and general holiday (that is, restricted
hours). Noise control on
construction activities taking place at other times is subject to the Criteria
for Evaluating Noise Impact stated
in Table 1B of Annex 5 in the
EIAO-TM. The noise limit is Leq
(30 minutes) 75 dB(A) at the façades of dwellings and 70 dB(A) at the
façade of schools (65 dB(A) during examinations). The EIAO-TM construction noise criteria
are summarised in Table 4.1.
4.3.2
Table 4.1 Daytime Construction Noise Criteria
|
Noise Level in Leq(30-minutes), dB(A)
|
Domestic premises
|
75
|
Educational Institution
|
70
|
|
65
|
Note: The above standards apply to uses which rely on opened windows for
ventilation
4.3.3
Between 1900 and 0700 hours and
all day on Sundays and public holidays, activities involving the use of PME for
the purpose of carrying out construction work is prohibited unless a
construction noise permit (CNP) has been obtained. A CNP may be granted provided that the
Acceptable Noise Level (ANL) for the noise sensitive receivers can be complied
with. ANLs are assigned depending
upon the area sensitive rating (ASR).
The corresponding ANLs for evening and night time periods are given in Table
4.2.
Table 4.2 Acceptable
Noise Levels
|
Acceptable Noise Level in Leq(5-minutes), dB(A)
|
|
ASR B
|
ASR C
|
Evening (1900 to 2300 hours)
(1)
|
60
|
65
|
70
|
|
45
|
50
|
55
|
Note: (1) Includes Sundays and Public Holidays during daytime
and evening
4.3.4
Despite any description or
assessment made in this EIA Report on construction noise aspects, there is no
guarantee that a Construction Noise Permit (CNP) will be issued for the project
construction. The Noise Control
Authority will consider a well-justified CNP application, once filed, for
construction works within restricted hours as guided by the relevant Technical
Memoranda issued under the Noise Control Ordinance. The Noise Control Authority will take
into account of contemporary conditions / situations of adjoining land uses and
any previous complaints against construction activities at the site before
making his decision in granting a CNP.
Nothing in this EIA Report shall bind the Noise Control Authority in
making his decision. Failure to
comply with any such conditions will lead to cancellation of the CNP and
prosecution action under the NCO.
4.3.5
Under the DA-TM, the use of
five types of Specified Powered Mechanical Equipment (SPME) and three types of
Prescribed Construction Work (PCW) within a designated area during restricted
hours would require a valid CNP.
The SPME includes hand-held breaker, bulldozer, concrete lorry mixer,
dump truck and hand-held vibratory poker.
The PCW are:
·
erecting
or dismantling of formwork or scaffolding
·
loading,
unloading or handling of rubble, wooden boards, steel bars, wood or scaffolding
material
·
hammering
4.3.6
As defined in the Noise Control
Designated Area Plan, all the works areas of the proposed Project are within
the Designated Area.
4.3.7
In general, it should not be
presumed that a CNP will be granted for carrying out PCW within a designated
area during the restricted hours.
The CNP may be granted for the execution of construction works during restricted
hours involving the use of PME and/or SPME if the relevant Acceptable Noise
Levels and criteria stipulated in the GW-TM and DA-TM can be met.
4.3.8
According to the construction
programme, most of the proposed construction works will be carried out during
non-restricted hours, except for underground tunneling work and some
construction activities in order to avoid local traffic impact. In case of any construction activities
during restricted hours, it is the Contractor’s responsibility to ensure compliance
with the NCO and the relevant TMs.
The Contractor will be required to submit CNP application to the Noise
Control Authority and abide by any conditions stated in the CNP, should one be
issued.
4.4.1
The major fixed plant
noise sources identified are ventilation shafts of the proposed Project which
would generate potential noise impact during operation. Fixed noise source such
as ventilation noise is controlled by the NCO and IND-TM. The appropriate Acceptable Noise Levels (ANL)
generated by fixed plant at neighbouring NSRs are provided in the IND-TM. The representative NSRs in the vicinity
of ventilation shafts are located in urban area and are fronting the busy
Nathan Road with an annual average daily traffic flow in excess of 30,000 in that road section
according to Annual Traffic Census 2006 published by Transport Department. Most of the NSRs will be directly
affected by traffic noise. In this connection, the Area Sensitivity Rating
(ASR) for these NSRs has been assumed as ‘C’. The ANLs for an ASR of ‘C’ under the IND-TM
are shown in
Table 4.3. The EIAO-TM recommends
that noise standard for fixed noise source are (a) 5 dB(A) below the
appropriate ANL, or (b) the prevailing background noise levels (For quiet areas
with level 5 dB(A) below the ANL). The existing background noise level
dominated by busy traffic along Nathan Road and community noise is expected to
be higher than ANL – 5dB(A), therefore, the noise criteria of ANL – 5dB(A) i.e.
65/55 dB(A) (daytime and night-time) have been adopted for the assessment.
Table 4.3 Acceptable
Noise Level for Fixed Plant Noise
Time Period
|
NCO criteria
Leq (30-min),
dB(A)
|
EIAO-TM
Leq (30-min),
dB(A)
|
ASR ‘C’
|
ASR ‘C’
|
Daytime
and Evening (0700-2300 hours)
|
70
|
65
|
Night-time
(2300-0700 hours)
|
60
|
55
|
4.4.2
In any event, the Area
Sensitivity Rating assumed in this EIA Report is for indicative
assessment. It should be noted that
the fixed noise sources are controlled under section 13 of the NCO. At the time of investigation, the Noise
Control Authority shall determine noise impact from concerned fixed noise
sources on the basis of prevailing legislation and practices being in force,
and taking account of contemporary conditions/situations of adjoining land
uses. Nothing in this EIA Report shall bind the Noise Control Authority in the
context of law enforcement against all the fixed noise sources being assessed.
4.5.1
In order to evaluate the
construction and operation noise impacts from the proposed Project,
representative existing noise sensitive receivers (NSRs) within the Study Area
are identified for assessment. Only
the first layer of NSRs has been identified for assessment because it provides
acoustic shielding to those receivers at further distance behind. As the centrally air-conditioned
buildings do not rely on opened windows for ventilation, the noise standard as
stipulated in Tables 1A and 1B of
Annex 5 of EIAO-TM would not be applicable, and hence these buildings have not
been identified for noise impact assessment. Table 4.4 shows the
representative NSRs for this noise impact assessment.
Table 4.4 Summary of
Representative Noise Sensitive Receivers
NSR
ID
|
Location
|
Permitted
Land Use
|
Number
of floors
|
Horizontal
Separation from Closest Works Area Boundary (m)
|
N1
|
Hai Phong Mansion (53-55 Haiphong Road)
|
Residential and commercial
|
15 domestic floors above 3 commercial use floors
|
17
|
N2
|
Majestic House (80 Nathan Road)
|
Residential and commercial
|
13 domestic floors above 3 commercial use floors
|
30
|
N3
|
Comfort Building (86-88 Nathan Road)
|
Residential and commercial
|
11 domestic floors above 3 commercial use floors
|
9
|
N4
|
Burlington Arcade (90-94C
Nathan Road)
|
Residential and commercial
|
14 domestic floors above 2 commercial use floors
|
29
|
*N5
|
Milton Mansion (96 Nathan Road)
|
Residential and commercial
|
12 floors
|
19
|
N6
|
Pacific Mansion (172-174 Nathan Road)
|
Residential and commercial
|
10 domestic floors above 4 commercial use floors
|
165
|
N7
|
Kowloon Mosque and Islamic
Centre (105 Nathan Road)
|
Religionary
|
3
|
24 (East façade N7a),
7 (South façade N7b)
|
Remark: (*) Refer to Section 4.5.2
for the nature of this NSR
4.5.2
According to the occupation
permit of Milton Mansion (N5) issued by Building Department, the allowed uses
are both commercial and residential.
Although it is identified as commercial use during the site survey, it
is selected as a representative sensitive receiver in the assessment to study
the impact level at this NSR should residential use be happened during the
construction period of the Project.
4.5.3
Two construction sites within
the study area are found along Nathan
Road i.e. 63 Nathan Road (iSquare) and 98 Nathan Road
(Tung Ying Building Redevelopment).
Both are commercial use. The
construction of the Urban Redevelopment Authority (URA) development at Mody Road (hotel
and service apartment use) is almost complete. According to the latest Outline Zoning
Plan, most of the land uses within the study area are commercial use with a few
G/IC, Open Space, Other Specified Uses and a few residential uses along Austin Road. No
planned/committed noise sensitive receiver is identified within the study area
during a site visit conducted on 9-Oct-2007.
4.5.4
In the absence of the programme
of planned/committed noise sensitive developments, construction and fixed noise
impact assessment will only focus on existing NSRs. The representative NSRs selected for
assessments of construction noise and fixed noise have been shown in Figure
4.1. The photographs of the
representative NSRs are shown in Appendix 4.1. Prior agreement with Environmental
Protection Department has been sought on the selected representative assessment
points for quantitative noise assessment.
Construction Noise
4.6.1
The
Project is scheduled to commence in June 2009 and to be completed in 2012. According to the
construction programme, there are seven major construction tasks. Some
individual tasks have different stages.
Table 4.5 summarises the different tasks and the construction
periods. Most of the construction
tasks are planned to be carried out during unrestricted hours. In case of any construction activities
during restricted hours, it is the Contractor’s responsibility to ensure
compliance with the NCO and the relevant TMs. The Contractor will be required to
submit CNP application to the Noise Control Authority and abide by any
conditions stated in the CNP, should one be issued.
Table 4.5 Construction
Tasks Involved
Tasks
|
Description
|
*Construction Period
|
1
|
Plant Building
|
July 2009 to December
2010
|
2
|
Entrance A1
|
November 2010 to November
2011
|
3
|
TST Connection Chamber
|
July 2009 to March 2010
|
4
|
Satellite Concourse
|
November 2009 to January
2012
|
5
|
Subway to TST Station
|
March 2011 to December
2011
|
6
|
Subway to Miramar
Shopping Centre
|
February 2011 to December
2011
|
7
|
Emergency Stair at Miramar Shopping Centre
|
July to August 2009 and
November 2011 to February 2012
|
Note: (*)
Construction period involving use of powered mechanical
equipment only.
4.6.2
The construction noise
assessment has been carried out on a weekly basis from the commencement of the
Project. The construction tasks of
the Project taking place concurrently within 300m of a given NSR are considered to contribute to
the cumulative impact at that NSR.
Noise sources from the areas greater than this distance have been
excluded from the assessment.
4.6.3
In accordance with the EIAO,
the methodology outlined in the GW-TM has been used for the assessment of construction
noise (excluding percussive piling) and reference has been to the EIAO Guidance
Note No.9/2004 on preparing the assessment.
Sound Power Levels (SWLs) of the equipment were taken from Table 3 of this
TM. Where no SWL was supplied in
the GW-TM, reference was made to BS 5228, previous similar studies or from
measurements taken at other sites in Hong Kong.
4.6.4
Schedule of powered mechanical
equipment (PME) for the different construction tasks during normal daytime working
hours is presented in Appendix 4.2.
The proposed plant inventory and utilization rate adopted in the
assessment are considered practical and adequate in achieving the construction
programme. The plant inventory has
been provided as an option and the contractor may propose alternative plant
schedule should it be considered necessary and appropriate.
4.6.5
The assessment is based on the
cumulative SWL of PME likely to be used for each location, taking into account
the construction period in the vicinity of the receiver location. To predict the noise level, PME was
divided into groups required for each discrete construction task. The objective was to identify the worst
case scenario representing those items of PME that would be in use concurrently
at any given time. The sound
pressure level of each construction task was calculated, depending on the
number of plant and distance from receivers. The noise levels at NSRs were then
predicted by adding up the SWLs of all concurrent construction tasks.
4.6.6
Much of the excavation areas
will be decked and this will shield the noise from construction plant operating
below the deck. For example, the
rock drill used for excavation has noise emission but would be totally enclosed
as it will be operated underground below the deck. Considerations will also be
given to the location and the orientation of the temporary fixed noise sources
required for the ventilation of the works area underneath the decked area. If
exhaust above ground is required, it shall be located away from the existing
residential building and facing towards the Kowloon Park
(transient use). If required, silencer will be provided. It is anticipated that
a metal sheet cover with surface density of 10kg/m2 or more covering the excavation
areas would result in at least 20 dB(A) noise reduction. Therefore, a noise reduction of 20 dB(A)
was applied for the activities carried out underground. Schematic diagrams
showing the typical site arrangement of underground works are shown in Figures
4.2 and 4.3.
4.6.7
A positive 3 dB(A) façade
correction was added to the predicted noise levels in order to account for the
facade effect at each NSR.
Fixed Noise in Operation Phase
4.6.8
In the proposed Project two
ventilation shafts, one for exhaust extraction and one for smoke extraction,
would be integrated with the Tung Ying
Building Redevelopment and Hotel Miramar.
4.6.9
Potential noise impacts arising
from the operation of ventilation fans is expected at the sensitive receivers,
and this fixed plant noise impact has been assessed in accordance with the
IND-TM.
4.6.10
Table 4.6 summarises the ventilation shafts would be constructed for the
proposed Project.
Table 4.6 Ventilation
Shafts for the proposed Project
Location
|
Use
|
Tung Ying Building
|
*Exhaust/ Smoke extraction
|
Hotel Miramar
|
*Exhaust/ Smoke extraction
|
Note: (*) The use is either for exhaust or smoke extraction which is still not
finalised in the design.
4.6.11
The ventilation fans for the
smoke extraction and exhaust are all located underground inside the mezzanine
level of the satellite concourse.
4.6.12
The ventilation fans of the
smoke extraction shaft are operated for emergency only, however routine test of
those ventilation fans would be carried out during day time. The potential
impact from the concurrent operation of this shaft during day time period is
assessed in the study.
4.6.13
The assessment assumes that all
duty ventilation fans are operated for each ventilation shaft. Screening corrections from other
buildings / structures and directivity have also been excluded in the assessment. All ventilation fans provided for each
ventilation shaft will be installed with silencers.
4.6.14
In the absence of any detailed
information and noise specification of the proposed fixed plant, the maximum
permissible noise emission levels were determined for future detailed design of
the fixed plant.
4.6.15
For the assessment of noise
from the fixed plant, the maximum permissible sound power levels (Max SWLs) of
the identified fixed noise sources were determined by adopting standard
acoustics principles. The following
formula was used for calculating the Max SWLs of the fixed plant.
SPL = Max SWL – DC + FC
where
·
Sound
Pressure Level, SPL in dB(A)
·
Maximum
Permissible Sound Power Level, Max SWL in dB(A)
·
Distance
Attenuation, DC in dB(A) = 20 log D + 8 [where D is the distance in metres]
·
Façade
Correction, FC in dB(A) = 3 dB(A)
4.6.16
A positive 3 dB(A) was added to
predicted noise levels at the NSRs due to the façade effect.
4.6.17
No corrections have been
applied for tonality, intermittency or impulsiveness. If the noise exhibits any of these
characteristics during the operation of the plant, the noise limit should be
reduced in accordance with the recommendation given in Section 3.3 of IND-TM.
Construction Phase
4.7.1
The scope of this Project includes
modification to the existing Entrance A1 and construction of the plant basement
below; construction of a satellite concourse with integrated entrances to Tung Ying Building
and Hotel Miramar; construction of subways connecting TST station and Miramar
Shopping Centre with an integrated entrance and an emergency exit at Miramar
Shopping Centre. Potential construction impacts of the Project may arise from
the following activities:
·
Demolition
of existing structure of Entrance A1 and construction of the plant basement
below
·
Excavation
at Entrance A1
·
Excavation
at the existing Nathan Road
southbound carriageway and footpath for satellite concourse, connection chamber
and emergency exit
·
Construction
of two subways by mined excavation
·
Road
and pavement reinstatement and earthworks
4.7.2
Driven piling and blast method
would not be adopted for the construction works. The subway would be built
using tunneling by mining method and no tunnel boring machine would be used.
4.7.3
The Tung Ying
Building Redevelopment located nearby the proposed works area of this Project
would be carried out concurrently.
It is expected that the foundation and infrastructure works of the Tung Ying Building Redevelopment will be completed at the
time of the commencement of this Project in June 2009. Consequently, cumulative environmental
impacts contributed from the Tung Ying
Building Redevelopment are envisaged to be insignificant.
4.7.4
Another new commercial
development (iSquare) is found at 63
Nathan Road (ex-Hyatt Regency Hong
Kong Hotel at the junction of Peking Road and Nathan Road) which is about 95m to the south of the new plant basement
works area of the Project. The
commercial development is scheduled to open in 2009 and all infrastructure
construction works are expected to be completed by July 2009 when this Project
start. Hence cumulative
environmental impacts generated from this commercial development are not
anticipated.
Operation Phase
4.7.5
Ventilation noise affecting
sensitive receivers in the study area may arise from the proposed ventilation
shafts under the Project.
Construction Phase
4.8.1
For normal daytime working
hours, exceedences of the construction noise criteria i.e. Leq (30 minutes)
75 dB(A) for residential uses are predicted at representative NSRs in the
absence of mitigation measures.
4.8.2
Details of construction noise
calculations and results are presented in Appendix 4.3. A summary of the unmitigated
construction noise levels of the representative NSRs during normal daytime
working hours within the construction period of the Project is listed in Table
4.7.
Table 4.7 Summary of Unmitigated Construction
Noise Levels at Representative NSRs During Normal
Daytime Working Hours
NSR
ID
|
Predicted
Noise Levels, dB(A)
|
Daytime
Construction Noise Criteria, dB(A)
|
N1
|
56 – 87
|
75
|
N2
|
57 – 81
|
75
|
N3
|
60 - 89
|
75
|
N4
|
62 – 83
|
75
|
*N5
|
62 – 85
|
*75
|
N6
|
46 – 66
|
75
|
N7a
|
55 – 83
|
75
|
N7b
|
46 – 85
|
75
|
Note: (*)
Noise criteria would be applied only if residential use exist in NSR N5 during the period of construction.
4.8.3
Results show that the predicted
noise levels related to the concurrent construction works of the Project at
NSRs N1 to N7 are in the range of 46 to 89 dB(A) and will exceed the EIAO-TM noise criteria by up to 14
dB(A). Mitigation measures are
considered necessary in order to abate the construction noise impacts at all
works areas.
Cumulative Impacts
4.8.4
As described in Sections 4.7.3
and 4.7.4, it is expected that the foundation and infrastructure
works of the Tung Ying Building
Redevelopment and all infrastructure construction works of the construction
site of another commercial development at 63 Nathan Road are expected to be completed
at the time of the commencement of this Project. Thus, cumulative environmental impacts
are not expected.
Operation Phase
4.8.5
The ventilation shafts are
proposed to be installed at the redeveloped Tung Ying
Building and Hotel
Miramar. As the exact locations of the openings of the two ventilation shafts
are still under design, the worst locations (closest to the identified NSRs) at
the facades of the two buildings are assumed for the assessment. The assumed
worst locations for the shaft openings are shown in Figure 4.4. The
potentially worst affected NSR is N5 which is the closest identified NSR. Hence
N5 was selected for the assessment and the corresponding Max SWLs of the
ventilation shafts were determined in accordance with the EIAO-TM criteria by the
methodology stated in Section 4.6.14. Table 4.8 presents a summary of
the required Max SWLs for ventilation shafts proposed in the Project. MTRCL would take the responsibility of
the design and maintenance of the proposed ventilation system and implement the
noise mitigation measures to ensure the noise criteria could be met.
Table 4.8 Summary of
Max SWL for Each Ventilation Shaft
*Source Location
|
**Direction of Shaft Opening
|
Shortest horizontal distance to N5, m
|
Maximum SWL at 0700-2300, dB(A)
|
Maximum SWL at 2300-0700, dB(A)
|
Tung Ying Building
|
West (Nathan Road)
|
17
|
95
|
85
|
South (Granville Road)
|
15
|
94
|
84
|
Hotel Miramar
|
West (Nathan Road)
|
44
|
103
|
93
|
Note: (*) Only
one of the sources would be in operation as the exact locations for exhaust or
smoke extraction are still under design.
(**) The
vent shaft would be located at one direction only. The exact location of the
shaft opening from Tung
Ying
Building is still under
design.
Cumulative Impacts
4.8.6
As described in Sections 4.6.12,
routine test of those ventilation fans of the smoke extraction shaft would be
carried out during day time. Potential cumulative noise impact from the
concurrent operation of both the exhaust and smoke extraction shafts during day
time period is anticipated.
4.8.7
In order to have the overall
noise impact from the two shafts still meeting the daytime noise criteria, the
sound energy from the two shafts should be halfed i.e. the original SWL –
3dB(A). The maximum SWL for the two shafts taking into account the cumulative
effect is summarised in Table 4.9.
Table 4.9 Summary of Max SWL for Each
Ventilation Shaft with Consideration of Cumulative Effect
*Source Location
|
**Direction of Shaft Opening
|
Shortest horizontal distance to N5, m
|
Maximum SWL at 0700-2300, dB(A)
|
Maximum SWL at 2300-0700, dB(A)
|
Tung Ying Building
|
West (Nathan Road)
|
17
|
92
|
85
|
South (Granville Road)
|
15
|
91
|
84
|
Hotel Miramar
|
West (Nathan Road)
|
44
|
100
|
93
|
Note: (*) Assuming
routine test of the smoke extraction would be carried out in 0700 to 2300 hours
only.
4.8.8
As the maximum permissible
sound power levels at the ventilation shafts are derived based on the shortest
horizontal distance from the nearest assessment point, adverse operation noise
impact at all floors of all identified NSRs are not expected provided the fixed
plants are designed to meet the Max SWLs.
4.8.9
Operation noise mitigation measures such as silencer and acoustic
louver will be implemented wherever applicable to ensure that the
above-specified Max SWLs could be achieved.
Construction Noise
4.9.1
In order to reduce the
excessive noise impacts at the affected NSRs during normal daytime working
hours, mitigation measures such as adopting quiet powered mechanical equipment,
movable noise barriers and temporary noise barriers are recommended. It is practical to specify the total SWL
of all plant to be used on site. The Contractors
do not have to use specific items of quiet plant adopted in this assessment,
but to use other type of quiet plant, which have the
same total SWL, to meet their needs.
Adoption of Quieter PME
4.9.2
In order to reduce the
excessive noise impacts at the affected NSRs during normal daytime working
hours, quieter PME are recommended.
The quieter PME adopted in the
assessment were taken from the BS5228: Part 1:1997 and
are presented in Table 4.10. It should be noted that the silenced PME
selected for assessment can be found in Hong Kong.
Table 4.10 Quieter PME Recommended for Adoption
during Construction Phase
PME
|
Power rating/size, weight
|
Reference
|
SWL
|
Hydraulic
Breaker, Excavator mounted
|
52kW
|
BS C8-12
|
106
|
Concrete Lorry Mixer
|
22kW, 6m3
|
BS C6-23
|
100
|
Mobile Crane
|
62kW
|
BS C7-114
|
101
|
Vibratory Poker,
Hand-held
|
2kW each poker
|
BS C6-20
|
102
|
Note: Quieter PME
are not applicable for works below decking.
4.9.3
Whilst quieter PME are listed, the Contractor may be able to obtain particular models of plant that
are quieter than the PMEs given in GW-TM.
Use of Movable Noise Barrier
4.9.4
The use of movable barrier for
certain PME can further alleviate the construction noise impacts. In general, 5 dB(A) reduction for
movable PME and 10 dB(A) for stationary PME can be achieved depending on the
actual design of movable noise barrier. The Contractor
shall be responsible for design of the movable noise barrier with due
consideration given to the size of the PME and the requirement of intercepting
the line of sight between the NSRs and PME. Barrier material of surface mass in
excess of 7 kg/m2
is recommended to achieve the predicted screening effect.
Use of Noise Enclosure/Acoustic Shed
4.9.5
The use of noise enclosure or
Acoustic Shed is to cover stationary PME such as air compressor and concrete
pump. With the adoption of the
noise enclosure, the PME could be completely screened, and noise reduction of
15 dB(A) can be achieved according to the GW-TM.
Use of Silencer
4.9.6
To reduce noise emission from
the ventilation fans, silencers are also recommended to be used in fan
ventilation system to attenuate noise generated during fan operation to achieve
a noise reduction of 15dB(A). The
Contractor shall be responsible for selection of appropriate silencers for the
ventilation fans.
Use of Noise Insulating Fabric
4.9.7
Noise insulating fabric (the
Fabric) can also be adopted for certain PME (e.g. drill rig, pilling auger
etc). The Fabric should be lapped
such that no opening or gaps on the joints. Technical data from manufacturer states
that by using the Fabric, a noise reduction of over 10 dB(A) can be achieved on
noise level (Reference was made from Modifications
to MTRC Tsim Sha Tsui Station Variation of Environmental Permit EP-113/2001/C). As an conservative approach, a noise
reduction of 10 dB(A) for the PME lapped with the Fabric was assumed.
4.9.8
A summary of the assumed noise
reduction effects achieved by the movable noise barrier, noise enclosure,
silencer and fabric for certain item of PME is presented in Table 4.11.
Table 4.11 Noise Mitigation
Measures for Certain PME during Construction Phase
PME
|
Mitigation
Measures Proposed
|
Noise Reduction, dB(A)
|
Air Compressor
|
Noise enclosure
|
15
|
Compactor, vibratory
|
Movable noise barrier
|
5
|
Concrete pump
|
Noise enclosure
|
15
|
Cutter, Circular, Steel
|
Movable noise barrier
|
5
|
Drill rig, rotary type
(diesel)
|
Noise insulating fabric
|
10
|
Electric Winch
|
Movable noise barrier
|
10
|
Grout Mixer
|
Movable noise barrier
|
10
|
Grout Pump
|
Movable noise barrier
|
10
|
Handheld Breaker
|
Movable noise barrier
|
10
|
Hoist, passenger /
material (electric)
|
Movable noise barrier
|
10
|
Pilling, earth auger
|
Noise insulating fabric
|
10
|
Poker, vibratory,
hand-held
|
Movable noise barrier
|
10
|
Saw, concrete
|
Movable noise barrier
|
5
|
Soil pump
|
Movable noise barrier
|
10
|
Ventilation fan
|
Silencer
|
15
|
Ventilation blower
|
Silencer
|
15
|
Water pump
|
Movable noise barrier
|
10
|
Welder/Generator,
portable
|
Movable noise barrier
|
10
|
Note: No mitigation measures are applied for works
below decking.
Mitigated Construction Noise Impacts
4.9.9
With the implementation of all
above-mentioned mitigation measures, the total SWLs of each activity were
predicted, and are presented in Appendix 4.5. The predicted noise levels at most of
the representative NSRs would comply with the EIAO-TM noise criteria. Table 4.12 presents the mitigated
noise levels during normal daytime working hours at NSRs.
Table 4.12 Mitigated Construction
Noise Levels
NSR
|
Predicted
Noise Levels, dB(A)
|
Daytime
Construction Noise Criteria, dB(A)
|
N1
|
42
– 79
|
75
|
N2
|
44
– 75
|
75
|
N3
|
45
– 77
|
75
|
N4
|
47
– 76
|
75
|
*N5
|
48
– 78
|
*75
|
N6
|
43
– 61
|
75
|
N7a
|
45
– 75
|
75
|
N7b
|
46
– 77
|
75
|
Note: (*)
Noise criteria would be applied only if residential use exist in NSR N5 during the period of construction.
Ventilation Noise
4.9.10
With the fixed plant properly
designed to meet the maximum SWL listed in Table 4.8, there would not be
any residual impacts predicted.
However, it is still recommended that the following noise reduction
measures shall be considered as far as practicable during construction:
·
Choose
quieter plant such as those which have been effectively silenced.
·
Include
noise levels specification when ordering new plant (including chillier and E/M
equipment).
·
Locate
fixed plant/louver away from any NSRs as far as practicable.
·
Locate
fixed plant in walled plant rooms or in specially designed enclosures.
·
Locate
noisy machines in a basement or a completely separate building.
·
Install
direct noise mitigation measures including silencers, acoustic louvers and
acoustic enclosure where necessary.
·
Develop
and implement a regularly scheduled plant maintenance programme so that
equipment is properly operated and serviced in order to maintain controlled
level of noise. The programme
should be implemented by properly trained personnel.
Construction
Phase
4.10.1
With the implementation of the
above-mentioned mitigation measures, the construction noise levels at
representative NSRs N2, N6 and N7a
are predicted to comply with the noise standards stipulated in the
EIAO-TM. Residual construction
noise impacts are predicted at NSRs N1, N3, N4, N5 (if N5 would be in residential use during construction phase) and
N7b.
4.10.2
The potential residual impacts
at the affected NSRs are summarised in Table 4.13.
Table 4.13 Construction Noise Residual Impacts
NSR ID
|
Exceedance of the EIAO-TM
Criterion of 75 dB(A)
|
1Approximate number of days with exceedance
|
N1
|
1
|
52 days
|
|
2
|
24 days
|
|
3
|
17 days
|
|
4
|
8 days
|
N3
|
1
|
68 days
|
|
2
|
30 days
|
N4
|
1
|
30 days
|
N7b
|
1
|
5 days
|
|
2
|
25 days
|
Notes: (1) Sums
of individual time periods of exceedance according to the tentative
construction programme
4.10.3
The highest residual construction noise impacts i.e. 4 dB(A)
was predicted at Haiphong Mansion (N1), after implementing the mitigation
measures described in Tables 4.10 and 4.11. The residual construction noise
impacts predicted at Comfort Building (N3) and Burlington Arcade (N4), after
implementing the proposed mitigation measures, are not greater 2 dB(A) and
1dB(A) respectively.
The sums of the individual exceedance duration are summarised in Table
4.14.
Table 4.14 Durations of Construction Noise Residual Impacts
NSR ID
|
1Number of days with exceedance
|
1 to 3 dB(A)
|
4 dB(A)
|
N1
|
93
|
8
|
N3
|
98
|
0
|
N4
|
30
|
0
|
N7b
|
30
|
0
|
Notes: (1) Sum of individual time periods of exceedance
4.10.4
It is not expected that Milton Mansion
(NSR N5) which is currently in commercial use would involve residential use
during the construction period of this Project. However, the potential residual
construction noise impact at this NSR was assessed for this scenario. The residual construction noise impacts
at the NSR are summarised in Table 4.15.
Table 4.15 Construction Noise Residual Impacts at NSR N5
NSR ID
|
Exceedance of the EIAO-TM
Criterion of 75 dB(A)
|
1Approximate number of days with exceedance
|
N5
|
1
|
1 days
|
|
3
|
30 days
|
Notes: (1) Sums
of individual time periods of exceedance according to the tentative
construction programme
4.10.5
The exceedances predicted at
the NSRs were mainly due to the proposed construction works to be carried out at works areas of the new plant basement, TST
connection chamber and the satellite concourse. The PME inventory
adopted for these works has been reviewed. However, the number
of proposed PME for each construction activity was found to be minimal and
further reduction of the PME number would be impractical for carrying out the
construction works. In
addition, re-scheduling of the construction programme has been considered. Since the
residual construction noise impacts at the sensitive receivers are mainly due
to the close proximity of the works area, re-scheduling of the construction programme could not be useful in mitigating the residual
impacts.
4.10.6
The feasibility of
installing additional mitigation measure in terms of a large noise
barrier/enclosure around the site areas has also
been considered. However, implementing a large noise
barrier/enclosure as an additional mitigation measure would cause the following
inconvenience and environmental problems:
More
area at the existing traffic lane and pedestrian path would be occupied due to
the foundation of the large noise barrier/enclosure i.e. inconvenience to the
pedestrians and drivers.
Elongated
the construction period and additional potential construction noise impact from
the installation/un-installation of the noise barrier/enclosure.
Visual
impact to the pedestrians and the nearby residential buildings, shops and
hotel, especially low level receivers will be very significant.
Massive
arrangement would be lead to safety problem in case of emergency.
Mucking
out opening could not be arranged in a flexible manner to suit the progress of
the excavation. Energy and time
wastage in handling of spoil via long routing to the opening would be anticipated.
4.10.7
The longest duration of noise
exceedance predicted is about 101 days (93 days of 1 to 3 dB(A) and 8 days of 4
dB(A)) at NSR N1. In considering the environmental benefits and the potential
inconvenience/problems that may arise, it is considered that a large noise
barrier/enclosure not a practical further mitigation measure.
4.10.8
Nevertheless, the good site
practices listed below shall be adopted by all Contractors to further
ameliorate the noise impacts.
Although the noise mitigating effects are not easily quantifiable and
the benefits may vary with the site conditions and operating conditions, good
site practices are easy to implement and do not impact upon the works schedule.
·
Only
well-maintained plant shall be operated on-site and plant shall be serviced
regularly during the construction program.
·
Silencers
or mufflers on construction equipment shall be utilised and shall be properly
maintained during the construction program.
·
Mobile
plant, if any, shall be sited as far away from NSRs as possible.
·
Machines
and plant (such as trucks) that may be in intermittent use shall be shut down
between works periods or shall be throttled down to a minimum.
·
Plant
known to emit noise strongly in one direction shall, wherever possible, be
orientated so that the noise is directed away from the nearby NSRs.
·
Material
stockpiles and other structures shall be effectively utilised, wherever
practicable, in screening noise from on-site construction activities.
Operation Phase
4.10.9
No adverse operation residual
noise impact are envisaged if the noise emissions from the proposed fixed plant
are designed to meet the maximum allowable sound power level with appropriate
noise reduction measures in place.
4.11
Environmental Monitoring
and Audit
Construction Noise
4.11.1
An EM&A programme is
recommended to be established according to the predicted occurrence of noisy
activities. All the recommended
mitigation measures for daytime normal working activities shall be incorporated
into the EM&A programme for implementation during construction. Given the study area is highly
interfered by the heavy traffic at Nathan
Road, manned regular noise monitoring is
recommended. Details of the programme are provided in the stand-alone EM&A
Manual. As residual noise impact is predicted in this study, it is recommended
to set up a community liaison channel to handle any public enquiry and
complaint.
Operation Noise
4.11.2
Any
necessary mitigation measures would be implemented to ensure the compliance of the operation noise levels with the EIAO-TM noise
criteria.
Construction Phase
4.12.1
Noise arising from the
construction activities of the project will have unavoidable potential impact
on the NSRs located in the vicinity of the works areas. Unmitigated cumulative construction
noise levels at the representative NSRs are predicted, which are found to be in
the range of 46 to 89 dB(A), exceeding the EIAO-TM daytime construction noise
limit by up to 14 dB(A).
4.12.2
Mitigation measures are
recommended to reduce the noise levels to within the EIAO-TM noise criterion,
including good site practices, quieter plant, silencer, movable noise barrier
and decking over the excavation areas.
With the recommended mitigation measures in place, noise levels at most
of the NSRs are predicted to comply with the EIAO-TM daytime construction noise
criterion and no adverse residual construction noise impact is expected. Some NSRs, including N1, N3 and N4
located in close proximity to the works areas, would still be exposed to
exceedances by 1 to 4dB(A) for short term.
4.12.3
Whilst
this impact assessment does indicate some noise exceedances for limited periods
of time, even with the consideration of all practicable mitigation measures,
during the actual construction period as much as practically possible will be done
to reduce construction noise still further, and there will be on-going liaison
with all concerned parties and site monitoring to deal with and minimise any
exceedances.
4.12.4
A
construction noise EM&A programme is recommended to check the compliance of
the noise criteria during normal daytime working hours. As residual noise impact is predicted in this study, it is
recommended to set up a community liaison channel to handle any public enquiry
and complaint.
Operation Phase
4.12.5
The assessment results indicated
that predicted noise levels at all NSRs arising from the fixed plant of the
Project will comply with the EIAO-TM criteria, with the noise emissions from
the fixed plant controlled to achieve the specified Max SWL by proper noise
reduction measures. Thus, no
adverse fixed plant noise impacts are expected.
5.
construction water
quality impact
5.1.1
This section assesses the water
quality impact during construction in accordance with the criteria and
guidelines given in Annex 6 and Annex 14 of the EIAO TM. Clause 3.5.4
of the EIA Study Brief sets out the scope and requirements of the assessment.
5.1.2
As the construction activities
of the Project will be land-based, direct impacts on water bodies will not
arise. Nevertheless, the
construction activities at the works area may generate surface run-off which
may cause adverse water quality impacts if not properly controlled or
mitigated. Recommendations for
mitigation measures have been made, where necessary, to reduce the identified
water quality impacts to an acceptable level.
5.2.1
The criteria for evaluating
water quality impacts in this EIA Study include:
·
Technical
Memorandum on Environmental Impact Assessment Process (Environmental Impact Assessment
Ordinance) (EIAO TM);
·
Water
Pollution Control Ordinance (WPCO);
·
Technical
Memorandum on Standards for Effluents Discharged into Drainage and Sewerage
Systems, Inland and Coastal Waters (TM-DSS);
·
Hong Kong Planning Standards and Guidelines (HKPSG); and
·
Practice
Note for Professional Persons (ProPECC), Construction Site Drainage (PN1/94).
5.3.1
The EIAO TM was issued by the
EPD under Section 16 of the EIAO.
It specified the assessment method and criteria that was followed in
this Study. Reference sections in
the EIAO TM provide the details of assessment criteria and guidelines that are
relevant to the water quality assessment, including:
·
Annex
6 – Criteria for Evaluating Water
Pollution; and
·
Annex
14 – Guidelines for Assessment of Water Pollution.
5.4.1
The Water Pollution Control Ordinance (Cap. 358), in existence since
1980, is the major legislation relating to the protection and control of water
quality in Hong Kong. According to the Ordinance and its
subsidiary legislation, Hong Kong waters are
divided into ten water control zones (WCZ). Corresponding statements of Water
Quality Objectives (WQO) are stipulated for different water regimes (marine
waters, inland waters, bathing beaches subzones, secondary contact recreation
subzones and fish culture subzones) in each of the WCZ based on their
beneficial uses. The study area is
located within the Victoria Harbour
WCZ and the corresponding WQO are listed in Table 5.1.
Table 5.1 Summary
of Water Quality Objectives for Victoria Harbour WCZ
|
Objectives
|
Sub-Zone
|
Offensive Odour, Tints
|
Not to be present
|
Whole zone
|
Colour
|
Not to exceed 50 Hazen units, due to human activity
|
Inland waters
|
Visible foam, oil scum, litter
|
Not to be present
|
Whole zone
|
E. coli
|
Not to exceed 1000 per 100 mL, calculated as the geometric mean of the
most recent 5 consecutive samples taken at intervals of between 7 and 21 days
|
Inland waters
|
Dissolved Oxygen (DO) within 2 m
of the seabed
|
Not less than 2.0 mg L-1 for 90% of samples
|
Marine waters
|
Depth-averaged DO
|
Not less than 4.0 mg L-1 for 90% of samples
|
Marine waters
|
Dissolved Oxygen
|
Not less than 4.0 mg L-1
|
Inland waters
|
pH
|
To be in the range of 6.5
- 8.5, change due to human activity not to exceed 0.2
|
Marine waters
|
|
Not to exceed the range of 6.0 - 9.0 due to human activity
|
Inland waters
|
Salinity
|
Change due to human activity not to exceed 10% of ambient
|
Whole zone
|
Temperature
|
Change due to human activity not to exceed 2 oC
|
Whole zone
|
Suspended solids
|
Not to raise the ambient level by 30% caused by human activity
|
Marine waters
|
|
Annual median not to exceed 25 mg L-1 due to human activity
|
Inland waters
|
Ammonia
|
Annual mean not to exceed 0.021 mg L-1 as unionised form
|
Whole zone
|
Nutrients
|
Shall not cause excessive algal growth
|
Marine waters
|
|
Annual mean depth-averaged inorganic nitrogen not to exceed 0.4 mg L-1
|
Marine waters
|
BOD5
|
Not to exceed 5 mg L-1
|
Inland waters
|
Chemical Oxygen Demand
|
Not to exceed 30 mg L-1
|
Inland waters
|
Toxic substances
|
Should not attain such levels as to produce significant toxic,
carcinogenic, mutagenic or teratogenic effects in humans, fish or any other
aquatic organisms.
|
Whole zone
|
|
Human activity should
not cause a risk to any beneficial use of the aquatic environment.
|
Whole zone
|
Source: Statement
of Water Quality Objectives (Victoria Harbour
(Phases One, Two and Three) Water Control Zone).
5.5.1
Besides setting the WQOs, the
WPCO controls effluent discharging into the WCZs through a licensing
system. Guidance on the permissible
effluent discharges based on the type of receiving waters (foul sewers, storm
water drains, inland and coastal waters) is provided in the Technical Memorandum (TM) on Standards for
Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal
Waters. The limits given in the
TM cover the physical, chemical and microbial quality of effluents. Any effluent discharge during the
construction stage should comply with the standards for effluents discharged
into the inshore waters of the Victoria
Harbour WCZ, as shown in Table 9a
of the TM.
5.6.1
A practice note (PN) for
professional persons was issued by the EPD to provide environmental guidelines
for handling and disposal of construction site discharges. The ProPECC PN 1/94 “Construction Site
Drainage” provides good practice guidelines for dealing with various types of
discharge from a construction site.
Practices outlined in the PN shall be followed as far as possible during
construction to minimize the water quality impact due to construction site
drainage.
5.7.1
With the implementation of Harbour Area Treatment Scheme (HATS) Stage
1, the water quality in middle portion of the Victoria Harbour has been improved.
5.7.2
EPD’s routine water quality
monitoring programme data from stations VM5 and VM6 (Figure 5.1), which
are nearest to the Project site, provides an acceptable reference of the
baseline water quality for the Project.
According to the “2006 Marine Water Quality in Hong
Kong” published by the Environmental Protection Department (EPD),
a summary of the monitoring data at these stations is given in Table 5.2.
Table 5.2 Marine Water Quality
of Victoria
Harbour WCZ at the Selected Monitoring Station in 2006
Determinand
|
Monitoring Station
|
WPCO WQOs
(in marine waters)
|
VM5
|
VM6
|
Temperature (oC)
|
23.7 (17.4-27.5)
|
23.6 (17.5-27.4)
|
natural daily level ± 2 oC
|
Salinity (psu)
|
31.4 (27.3-32.8)
|
31.5 (27.3-32.8)
|
natural ambient level ± 10 %
|
Dissolved Oxygen (mg/L)
|
5.5 (4.3-7.1)
|
5.5 (4.0-6.9)
|
³ 4 mg L-1
|
Dissolved Oxygen Bottom (mg/L)
|
5.4 (3.8-7.3)
|
5.4 (2.7-7.2)
|
³ 2 mg L-1
|
Dissolved Oxygen (% Saturation)
|
77 (65-91)
|
78 (60-89)
|
N/A
|
Dissolved Oxygen Bottom
(% Saturation)
|
76 (56-94)
|
75 (40-93)
|
N/A
|
pH
|
7.9 (7.7-8.1)
|
7.9 (7.7-8.1)
|
6.5 - 8.5 (± 0.2 from natural range)
|
Secchi Disc Depth (m)
|
1.8 (1.4-2.7)
|
2.1 (1.5-2.7)
|
N/A
|
Turbidity (NTU)
|
11.6 (6.5-18.5)
|
11.1 (5.2-14.2)
|
N/A
|
Suspended Solids (mg/L)
|
4.6 (1.7-8.9)
|
4.5 (2.0-8.9)
|
£ natural ambient level + 30%
|
BOD5 (mg/L)
|
1.0 (0.2-1.9)
|
0.8 (0.1-1.8)
|
not applicable to marine waters
|
Ammonia Nitrogen (mg/L)
|
0.16 (0.09-0.30)
|
0.16 (0.11-0.25)
|
N/A
|
Unionized Ammonia (NH3-N) (mg/L)
|
0.005 (0.003-0.008)
|
0.005 (0.003-0.007)
|
£ 0.021 mg L-1
|
Nitrite Nitrogen (mg/L)
|
0.027 (0.009-0.093)
|
0.027 (0.009-0.095)
|
N/A
|
Nitrate Nitrogen (mg/L)
|
0.12 (0.04-0.27)
|
0.13 (0.04-0.28)
|
N/A
|
Total Inorganic Nitrogen (TIN) (mg/L)
|
0.31 (0.14-0.50)
|
0.32 (0.16-0.51)
|
£ 0.4 mg L-1
|
Total Kjeldahl Nitrogen (mg/L)
|
0.40 (0.25-0.58)
|
0.38 (0.29-0.59)
|
N/A
|
Total Nitrogen (mg/L)
|
0.55 (0.30-0.83)
|
0.53 (0.34-0.73)
|
N/A
|
Ortho-phosphate (mg/L)
|
0.03 (0.02-0.04)
|
0.03 (0.02-0.05)
|
N/A
|
Total-Phosphorus (mg/L)
|
0.06 (0.03-0.08)
|
0.06 (0.03-0.08)
|
N/A
|
Silica (as SiO2) (mg/L)
|
0.9 (0.3-1.7)
|
0.9 (0.3-1.8)
|
N/A
|
Chlorophyll-a (mg/L)
|
2.8 (0.9-8.6)
|
2.9 (0.9-10.1)
|
N/A
|
E.coli (cfu/100mL)
|
7700 (1900-22000)
|
5500
(650-33000)
|
not applicable to marine waters
|
Faecal Coliforms (cfu/100mL)
|
19000 (3500-65000)
|
13000 (2500-10000)
|
N/A
|
Note: 1. Except
as specified, data presented are depth-averaged results.
2.
Depth-averaged results at each station are calculated
as arithmetic means of measurements at all available depths (i.e. S, M, B)
except for E.coli and faecal
coliforms which are geometric means.
3.
Data presented are annual arithmetic means except for E.coli and faecal coliforms which are
annual geometric means.
4.
Data enclosed in brackets indicate the ranges.
5.
Shaded cells indicate non-compliance with the WQOs.
5.7.3
Full compliance with the WQO
for depth-averaged and bottom dissolved oxygen and depth-averaged NH3-N
was achieved at VM5 and VM6 in
2006.
5.8.1
The assessment of the potential
impact of land-based construction activities on water quality has been
undertaken in a qualitative manner.
Consideration has been given to controlling potentially harmful impacts
from site works and to the use of ‘best’ practice measures to minimise the
potential for discharges of pollutants to the nearby waters of the Victoria
Harbour. The assessment of potential water
pollution impacts of this Project has involved the following tasks:
·
identifying
water sensitive receivers in the vicinity of this Project;
·
defining
type and extent of construction activities with the potential to affect water
quality;
·
identifying
specific locations of those construction activities;
·
assessing
the potential impacts arising from the construction activities of the Project;
and
·
recommending
mitigation measures for minimising any identified adverse impacts on water
quality associated with the Project.
5.9.1
The closest water receiving
body in the vicinity of the project site is the Victoria
Harbour WCZ. Due to the highly
urbanised nature of Kowloon
Peninsula, there are no
natural streams located within 300m
from the works site boundary.
5.9.2
There are no marine biological
sensitive receivers such as mariculture zones, commercial fisheries, or shell
fisheries within the vicinity of the construction site.
5.10.1
Potential sources of water
quality impact associated with the proposed construction activities at the
works areas of the Project have been identified and include:
·
construction
runoff and drainage;
·
underground
works;
·
sewage
effluent; and
·
general
construction activities.
5.11
Evaluation of Potential Water
Quality Impacts
Construction Runoff and drainage
5.11.1
Construction site runoff
comprises:
·
runoff
and erosion from exposed soil surface, drainage channels and earth working
areas;
·
wash
water from dust suppression sprays and wheel washing facilities; and
·
fuel,
oil and lubricants from construction vehicles and equipment.
5.11.2
Construction runoff may cause
physical, chemical and biological effects.
Any increase in sediment loads and debris from the site could accumulate,
leading to blocked drainage channels, and associated local flooding when heavy
rainfall occurs, as well as affecting the water quality in Victoria Harbour.
5.11.3
Chemical and biological effects
may also arise as a result of construction runoff. Primary chemical effects may result from
liquids containing significant amounts of concrete and cement-derived
materials, including concrete wash.
These may include localised increase in turbidity and discoloration,
elevation in pH, and accretion of solids.
A number of secondary effects may also result in toxic effects to water
biota due to elevated pH values, reduce decay rates of faecal micro-organisms and
photosynthetic rate due to the decreased light penetration.
5.11.4
No adverse water quality
impacts are expected at the Victoria
Harbour WCZ given a considerable distance of the WSR from the Project site
(more than 0.5 km
away). All construction works for
the Project will take place in-land and within the proposed work area. With the implementation of adequate
construction site drainage and provision of silt removal facilities at the work
areas as described in Section 5.13.2, there
will not be any direct water quality impacts on the Victoria
Harbour WCZ.
Underground Works
5.11.5
During wet periods, rainfall
and surface runoff entering exposed underground works area can lead to
construction runoff with high suspended solids (SS) content. Mitigation shall be designed to reduce
the influx of rainwater into the exposed underground works area.
5.11.6
Surface runoff may also be
contaminated by grouting chemicals that would be required for the temporary
walling works. The wastewater
generated during the underground works will contain high concentrations of SS
and require settlement prior to discharge.
Oil interceptors shall also be installed to remove the oil, lubricants
and grease from the wastewater arising from the underground works.
5.11.7
Ingressive groundwater would be pumped out from underground works area. Pumped water having a high content of SS should be treated on-site
prior to off-site discharge.
Sewage Effluent
5.11.8
Sewage is characterised by high
levels of BOD, ammonia and E.coli. Sewage generated from the construction
workforce will have the potential to cause water pollution. However,
limited quantity of sewage would be generated, which is mainly arising from the
sanitary facilities provided on-site.
5.12.1
On-site construction activates
may cause water pollution from the following:
·
Uncontrolled
disposal of debris and rubbish such as packaging,
construction materials and refuse etc; and
·
Spillages
of liquid stored on-site, such as oil, diesel and solvents etc.
5.12.2
However, the effects on water
quality from these construction activities
are likely to be minimal, provided that site boundaries are well maintained and
good construction practices are implemented to ensure that litter, fuel and
solvents are stored and handled properly, as detailed in Sections 6.9.8
– 6.9.9.
5.13.1
Recommended mitigation measures
for containing and minimizing potential water quality impacts during the
construction activities are described below.
Construction Runoff and Site Drainage
5.13.2
Construction runoff and site
drainage should be prevented or minimized in accordance with the guidelines
stipulated in ProPECC PN 1/94 “Construction Site Drainage”. The specified mitigation measures and
practices include the following:
·
Provision
of perimeter drains to intercept off-site water around the site with internal
drainage works and erosion and sedimentation control facilities implemented. These shall be constructed in advance of
site formation works and earthworks. Earth bunds or sand bag barriers shall be
provided on-site to direct storm water to silt removal facilities. The design of the temporary on-site
drainage system will be undertaken by the Contractor prior to the commencement
of construction.
·
All
drainage facilities and erosion and sediment control structures shall be
regularly inspected and maintained to ensure proper and efficient operation at
all times and particularly during rainstorms. Deposited silt and grit shall be
regularly removed, at the onset of and after each rainstorm to ensure that
these facilities are functioning properly at all times.
·
Exposed
slope/soil surface shall be covered by tarpaulin as soon as possible to reduce
the potential of soil erosion.
Arrangements should always be in place to ensure that adequate surface
protection measures can be safely carried out well before the arrival of a
rainstorm. Other measures that need
to be implemented before, during and after rainstorms are summarized in ProPECC
PN 1/94.
·
Open
stockpiles of construction materials (e.g. aggregates, sand and fill material)
or construction wastes on-site of more than 50m3 shall be covered with tarpaulin or
similar fabric during rainstorms.
·
Construction
works shall be programmed to minimise surface excavation works during the rainy
seasons (April to September). All
exposed earth areas shall be completed and vegetated as soon as possible after
earthworks have been completed, or alternatively, within 14 days of the
cessation of earthworks where practicable.
If excavation of soil cannot be avoided during the rainy season, or at
any time of year when rainstorms are likely, exposed surfaces shall be covered
by tarpaulin or other means.
·
Manholes
shall always be adequately covered and temporarily sealed so as to prevent
silt, construction materials or debris being washed into the drainage system
and storm runoff being directed into foul sewers.
·
Precautions
be taken at any time of year when rainstorms are likely, actions to be taken
when a rainstorm is imminent or forecasted, and actions to be taken during or
after rainstorms are summarised in Appendix A2 of ProPECC PN 1/94.
·
All
vehicles and plant should be cleaned before leaving a construction site to
ensure no earth, mud, debris and the like is deposited by them on roads. An adequate designed and sited wheel
washing facilities shall be provided at every construction site exit, where
practicable. Wash-water shall have
sand and silt settled out and removed at least on a weekly basis to ensure the
continued efficiency of the process.
The section of access road leading to, and exiting from, the wheel-wash
bay to the public road shall be paved with sufficient backfall toward the
wheel-wash bay to prevent vehicle tracking of soil and silty water to public
roads and drains.
·
Oil
interceptors shall be provided in the drainage system downstream of any
oil/fuel pollution sources. The oil
interceptors shall be emptied and cleaned regularly to prevent the release of
oil and grease into the storm water drainage system after accidental
spillage. A bypass shall be
provided for the oil interceptors to prevent flushing during heaving rain.
·
Construction
solid waste, debris and rubbish on site shall be collected, handled and
disposed of properly to avoid water quality impacts. Requirements from solid waste management
are detailed in Section 6 of the Report.
5.13.3
By adopting the above
mitigation measures with Best Management Practices (BMPs), no adverse water
quality impact of construction runoff and site drainage is anticipated.
Underground Works
5.13.4
Underground works shall be
conducted sequentially to limit the amount of construction runoff generated
from exposed areas during the wet season (April to September).
5.13.5
Uncontaminated discharge shall
pass through settlement tanks prior to off-site discharge. A discharge licence
under the WPCO would be required for discharge to the stormwater drain. It may be a stipulation of the WPCO
licence to require the Contractor to monitor the quality/quantity of the
discharge to show compliance with the conditions of the licence.
5.13.6
The wastewater, including
surface runoff and ingressive groundwater in underground area, with a high concentration
of SS shall be treated (e.g. by settlement in tanks with sufficient retention
time) before discharge. Oil
interceptors shall also be installed to remove the oil, lubricants and grease
from the wastewater.
Sewage Effluent
5.13.7
Temporary sanitary facilities,
such as portable chemical toilets, shall be employed on-site where necessary to
handle sewage from the workforce. A
licensed contractor would be responsible for appropriate disposal of waste
matter and maintenance of these facilities.
5.14.1
Debris and rubbish generated
on-site shall be collected, handled and disposed of properly to avoid being
flushed or blown by wind into the drainage culvert. Stockpiles of cement and other
construction materials should be kept covered when not being used.
5.14.2
Oils and fuels shall only be
used and stored in designated areas which have pollution prevention
facilities. To prevent spillage of
fuels and solvents, all fuel tanks and storage areas shall be provided with locks
and be sited on sealed areas, within bunds of a capacity equal to 110% of the
storage capacity of the largest tank.
The bund shall be drained of rainwater after a rain event.
5.15
Evaluation of Residual Impacts
5.15.1
With the full implementation of
the recommended mitigation measures for the construction phase of the proposed
Project, no unacceptable residual impacts on water quality are expected.
5.16.1
Water quality monitoring is not
considered necessary during the construction phase as no unacceptable water
quality impact is expected.
However, it is recommended that regular site inspections be undertaken
to inspect the construction activities and works area in order to ensure the
recommended mitigation measures are properly implemented. Any effluent discharges from the site
will be required to comply with the terms and conditions of a discharge
licence, issued by EPD, under the WPCO.
5.17.1
The key issue in terms of water
quality during the construction phase of the Project is construction runoff and
site drainage, underground works, sewage effluent and general construction site
activities. Minimisation of water
quality deterioration can be achieved through implementing adequate mitigation
measures such as control measures on site runoff and drainage from the works
areas to minimise construction runoff, and on-site treatment of site runoff and
drainage prior to discharge. Proper
site management and good housekeeping practices will also be required to ensure
that construction wastes and other construction-related materials will not
enter the drainage culvert. Sewage
effluent arising from the construction workforce shall also be handled through
provision of portable toilets.
5.17.2
With the implementation of
these recommended mitigation measures (Section 5.13), the construction
works for the Project is not expected to result in unacceptable impacts on
water quality. Site inspections
shall be undertaken routinely to inspect the works areas in order to ensure the
recommended mitigation measures are properly implemented.
6.
waste management
6.1
Introduction
6.1.1
This section identifies the
types of solid wastes that are likely to be generated during the construction
phase of the Project and evaluates the potential environmental impacts that may
result from these wastes in accordance with the criteria and guidelines given
in Annex 7 and Annex 15 of the EIAO TM.
6.1.2
It is recognised that the
quantity of waste associated with the construction works is relatively small
and will mainly involve excavated material. Besides, given the progressive nature of
the construction works, the quantity of excavated material generated daily
would be limited. Nevertheless,
given the density of the built-up area surrounding the project site, proper
waste management is considered necessary to avoid generation of any significant
environmental impact associated with the handling, collection and disposal of
construction waste. Environmental
mitigation measures required to mitigate these environmental impacts were
identified and recommended.
6.1.3
Waste management during the
operational phase will be similar to the existing operation of TST MTR Station
and the other MTR Stations and is not expected to be key issue of the EIA
study.
6.2.1
The criteria and guidelines for
assessing waste management implications are set out in Annex 7 and Annex 15 of
the Technical Memorandum on Environmental
Impact Assessment Process (EIAO-TM), respectively.
6.2.2
The following legislation
relates to the handling, treatment and disposal of wastes in the Hong Kong SAR
and has been used in assessing potential impacts:
·
Waste
Disposal Ordinance (Cap. 354)
·
Waste
Disposal (Chemical Waste) (General) Regulation (Cap. 354)
·
Land
(Miscellaneous Provisions) Ordinance (Cap. 28)
·
Public
Health and Municipal Services Ordinance (Cap. 132) - Public Cleansing and
Prevention of Nuisances Regulation
6.3.1
The Waste Disposal Ordinance (WDO) prohibits the unauthorised disposal
of wastes. Construction waste is
defined as any substance, matter or thing that is generated from construction
work and abandoned, whether or not it has been processed or stockpiled before
being abandoned, but does not include any sludge, screenings or matter removed
in or generated from any desludging, desilting or dredging works. Under the WDO, wastes can be disposed of
only at designated waste disposal facilities.
6.3.2
Under the WDO, the Chemical Waste (General) Regulation 1992
provides regulations for chemical waste control, and administers the
possession, storage, collection, transport and disposal of chemical
wastes. The Environmental
Protection Department (EPD) has also issued a ‘guideline’ document, the Code of Practice on the Packaging, Labelling
and Storage of Chemical Wastes (1992), which details how the Contractor
should comply with the regulations on chemical wastes.
6.3.3
The Public Cleansing and Prevention of Nuisances Regulation provides
control on illegal tipping of wastes on unauthorised (unlicensed) sites.
6.4.1
The current policy related to
the disposal of C&D material is documented in the Works Branch Technical
Circular No. 2/93, ‘Public Dumps’. Construction and demolition materials
that are wholly inert, namely public fill, should not be disposed of to
landfill, but taken to public filling areas, which usually form part of
reclamation schemes. The Land (Miscellaneous Provisions) Ordinance
requires that dumping licences be obtained by individuals or companies who
deliver public fill to public fill reception facilities. The Civil Engineering & Development
Department (CEDD) issues the licences under delegated powers from the Director
of Lands.
6.4.2
Under the Waste Disposal (Charges for Disposal of Construction Waste) Regulation,
enacted in January 2006, construction waste delivered to a landfill for
disposal must not contain more than 50% by weight of inert material. Construction waste delivered to a
sorting facility for disposal must contain more than 50% by weight of inert material,
and construction waste delivered to a public fill reception facility for
disposal must consist entirely of inert material.
6.4.3
Measures have been introduced
under Environment, Transport and Works Bureau (ETWB) TCW No. 33/2002,
“Management of Construction and Demolition Material Including Rock” to enhance
the management of construction and demolition material, and to minimize its
generation at source.
6.5.1
The criteria for assessing
waste management implications are outlined in Annex 7 of the EIAO-TM. The methods for assessing potential
waste management impacts during the construction phase follow those presented
in Annex 15 of the EIAO-TM and include the following:
·
Estimation
of the types and quantities of the wastes to be generated.
·
Assessment
of potential impacts from the management of solid waste with respect to
potential hazards, air and odour emissions, noise, wastewater discharge and
transport.
·
Assessment
of impacts on the capacity of waste collection, transfer and disposal
facilities.
6.6.1
The construction activities to
be carried out for the proposed Project will generate a variety of wastes that
can be divided into distinct categories based on their composition and ultimate
method of disposal. The identified
waste types include:
·
Construction
and demolition (C&D) materials
·
General
refuse
·
Chemical
waste
6.6.2
Each type of waste arising is
described below, together with an evaluation of the potential environmental
impacts associated with generation, handling, storage, transport and disposal
of each waste type. Prior to
consideration of disposal options for each waste type, opportunities for waste
reduction, reuse, or recycling were identified.
Construction and Demolition Materials
6.6.3
The main construction and
demolition (C&D) materials is excavated material from underground
works. The estimated total volume
of C&D material is estimated to be 26,160m3. A breakdown of the estimated quantities
of C&D materials from the different work areas of the Project is given in Table
6.1.
Table 6.1 Estimated
Quantities of C&D Materials
Construction
|
Rock, m3
|
Artificial Hard
Material, m3
|
Soil Materials, m3
|
|
Area
|
Grade
III or above – MDG/SDG
|
Bituminous
/
Concrete
pavement
|
Fill
|
Grade IV
|
Others
|
Total, m3
|
& V
|
|
Plant basement
|
2400
|
125
|
2600
|
3025
|
435
|
8585
|
TST Connection Chamber
|
0
|
15
|
115
|
135
|
135
|
400
|
Satellite Concourse
|
410
|
210
|
2640
|
2640
|
2310
|
8210
|
Subway TST
|
0
|
170
|
0
|
3390
|
105
|
3665
|
Subway MSC
|
4,150
|
175
|
0
|
105
|
0
|
4430
|
Emergency stair at MSC
|
585
|
15
|
80
|
80
|
110
|
870
|
|
|
|
|
26,160
|
6.6.4
Based on the current scheme for
the northern subway, an estimated total quantity of approximately 3,140m3 imported general fill
is required for backfilling the plant basement, TST connection chamber and
satellite concourse. The
possibility to retain some of the excavated material generated on-site for
subsequently reuse as backfill material after the completion of the
construction was evaluated with Project Engineers but not considered
practicable. Given the necessary
lane-by-lane progressive approach to the construction activities in order to
maintain the traffic on Nathan
Road, the works area available for the
construction works will be very limited.
Storage of excavated material on-site is not considered practicable as
the site is small and could become a source of nuisance to the public and
concerns on the nearby OVTs; and therefore, there are constraints on reused on
C&D Material. Nonetheless, the possibilities for re-use/ temporary storage
of C&D material will be further explored by the Contractor.
Table 6.2 Summary of C&D Materials Generated,
Reused and Disposed
C&D materials
|
Quantity of
C&D Material m3
|
|
General
|
Reused
(with constraints)
|
Disposed
|
Soil Material
|
Fill
|
5,435
|
2,140
|
3,295
|
Grade IV & V
|
9,375
|
1,000
|
8,375
|
Others
|
3,095
|
0
|
3,095
|
Rock
|
Grade III as above
– MDG/SDG
|
7,545
|
0
|
7,545
|
Artificial material
|
Bituminous/Concrete
pavement
|
710
|
0
|
710
|
|
Sub Total
|
26,160
|
3,140
|
23,020
|
6.6.5
The Construction Contractor
should prepare a Waste Management Plan (WMP) on waste reduction, re-use,
recycling and disposal practice. The excavated material is expected to be the
only major source of C&D materials, which will be inert suitable for reuse
in public fill reception facility.
The amount on C&D waste will be insignificant and shall be disposed
of at landfills when encountered.
Owing to a small amount of C&D generated in this project (max of
26,160m3), the surplus
material might be disposed of at the planned Construction and Demolition
(C&D) Material Handling Facility at TKO Area 137, as the last resort.
6.6.6
The excavated material
generated daily onsite shall be delivered to a truck parked within the works
area and delivered to another project site, a public fill reception facility or
other reclamation sites as appropriate.
Assuming a 8 hours working day and a truck capacity of 7.5m3, it can be calculated that
the average number of trucks involved is 0.6 per hour.
6.6.7
The final destinations of the
excavated material will be determined, subject to the availability of public
fill reception facilities, by the Waste Management Plan to be prepared by the
Contractor and agreed with CEDD.
Provided that a trip-ticket system is established for the disposal of
the inert C&D material, as recommended in Section 6.9.2,
and that good site practices are adhered to, adverse environmental impacts and
nuisance would not be expected.
6.6.8
The generation of C&D
materials is considered to be small and is not envisaged to have any adverse
impact on the capacity of landfills and public fill reception facilities.
Chemical Waste
6.6.9
The maintenance and servicing
of construction plant and equipment may generate some chemical wastes such as
cleaning fluids, solvents, lubrication oil and fuel. It is difficult to quantify the amount
of chemical waste that will arise from the construction activities since it
will be dependent on the Contractor’s on-site maintenance requirements and the
amount of plant utilised. Because of the limited available works area, there would only be
very limited maintenance and servicing of plant and equipment on-site. It is
anticipated that the quantity of chemical waste, such as lubricating oil and
solvent produced from plant maintenance, will be small and in the order of a
few cubic metres per month. The
amount of chemical waste to be generated will be quantified in the site Waste
Management Plan to be prepared by the Contractor.
6.6.10
Chemical wastes arising during
the construction phase may pose environmental, health and safety hazards if not
stored and disposed of in an appropriate manner as stipulated in the Waste Disposal (Chemical Waste) (General)
Regulations. The potential
hazards include:
·
Toxic
effects to workers
·
Adverse
impacts on water quality from spills
·
Fire
hazards
6.6.11
Materials classified as
chemical wastes will require special handling and storage arrangements before
removal for appropriate treatment at the Chemical Waste Treatment Centre (CWTC)
or other licensed facility.
Wherever possible opportunities should be taken to reuse and recycle
materials. Mitigation and control requirements for chemical wastes are detailed
in Section 6.9.8. Provided that the handling, storage and
disposal of chemical wastes are in accordance with these requirements, adverse
environmental impacts would not be expected to result.
General Refuse
6.6.12
The construction workforce will
generate general refuse comprising food scraps, waste paper, empty containers,
etc. Such refuse shall be properly
managed so intentional or accidental release to the surrounding environment
does not occur. Disposal of refuse
at sites other than approved waste transfer or disposal facilities shall be
prohibited. Effective collection of
site wastes will be required to prevent waste materials being blown around by
wind or creating an odour nuisance or pest and vermin problem. Waste storage areas shall be well
maintained and cleaned regularly.
With the implementation of good waste management practices at the site,
adverse environmental impacts would not be arise from the storage, handling and
transportation of workforce wastes.
Good Site Practices
6.7.1
Adverse impacts related to
waste management are not expected to arise, provided that good site practices
are strictly followed.
Recommendations for good site practices during the construction
activities include:
·
Nomination
of an approved person, such as a site manager, to be responsible for good site
practices, arrangements for collection and effective disposal to an appropriate
facility, of all wastes generated at the site.
·
Training
of site personnel in proper waste management and chemical waste handling
procedures.
·
Provision
of sufficient waste disposal points and regular collection for disposal.
·
Appropriate
measures to minimise windblown litter and dust during transportation of waste
by either covering trucks or by transporting wastes in enclosed containers.
·
Regular
cleaning and maintenance programme for drainage systems, sumps and oil
interceptors.
·
A
Waste Management Plan should be prepared and submitted to the Engineer for
approval. One may make reference to
ETWB TCW No. 19/2005 for details.
·
A
recording system for the amount of wastes generated, recycled and disposed
(including the disposal sites) should be proposed.
6.7.2
In order to monitor the
disposal of C&D materials at public fill reception facilities, as
appropriate, and to control fly tipping, a trip-ticket system shall be included
as one of the contractual requirements.
One may make reference to ETWB TCW No. 31/2004 for details. The use of a trip-ticket system is
required to avoid any illegal or unplanned dumping of waste generated by the
Project.
Waste Reduction Measures
6.7.3
Good management and control can
prevent the generation of a significant amount of waste. Waste reduction is best achieved at the
planning and design stage, as well as by ensuring the implementation of good
site practices. Recommendations to
achieve waste reduction include:
·
Segregation
and storage of different types of waste in different containers, skips or
stockpiles to enhance reuse or recycling of materials and their proper
disposal.
·
Encourage
collection of aluminium cans, PET bottles and paper by providing separate
labelled bins to enable these wastes to be segregated from other general refuse
generated by the work force.
·
Any
unused chemicals or those with remaining functional capacity shall be recycled.
·
Proper
storage and site practices to minimise the potential for damage or
contamination of construction materials.
·
Plan
and stock construction materials carefully to minimise amount of waste
generated and avoid unnecessary generation of waste.
6.7.4
Because of the limited
available works area, the possibility for segregation, storage and reuse of
materials would be limited.
6.7.5
In addition to the above
measures, specific mitigation measures are recommended below for the identified
waste arisings to minimise environmental impacts during handling, transportation
and disposal of these wastes.
Construction and Demolition Material
6.7.6
Within stockpile areas, the
following measures shall be taken to control potential environmental impacts or
nuisance:
·
covering stockpile of C&D material entirely by
clean impervious sheet to reduce potential dust impact;
·
locating
stockpiles to minimise potential visual impacts; and
·
minimizing
land intake of stockpile areas as far as possible.
Chemical Wastes
6.7.8
After use, chemical wastes (for
example, cleaning fluids, solvents, lubrication oil and fuel) should be handled
according to the Code of Practice on the
Packaging, Labelling and Storage of Chemical Wastes. Spent chemicals should
be collected by a licensed collector for disposal at the CWTC or other licensed
facility, in accordance with the Waste
Disposal (Chemical Waste) (General) Regulation.
General Refuse
6.7.9
General refuse shall be stored
in enclosed bins or compaction units separate from C&D material. A licensed waste collector shall be
employed by the contractor to remove general refuse from the site, separately
from C&D material. Preferably
an enclosed and covered area shall be provided to reduce the occurrence of 'wind blown'
light material.
6.8
Evaluation of Residual Impacts
6.8.1
With the implementation of the
recommended mitigation measures for the handling, transportation and disposal
of the identified waste arisings, no residual impact is expected to arise
during the construction of the proposed Project.
6.9.1
Waste management will be the
contractor’s responsibility to ensure that all wastes produced during the
construction of the Project are handled, stored, recycled, reused, transported
and disposed of in accordance with good waste management practices and EPD’s
regulations and requirements. The
recommended mitigation measures shall form the basis of the site Waste
Management Plan to be developed by the Contractor in the construction stage and
deposited with EPD.
6.9.2
It is recommended that the
waste generated during the construction will be audited periodically to
determine if wastes are being managed in accordance with approved procedures
and the site Waste Management Plan.
In addition, the routine site inspections should check the
implementation of the recommended good site practices and other waste
management mitigation measures.
6.10.1
Wastes generated by the
construction activities are likely to include C&D materials from the
construction works, general refuse from the workforce and chemical waste from
any maintenance of construction plant and equipment. Provided that these identified waste
arisings are handled, transported and disposed of using approved methods and
that the recommended good site practices are strictly followed, adverse
environmental impacts will not be anticipated during the construction works.
7.1.1
This chapter outlines the
landscape and visual impact assessment associated with MTR Tsim Sha Tsui
Station Northern Subway.
7.1.2
The assessment includes:
·
a definition of the scope and
contents of the study, including a description of the assessment methodology,
·
a review of the relevant
planning and development control framework,
·
a baseline study providing a
comprehensive and accurate description of the baseline landscape resources and
Visual Sensitive Receivers (VSRs),
·
recommendation of appropriate
mitigation measures and associated implementation programmes,
·
identification of the potential
landscape and visual impacts and prediction of their magnitude and potential
significance, before and after the mitigation measures, and
·
an assessment of the acceptability
or otherwise of the predicted residual impacts, according to the five criteria
set out in Annex 10 of the EIAO-TM.
7.1.3
The landscape and visual impact
assessment follows the criteria and guidelines as stated in Annexes 10 and 18
of the EIAO TM. Colour photographs
showing baseline conditions, and photomontages and illustrative materials
supporting conclusions are provided and the locations of all key viewpoints are
clearly mapped. Photomontages at
representative locations provide comparison between existing views, proposals
on day 1 after completion without mitigation measures, on day 1 completion with
mitigation measures, and in year 10 after with mitigation measures in
accordance with EIAO Guidance Note No. 8/2002.
7.2.1
The following legislation,
standards and guidelines are applicable to landscape and visual impact
assessment associated with the construction and operation of the project:
·
Environmental Impact Assessment
Ordinance (Cap.499.S.16) and the Technical Memorandum on EIA Process (EIAO TM),
particularly Annexes 10 and 18,
·
Environmental Impact Assessment
Ordinance Guidance Note 8/2002,
·
Town Planning Ordinance (Cap
131),
·
ETWB TCW No. 2/2004 -
Maintenance of Vegetation and Hard Landscape Features,
·
ETWB TCW No. 29/2004 -
Registration of Old and Valuable Trees, and Guidelines for their Preservation,
·
ETWB TCW No. 3/2006 - Tree
Preservation,
·
Hong Kong Planning Standards
and Guidelines, particular Chapter 4 and Chapter 11,
·
Land Administration Office Instruction
(LAOI) Section D-12 - Tree Preservation,
·
Study on Landscape Value
Mapping of Hong Kong,
·
WBTC No. 25/92 - Allocation of
Space for Urban Street Trees, and
·
WBTC No. 7/2002 - Tree Planting
in Public Works.
7.3.1
Landscape and visual impacts
have been assessed separately for the construction and operational phases.
7.3.2
The assessment of landscape
impacts has involved the following procedures:
·
Identification of the baseline landscape resources found within the
study area.
This is achieved by site visit and desktop study of topographical maps,
information databases and photographs.
·
Assessment of the degree of sensitivity to change of the landscape
resources.
This is influenced by a number of factors including:
- quality and maturity of
landscape resources/characters,
- rarity of landscape
resources/characters,
- whether is considered
to be of local, regional, national or global importance,
- whether there are any
statutory or regulatory limitations/requirements relating to the landscape resource/characters,
and
- ability of the
landscape resource/character to accommodate change.
The Sensitivity of
each landscape resources and character areas is classified as follows:
High:
|
Important landscape or landscape resources of particularly
distinctive character or high importance, sensitive to relatively small
changes.
|
Medium:
|
Landscape or landscape resources of moderately
valued landscape characteristics reasonably tolerant to change.
|
Low:
|
Landscape or landscape resources of low valued
landscape characteristics highly tolerant to change.
|
·
Identification of potential sources of landscape impacts. These are the various
elements of the construction works and operational procedures that would
generate landscape impacts.
·
Identification of the magnitude of landscape impacts. The magnitude of the
impact (or magnitude of change) depends on a number of factors including:
- the
physical extent of the impact,
- compatibility
of the project with the surrounding landscape,
- duration
of impacts i.e. whether it is temporary (short, medium or long term), under
construction and operation phases, and
- reversibility
of change.
The magnitude of
landscape impacts is classified as follows:
Large:
|
The landscape or landscape resources would suffer a
major change.
|
Intermediate:
|
The landscape or landscape resources would suffer
moderate change.
|
Small:
|
The landscape or landscape resources would suffer slight
or barely perceptible change.
|
Negligible:
|
The landscape or landscape resources would suffer no
discernible change.
|
·
Identification of potential landscape mitigation measures. Mitigation measures may take the form of
- adopting
alternative design or revisions to the basic engineering the architectural
design to prevent and/or minimize adverse impacts,
- remedial
measures such as colour and textural treatment of physical, engineering and
building features,
- compensatory
measures such as the implementation of landscape design measures (e.g. tree
planting, creation of new open space etc) to compensate for unavoidable adverse
impacts and to attempt to generate potentially beneficial long term impacts.
A programme for the mitigation measures is
provided. The agencies responsible
for the funding implementation, management and maintenance of the mitigation
measures are identified.
·
Predicted significance of landscape impacts before and after the
implementation of the mitigation measures. By
synthesizing the magnitude of the various impacts and the sensitivity of the
various landscape resources it is possible to categories impacts in a logical,
well-reasoned and consistent fashion.
Table 7.1 shows the rationale
for dividing the degree of significance into four thresholds, namely
insubstantial, slight, moderate, and substantial, depending on the combination
of a negligible-small-intermediate-large magnitude of impact and a
low-medium-high degree of sensitivity of landscape resource/character.
Table 7.1 Relationship between
Receptor Sensitivity and Impact Magnitude in Defining Impact Significance
Magnitude
of Impact (Change)
|
Large
|
Moderate
|
Moderate / Substantial
|
Substantial
|
Intermediate
|
Slight / Moderate
|
Moderate
|
Moderate / Substantial
|
Small
|
Insubstantial / Slight
|
Slight / Moderate
|
Moderate
|
Negligible
|
Insubstantial
|
Insubstantial
|
Insubstantial
|
|
Low
|
Medium
|
High
|
|
Receptor
Sensitivity (of
Landscape Resource, Landscape Character Area or VSRs)
|
·
Prediction of Acceptability of Impacts. An overall assessment of the
acceptability, or otherwise, of the impacts according to the five criteria set
out in Annex 10 of the EIAOTM.
7.3.3
The assessment of visual
impacts has involved the followings:
·
Identification of Zones of Visual Influence (ZVIs) during the
construction and operational phase of the project. This is achieved by site visit and
desktop study of topographic maps and photographs, and preparation of
cross-section to determine visibility of the project from various locations.
·
Identification of Visual Sensitive Receivers (VSRs) within the Zone
of Visual Influence (ZVIs) at construction and operational stages. These are the people
who would reside within, work within, play within, or travel through, the ZVIs.
·
Assessment of the degree of sensitivity to change of the VSRs. Factors considered include:
- the type
of VSRs, which is classified according to whether the person is at home, at
work, at school, at play, or travelling.
Those who view the impact from their homes are considered to be highly
sensitive as the attractiveness or otherwise of the outlook from their home
will have a substantial effect on their perception of the quality and
acceptability of their home environment and their general quality of life. Those who view the impact from their
workplace and at school are considered to be only moderately sensitive as the
attractiveness or otherwise of the outlook will have a less important, although
still material, effect on their perception of their quality of life. The degree to which this applies depends
on whether the workplace is industrial, retail or commercial. Those who view the impact whilst taking
part in an outdoor leisure activity may display varying sensitivity depending
on the type of leisure activity.
Those who view the impact whilst travelling on a public thoroughfare
will also display varying sensitivity depending on the speed of travel.
- other
factors which are considered (as required by EIAO GN 8/2002) include the value
and quality of existing views, the availability and amenity of alternative
views, the duration or frequency of view, and the degree of visibility.
The
sensitivity of VSRs is classified as follows:
High:
|
The VSR is highly sensitive to any change in their
viewing experience.
|
Medium:
|
The VSR is moderately sensitive to any change in
their viewing experience.
|
Low:
|
The VSR is only slightly sensitive to any change in their
viewing experience.
|
·
Identification of relative numbers of VSRs. This is expressed in
term of whether there are very few, few, many or very many VSRs in any one
category of VSR.
·
Identification of potential sources of visual impacts. These are the various
elements of the construction works and operational procedures that would
generate visual impacts.
·
Assessment of the potential magnitude of visual impacts. Factors considered
include:
- the
compatibility with the surrounding landscape,
- the
duration of the impact,
- the
reversibility of the impact,
- the scale
of the impact and distance of the source of impact from the viewer, and
- the
degree of visibility of the impact, and the degree of which the impact
dominates the field of vision of the viewer.
The magnitude of
visual impacts is classified as follows:
Large:
|
The VSRs would suffer a major change in their
viewing experience.
|
Intermediate:
|
The VSRs would suffer a moderate in their viewing
experience.
|
Small:
|
The VSRs would suffer a small change in their
viewing experience.
|
Negligible:
|
The VSRs would suffer no discernible change in their
viewing experience.
|
·
Identification of potential visual mitigation measures. These may take the form of adopting alternative designs or
revisions to the basic engineering and architectural design to prevent and/or
minimise adverse impacts, remedial measures such as colour and textural
treatment of building features, and tree planting to screen the roads and
associated bridge structures. A
programme for the mitigation measures is provided. The agencies responsible for the
implementation, management and maintenance of the mitigation measures are
identified and their approval-in-principle has been sought.
·
Prediction of the significance of visual impacts before and after
the implementation of the mitigation measures. By synthesising the magnitude of the
various visual impacts and the sensitivity of the VSRs, and the numbers of VSRs
that are affected, it is possible to categorise the degree of significance of
the impacts in a logical, well-reasoned and consistent fashion. Table
7.1 shows the rationale for dividing the degree of significance into four
thresholds, namely, insubstantial, slight, moderate and substantial, depending
on the combination of a negligible-small-intermediate-large magnitude of impact
and a low-medium-high degree of sensitivity of VSRs.
The
significance of visual impacts is categorised as follows:
Substantial:
|
Adverse / beneficial impact where the proposal would
cause significant deterioration or improvement in existing visual quality.
|
Moderate:
|
Adverse / beneficial impact where the proposal would
cause a noticeable deterioration or improvement in existing visual quality.
|
Slight:
|
Adverse / beneficial impact where the proposal would
cause a barely perceptible deterioration or improvement in existing visual
quality.
|
Insubstantial:
|
No discernible change in the existing visual
quality.
|
·
Prediction of Acceptability of Impacts. An overall assessment of the
acceptability, or otherwise, of the impacts according to the five criteria set
out in Annex 10 of the EIAOTM.
7.3.4
It is assumed that funding,
implementation, management and maintenance of the mitigation proposals can be
satisfactorily resolved according to the principles in ETWB TCW 3/2006. All mitigation proposals in this report
are practical and achievable within the known parameters of funding,
implementation, management and maintenance. The suggested agents for the funding and
implementation (and subsequent management and maintenance, if applicable) are
indicated in Tables 7.5 and 7.6. Approval-in-principle to the
implementation, management and maintenance of the proposed mitigation measures
is being sought from the appropriate authorities.
7.4.1
The Study Area is shown in Figure
7.1. According to EIA Study
Brief No. ESB-168/2007, the study area for the landscape impact assessment
shall include areas along Nathan
Road in the proximity of the Project and at Haiphong Road in
the proximity of the proposed new plant basement. Boundary for the visual
impact assessment shall be defined by the visual envelope of the Project and
associated works.
Review
of the Outline Zoning Plans (OZPs)
7.5.1
In this study, Tsim Sha Tsui
Outline Zoning Plan (No. S/K1/22 dated 17 October 2006) is reviewed.
7.5.2
Entrance A1 Upgrade is located
on the “O” zone. The footprint of
the upgraded entrance is slightly larger than the existing one. The existing structure is twenty-six
years old. The design intention of
the Entrance A1 Upgrade is to create a transparent glass box feature with
improved vertical access into the station, which includes escalators to the
existing Adit A1 and disabled lift to the station. The intention of using a transparent
structure is to minimize the visual bulkiness and provide better visual
integration with the surrounding.
The disabled lift will serve street and the Kowloon Park
entrance which will enhance connectivity from the park and the street into the
station. Those proposed works will
also improve the circulation flow at the northern end of TST Station. The Entrance A1 Upgrade will not have
any insurmountable impacts on the landscape planning framework, including areas
of high landscape value, open space and amenity area as shown in the OZP.
7.5.3
As part of the emergency
evacuation requirements for the subway an Emergency Exit is located in the east
footpath and planter of Nathan
Road in front of Miramar Shopping Centre. To minimize any sight line problems and
visual impacts as blockage to the Miramar Shopping Centre ground level shops,
the above-ground structure of this stair will be the same level as the adjacent
planter. The parapet is finished
with materials similar to adjacent planter to provide total integration and is
considered visually compatible with the existing urban context.
Review
of the Greening Master Plan (GMP)
7.5.4
Greening Master Plan (GMP) for
TST Area by Civil Engineering Development Department (CEDD) plans to upgrade
the landscape quality by planting more greenery along the Nathan Road in the
future, most of the trees and palms proposed by the CEDD are common species and
with medium amenity value and high survival rate after tree transplanting. Some of these trees will be affected by
this project during the construction period and are proposed to be transplanted
where practical and possible. After
completion of construction works, all the greenery will be replanted in
accordance the Greening Master Plan.
As such, the proposed project will not have any significant impact on
the oval greening master plan proposal.
Landscape
Resources
7.6.1
The baseline landscape
resources that will be affected during the Construction Phase and Operation
Phase, together with their sensitivity to change, are described below. The locations of baseline landscape
resources are mapped in Figure 7.2. Photo views illustrating the
landscape resources, along Nathan
Road in the proximity of the Project and at Haiphong Road in
the proximity of the proposed new plant basement, are illustrated in Figures
7.2.1, 7.2.2 & 7.2.3. For ease of reference and co-ordination
between text, tables and figures, each landscape resource is given an identity
number.
Existing Open Space
7.6.2
Kowloon Park is the main
open space identified within the study area. Only the main entrance of Kowloon Park will have interfacing issue with
the proposed project.
Existing Trees
7.6.3
There are a number of existing
trees in the planting along central median of Nathan Road, along roadside planting area
in front of Miramar Shopping Centre, in front of Park Lane Shopper’s Boulevard
and along Haiphong Road. Along Nathan Road in the proximity of the
Project and at Haiphong Road
in the proximity of the proposed new plant basement, there are 22 OVTs
identified along Nathan Road
and Haiphong Road. The crown of these OVTs are shown in Figure
7.2. In general, the spread of
root for OVTs shall be approximately equal to the crown spread. Most of the trees along Haiphong Road are
growing within raised planters & root spread would be contained within the
planter. There are two OVTs (T73 and T78) growing on the natural slope above
the planters/retaining wall of Haiphong
Road, and roots are anchoring on the slope.
7.6.4
Existing open space and
existing vegetation are the key landscape resources identified within the Study
Area. These resources are shown in Figure
7.2 and described as Table 7.2.
Landscape
Character Area
7.6.5
Identification of LCA has made
reference to Study on Landscape Value Mapping of Hong Kong. There is one LCA identified within the
study area which is Tsim Sha Tsui Organic Mixed Urban Development Landscape. An aerial photograph showing the
baseline landscape character areas and resources are shown in Figure 7.2A.
Table 7.2 List of the
Landscape Resources and Their Sensitivity to Change
Id. No.
|
Landscape Resource
|
Description
|
Sensitivity to Change
(Low, Medium, High)
|
LR01
|
Existing Planting Strip
along central median of Nathan
Road
|
There are 17 palms (Wodyetia
bufurcata) along the central median of Nathan Road. They are at approx. 6m high with medium health and amenity
value. It is noted that these trees are planted after April 2007 under CEDD’s
Green Master Plan for Tsim Sha Tsui.
|
Medium
|
LR02
|
Roadside planting in
front of Miramar
shopping centre
|
There are 4 trees found in the roadside planter in front of Miramar
Shopping Centre. They are all Ficus microcarpa and one of them is OVTs.
Two more OVTs are located near by Heritage Resource Centre of the
Antiquities & Monuments Office.
All the OVTs are Ficus microcarpa.
|
High
|
LR03
|
Roadside planting in
front of Park Lane Shopper’s Boulevard
|
There are approximate 20 trees along
the roadside planting area along Nathan
Road, of which 17 nos. are OVTs (Ficus microcarpa) with high amenity
value and good health.
|
High
|
LR04
|
Street planting along Haiphong Road
|
There are approximate 12 trees found along the Haiphong Road, of which 2 are OVTs.
Dominant species are Caryata ochiandra,
Washingtonia robusta and Delonix
regia. The trees are of medium to high amenity value and good
health.
|
High
|
LR05
|
Entrance of Kowloon Park
|
Entrance of Kowloon
Park is between
existing Entrance A1 and Kowloon Mosque and Islamic Centre. There is a
triangular planter with climbers (Lonicera
japonica and Pyrostegia ignea)
climbing on the steel arch across the entrance and three palms are located
next to Kowloon Mosque and Islamic Centre.
Four new trees were planted under GMP, they are Elaeocarpus apiculatus.
|
Medium
|
LCA
|
Tsim Sha Tsui Organic
Mixed Urban Development Landscape
|
The proposed work area belongs to Tsim Sha Tsui Organic Mixed Urban
Development Landscape in which identified as a Urban Landscape Types, for
predominantly residential, commercial and retail lands uses.
This character area has less sensitive on high-rise & low-rise
commercial/institutional, high-rise, medium-rise and low-rise residential
development; but more sensitive on industrial or port-related,
storage/warehousing and railway or major highway development; and not
applicable to the reclamation, quarry or landfill and golf course
development.
|
Low
|
Zone
of Visual Influence (ZVI)
7.6.6
The ZVI are the same during the
construction and operation phases as surrounding buildings are all at high
level. The Zone of Visual Influence
for the Project is illustrated in Figure 7.3. Photo views illustrating the Visual
Sensitive Receivers (VSRs) within the study area are illustrated in Figures 7.3.1
to 7.3.2 Due to the district
land area, the ZVI is quite intensive and is generally defined by the following
buildings:-
·
To the east by Golden Crown
Court, Cheong Hing Building, Mass Resources Development, Manson House, Majestic
House, HSBC Building, Comfort Building, Burlington Arcade, Milton House, Hotel
Miramar and Miramar Shopping Centre;
·
To the west by Hai Phong
Mansion, Health Education Exhibition & Resource Centre, Heritage Resource
Centre of the Antiquities & Monuments Office, St. Andrew’s Church, Kowloon
Mosque and Islamic Centre and Park Lane Shopper’s Boulevard;.
Visual
Sensitive Receivers (VSRs)
7.6.7
Table 7.3 lists out the key VSRs found within the ZVIs. For ease of reference, each VSR is given
an identity number, which is used in all relevant tables and figures in this
report. The sensitivity to changes
for each VSRs are tabled in Table 7.3.
Table 7.3 Visual Sensitive Receivers
(VSRs) and Their Sensitivity to Change
Id. No.
|
Key Visual Sensitive
Receivers (VSRs)
|
Type
of VSRs
|
Number of Individuals (Many/ Medium/ Few/
Very Few)
|
Quality
of Existing View
(Good/
Fair/ Poor)
|
Availability
of Alternative Views
(Yes/
No)
|
Minimum
Distance between VSRs and Impact Source (m)
|
Degree of Visibility (Full/ Partial/
Glimpse)
|
Frequency
of View
(Very
Frequent/ Frequent/ Occasional/ Rare)
|
Sensitivity to Change
(Low, Medium, High)
|
C01
|
Parmanand
House
|
Commercial/ Residential
|
Few
|
Fair
|
Yes
|
~40
|
Partial
|
Occasional
|
Medium
|
C02
|
Hai Phong Mansion
|
Commercial/ Residential
|
Few
|
Fair
|
Yes
|
~20
|
Partial
|
Occasional
|
Medium
|
C03
|
Mirador Mansion
|
Commercial/ Residential
|
Few
|
Fair
|
Yes
|
~80
|
Partial
|
Occasional
|
Medium
|
C04
|
Golden
Crown Court, Cheong Hing Building
and Mass Resources Development
Building
|
Commercial/ Residential
|
Few
|
Fair
|
Yes
|
~40
|
Partial
|
Occasional
|
Medium
|
C05
|
Manson
House and Majestic House
|
Commercial/ Residential
|
Few
|
Fair
|
Yes
|
~30
|
Partial
|
Occasional
|
Medium
|
C06
|
HSBC Building,
Comfort Building,
Burlington Arcade and Milton Mansion
|
Commercial/ Residential
|
Few
|
Fair
|
Yes
|
~30
|
Partial
|
Occasional
|
Medium
|
C07
|
Hotel
Miramar
|
Commercial
|
Few
|
Fair
|
Yes
|
~10
|
Partial
|
Occasional
|
Medium
|
C08
|
Miramar Shopping Centre
|
Commercial
|
Very Few
|
Fair
|
Yes
|
~5
|
Partial
|
Occasional
|
Low
|
C09
|
Park
Lane Shopper’s Boulevard
|
Commercial
|
Very Few
|
Fair
|
Yes
|
~10
|
Partial
|
Occasional
|
Low
|
CDA01
|
CADD
Redevelopment Area
|
Commercial
|
Very Few
|
Fair
|
Yes
|
~20
|
Partial
|
Occasional
|
Low
|
GIC01
|
Health
Education Exhibition & Resource Centre
|
Institutional
|
Very Few
|
Fair
|
Yes
|
~5
|
Glimpse
|
Rare
|
Low
|
GIC02
|
Kowloon Mosque and Islamic Centre
|
Institutional
|
Very Few
|
Fair
|
Yes
|
~20
|
Partial
|
Occasional
|
Low
|
GIC03
|
Heritage
Resource Centre of the Antiquities & Monuments Office and St. Andrew’s
Church
|
Institutional
|
Very Few
|
Fair
|
Yes
|
~50
|
Partial
|
Rare
|
Low
|
T01
|
Nathan Road – Vehicular and Pedestrian
|
Travelling
|
Many
|
Fair
|
Yes
|
0
|
Glimpse
|
Frequent
|
Low
|
O01
|
Open
Space
|
Travelling
|
Many
|
Fair
|
Yes
|
0
|
Partial
|
Frequent
|
Medium
|
7.7
Landscape Impact Assessment
Sources
of Landscape Impacts
Construction
Phase
7.7.1
Sources of impacts in the
construction phase would include:
·
construction of the plant
basement and Entrance A1 upgrade,
·
construction of emergency exit,
·
construction of satellite
concourse,
·
construction of subway/connection
chamber,
·
utilities diversions,
·
temporary site access areas,
site cabins and heavy machinery,
·
increased road traffic
congestion,
·
temporary traffic arrangement,
·
after dark lighting, and
·
dust during dry weather.
Operation
Phase
7.7.2
The sources of impacts of the
project at the operational stage would be:
·
Upgrade of entrance A1, and
·
Emergency exit.
Nature
and Magnitude of Unmitigated Landscape Impacts in Construction Phase
7.7.3
The magnitude of the impacts,
before implementation of mitigation measures, on the landscape resources and
character areas that would occur in the construction phase are described and
tabulated in Table 7.4. All
impacts are adverse unless otherwise stated.
7.7.4
Based on the temporary works,
all OVTs are not affected by the works.
The crown and root of OVTs are preserved in situ.
Table
7.4 Significant
Landscape Impacts of the Proposed Works during Construction Phase
Id No.
|
Landscape Resources
|
Source of Impact
|
Description of Impacts
|
Magnitude of Impacts
|
LR01
|
Existing Planting Strip along central median of Nathan Road
|
Construction of :
·
Satellite
Concourse
·
Subway/Connection
Chamber
·
Temporary
traffic arrangement
|
·
There
will be impact on 17 palms during construction period, all of them are Wodyetia bufurcata, temporary
transplanting is recommended during the construction period.
|
Intermediate
|
LR02
|
Roadside planting in front of Miramar shopping centre
|
Construction of Emergency exit at Subway MSC
|
·
There
are 4 trees found in the roadside planter in front of Miramar Shopping
Centre. They are all Ficus microcarpa
and one of them is OVTs.
·
Two
more OVTs are located near by Heritage Resource Centre of the Antiquities
& Monuments Office.
·
All
the OVTs are Ficus microcarpa
|
Intermediate
|
LR03
|
Roadside planting in front of Park Lane Shopper’s
Boulevard
|
No impact
|
·
No
Impact
|
Negligible
|
LR04
|
Street planting along Haiphong Road
|
Construction of :
·
Plant
Basement
·
Reconstruction
of Entrance A1
|
·
3
trees will be affected. They are Delonix regia of poor amenity
value. These trees are
recommended to be felled as the survival rate of transplanting is considered
as low. Compensatory planting is
recommended that 4 nos. trees are to be planted within the area further to
completion of works.
|
Intermediate
|
LR05
|
Entrance of Kowloon
Park
|
Construction of :
·
Plant
basement
·
Reconstruction
of Entrance A1
|
·
There
will be impact on the triangular planter and the steel arch will be removed during
construction stage.
·
There
will be impact on 3 palms during construction period; all of them are Roystonea regia of medium amenity
value. Temporary transplanting is recommended during the construction period.
·
There
will be impact on 4 new planted trees under GMP, all of them are Elaeocarpus apiculatus of medium
amenity value. Temporary
transplanting is recommended during the construction period.
·
Access
to Health Education Exhibition and Resource Centre will
be temporarily blocked during the construction period for approx. 2.5 months.
|
Intermediate
|
LCA
|
Tsim Sha Tsui Organic Mixed Urban Development Landscape
|
Construction of :
·
Satellite
concourse
·
Subway/connection
chamber
·
Emergency
exit
·
Plant
Basement and Entrance A1 upgrade
·
Temporary
traffic arrangement
|
·
Totally 30 trees will be
affected.
|
Intermediate
|
Remark : Affected trees are trees
which would be felled or transplanted.
Nature
and Magnitude of Unmitigated Landscape Impacts in Operation Phase
7.7.5
The magnitude of the impacts,
before implementation of mitigation measures, on the landscape resources that
will occur in the operation phase are slight, as only a small planting area is
deducted for the proposed emergency exit.
The landscape areas around Entrance A1 and the roadside planting along
the central median of Nathan Road
will be reinstated after construction.
Landscape
and Visual Mitigation Measures in Construction and Operation Phase
7.7.6
The proposed landscape and
visual mitigation measures in the construction and operation are listed in Tables
7.5 and 7.6 below, together with an indication of Funding,
Implementation and Maintenance Agencies.
Generally, all landscape mitigation measures are to be implemented as
early as possible. Tentative date
for such implementation shall follow the programme of project works as tabled
in Section 2.7.
Table 7.5 Proposed Mitigation
Measures for Construction Phase
ID No.
|
Proposed Mitigation
Measures
|
Funding and Implementation Agency
|
Landscape
|
|
|
CM11
|
Existing trees including
OVTs to be retained on site shall be carefully protected and maintained
during construction. Encroachment
of any works close to the drip line of OVTs should be avoided.
|
MTRCL
|
CM2
|
Trees of high amenity
and survival rate after transplanting which unavoidably affected by the works
shall be transplanted where practical.
|
MTRCL
|
Visual
|
|
|
CM31
|
Control of night – time lighting.
|
MTRCL
|
CM4
|
Erection of decorative screen hoarding compatible with surrounding
setting.
|
MTRCL
|
Note: (1) Mitigation measures refer to
Good Site Practices
Table 7.6 Proposed Mitigation Measures for Operation
Phase
ID No.
|
Proposed
Mitigation Measures
|
Funding and
Implementation Agency
|
Maintenance/ Management Agency
|
Landscape
|
|
|
|
OM12
|
Aesthetic design of Entrance A1 (Minimisation of building bulk and adoption
of transparent material) and Emergency Exit
|
MTRCL
|
MTRCL
|
OM3
|
Planting of 4 nos. of Delonix regia or species as agreed with LCSD along Haiphong Road
|
MTRCL
|
LCSD
|
Visual
|
|
|
|
OM2
|
Reinstatement of Kowloon Park
entrance
|
MTRCL
|
LCSD
|
Note: (2) Aesthetic design treatment of Entrance A1 and Emergency Exit refers to
Figure 7.5.1 to 7.5.3.
Programme of Implementation of
Landscape and Visual Mitigation Measures
7.7.7
The Construction Phase Measures
(CM1 to CM4) listed above shall be adopted from the commencement of
construction and shall be in place throughout the entire construction
period. The design principles (OM1)
shall be implemented so that the measures are in place at the date of
commissioning of the Project. Reinstatement of the entrance to Kowloon Park
(OM2) shall be implemented upon the completion of construction.
Prediction of Significance of
Landscape Impacts
7.7.8
The potential significance of
landscape impacts during the construction and operation phases, before and
after mitigation, is provided below in Table 7.7. The assessment follows
the proposed methodology and assumes that the appropriate mitigation measures
identified in Tables 7.5 and 7.6 above would be implemented, and
the full effect of the soft landscape mitigation measures would be realized
after 10 years.
Residual
Landscape Impacts in Construction and Operation Phase
7.7.9
Residual impacts of moderate to
insubstantial significance are summarized as below.
Impact
on Existing Trees
7.7.10
Based on detailed tree survey,
during the construction period, approximately 30 trees will be affected by
construction works. There are no
rare species or endangered species but common species. Those trees with good amenity value and
high survival rate after transplanting which unavoidably affected by the work
will be transplanted where possible.
Based on preliminary tree survey information, all trees to be affected
are proposed to be transplanted except the 3 nos. of Delonix regia along Haiphong
Road. Further to the completion of the
construction works, the transplanted trees would be re-planted on-site. Moreover, compensatory planting of 4
nos. of trees along Haiphong Road
is proposed. Detailed tree preservation, transplanting and
compensatory planting proposals shall be submitted to
relevant government departments for approval in accordance with ET WBTC no.
3/2006. After completion of the
engineering works and implementation of tree preservation and transplanting
works, the residual impacts on existing trees are considered as slight with
mitigation measures.
Impact
on OVTs
7.7.11
The residual impacts on OVTs
are considered as insubstantial with mitigation measures as no OVTs will be
affected. The crown and root of
OVTs will be preserved in situ.
7.7.12
The proposed emergency exit in
front of the Miramar Shopping Centre has been designed to place well away from
the OVT in the roadside planter. It
will be located at approximately 12m
from the trunk of the OVT and approximately 5m away from its drip line. Nevertheless, appropriate protection
measures for the OVT as recommended by Professor C.Y. Jim of the University of Hong Kong are proposed. Extra care will be taken to ensure that
the OVT will not be unduly affected.
·
Measures stipulated in the ETWB
TCW No. 29/ 2004 will be followed as appropriate.
·
The area will be instituted to
guard against intrusion into Cordon Zone (CZ).
·
The CZ should not be allowed to
become a resting place, eating or recreational space for workers.
·
No construction crews, vehicles
or equipment should be allowed for enter the CZ.
·
Construction materials and
equipment should not be stored inside the CZ.
·
Construction wastewater or
effluent should not flow into the CZ.
·
Exhaust fames and hot air
emanated by construction machines should not drift into the tree crown.
·
The existing concrete paving
and soil within CZ should be kept intact to avoid disturbing the soil and the
enclosed roots.
·
As far as practicable,
construction equipment with a short rig or body should be employed to avoid
conflicts with the tree crown.
·
Grouting will be carried out in
a controlled and effective manner for the protection of tree roots along Nathan Road.
·
A programme of close monitoring
of tree condition before (baseline evaluation), during and for one year after
completion of construction, shall be instituted at regular intervals.
·
Induction seminar will be
organized to coach construction workers and their supervisors of the need and
the precautions to protect the tree.
·
Precautionary measures, such as
site inspection on tree condition, shall be conducted to protect the trees
during the construction stage.
Impacts
on LCA
7.7.13
The proposed work area belongs
to Tsim Sha Tsui Organic Mixed Urban Development Landscape, during the
construction phase there will be moderate temporary impact due to the
construction activities.
7.7.14
During the operation phase, the
proposed structures are relatively small in scale and less sensitive to Tsim
Sha Tsui Organic Mixed Urban Development Landscape. There will not be any insurmountable
impacts.
Impact
on Entrance to Kowloon
Park
7.7.15
During construction phase, a
temporary access to Kowloon
Park near Entrance A1
would be provided during construction stage. There will be minimal impact on
the park users and circulation to and within Kowloon Park/
Health Education Exhibition and Resource Centre. Since the impact is temporary in nature,
it is considered that the residual impact is moderate.
7.7.16
During the operation phase, the
wide stairway leading to Kowloon
Park (15m wide) will be permanently narrowed
(approx. 2m) by the
expansion of Entrance A1. The
persons using this entrance throughout the day are relatively small and the
reduction is width will not have any impact to the level of service of the
pedestrian user. As the new
disabled lift serves the Kowloon
Park entrance directly
from the station, substantial users will by pass the existing stairs and use
the new lift.
Table 7.7 Significance
of Landscape Impacts in the Construction and Operation Phases
Id. No.
|
Landscape Resources
|
Sensitivity to Change (Low, Medium, High)
|
Magnitude of Change (Negligible, Small, Intermediate, Large)
|
Impact Significance before Mitigation (Insubstantial, Slight, Moderate, Substantial)
|
Recommended Mitigation Measures
|
Impact Significance
Day 1 after Mitigation
|
Impact Significance
10 years after Mitigation
|
(Insubstantial, Slight, Moderate, Substantial)
|
Construction
|
Operation
|
Construction
|
Operation
|
Construction
|
Operation
|
Operation
|
LR01
|
Existing Planting Strip
along central median of Nathan
Road
|
Medium
|
Intermediate
|
Negligible
|
Moderate
|
Insubstantial
|
CM2
|
Slight
|
Insubstantial
|
Insubstantial
|
LR02
|
Roadside planting in
front of Miramar
shopping centre
|
High
|
Intermediate
|
Small
|
Moderate
|
Slight
|
CM1,
CM2,
OM1
|
Slight
|
Slight
|
Slight
|
LR03
|
Roadside planting in
front of Park Lane Shopper’s Boulevard
|
High
|
Negligible
|
Negligible
|
Negligible
|
Negligible
|
Not required
|
Negligible
|
Negligible
|
Negligible
|
LR04
|
Street planting along Haiphong Road
|
High
|
Intermediate
|
Small
|
Moderate
|
Slight
|
CM1,
CM2,
OM1,
OM3
|
Slight
|
Slight
|
Insubstantial
|
LR05
|
Entrance of Kowloon Park
|
Medium
|
Intermediate
|
Small
|
Moderate
|
Slight
|
CM1,
CM2,
OM1,
OM3
|
Moderate
|
Slight
|
Slight
|
LCA
|
Tsim Sha Tsui Organic
Mixed Urban Development Landscape
|
Low
|
Intermediate
|
Negligible
|
Moderate
|
Insubstantial
|
CM1,
CM2,
OM1,
OM3
|
Moderate
|
Insubstantial
|
Insubstantial
|
7.8
Visual Impact Assessment
Potential
Sources of Visual Impacts
7.8.1
The sources of visual impacts
due to the Project would create varying levels of visual impact during the
construction and operation phases.
The main sources of visual impacts of proposed MTR Tsim Sha Tsui Station
Northern Subway consists of the followings in the construction and operation
phases:
Construction
Phase
·
Construction of the plant
basement and Entrance A1 upgrade;
·
Emergency exit in front of
Miramar Shopping Centre;
·
Construction of satellite
concourse during construction period; and
·
Construction of subway /
connection chamber.
Operation
Phase
·
Upgrade of entrance A1
(proposed transparent glass structure
is to be built at the junction of Nathan
Road and Haiphong
Road); and
·
Emergency exit.
Visual
Mitigation Measures
7.8.2
The proposed Visual Mitigation
Measures in the Construction and Operation Phases are summarized in Tables
7.5 and 7.6, together with an indication of Funding, Implementation,
Management and Maintenance Agencies.
Prediction
of Significance of Visual Impacts
7.8.3
An assessment of the potential
significance of the visual impacts during the construction and operation
phases, before and after mitigation is provided in detail in Table 7.8. This follows the methodology outlined in
Section 7.3 and assumes that the appropriate mitigation measures identified in Tables
7.5 and 7.6 above would be implemented, and that the full effect of
the soft landscape mitigation measures would be realized after ten years.
Residual
Visual Impacts
Construction
Phase
7.8.4
Residual visual impacts in the
Construction Phase are listed out in Table 7.8. In the Construction
Phase, after the implementation of proposed mitigation measures, there will
still be some residual visual impacts as shown in Table 7.8.
Operation
Phase
7.8.5
Residual visual impacts in the
Operation Phase are listed out in Table 7.8. Photomontages showing the residual
impact are shown in Figure 7.4.1 to 7.4.3. In the Operation Phase, after the
implementation of proposed mitigation measures, there will still be some
residual visual impacts as shown in Table 7.8.
Conclusion
on Visual Impact Assessment
During
the construction period
7.8.6
The residents, pedestrian,
vehicle users, offices and commercial buildings around will have direct, close
views of construction works including the plant basement, upgrading works for
Entrance A1, satellite concourse, connection chamber and emergency exit. During the construction period,
decorative hoardings, use of temporary decking and limiting the area of the
work site are proposed to establish to minimize the visual affect. There is expected to be moderate residual
impact to Nathan Road
users and Kowloon Park Users.
Impacts on other VSRs are considered as slight to insubstantial.
During
the operation period
7.8.7
The proposed transparent glass
box of Entrance A1 will reduce the bulky effect of the new structure (See Figure
7.4.1). It is considered that the new Entrance A1 is compatible with the
adjacent urban setting.
7.8.8
Proposed emergency exit is
proposed within the planter in front of Miramar Shopping Centre and is
integrated with the exiting planter.
The stair is level with the planter wall to reduce the visual impacts to
the ground level shops at Miramar Shopping Centre and the sightline problems to
vehicle users on Nathan Road
(See Figure 7.4.2 and 7.4.3). There
will not be any significant visual impact.
7.8.9
As a whole, the residual
impacts on VSRs are slight to insubstantial.
Table 7.8 Significance of Visual Impacts in the Construction
and Operation Phases (Note: All impacts adverse unless otherwise noted.)
Id No
|
Key
Visual Sensitive Receiver (VSR)
|
Receptor Sensitivity
(Low,
Medium, High)
|
Main Source of Visual Impacts
|
Magnitude of Impact (Negligible,
Small, Intermediate, Large)
|
Impact Significance without
Mitigation Measures (Insubstantial, Slight, Moderate, Substantial)
|
Recommended
Mitigation Measures
|
Residual Impact Significance with
Mitigations
(Insubstantial,
Slight, Moderate, Substantial)
|
Construction
|
Operation
|
Construction
|
Operation
|
Construction
|
Operation
|
Day 1
|
Year 10
|
C01
|
Parmanand House
|
Medium
|
Reconstruction
of Entrance A
|
Negligible
|
Negligible
|
Insubstantial
|
Insubstantial
|
Not required
|
Insubstantial
|
Insubstantial
|
Insubstantial
|
C02
|
Hai Phong
Mansion
|
Medium
|
Reconstruction
of Entrance A
|
Small
|
Small
|
Moderate
|
Moderate
|
CM3, CM4,
OM2
|
Slight
|
Slight
|
Slight
|
C03
|
Mirador Mansion
|
Medium
|
Reconstruction
of Entrance A
|
Negligible
|
Negligible
|
Insubstantial
|
Insubstantial
|
Not required
|
Insubstantial
|
Insubstantial
|
Insubstantial
|
C04
|
Golden
Crown Court, Cheong Hing Building
and Mass Resources Development
Building
|
Medium
|
Reconstruction
of Entrance A
|
Small
|
Small
|
Slight
|
Slight
|
CM3, CM4,
OM2
|
Slight
|
Slight
|
Slight
|
C05
|
Manson
House and Majestic House
|
Medium
|
Reconstruction
of Entrance A
Construction
of satellite concourse
Construction
of subway/ connection chamber
|
Small
|
Small
|
Slight
|
Slight
|
CM3, CM4,
OM2
|
Slight
|
Slight
|
Slight
|
C06
|
HSBC Building,
Comfort Building,
Burlington Arcade and Milton Mansion
|
Medium
|
Reconstruction
of Entrance A
Construction
of satellite concourse
Construction
of subway/ connection chamber
|
Small
|
Small
|
Slight
|
Slight
|
CM3, CM4
|
Slight
|
Slight
|
Slight
|
C07
|
Hotel
Miramar
|
Medium
|
Construction
of Emergency Exit
Construction
of satellite concourse
Construction
of subway/ connection chamber
|
Small
|
Small
|
Slight
|
Slight
|
CM3, CM4
|
Slight
|
Slight
|
Slight
|
C08
|
Miramar Shopping Centre
|
Low
|
Construction
of Emergency Exit
Construction
of satellite concourse
Construction
of subway/ connection chamber
|
Small
|
Small
|
Slight
|
Slight
|
CM3, CM4
|
Slight
|
Slight
|
Slight
|
C09
|
Park
Lane Shopper’s Boulevard
|
Low
|
Construction
of satellite concourse
Construction
of subway/ connection chamber
|
Small
|
Small
|
Slight
|
Insubstantial
|
CM3, CM4
|
Slight
|
Insubstantial
|
Insubstantial
|
CDA01
|
CADD Redevelopment Area
|
Low
|
Construction
of Emergency Exit
Construction
of satellite concourse
Construction
of subway/ connection chamber
|
Small
|
Negligible
|
Slight
|
Insubstantial
|
CM3, CM4
|
Slight
|
Insubstantial
|
Insubstantial
|
GIC01
|
Health Education Exhibition &
Resource Centre
|
Low
|
Reconstruction
of Entrance A
|
Negligible
|
Negligible
|
Insubstantial
|
Insubstantial
|
CM3, CM4,
OM2
|
Insubstantial
|
Insubstantial
|
Insubstantial
|
GIC02
|
Kowloon Mosque and Islamic
Centre
|
Low
|
Reconstruction
of Entrance A
Construction
of satellite concourse
Construction
of subway/ connection chamber
|
Small
|
Small
|
Slight
|
Slight
|
CM3, CM4,
OM2
|
Slight
|
Slight
|
Insubstantial
|
GIC03
|
Heritage
Resource Centre of the Antiquities & Monuments Office and St. Andrew’s
Church
|
Low
|
Construction
of Emergency Exit
|
Negligible
|
Negligible
|
Insubstantial
|
Insubstantial
|
CM3, CM4,
|
Insubstantial
|
Insubstantial
|
Insubstantial
|
T01
|
Nathan
Road – Vehicular and Pedestrian
|
Low
|
Reconstruction
of Entrance A
Construction
of Emergency Exit
Construction
of satellite concourse
Construction
of subway/ connection chamber
|
Intermediate
|
Small
|
Moderate
|
Slight
|
CM3, CM4,
OM2
|
Moderate
|
Slight
|
Insubstantial
|
O01
|
Open Space Users in Kowloon Park
|
Medium
|
Reconstruction
of Entrance A
Construction
of satellite concourse
Construction
of subway/ connection chamber
|
Intermediate
|
Intermediate
|
Moderate
|
Moderate
|
CM3, CM4,
OM2
|
Moderate
|
Slight
|
Insubstantial
|
* C = Commercial,
GIC = Government/Institution/Community, CDA = Comprehensive Development Areas,
T = Transport related (land)
7.9.1
The Project is located in Tsim
Sha Tsui district which is an urban area with mixture of commercial and
residential developments. The
proposed works are along Nathan
Road from Cameron Road junction to Miramar Shopping
Centre near Kimberley Road.
7.9.2
No significant impact on the
planning and development control framework as the affected areas are small and
the proposed development are compatible with the adjacent development
framework.
7.9.3
There are approximate 30 trees
affected during the construction period and none of them are OVTs. The crown and root of OVTs shall be
preserved insitu. Based on
preliminary tree survey information, all affected trees except 3 nos.
at Haiphong Road shall be transplanted.
Compensatory planting is proposed for the felled trees. A detailed tree preservation, transplanting and
compensatory planting proposals will be submitted to
relevant government department for approval in accordance ET WBTC no. 3/2006
separately.
7.9.4
The proposed work area belongs
to Tsim Sha Tsui Organic Mixed Urban Development Landscape Character. During the construction, there will be
moderate residual impact due to the temporary works. During operation, the residual impact will
be insubstantial as the proposed works blend in well with the existing urban
landscape character.
7.9.5
During construction phase, a
temporary access to Kowloon
Park near Entrance A1
would be provided during construction stage. There will be minimal impact on
the park users and circulation to and within Kowloon Park/
Health Education Exhibition and Resource Centre. Since this impact is temporary in
nature, it is considered that the residual impact is moderate.
7.9.6
During the operation phase, the
stairway to Kowloon
Park will be reduced by
about 2m by the new
Entrance A1 Upgrade structure. As
the existing stairway is 15m
wide and pedestrian using this area is relatively low, the impact is considered
as slight.
7.9.7
The residents, pedestrian,
vehicle users, offices and commercial buildings around will have direct, close
views of construction of the works including satellite concourse, connection
chamber, reconstruction of plant basement and Entrance A1 and emergency
exit. During the construction
period, decorative hoardings and the use of temporary decking and by limiting
the area of the work site are proposed to minimize the visual affect. There is expected to be slight to
insubstantial to high rise VSRs and moderate to low level VSRs such as Nathan Road users
and Kowloon Park users.
7.9.8
Overall, it is considered that
the residual landscape and visual impacts of the proposed project are
considered acceptable with mitigation measures during construction and
operation.
8.1.1
This section will identify and
assess any adverse impacts to any heritage resources within the project Study
Area and propose measures to avoid and/ or mitigate these impacts. All heritage resources will be
identified as part of the Built Heritage Impact Assessment (BHIA) with special
attention paid to the following known structures; The Former Kowloon British
School (Declared Monument),
Block S4 of the Former Whitfield Barracks (Grade III Historical Building)
and the old retaining wall on Haiphong
Road.
The assessment will follow the Criteria and Guidelines for Assessing the
Cultural Heritage Impacts as Stated in Annex 10 and 19 of the Technical
Memorandum of the EIAO. Any
potential physical disturbance during both the Construction and Operational
Phases will be identified and the extent of the effects will be assessed and
measures recommended for avoidance of any such identified disturbance through
alternative design options and construction methods where applicable.
8.2.1
Legislation, Standards,
Guidelines and Criteria relevant to the consideration of Cultural Heritage
impacts under this study include the following:
·
Antiquities
and Monuments Ordinance
·
Environmental
Impact Assessment Ordinance
·
Hong Kong Planning Standards and Guidelines
·
Technical Memorandum on Environmental Impact
Assessment Process
·
Criteria for Cultural
Heritage Impact Assessment
Antiquities
and Monuments Ordinance
8.2.2
The Antiquities and Monuments Ordinance (Cap.53) provides the
statutory framework to provide for the preservation of declared monuments. The Ordinance also contains the
statutory procedures for the declaration of monument which can be any place,
building, site or structure, which the Antiquities Authority considers to be of
public interest by reason of its historical, archaeological or palaeontological
significance.
8.2.3
Under Section 6 and subject to
sub-section (4) of the Ordinance, the following acts are prohibited in a
proposed monument or monument, except under permit;
·
To excavate, carry on building works, plant or
fell trees or deposit earth or refuse on or in a proposed monument or monument.
·
To demolish, remove, obstruct, deface or
interfere with a proposed monument or monument.
8.2.4
The discovery of an Antiquity,
as defined in the Ordinance must be reported to the Antiquities Authority (the
Authority), or a designated person.
The Ordinance also provides that, the ownership of every relic
discovered in Hong Kong after the commencement
of this Ordinance shall vest in the Government from the moment of
discovery. The Authority on behalf
of the Government may disclaim ownership of the relic.
Hong Kong Planning Standards and Guidelines
8.2.5
Chapter 10 of the HKPSG details
the principles of conservation, the conservation of natural landscape and
habitats, historic buildings and archaeological sites. It also addresses the issue of
enforcement. The appendices list
the legislation and administrative controls for conservation, other
conservation related measures in Hong Kong,
and Government departments involved in conservation. It also intones that planning should include a
respect for local activities, culture and tradition.
Technical
Memorandum on Environmental Impact Assessment Process
8.2.6
The general criteria and
guidelines for evaluating and assessing impacts to Cultural Heritage are listed
in Annexes 10 and 19 of the Technical Memorandum on Environmental Impact
Assessment Process (EIAO-TM).
The guidelines state that preservation in totality and measures for the
integration of sites of cultural heritage into the proposed project will be a
beneficial impact. It also states
that destruction of a site of cultural heritage must only be undertaken as a
last resort.
Criteria
for Built Heritage
Impact Assessment
8.2.7
This document, as issued by the
Antiquities and Monuments Office (AMO), outlines the specific technical requirement
for conducting terrestrial archaeological and built heritage impact assessments
(BHIA). It includes the parameters
and scope for the Baseline Study, specifically desk-based research, field
survey and the reporting requirements.
Besides, the prerequisite conditions for conducting impact assessment
and mitigation measures are presented in detail.
Baseline
Study
8.3.1
A desk-based study was
undertaken to determine the presence of historical occupation of the Study Area
and thus to assess the potential for built heritage resources to be
present. Information was gathered
from the following sources; the AMO published and unpublished papers and
studies; publications on relevant historical, anthropological and other
cultural studies; unpublished archival, papers, records; collections and
libraries of tertiary institutions; historical documents which can be found in
Public Records Office, Lands Registry, District Lands Office, District Office,
Museum of History; cartographic and pictorial documentation.
8.3.2
In addition to the desk-based
review, in cases where the sources of information proved to be inadequate or
where the project area had not been adequately studied before, field survey was
conducted to assemble the necessary data.
Study
Area
8.3.3
As there was no project study
boundary listed in the project brief, a study area with 300 meter boundary was
made reference to previous approved railway EIA Studies i.e. Kowloon Southern
Link and Western Island Line. It was chosen to ensure that a comprehensive
inventory of all historical buildings that could possibly be affected by the
proposed works would be included in the report.
Resources
to be Covered by the Built Heritage Impact Assessment
8.3.4
The resources shall include,
but will not be limited to the following;
·
All pre 1950 structures, which
include any built feature (apart from graves and historical land use features,
which are dealt with separately), such as domestic structures, ancestral halls,
temples, shrines, monasteries and nunneries, village gates, wells, schools,
historic walls, bridges and stone tablets;
·
Any post 1950 structure deemed
to possess features containing architectural or cultural merit;
·
All Declared and Proposed Monuments
and Graded Historical Buildings
as issued by the AMO;
·
All Government Historic Sites
Identified by AMO;
·
All pre-war clan graves; and
·
Cultural landscape features,
such as fung shui woods and ponds, historical tracks and pathways, stone walls
and terraces, ponds and other agricultural features.
Impact
Assessment and Mitigation Recommendations
8.3.5
Prediction and Identification
of both direct and indirect impacts that may affect the built heritage
resources within the project Area will be undertaken with special attention
paid to the built heritage resources identified in the project Study
Brief. Preservation in totality
must be taken as the first priority.
If, due to site constraints and other factors, only preservation in part
is possible, this must be fully justified with alternative proposals or layout
designs which confirm the impracticability of total preservation. Mitigation measures shall not be
recommended or taken as de facto means to avoid preservation of heritage
sites. They must be proved beyond
all possibilities to be the only practical course of action. If avoidance of the heritage site is not
possible, amelioration can be achieved by minimizing the potential
impacts. As well, any disturbance
to heritage resources that may cause physical damage should be avoided wherever
possible through alteration of design, construction method or protective
measures as appropriate.
Previous
Investigations
Kowloon Southern
Link - Contract No GSA-5100: EIA and Associated Services: Cultural Heritage
Impact Assessment (Archaeological Assessments Ltd 2003)
8.4.1
The built heritage impact
assessment for the project included the Study Area for the current
project. The built heritage
resources associated with the Former Whitfield Barracks were included in the
field survey as was the Former Kowloon British School, the Fuk Tak Koo Mui
Temple (a modern temple building located near the corner of Canton and Haiphong
Roads), St. Andrew’s Church Compound, a 1930’s high rise structure at #190 Nathan Road and the
historical retaining wall and War Department Boundary Stone at the Southwest
Corner of Kowloon Park.
Agreement No CE 39/2002(DS)
Drainage Improvement in East Kowloon -Cultural
Heritage Impact Assessment (Archaeological Assessments Ltd 2004)
8.4.2
The built heritage impact
assessment for this project included the South-eastern sections of the current
project Study Area. The report
identifies the following built heritage resources found in the current project
Study Area; The Former Kowloon British School, The Hong Kong Observatory, St.
Andrew’s Church Compound and the building at #190 Nathan Road.
Historical
Background
8.4.3
The historical village of Tsim
Sha Wai is thought to have been
situated in the vicinity of Hanoi Road, with the remainder of the southern part
of the peninsula consisting of open hilly terrain with the southern section
described as a “rocky and precipitous” southern shore with a sandy shore
running between the promontories that were to become the site of the Marine
Police Station (Water Police Station in the 19th Century) and Signal
Hill (Hayes 1966). In general it
can be stated that the earliest British occupation was primarily for military
purposes, as can be seen in the large portions of the district that were
controlled by the War Department at the time, including the Former Whitfield
Barracks, which ceased military ownership in 1967 and is currently Kowloon
Park.
Declared
Monuments and Graded Historical Buildings
8.4.4
The following inventory of
Declared Monuments was compiled using the list of Declared Monuments as issued
by the Antiquities and Monuments Office as of 11 July 2008.
The
Former Kowloon British
School
8.4.5
The building currently houses
the Antiquities and Monuments Office of LCSD. The building was originally
constructed in 1900 as a school for foreign residents living in Hong Kong through a donation of $15 000 by Sir Robert Ho
Tung. The school is Victorian style
structure modified to accommodate the local climate through addition of wide
verandahs, high ceilings and pitched roofs. It was officially opened in 1902 (AMO
File).
The
Hong Kong Observatory
8.4.6
The Hong Kong Observatory is a
colonial style building built in 1883.
It is a rectangular two storey building with arched windows, columns and
long verandahs (Rodwell 1992). It
is currently being used as an administrative centre for the observatory (AMO
File).
Whitfield
Barracks, Kowloon West II Battery
(Grade I Historical Building)
8.4.7
The West Battery is currently part of a children’s adventure playground
in Kowloon Park. The battery was
constructed between 1878 and 1899 and probably abandoned in 1916. The battery still retains original
features, such as renovated gun emplacements and 5 inch breech loading naval
guns that were discovered during works in Chatham Road in 1980 (AMO File).
St.
Andrew’s Church Compound (Grade II Historical
Building)
8.4.8
The church was completed in
1906. It is a cruciform shaped structure with a bell tower at the front of
typical Gothic style architecture with pointed arches and arched windows. The church is the oldest Protestant Church
in Kowloon.
During the Japanese Occupation it was converted into a Shinto Shrine. The church was restored in 1959 and a
multi-storied Christian Centre was constructed in 1977 (AMO File).
Whitfield
Barracks Blocks 58, S4, S61 and S62 (Grade III Historical Buildings)
8.4.9
The site of the former
Whitfield Barracks is now the location of Kowloon Park.
The barracks were established in 1861 and the
buildings constructed in the 1880’s. There
are four remaining former barracks buildings, S61 and S62 were originally
constructed by 1910 and served as the Hong Kong Museum of History from 1983 to
1998, they have recently been converted into the Hong Kong Heritage Discovery
Centre, Block S4 is currently being used as an educational centre (it should be
noted that two granite columns removed from the former building belonging to
the Eu Yan Sang Medicine Company have been
relocated to the platform in front of Block S4 at 1992). and Block 58 was used
as storage for the Hong Kong Museum of History (AMO File). The principal Eu Yan Sang shop was
located at Queen’s Road Central at 1926 which was moved from the 1st Bonham
Strand shop. At that time, there was a silver knight statue and a pair of rock
lions (together with two columns) at the entrance which made the characteristic
landmark of the shop. At 1992, this principal shop was moved to the opposite of
the road and the current pair of columns was relocated to the front entrance of
the Health Education Exhibition Centre (S4).
Non-Graded
Built Heritage Resources
8.4.10
There is an historical
retaining wall running along Northern side of Haiphong Road. An interesting feature located at the
south west corner of the retaining wall on Haiphong Road is a War Department
Boundary Marker, showing the location of the exact southwest corner of the
original Whitfield barracks, one of the earliest mapped lots in Kowloon (AMO Files).
8.4.11
The Fuk Tak
Koo Mui
Temple is a modern structure located behind the temporary market at the
western end of Haiphong Road.
8.4.12
The 1930’s high rise structure at the corner of Nathan and
Austin Roads has ground floor walls that are covered by modern material. The 3 upper stories are covered in
render designed to imitate masonry.
The north facing wall has a balcony on each of the upper floors. There is a canopy over the top balcony.
8.5.1
All of the project Study Area
was covered by the field survey for the BHIA, no additional built heritage resources were identified apart
from those listed in the desk-based study.
A catalogue of the resources as surveyed for the project can be found in
Appendix 8.2. All resources apart from the Hong
Kong Observatory (due to restricted access) were covered by the field survey.
1:1000 scale maps showing the boundary of all of the resources can be found in Annex
1 through 5
in Appendix 8.1.
Construction Phase
8.6.1
Blasting and tunnel boring
machine has been ruled out for the construction of the proposed subway or
associated works. For the construction of the plant basement and satellite
concourse, a temporary cofferdam wall will be formed using sheet piles to be
installed by non-vibratory piler, while other piling works will include
"bored piles" type.
8.6.2
As indentified in
Section 8.5, there is a heritage building
presently in use as an Education Centre is comprised of two parts ~ the Heritage Structure (which defined as the brick-built structure) and a Modern Extension built in r.c.
partly over the existing Entrance A1 subway, which we have not considered to be
part of the Heritage Structure. The Heritage Structure can itself be divided
into two portions. The section, nearer to the modern extension, that has been retrofitted
with steel beams, as part of the conversion to its modern use, through the external walls below the roof
structure and are supported on independent steel
columns on pad footings outside the building. The second part is further away from the planned construction works and has not been modified.
8.6.3
Proximity of the
excavation for the plant basement is close to the heritage structure and there
is a possibility that settlement can occur if works are not carried out
cautiously. The excavation for the plant basement will be firmly supported to
minimise any movement that will be induced from soil movement. The historical
building Block S4 has already been subjected to dewatering and settlement from
TST Station construction in the 1976 to 1979 (these settlements are largely
irreversible and can not be generated again by lowering the water table to the
same extent). However, it is proposed that the ground water table shall be
maintained to its present level around the structure during construction to
eliminate the potential for settlement. Furthermore, during the 1979
construction, there is a line of piles left in place from the 1979 works
(between the subway structure and the heritage structure) creating a stiff wall
between the plant basement excavation and the heritage structure thereby
reducing any potential for settlement. The existing A1 subway structure is also
very stiff and will also act as a reinforcing beam to reduce any
further ground movement anticipated in the area.
8.6.4
Section of the building
which is composed of a modern extension and the (brick) heritage structure and
supplementary steel props will adapt itself to any settlement (which is
considered to be minimal) without any dramatic events.
8.6.5
On the other hand, potential
visual impact to the built heritage resources may arise due to construction
works at surface.
Operation Phase
8.6.6
The upgrading and construction
of above ground entrances have the potential to have adverse visual impacts on
the environmental setting of built heritage resources.
Construction Phase
8.7.1
The following built heritage
resources have been identified in the project Study Area, and is within 300 metres of the proposed works area, see Table 8.1. The layout plan for the proposed works
can be found in the Subway Layout Plan, Figure 2.1.
Note:
[1] Resources
specifically required for detailed assessment under ESB
[2] Supplementary
background information in the area for the public
[3] Approximate
horizontal distance to the closest works location i.e. piling or excavation
locations but not the site hoarding boundary.
8.7.2
From Table 8.1,
the majority of the built heritage resources are located far away from the
proposed construction works, i.e. they are situated between 60 and 270 metres
away. Other than NRS-05 and NRS-08,
all other identified resources are located at a significant distance away from
the project and therefore will not be impacted upon by the proposed
construction works.
8.7.3
The resources NRS-05 and NRS-08
i.e. Block S4 of the former Whitfield Barracks and the retaining wall of the
Former Whitfield Barracks are located in close proximity to the proposed works
area of the Plant Basement.
Section 8.6 has identified the settlement and visual impacts.
8.7.4
As mentioned above,
Block S4 (Heritage structure) has undergone various degrees of modification and
modernization. The heritage section
has been modernised with structural beams. The current façade of the building
is a modern addition and windows are modern along the sides of the building.
The construction works will require the temporary removal of the two columns
(east of brick wall of modern extension). The two granite columns will be
stored securely during construction period, and reinstated back to its original location after completion of works. Hence, the impact will be minimized.
8.7.5
The excavation of the
plant basement could induce settlement around the heritage building, as there
is an existing line of piles from 1979 MTR construction including the existing
entrance A1 subway which acts as a stiff reinforcing beam, anticipated
settlement is considered minimal. With a ground water regime to maintain the
ground water draw-down around the present level, no settlement from dewatering
of the plant basement is expected.
8.7.6
Precautions shall be
taken throughout the constructions stage to prevent any damage to the
historical building. Moreover,
MTRCL is required to instigate an assurance system and control scheme to ensure
the management of the construction works are at a standard not inferior to that
required under the Building Ordinance.
8.7.7
There is a potential temporary
visual impact from the cut-and-cover construction works which could be
minimized by erecting sensitively designed hoardings.
Operation
Phase
8.7.8
The Block S4 of the
former Whitfield Barracks, which is used as the Health Education Exhibition and
Resource Centre, is situated in close proximity to the site of the proposed
upgrading of the existing MTR Entrance A1 of the Tsim Sha Tsui MTR Station
(less than 20 metres). The
photomontage for the Entrance A1 Upgrade is shown in Figure 8.1. No adverse visual
impacts will arise from the operation of the upgraded entrance based upon the
following assessment:
·
The current surroundings of
Block S4 outside of Kowloon Park do not have any historical connection with the
historical function of the structure as part of the Whitfield Barracks and the
proposed upgrading of the entrance will not impact on any resources associated
with the former Whitfield Barracks;
·
Block S4 is a renovated
historical structure and the current façade of the building is a modern
addition;
·
The upgraded Entrance A1 will
not alter the existing character of the urban setting of Block S4, photographs
of the existing environment are provided in Plates 1 through 4 in Appendix 8.3;
8.7.9
As the modified Entrance A1 is
situated approximately 330 metres from the Former Kowloon
British School,
it will not have any adverse impacts on this recorded resource. Entrances Q1, Q2 and Q3 are all situated
underground and will have no visual impacts at ground level. A map showing the location of the
identified built heritage resources can be seen in Annex 6 in
Appendix 8.1.
8.7.10
The old retaining wall on Haiphong Road is not
a visually sensitive structure and will not be adversely impacted by Entrance
A1 during the operation phase.
Construction Phase
8.8.1
Temporary visual impact during
construction phase could be minimized by the use of sensibly designed
hoardings. Regarding the
construction near the historical buildings, the impacts has identified as
minimal. However, precautions
shall be taken throughout the constructions stage to
prevent any damage to the historical building. Moreover, MTRCL is required to instigate
an assurance system and control scheme to ensure the management of the
construction works are at a standard not inferior to that required under the
Building Ordinance.
8.8.2
In addition, before the
commencement of the construction work, the Contractor shall also consult AMO on
any other mitigation measures that would be required administratively or under
Antiquities and Monuments Ordinance.
The Contractor shall implement these requirements from AMO during the
construction period. Method statement
of the removal/reinstate works for two granite columns should be agreed with
AMO by the Contractor.
Operation Phase
8.8.3
No adverse impacts to the
identified resources are anticipated during the operation phase of the project
and hence no mitigation measures will be required.
8.9.1
The proposed works will not
cause any insurmountable adverse impacts if the mitigation measures as
presented are adopted. The
Contractor will be responsible for implementing the recommended measures.
9.1.2
To ensure effective and timely
implementation of the recommended mitigation measures, it is considered
necessary to develop EM&A procedures and mechanisms in order to alleviate
those residual impacts to comply with the requirements of the EIAO-TM.
9.1.3
This chapter provides an outline
of the EM&A requirements for the Project. A detailed scope of work will be
provided in the EM&A Manual, prepared in accordance with Annex 21 of the
EIAO-TM and EPD’s EM&A Guidelines for Development Projects in Hong Kong.
9.1.4
The objectives of carrying out
EM&A for the Project include the following:
·
to provide a database against
which any short or long term environmental impacts of the Project can be
determined;
·
to provide an early indication
should any of the environmental control measures or practices fail to achieve
the acceptable standards;
·
to monitor the performance of
the Project and the effectiveness of mitigation measures;
·
to verify the environmental
impacts predicted in this EIA;
·
to determine project compliance
with regulatory requirements, standards and government policies;
·
to take remedial action if
unexpected problems or unacceptable impacts arise; and
·
to provide data to enable an
environmental audit.
9.1.5
The following sections
summarise the recommended EM&A requirements. Details of EM&A are
provided in a stand-alone EM&A Manual.
9.2.1
No exceedances of the HKAQO
criteria were predicted at ASRs in the vicinity of the construction sites. With implementation of the proposed dust
suppression measures stipulated in the Air Pollution Control (Construction
Dust) Regulation, good site practices and regular dust monitoring and audit,
the potential dust impact would be minimized and comply with HKAQO.
9.2.2
Dust monitoring requirements
are recommended in the EM&A Manual to ensure the efficiency of the control
measures.
Construction Phase
9.3.1
An EM&A programme is
recommended to be established according to the predicted occurrence of noisy
activities. All the recommended
mitigation measures for daytime normal working activities shall be incorporated
into the EM&A programme for implementation during construction. Details of the programme are provided in
the stand-alone EM&A Manual.
Operation Phase
9.3.2
Any
necessary mitigation measures would be implemented to ensure the compliance of the operation noise levels with the EIAO-TM noise
criteria.
9.4.1
The water quality assessment
concluded that the identified water quality impacts can be minimized by
implementing the recommended mitigation measures for the construction works,
such as control measures on site runoff and drainage from the works areas and
proper site management and good housekeeping practices. No unacceptable residual water quality
impact was expected and hence water quality monitoring was considered not
necessary during the construction phase.
Any effluent discharges from the site would be required to comply with
the terms and conditions of a discharge licence, issued by EPD, under the WPCO. It is recommended that regular site
inspections be undertaken during the construction activities and works areas in
order to ensure the recommended mitigation measures are properly implemented.
9.5.1
Waste management will be the
contractor’s responsibility to ensure that all wastes produced during the
construction of the Project are handled, stored and disposed of in accordance
with the recommended good waste management practices and EPD’s regulations and
requirements. The mitigation
measures recommended in Section 6 shall form the basis of the site Waste
Management Plan to be developed by the Contractor at the construction stage.
9.5.2
It is recommended that the
waste generated during the construction shall be audited periodically to
determine if wastes are being managed in accordance with approved procedures
and the site Waste Management Plan.
The audits shall look at all aspects of waste management including waste
generation, storage, transport and disposal. An appropriate audit programme will need
to be undertaken. In addition, the
routine site inspections shall check the implementation of the recommended good
site practices and other waste management mitigation measures.
Construction Phase
9.6.1
Based on detail tree survey,
during the construction period, approximately 30 trees will be affected due to
the construction of MTR Tsim Sha Tsui Station Northern Subway. None of the OVTs are affected by the
works. Appropriate protection measures will be implemented for the OVT near the
proposed Emergency Exit in front of the Miramar Shopping Centre. Those affected trees with good amenity
value and high survival rate after transplanting which are unavoidably affected
by the work will be transplanted where possible. Detailed tree preservation,
transplanting including compensatory planting proposals shall be submitted to
relevant government departments for approval in accordance with ET WBTC no.
3/2006.
9.6.2
The proposed work area belongs
to Tsim Sha Tsui Organic Mixed Urban Development Landscape, during the
construction phase, although the proposed work is not high sensitive to this
zone, there will be moderate residual impact due to the temporary works.
9.6.3
Health Education Exhibition and
Resource Centre can be accessed from Kowloon
Park by two entrances, during
construction phase, one of the entrances nearby Entrance A1 to Kowloon Park will be blocked for approximate
2.5months, slightly inconvenience to the park and exhibition centre users may
occur, the residual impacts are considered as moderate.
Operation Phase
9.6.4
The residual impacts on
existing trees are considered as insubstantial.
9.6.5
The impacts on entrance to Kowloon Park during operation phase are
considered as slight with mitigation measures as reinstatement will be
provided.
9.6.6
The overall visual impact to
the VSRs are considered as slight to insubstantial, with mitigation measures,
as the proposed structures are low and with aesthetic facades.
9.7
Built Heritage Impact
9.7.1
It is recommended to use
appropriately designed hoardings to minimise the potential temporary visual
impacts from the cut-and-cover construction in the vicinity of the two
identified resources i.e. Block S4 of the former Whitfield Barracks and the
retaining wall of the Former Whitfield Barrack. Regarding the construction near the historical buildings, the
impacts has identified as minimal.
However, precautions
shall be taken throughout the constructions stage to
prevent any damage to the historical building. Moreover, structural monitoring
system, including pre-construction survey shall be designed and implemented by
a Registered Structural Engineer from the Contractor to ensure compliance with
the Building Ordinance.
9.7.2
EM&A requirements for
landscape and visual impacts will also be applicable for the protection of
heritage resources.
10.1.1
This EIA Report has provided an
assessment of the potential environmental impacts associated with the
construction and operation phases of the Tsim Sha Tsui Station Northern Subway
Project.
10.1.2
The identified key
environmental issues below have been assessed in this EIA report, in accordance
with the EIA Study Brief (No. ESB-168/2007) registered under the EIAO for the
Project:
·
Construction air quality
impact;
·
Noise impact;
·
Construction water quality
impact;
·
Waste management impact;
·
Landscape and visual impact; and
·
Built heritage impact.
10.1.3
The findings of this EIA study
have determined the likely nature and extent of environmental impacts predicted
to arise from the construction and operation of the Project. The EIA has, where appropriate, identified
mitigation measures to ensure compliance with environmental legislation and
standards.
10.1.4
Overall, the EIA study for the
proposed Project, with the implementation of the proposed mitigation measures
for construction and operation phases, would comply with all applicable environmental
standards and legislation except construction noise impact.
10.1.5
Residual noise impacts during
daytime construction are predicted at certain NSRs. Exceedances of the EIAO-TM criterion of
75 dB(A) are in a range of 1 to 4 dB(A).
10.1.6
Table 10.1 summarises the environmental outcomes that have accrued from
environmental considerations and analysis during the EIA process and
implemented in design of the Project and the recommended mitigation measures.
Environmental monitoring and audit mechanisms have been recommended, where
necessary, to verify the accuracy of the EIA predictions and the effectiveness
of recommended mitigation measures.
Table 10.1 Summary
of Key Environmental Outcomes
Key Environmental Issue
|
Environmental Outcomes and
Mitigation Measures
|
Population Benefited and
Environmental Sensitive Areas Protected
|
Population Benefited
|
The proposed Project is
located in the urban area of Tsim Sha Tsui along Nathan Road of section from Haiphong Road to Miramar
Shopping Centre near Kimberley
Road junction. The population benefitted from
the mitigation measures recommended in this EIA Study are dominantly the
residential and commercial sensitive receivers of the high rise buildings in
the close proximity to the works areas.
|
|
Environmentally Sensitive Receivers Protected
|
Sensitive receivers along
the proposed works areas have been identified including residential
buildings, commercial buildings, service apartment, hotels, shops,
religionary, G/IC and heritage buildings. A package of mitigation measures has
been recommended to protect these sensitive receivers to the maximum
practicable extent.
Referring to the
assessment results, all sensitive receivers can be protected to meet the
relevant criteria during the operation phase. Residual environmental impacts are not
anticipated except there would be residual construction noise impacts at some
of the noise sensitive receivers with exceedances by 1 to 4 dB(A) for short
term even after exhausting all practicable direct noise mitigation
measures. A
community liaison channel to be set up would handle any public enquiry and complaint.
|
|
Key Environmental Problems
Avoided
|
Avoidance or Minimization of Above-Ground Structure
|
Most part of the proposed Project is underground structure. During
construction phase, the cut-and–cover components of the scheme have been
limited to Satellite Concourse, Plant Basement, Connection Chamber and
Emergency Exit Stair. During
operation phase, the above ground structures are only the modified Entrance
A1 and the integrated ventilation shafts. As a result, the number of
sensitive receivers would be minimized.
|
|
Environmental Friendly
Designs Adopted and Environmental Benefits
|
Orientation of Ventilation
Shafts
|
In order to minimize the associated noise impacts from the operation
of the proposed ventilation shafts, the detailed design will maximise the
possibility of the shaft opening to face away from the neighboring sensitive
receivers, where practicable.
This will ensure that noise generated would be minimal by the design
itself. Adequate attenuation will
also be incorporated into the detailed design to ensure compliance with the
relevant statutory noise criteria.
|
|
Alignment
|
The Old and Valuable Trees (OVTs) are protected by shifting the subway
alignment towards the east side of Nathan
Road away from the row of OVTs on west footpath
of Nathan Road
in the design.
The entrances proposed at the western
footpath of Nathan Road
were not further pursued that no OVTs would be affected.
|
|
Environmental Friendly
Construction
|
The TNS subway is the most direct and shortest link to the proposed
entrances, i.e. minimise the extent of the construction works area and limit
the works area to the section of Nathan
Road.
The subway tunnels which form of a large proportion of the project are
to be constructed using tunnelling by mining method. The environmental benefits include:
- minimal airborne noise and dust impacts
on nearby sensitive receivers;
- minimal
impact on the traffic and pedestrians at street level during construction.
Although there are potential disbenefits associated with the use of
cut-and-cover methods in terms of dust and airborne noise emission during construction. These impacts can be mitigated through
undertaking the bulk excavation activities under a road deck, phasing and
sequence of construction activities associated with the site clearance and
temporary deck construction, as well as implementation of sufficient dust and
noise mitigation measures during the execution of the construction
activities.
|
|
Construction Air Quality
|
No exceedances of the AQO
criteria were predicted at ASRs in the vicinity of the construction sites.
No adverse dust impacts is
expected on the identified ASRs with the implementation of dust suppression
measures stipulated in Air Pollution control (Construction Dust) Regulation.
|
|
Noise
|
NSRs in the vicinity of the
construction sites will be affected during construction of the TNS
Project. With the adoption of
quieter plant, movable noise barrier, noise enclosure and noise insulating
fabric and good site practices, most of the representative NSRs were
predicted to comply with the EIAO-TM noise criteria.
Some residual construction
noise impact will be expected at certain NSRs located close to the works
areas with the proposed mitigation measures are in place. Good site practices
could ameliorate the noise impacts.
The Noise Control
Authority will consider a well-justified Construction Noise Permit (CNP)
application for construction works within restricted hours as guided by the
relevant Technical Memoranda issued under the Noise Control Ordinance. The Noise Control Authority will take
into account of contemporary conditions / situations of adjoining land uses
and any previous complaints against construction activities at the site
before making his decision in granting a CNP. Despite any description made in
this EIA Report on construction noise aspects, there is no guarantee that a
CNP will be issued for the project construction.
|
|
Construction Water
Quality
|
The key issue in terms of
water quality during the construction phase of the Project will be
construction runoff and site drainage, underground works, sewage effluent and
general construction site activities.
Minimisation of water quality deterioration can be achieved through
implementing adequate mitigation measures such as control measures on site
runoff and drainage from the works areas to minimise construction runoff, and
on-site treatment of site runoff and drainage prior to discharge. Proper site management and good
housekeeping practices will also be required to ensure that construction
wastes and other construction-related materials would not enter the drainage
culvert.
With the implementation of
these recommended mitigation measures (Section
5.13), the construction works for the Project is not expected to result
in unacceptable impacts on water quality. Site inspections shall be undertaken
routinely to inspect the works areas in order to ensure the recommended
mitigation measures are properly implemented.
|
|
Waste Management
|
Wastes generated by the
construction activities are likely to include C&D materials from the
construction works, general refuse from the workforce and chemical waste from
any maintenance of construction plant and equipment. Provided that these identified waste
arisings are handled, transported and disposed of using approved methods and
that the recommended good site practices are strictly followed, adverse
environmental impacts is not be anticipated during the construction works.
|
|
Landscape and Visual
|
No
significant impacts on the planning and development control framework as the
affected areas are small compared to the overview.
Based on detail tree survey, during the
construction period, approximately 30 trees will be affected by the
construction of MTR Tsim Sha Tsui Station Northern Subway. None of them are OVTs. Most of the affected trees are
proposed to be transplanted with the exception of the 3 nos. of Delonix regia of poor condition along Haiphong Road. Re-planting of all transplanted trees
and compensatory planting at Haiphong
Road are proposed. Appropriate protection measures will be implemented for the OVT nearby the emergency exit.
The overall residual impacts on OVTs are considered as insubstantial
with mitigation measures.
The overall residual impacts on entrance to Kowloon Park
are considered as slight with mitigation measures as reinstatement will be
provided after construction.
The overall visual impact to the VSRs are considered as slight to
insubstantial with mitigation measures during operation phase, as the
proposed structures are low and with aesthetic facades.
Overall, it is considered
that the residual landscape and visual impacts of the proposed project are
considered acceptable with mitigation measures during construction and
operation.
|
|
Built Heritage
|
It is proposed to use sensitively designed hoardings to mininise any
visual impacts to the two built heritage structures.
Regarding the construction near the historical buildings, the impacts
has identified as minimal.
However, precautions shall be taken throughout the constructions stage
to prevent any damage to the historical building. Moreover, structural monitoring system,
including pre-construction survey shall be designed and implemented by a
Registered Structural Engineer from the Contractor to ensure compliance with
the Building Ordinance.
The proposed works will not cause any insurmountable adverse impacts
during operation phase.
|
|
|
|
|
|
10.1.7
The implementation schedule of
the proposed mitigation measures for the Project is presented in Appendix
10.1. For recommended
mitigation measures of each key environmental issue, the location and timing
for the measures have been clearly identified as well as the parties
responsible for implementing the measures.