Chapter Title Page
Figures
Figure 9.1 Proposed Land
Contamination Site Investigation Locations on
Figure 9.2 Proposed Land
Contamination Site Investigation Locations on South Horizons Station (SOH)
Appendices
Appendix 9.1 Contamination
Assessment Plan
Appendix 9.2 Contamination
Assessment Report
The potential environmental issues associated with land contamination have been reviewed and are presented in this section. The implications of land contamination for the proposed land uses for SIL(E) stations and the associated works areas at the study areas including Hong Kong School of Motoring (HKSM), Citybus Depot, ex-Wong Chuk Hang Estate, Lei Tung Estate, South Horizons and Ap Lei Chau Estate, have been assessed in accordance with the EIA Study Brief (ESB-181/2008).
9.2 Environmental Legislation, Standards and Guidelines
“Guidance
Note for
Further consideration of contamination issues is provided in Section 3 (Potential Contaminated Land Issues) of Annex 19 “Guidelines for Assessment of Impact on Sites of Cultural Heritage and Other Impacts” of the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM).
9.3 Description of the Environment/ Baseline Conditions
For
SIL(E), an Admiralty Station (ADM) is proposed which would be constructed to
the east of the existing ISL Admiralty station on
Over
the past decades, the study area has been utilised as commercial uses, open
areas, etc with low rise buildings, etc. In the late 70’s, after the commencement
of mass transit railway construction, the aforesaid area was used as site
office and open areas. Starting from early 90’s, the study area was turned into
a public park and underground carpark. The proposed station is going to locate
underneath the public park, i.e.
Table 9.1: Land Use History for Future SIL(E) Admiralty Station (ADM)
Date |
Ref. no. |
Height (ft) |
Land Use |
11/11/1945 |
4031 |
20,000 |
Low rise buildings |
25/5/1949 |
Y01508 |
8,600 |
Low rise buildings |
1/2/1963 |
Y07614 |
2,700 |
Open area, low rise buildings |
1/1/1969 |
Y14677 |
- |
Open area, low rise buildings |
14/9/1979 |
26855 |
4,000 |
Site office, open area |
28/11/1979 |
27904 |
4,000 |
Site office, open area |
25/10/1988 |
A14807 |
2,000 |
Site office, open area |
2/10/1991 |
A27674 |
4,000 |
Site office, open area |
12/5/1992 |
A30896 |
4,000 |
Site office, open area |
9/7/1993 |
A35230 |
4,000 |
Harcourt garden under construction, underground carpark |
8/10/1993 |
CN4721 |
4,000 |
Harcourt garden and underground carpark |
23/6/1997 |
CN17473 |
2,000 |
Harcourt garden and underground carpark |
31/10/1998 |
CN22126 |
4,000 |
Harcourt garden and underground carpark |
19/5/2006 |
CW71794 |
4,000 |
Harcourt garden and open space |
9.3.2
The
proposed Ocean Park (OCP) Station covers part of the former Hong Kong School of
Motoring (HKSM) and a small portion of the existing Citybus Depot (CBD). The
HKSM was in operation since 1985 until 2006 and Citybus Ltd. has taken the area
to the north of the proposed OCP station in late 90’s as a depot. The remaining
HKSM area was then handed over to
An
EIA study for the
A post-decontamination confirmation was prepared in accordance with Condition 2.10 of the Environmental Permit EP-249/2006/A and submitted to EPD in April 2007 confirming the completion of all decontamination works in the former HKSM site.
Soon after Citybus Ltd. has taken over part of the area previously used by HKSM, it was turned into a parking area for buses (depot). Based on the desktop studies and site inspection including land use history, questionnaires sent to relevant land users and government departments, the whole area is concrete paved and there was no evidence to show the existence of petrol refilling activities, car/buses maintenance or the presence of underground fuel tanks except that a vehicle washing facility was noted in the CBD site.
Table 9.2: Land
Use History for Future SIL(E)
Date |
Ref no. |
Height (ft) |
Land Use |
|
HKSM site |
CBD site |
|||
24/4/1949 |
Y01230 |
8,000 |
Farmland,
hillside, village houses |
Farmland,
hillside, village houses |
1/2/1963 |
Y06918 |
2,700 |
Farmland,
hillside, village houses |
Farmland,
hillside, village houses |
28/1/1976 |
12832 |
4,000 |
Open
area |
Open
area |
21/12/1977 |
20553 |
4,000 |
Open
area and carpark |
Open
area and carpark |
9/9/1987 |
A10402 |
4,000 |
HKSM |
HKSM |
20/10/1992 |
A32589 |
4,000 |
HKSM |
HKSM |
5/12/1993 |
A37065 |
4,000 |
HKSM |
HKSM |
9/8/2000 |
CN27613 |
4,000 |
HKSM |
Citybus
depot |
19/5/2006 |
CW71786 |
4,000 |
HKSM |
Citybus
depot |
During the construction of OCP station and its associated works, the area which is currently occupied by Citybus Ltd. would be used temporarily as site office and storage of construction material only. Subsequent property development is proposed at the same area but it is outside the scope of this EIA study.
9.3.3 Wong Chuk Hang Station (WCH)
According to the proposed SIL(E), a depot will be built in the area of ex-Wong Chuk Hang Estate close to the future Wong Chuk Hang (WCH) Station.
The
construction of Wong Chuk Hang Estate started in 1968 and was completed in
1973. The whole estate consisted of ten blocks which were built in phases over
the five year period. It was one of the sixteen “Government Low Cost Housing
Scheme” estates built and was the only one of this kind built on
Table 9.3: Land Use History for Future SIL(E) Wong Chuk Hang Station (WCH)
Date |
Ref. no. |
Height (ft) |
Land Use |
24/4/1949 |
6193 |
8,000 |
|
2/2/1963 |
Y6972 |
2,700 |
|
13/5/1967 |
Y13197 |
3,900 |
Site formation and construction of Wong Chuk Hang Estate |
1/1/1968 |
Y13937 |
3,000 |
Wong Chuk Hang Est. under construction |
29/1/1976 |
12832 |
4,000 |
Wong Chuk Hang Estate |
9/9/1987 |
A10402 |
4,000 |
Wong Chuk Hang Estate |
27/9/1988 |
A14545 |
4,000 |
Wong Chuk Hang Estate |
20/10/1992 |
A32591 |
4,000 |
Wong Chuk Hang Estate |
31/10/1995 |
CN11691 |
4,000 |
Wong Chuk Hang Estate |
23/10/1998 |
CN21061 |
4,000 |
Wong Chuk Hang Estate |
The Lei Tung Estate was built in 1987. It consists of eight 34 storey building. It is where the future LET Station locates.
According to the information collected during desktop study, Lei Tung Estate was built on the location around the former Lei Tung Temporary Housing Estate which was demolished in the early 80’s. Both estates cover an area of mainly hillside and farmland on the west side of Ap Lei Chau.
Table 9.4: Land Use History for Future SIL(E) Lei Tung Station (LET)
Date |
Ref. no. |
Height (ft) |
Land Use |
13/5/1967 |
Y13197 |
3,900 |
|
3/5/1982 |
41911 |
- |
Construction of Lei Tung Estate |
27/9/1988 |
A14548 |
4,000 |
Lei Tung Estate |
8/10/1993 |
CN4738 |
4,000 |
Lei Tung Estate |
9.3.5 South Horizons Station (SOH)
Before South Horizons was built, the whole area was occupied by both the Hong Kong Electric (HEC) Ap Lei Chau Power Plant and Oil Depot of Shell Hong Kong Ltd. The Hong Kong Electric Ap Lei Chau Power Plant was established in 1968 and decommissioned in 1989 leaving only the operations headquarters in Ap Lei Chau. Similarly, the Shell Oil Depot at Ap Lei Chau has been in operation since 1970 and decommissioned in the late 80’s. After the decommissioning, the South Horizons was built in 1992 to 1995 in four phases.
Table 9.5: Land Use History for Future SIL(E) South Horizons Station (SOH)
Date |
Ref. no. |
Height (ft) |
Land Use |
2/2/1963 |
Y06856 |
2,700 |
|
1/1/1969 |
Y14639 |
- |
Hong Kong Electric Power Plant under construction, Shell Oil Depot under construction |
21/12/1977 |
20557 |
4,000 |
Hong Kong Electric Power Plant, Shell Oil Depot, Ap Lei Chau Est. under construction |
3/5/1982 |
41912 |
- |
|
9/9/1987 |
A10406 |
4,000 |
|
12/5/1992 |
A31015 |
4,000 |
Construction of South Horizon, Hong Kong Electric Power Plant, Shell Oil Depot completely removed |
8/12/1992 |
A33525 |
6,000 |
South Horizons Phase 4 under construction |
8/10/1993 |
CN4737 |
4,000 |
South Horizons and Ap Lei Chau Estate |
31/10/1995 |
CN11690 |
4,000 |
South Horizons and Ap Lei Chau Estate |
In
1980, a bridge was constructed connecting
In order to identify and evaluate the potential contamination impacts associated with the Study Area, the following tasks have been undertaken:
¡ Desktop study to review the current and historical land uses;
¡ Acquisition of information related to potential land contamination from Environmental Compliance Division of Environmental Protection Department (EPD), Fire Services Department (FSD) and Lands Department; and
¡ Site reconnaissance to identify the existing land uses.
In addition, the following sources of information have been collated and reviewed:
¡ Aerial photos from Lands Department and Geotechnical Engineering Office (GEO);
¡ Ground Investigation (GI) reports from Civil Engineering and Development Department (CEDD) Geotechnical Information library; and
¡ Records and photographs from site visits.
9.5 Identification of Environmental Impact
The area where future SIL(E) ADM station is located was formed by reclamation and has been used for open space and commercial uses. By the time the construction of mass transit railway started, the area was used for site office as well as open areas. It has been confirmed that there was no activity or industry identified as per the Guidance Manual and Guidance Notes (Section 9.2 refers) within the proposed ADM station area that could potentially result in land contamination.
The
corresponding works area and vent shaft/ancillary building locations are located
mainly in the vicinity of ADM station, along Queensway, north of Harcourt Road and
close to the Hong Kong Park. These areas have been in the past used as
commercial and open area/roads/helipad (particularly for those in the vicinity
of ADM station) and residential (around
9.5.2
The
area south of OCP station was occupied by HKSM prior to handover to
The required land contamination assessment and remediation for the former HKSM is thus considered complete.
For the area which is currently used by Citybus Ltd, a contamination assessment strategy has been established and revealed no evidence of activities that would potentially result in significant land contamination. However, the existence of a vehicle washing machine was addressed during the desktop study and a prudent approach was adopted to further investigate its land contamination implication.
Other proposed works areas and ventilation building are for the Nam Fung Portal, viaduct and station construction. These areas were farmland, hillside and occupied with village houses in the past which indicate no land contamination issue.
9.5.3 Wong Chuk Hang Station (WCH)
According to the information received from various Government Departments during the contamination assessment stage and land use history, there was no activity or industry inside the ex-Wong Chuk Hang Estate that has contributed to land contamination. In addition, no Dangerous Goods (DG) store or Chemical Waste Store registration were recorded in the said Estate in its life span.
The corresponding works areas in the vicinity are for the construction of station, viaduct and a train depot which were in the past natural hillside, farmland as well as residential areas.
As such, it is considered that land contamination is not an issue for the said area in Wong Chuk Hang.
Based on the desktop review, it is unlikely that land contamination is an issue at Lei Tung Estate since it was built on natural hillside and farmland without any indication of industrial activities in the past.
Works areas are also required for the construction of the station, tunnel, site office and storage of construction materials in the vicinity. Similarly, no issue in land contamination could be concluded based on the past land uses.
9.5.5 South Horizons Station (SOH)
The
desktop study has indicated that the proposed location of the SOH station is
over the former oil depot of
It was considered likely that the original ground condition of the former oil depot has been significantly disturbed by the South Horizons construction works including excavation and filling. Nevertheless, contaminated soil may be present on this site and a site investigation strategy was therefore proposed.
Besides,
part of the SOH station is inside a cavern while the remaining part is to be
constructed by cut and cover along
Based on the assessment, no land contamination implication is therefore suggested in these areas
9.6 Prediction and Evaluation of Environmental Impact
Desktop review has been carried out for the 6 respective sites. Based on the review, we have summarized the results in Table 9-6.
Table 9.6: Potential Contamination for each Study Area
Site |
Desktop Studies |
Potential for Land Contamination |
Site Investigation |
Corresponding |
ADM |
No industries identified in accordance with the GM* and GN* |
Unlikely |
NO – no SI was proposed |
N/A |
CBD |
No indication of contaminating industries/activities except for the existence of a vehicle washing facility |
Anticipated significance is low |
YES – less intensive SI was proposed for CBD site and has been completed in June and July 2009 |
Industrial |
HKSM |
The area has been decontaminated during the EIA study for Ocean Park Development (Study Brief No. ESB-125/2005) |
Unlikely |
NO – no SI was proposed |
N/A |
WCH |
No industries identified in accordance with the GM* and GN* |
Unlikely |
NO – no SI was proposed |
N/A |
LET |
No industries identified in accordance with the GM* and GN* |
Unlikely |
NO – no SI was proposed |
N/A |
SOH |
Possible spillage/ leakage/ migration of fuel/ oil |
Anticipated significance is low |
YES – less intensive SI was proposed and has been completed in December 2008, June and July 2009 |
Industrial |
Out
of the six sites shown in Table 9-6, insignificant land contamination
implication was considered for four of them, i.e. Admiralty,
For the CBD site, the existence of vehicle washing facility has been addressed in the desktop review and a prudent approach has been adopted in further investigating the presence of land contamination. As such, less intensive sampling strategy was also proposed for the area.
The sampling strategy used during SI followed the principles of the Environmental Protection Department Guidance Manual and Guidance Notes as described in Section 9.2. Soil samples were obtained at a maximum depth of 3m using the “trial pit” method from each of the sampling locations (Figures 9.1 and 9.2). Three (3) samples per trial pit were taken vertically from typical depths of 0.5m, 1.5m and 3.0m below ground level in accordance with the Contamination Assessment Plan (CAP) (Appendix 9.1). At the same time, ground condition for each trial pit was logged accordingly. The samples were tested for a range of heavy metals, BTEX, VOCs and SVOCs by an HOKLAS laboratory, ALS Technichem (HK) Pty Ltd. All testing results is summarized in Table 9-7.
In the above table, all laboratory results were well below the respective RBRGs “Industrial” criteria indicating an acceptable environmental quality in terms of anticipated impact to future land users.
During
the operation phase, it is expected that defined procedures in handling
chemicals for the operation of a depot and railway station would be implemented
as part of MTRCL company’s policy. As such, no land contamination implication
is therefore considered.
Table 9.7: Analytical
Results for Soil Samples Taken from
* LOR – Limit of Reporting
* BH-1 to BH3 – Sampling locations at South Horizon Station (SOH)
* BH7 and BH8 – Sampling locations at Ocean Park Station (OCP)
* For details of testing results, please refer to the Contamination Assessment Report in Appendix 9.2
9.7 Mitigation of Adverse Environmental Impact
Mitigation measures are proposed for handling of the contaminated materials (if any) in order to minimize:
¡ The potentially adverse effects on the health and safety of construction workers; and
¡ The impacts arising from the disposal of potentially contaminated materials
The following measures are for contaminated material excavation and transportation:
¡ To minimize the chance for construction workers’ to come into contact with contaminated materials, bulk earth-moving excavation equipment should be employed;
¡ Contact with contaminated materials can be minimised by wearing appropriate clothing and personal protective equipment such as gloves and masks (especially when interacting directly with contaminated material), provision of washing facilities and prohibition of smoking and eating on site;
¡ Stockpiling of contaminated excavated materials on site should be avoided as far as possible;
¡ The use of contaminated soil for landscaping purpose should be avoided unless pre-treatment was carried out;
¡ Vehicles containing any excavated materials should be suitably covered to reduce dust emissions and/or release of contaminated wastewater;
¡ Truck bodies and tailgates should be sealed to stop any discharge;
¡ Only licensed waste haulers should be used to collect and transport contaminated material to treatment/disposal site and with the implementation of tracking system to avoid fly tipping;
¡ Speed control for trucks carrying contaminated materials should be carried out;
¡ Observe all relevant regulations in relation to waste handling, such as Waste Disposal Ordinance (Cap 354), Waste Disposal (Chemical Waste) (General) Regulation (Cap 354) and obtain all necessary permits where required; and
¡ Maintain records of waste generation and disposal quantities and disposal arrangements.
During operation phase, it is anticipated that defined procedures in handling chemicals are to be implemented as part of MTRCL company policy. As such, all relevant operational procedures shall be strictly followed to avoid land contamination.
9.8 Evaluation of Residual Impact
Based on the desktop review and available site investigation results for land contamination assessment of the Project, no contaminated land issue has been revealed and hence, no land remediation action is proposed at this stage.
As such, the residual impact in relation to land remediation is considered not an issue at this stage.
9.9 Environmental Monitoring and Audit
In view of the desktop review results and the Site Investigation Results, bulk excavation of soil for land remediation is not expected. As such, any environmental monitoring in relation to land remediation is not required.
On the other hand during construction phase, land contamination monitoring could be carried out in the form of regular site inspection. All related procedures and facilities in handling or storage of chemicals and chemical wastes should be audited regularly to make sure they are in order and intact and reported in the EM&A reports as such.
During operation phase, regular audits are expected in the form of company’s internal and external audits. All the procedures in handling chemicals and chemical wastes would then be audited against company policies, regulations and international standards. Subsequent audit results would be reported in the corresponding audit reports.
The land contamination assessment has been carried out which included a review of historical/current land uses, desktop review and site inspection. Other relevant information was also collected from related Government Departments during the assessment exercise.
All results have indicated insignificant contaminated land issue at ADM, WCH and LET sites. For OCP site, no similar issue was identified as land remediation had been carried out in the area south of OCP station (the former HKSM area) during another EIA study. For the area north of OCP station, i.e. the existing CBD, there was no evidence to show any sign of past activities that would potentially contributed to significant land contamination. As a result of the existence of a vehicle washing machine, a prudent approach in further site investigation was adopted and soil sampling strategy was proposed.
For the SOH site, it was where the former HEC Power Station and Shell Oil Depot located before South Horizons. Land contamination could be an issue due to the operation of the power plant as well as oil depot. Despite the aforesaid, it was believed the whole ground condition could have had seriously disturbed during the construction of South Horizons. As such, less intensive site investigation strategy was proposed.
SI was conducted in December 2008, June and July 2009 for the SOH and OCP stations where soil samples from five sampling locations were taken for laboratory analysis. Subsequent results have indicated the “Chemicals of Concern” (COC) of all locations at both SOH and OCP stations were well below their respective RBRGs “Industrial” criteria. Details of sampling and testing results are contained in the Contamination Assessment Report (CAR) in Appendix 9.2.
In view of the desktop review results and the Site Investigation Results, the significance of contamination to be low in the stations footprints as well as the concerned areas to the north and south OCP station. Bulk excavation of soil for land remediation is therefore not expected at this stage.
During the operation phase, it is expected that defined procedures in handling chemicals for the operation of a depot and railway station will be implemented as part of the MTRCL’s policy. As such, no land contamination implication is anticipated.