1. Advanced Works |
February 2012 to January 2015 |
36 months |
Construction of boundary fence and boundary patrol road on HK side |
2. Preparation Phase |
March to July 2013 |
5 months |
Tendering; land resumption |
3. Pre-construction |
August to September 2013 |
2 months |
Construction of site access roads and site office, site clearance, site preparation works etc. |
4. Construction |
October 2013 to December 2016 |
39 months |
Main construction works of the Project such as dredging of river sediment and soil excavation, construction of flood retardation pond, boundary fence and boundary patrol road on Shenzhen side, river modification works, dry weather flow interception works etc. |
5. Post-construction |
January 2017 to March 2017 |
3 months |
Demolition of temporary structures, landscaping works etc. |