Environmental Impact Assessment Ordinance, Cap.499
Application for Permission to Apply Directly for Environmental Permit
Application Number: DIR 007/1998
Project Title: Local Improvement to Tung Chung Road at Pak Kung Au and near Cheung Sha
Conditions of Approval to Apply Directly for an Environmental Permit
(1) | The applicant shall implement the mitigation measures described in the Project Profile and comply with the condition listed below: |
(2) | The applicant shall provide a temporary cover to the existing catchwater during the construction period at the Cheung Sha site in order to prevent earth material from falling into the catchwater. Details of the temporary cover shall be submitted to the Director of Environmental Protection for approval before commencement of work. |
- End -
Environmental Assessment & Noise Division
Environmental Protection Department
October 1998