Environmental Impact Assessment (EIA)
Ordinance, Cap.499
Application for Permission to Apply Directly
for Environmental Permit
Application No.: DIR-069/2002
Conditions Imposed under Sections 5(12) of
the EIAO
for Permission to Apply Directly for
Environmental Permit
1.
The project proponent shall conduct site investigation of
potentially contaminated land on the application site. Before the commencement
of the site investigation, the project proponent is required to submit for the
Director of Environmental Protection¡¦s (DEP¡¦s) approval a Contamination
Assessment Plan (CAP), which shall cover at least the transformer room, the
dangerous goods stores, the underground oil tanks, the area for above ground
acid and leach tanks, the underground solvent tank yard and the open air
distillation plant/underground waste solvent tank, with the exact sampling
locations and testing parameters of the soil and ground water.
2.
The project proponent shall carry out the site
investigation in accordance with the approved Contamination Assessment Plan.
3.
The project proponent shall submit for DEP¡¦s agreement a
Contamination Assessment Report (CAR).
4.
If contamination is confirmed by the Contamination
Assessment Report, the project proponent is required to submit for DEP¡¦s
approval a Remediation Assessment Plan (RAP).
5.
All the remediation actions identified in the approved
Remediation Assessment Plan shall be fully and properly implemented.
6.
No dismantlement works, which may disturb the ground of the
identified potentially contaminated sites, shall be carried out unless and until
the Contamination Assessment Plan and Remediation Assessment Plan submitted are
approved by DEP.
Note:
Under Section 17 of the
EIAO, the applicant may appeal to the Appeal Board the Director¡¦s decision
within 30 days of receipt of this reply.
Environmental Protection
Department
September 2002