Environmental
Impact Assessment (EIA) Ordinance, Cap. 499
Application
for Permission to Apply Directly for Environmental Permit
Application
No.: DIR-078/2003
Project
Title: Modifications to MTRC Mong Kok Station Entrances C3 & C4
Conditions
Imposed under Section 5(12) of the Ordinance
for
Permission to Apply Directly for Environmental Permit
1. An
Environmental Monitoring & Audit programme shall be established for the
construction of the project.
2. Construction
noise mitigation plan(s) shall be submitted to show the location and duration
of the noise mitigation measures including, but not limited to, temporary
hoardings, noise barriers and noise enclosures to be provided on site.
3. The
visual impact of the hoardings, barriers and enclosures shall be mitigated by
the use of suitable colour schemes, and the landscape impact of the pedestrian
area after the demolition of entrance C3 shall be reinstated with proper
landscape treatment, such as paving or planting.
4. All
measures described in the Project Profile submitted by the applicant on 7
January 2003, together with those requirements mentioned in the above
conditions, shall be fully implemented.
Note:
Under
section 17 of the EIA Ordinance, the applicant may appeal to the Appeal Board
against any of the above conditions within 30 days of the receipt of this
notice of the Directorˇ¦s decision.
Environmental
Protection Department
February
2003