Environmental
Impact Assessment (EIA) Ordinance, Cap.499
Application
for Permission to Apply Directly for Environmental Permit
Application
No.: DIR-083/2003
Project Title:
Reconstruction of Wong Shek Public Pier, Sai Kung North, Tai Po
Condition Imposed under
section 5(12) of the Ordinance
for Permission to
Apply Directly for Environmental Permit
1. All measures described in the Project Profile submitted by the applicant on 26 May 2003 shall be fully implemented.
2.
Three sets of
detailed architectural design drawings shall be submitted to the Director for approval
at least one month before the commencement of construction of the Project. The drawings shall be able to
demonstrate that the appearance of the pier and its roof will be compatible
with the existing visual environment.
Under section 17 of the EIA Ordinance, the applicant may appeal to the Appeal Board against any of the above conditions within 30 days of the receipt of this notice of the Director¡¦s decision.
Environmental Protection Department
July 2003