Environmental
Impact Assessment (EIA) Ordinance, Cap.499
Application
for Permission to Apply Directly for Environmental Permit
(Application
No: DIR-113/2005)
Project Title: Expansion and Extension of Fill Bank
at Tuen Mun Area 38
Conditions Imposed under Section 5(12) of the
Ordinance
for Permission to Apply Directly for Environmental
Permit
1.
All
measures described in the Project Profile submitted by the Applicant on 4
January 2005, together with those requirements mentioned in the following
conditions, shall be fully implemented.
2.
An
area of 100m x 100m in the north-eastern corner of the stockpiling area shall
be managed as a ˇ§truckload control zoneˇ¨ (Figure 1) where no more than 64
vehicle-trip per hour and 704 vehicle-trip per day shall be allowed to travel
to the control zone between 0800 and 2000 hours daily. No traffic to the control zone shall be
allowed between 2000 and 0800 hours daily.
3.
To
mitigate the operational noise impact, semi-enclosure with a material surface
density of at least 10 kg/m2 shall be erected along the at-grade
haul roads (Figures 2 and 3) before the occupation of the planned holiday camp.
4.
When
the planned holiday camp is occupied, operational and removal activities of the
fill bank shall be limited to the southern side of the stockpile during the
time between 2300 and 0700 hours (Figure 2).
5.
Hydroseeding
or earthy coloured geo-textile matting in green, grey or brown colour shall be
provided on the slopes of the fill bank along the eastern, northern and western
sides as the slopes of each layer of platform are formed.
6. The fill bank shall be fully
decommissioned by March 2009.
Note
Under Section 17 of the EIA
Ordinance, the Applicant may appeal to the Appeal Board against any of the
above conditions within 30 days of the receipt of this notice of the Directorˇ¦s
decision.
Environmental Protection
Department
February 2005