Environmental Impact Assessment (EIA) Ordinance, Cap. 499
Project Title:
Lamma Power Station ¨C
1. All measures described in the Project Profile submitted by
the Applicant on 24 July 2007 shall be fully implemented; and
2. Low-NOx burners in accordance with the information
described in the Project Profile shall be installed and operated at the
coal-fired Units L4 and L5 in the Lamma Power Station on or before operation of
the Project.
Note
Under Section 17 of the EIA Ordinance, the applicant may appeal to the
Appeal Board against any of the above conditions within 30 days of the receipt
of this notice of the Director¡¯s decision.
Environmental Protection Department
August 2007