Application for Permission to Apply Directly for Environmental
Permit
(Application No.: DIR-180/2009)
Project Title : Control of Water Pollution at
Sewage Pumping Station
for Permission to Apply Directly for Environmental Permit
1.
All measures described in the
Project Profile (No. PP-387/2009) submitted by the applicant on
2.
A contingency plan for emergency
discharge shall be developed prior to the commencement of construction of the
Project.
3.
Routine monitoring, inspection
and maintenance of the sewage pumping station should be carried out during
operation stage of the Project.
Note:
Under section 17 of the EIA Ordinance, the applicant may appeal to the Appeal Board against the above conditions within 30 days of the receipt of this notice of the Director¡¦s decision.
Environmental Protection Department