ENVIRONMENTAL PERMIT TO CONSTRUCT AND OPERATE A
DESIGNATED PROJECT
建造及營辦指定工程項目的環境許可證
A部 (許可證主要部分)
Pursuant to Section
10 of the Environmental Impact Assessment Ordinance (the EIAO), the Director of
Environmental Protection (the Director) grants this environmental permit to the
Major Works Project Management Office, Highways Department (hereinafter
referred to as the “Permit Holder”) to construct and operate the designated
project described in Part B subject to the conditions specified in Part C. The
issue of this environmental permit is based on the documents, approvals or
permissions described below:
根據《環境影響評估條例》(環評條例)第10條的規定,環境保護署署長(署長)將本環境許可證批予路政署主要工程管理處(下稱“許可證持有人”)以建造及營辦B部所說明的指定工程項目,但須遵守C部所列明的條件。本環境許可證的發出,乃以下表所列的文件、批准或許可作為根據﹕-
Application
No. 申請書編號 |
AEP-141/2002 |
|||
Document
in the Register : 登記冊上的文件: |
(1) Widening of
Yuen Long Highway between Lam Tei and Shap Pat Heung Interchange –
Preliminary Design and Ground Investigation Assignment (Register No.:
AEIAR-059/2002) -
Final Environmental Impact Assessment Report (December 2001)
[Hereinafter referred to as the “EIA Report”] -
Final EIA Executive Summary (December 2001) [Hereinafter referred to
as the “Executive Summary”] -
Environmental Monitoring and Audit Manual (December 2001) [Hereinafter
referred to as the “EM&A Manual”] (1) 元朗公路藍地至十八鄉段擴闊工程 – 初步設計及土地勘測 (登記冊編號: AEIAR-059/2002) -
環境影響評估報告 (2001年12月) [下稱「環評報告」] -
環境影響評估行政摘要 (2001年12月) [下稱「行政摘要」] -
環境監察及審核計劃 (2001年12月) [下稱「環監計劃」] (2) The
Director’s letter of approval of the EIA report dated 22 May 2002 (Reference:
(26) in Ax(1) to EP2/N6/A/62 IV) (2) 署長於2002年5月22日發出批准環評報告的信件 (檔案編號: (26) in Ax(1) to EP2/N6/A/62 IV) (3) Application
documents including all attachments submitted by the Permit Holder on 29 May
2002 (Application No. AEP-141/2002) (3) 申請文件包括許可證持有人於2002年5月29日提交的所有附件(申請書編號:AEP-141/2002) |
|||
|
|
|
||
Date 日期 |
|
(Mrs Shirley LEE) Acting Assistant Director (Environmental Assessment and Noise) for Director of Environmental Protection 環境保護署署長 (署理助理署長(環境評估及噪音)李韓琇玲代行) |
||
PART B (DESCRIPTIONS OF
DESIGNATED PROJECT)
B部 (指定工程項目的說明)
Hereunder is the description of the designated project
mentioned in Part A of this environmental permit (hereinafter referred to as
the “Permit”):
下列為本環境許可證(下稱“許可證”)A部所提述的指定工程項目的說明:
Title of Designated Projects 指定工程項目的名稱 |
Widening of Yuen
Long Highway between Lam Tei and Shap Pat Heung Interchange [The above designated project is hereinafter referred to as “the
Project”] 元朗公路藍地至十八鄉段擴闊工程 [這工程項目下稱"工程項目"] |
Nature
of Designated Projects |
Major improvements to existing roads. 現有道路之重大改善工程。 |
Location of Designated
Projects 指定工程項目的地點 |
The section of Yuen Long Highway between Lam Tei and Shap Pat Heung
Interchange. The location of the Project is shown in Figure 1 attached to
this Permit. 介乎藍地及十八鄉交匯處之間的一段元朗公路。工程項目的位置見載於本許可證夾附的圖1。 |
Scale and Scope of Designated Project(s) 指定工程項目的規模和範圍 |
(a)
Widening of the section of Yuen Long Highway between Lam Tei and Shap Pat
Heung Interchange from dual 2-lane to dual 3-lane, together with a 3.65m wide
hard shoulder for each carriageway; (a) 把介乎藍地及十八鄉交匯處之間的一段元朗公路由雙程雙線分隔車路擴闊至雙程三線分隔車路,包括每邊行車路上3.65米闊的路肩; (b)
Modification of the existing interchanges along Yuen Long Highway to suit the
above widening; (b) 修改元朗公路現有的交匯處以配合上述的擴闊工程; (c)
Modification and widening of existing highway structures, i.e. culverts,
bridges, underpasses, pedestrian subways, etc. to suit the widening; (c) 修改及擴闊現有的公路設施,即暗渠、橋樑、下通路、行人隧道等,以配合上述的擴闊工程; (d)
Realignment of the various slip roads connecting Yuen Long Highway to suit
the above widening; (d) 把各條接駁元朗公路的連接路重新定線,以配合上述的擴闊工程; (e)
Provisioning/re-provisioning of associated civil, geotechnical, landscaping,
drainage and water mains diversion works, public lighting such as
conventional street lighting, underpass / tunnel lighting, high mast lighting
and pedestrian subway lighting, traffic aids (including overhead sign
gantries), central divider / parapets, noise barriers and traffic control and
surveillance system (TCSS), police observation platforms along the widened
carriageway and interchanges, fire hydrants and fire supply mains; and (e) 提供/重設相關的土木、土力、景觀美化、渠務及水管改道工程、公共照明例如普通街燈、下通路/行車隧道照明、高桅燈及行人隧道照明、交通輔助設施(包括架空高架道路標誌)、道路中央分隔欄/防撞欄、隔音屏障和交通管制及監察系統 (TCSS)、沿著已擴闊的行車道及交匯處的警察瞭望平台、消防栓和消防供水管; 及 (f)
Rehabilitation of the existing highway pavement to extend its service life to
that of the new pavement. (f) 修復現行的公路路面使其使用期限延長至與新路面同一水平。 |
1. General
Conditions
1.1 The
Permit Holder shall ensure full compliance with all conditions of this
environmental permit. Any
non-compliance may constitute a contravention of the Environmental Impact
Assessment Ordinance (Cap. 499) and may become the subject of appropriate
action being taken under the Ordinance.
1.2
The Permit Holder shall ensure full
compliance with all legislation from time to time in force including but without
limitation to the Noise Control Ordinance (Cap. 400), Air Pollution Control
Ordinance (Cap. 311), Water Pollution Control Ordinance (Cap. 358), Dumping at
Sea Ordinance (Cap. 466) and Waste Disposal Ordinance (Cap. 354). This Permit does not of itself
constitute any ground of defence against any proceedings instituted under any
legislation.
1.3
The Permit Holder shall make copies
of this Permit together with all documents referred to in this Permit or the
documents referred to in Part A of the Permit readily available at all times
for inspection by the Director or his authorised officers at all sites/offices
covered by this Permit. Any
reference to the Permit shall include all documents referred to in the Permit
and also the relevant documents in the Register.
1.4
The Permit Holder shall give a copy
of this Permit to the person(s) in charge of the site(s) and ensure that such
person(s) fully understands all conditions and all requirements incorporated by
the Permit. The site(s) refers to site(s) of construction and operation of the
Project and shall mean the same hereafter.
1.5
The Permit Holder shall display conspicuously
a copy of this Permit on the construction site(s) at all vehicular site
entrances/exits or at a convenient location for public’s information at all
times. The Permit Holder shall
ensure that the most updated information about the Permit, including any
amended permit, is displayed at such locations. If the Permit Holder surrenders a part or the whole of the Permit,
the notice he sends to the Director shall also be displayed at the same
locations as the original Permit.
The suspended, varied or cancelled Permit shall be removed from display at
the construction site(s).
1.6
The Permit Holder shall construct
and operate the Project in accordance with the project descriptions in Part B
of this Permit.
1.7
The Permit Holder shall ensure that
the Project is designed, constructed and operated in accordance with the
information and all recommendations described in the EIA Report (Register No.: AEIAR-059/2002), other relevant documents in the Register; and the
information or mitigation measures described in this Permit, and mitigation
measures to be recommended in submissions that shall be deposited with or approved
by the Director as a result of permit conditions contained in this Permit, and
mitigation measures to be recommended under on going surveillance and
monitoring activities during all stages of the Project. Where recommendations
referred to in the documents of the Register are not expressly referred to in
this Permit, such recommendations are nevertheless to be implemented unless
expressly excluded or impliedly amended in this Permit.
1.8
All deposited submissions, as
required under this Permit, shall be rectified and resubmitted in accordance
with the comments, if any, made by the Director within one month of the receipt
of the Director’s comments or otherwise as specified by the Director.
1.9
All submissions approved by the
Director, all submissions deposited without comments by the Director, and all
submissions rectified in accordance with comments by the Director under this
Permit shall be construed as part of the permit conditions described in Part C
of this Permit. Any variation of the submissions shall be approved by the
Director in writing or as prescribed in the relevant permit conditions. Any
non-compliance with the submissions may constitute a contravention of the
Environmental Impact Assessment Ordinance. All submissions or any variation of
the submissions shall be certified by the Environmental Team (ET) Leader and
verified by the Independent Environmental Checker (IEC) referred to in Conditions 2.1 and 2.2 below, before
submitting to the Director under this Permit.
1.10
The Permit Holder shall release all
finalised submissions as required under this Permit, to the public by
depositing copies in the Environmental Impact Assessment Ordinance Register
Office, or in any other places, or any internet websites as specified by the
Director, or by any means as specified by the Director, for public inspection.
For this purpose, the Permit Holder shall provide sufficient copies of the
submissions.
1.11
The Permit Holder shall notify the
Director in writing the commencement date of construction of the Project no
later than one month prior to the commencement of construction of the Project.
The Permit Holder shall notify the Director in writing immediately if there is
any change of the commencement date of the construction.
1.12
All submissions to the Director required under
this Permit shall be delivered either in person or by registered mail to the
Environmental Impact Assessment Ordinance Register Office (currently at 27/F,
Southorn Centre, 130 Hennessy Road, Wanchai, Hong
Kong). Electronic copies of all finalised submissions required under this
Permit shall be prepared in Hyper Text Markup Language (HTML) (version 4.0 or
later) and in Portable Document Format (PDF version 4.0 or later), unless
otherwise agreed by the Director and shall be submitted at the same time as the
hardcopies.
1.13
For the purpose of this Permit, “commencement
of construction” does not include works related to site clearance and
preparation, or other works as agreed by the Director.
2.
Measures and Submissions for Commencement of the
Project
2.1
An ET shall be established by the
Permit Holder no later than one month before the commencement of construction
of the Project. The ET shall be headed by an ET Leader. The ET Leader shall be
a person who has at least 7 years' experience in environmental monitoring and
auditing (EM&A) or environmental management. The ET and the ET Leader shall
be responsible for the implementation of the EM&A programme in accordance
with the requirements as contained in the EM&A Manual. The ET Leader shall
keep a contemporaneous log-book of each and every circumstance or change of
circumstances which may affect the environmental impact assessment and each and
every non-compliance with the recommendations of the EIA Report or this Permit.
This log-book shall be kept readily available for inspection by all persons
assisting in supervision of the implementation of the recommendations of the
EIA Report and this Permit or by the Director or his authorized officers.
Failure to maintain records in the log-book, failure to discharge the duties of
the ET Leader as defined in the EM&A Manual or failure to comply with this
Condition would entitle the Director to require the Permit Holder by notice in
writing to replace the ET Leader. Failure by the Permit Holder to make
replacement, or further failure to keep contemporaneous records in the log-book
despite the employment of a new ET Leader may render the Permit liable to
suspension, cancellation or variation. The ET shall not be in any way an
associated body of the Contractor or the IEC for the Project.
2.2
An IEC shall be employed by the Permit Holder
no later than one month before the commencement of construction of the Project.
The IEC shall be a person who has at least 7 years' experience in EM&A or
environmental management. The IEC shall be responsible for duties defined in
the EM&A Manual and shall audit the overall EM&A programme, including
the implementation of all environmental mitigation measures, submissions
required in the EM&A Manual, and any other submissions required under this
Permit. In addition, the IEC shall be responsible for verifying the environmental
acceptability of permanent and temporary works, relevant design plans and
submissions under this Permit. The IEC shall verify the log-book(s) mentioned
in Condition 2.1 of this Permit. The IEC shall notify the Director by fax,
within 24 hours of each and every change of circumstances or non-compliance
with the recommendations of the EIA Report or this Permit, which might affect
the monitoring or control of adverse environmental impacts from the Project. In
case the IEC fails to so notify the Director of the same, fails to discharge
the duties of the IEC as defined in the EM&A Manual or fails to comply with
this Condition, the Director may require the Permit Holder by notice in writing
to replace the IEC. Failure to replace the IEC as directed or further failure
to so notify the Director despite employment of a new IEC may render the Permit
liable to suspension, cancellation or variation. Notification by the Permit
Holder is the same as notification by the IEC for the purpose of this Condition.
The IEC shall not be in any way an associated body of the Contractor or the ET
for the Project.
2.3
The Permit Holder shall, within one
month before the commencement of construction of the Project, deposit with the
Director 3 sets of construction noise mitigation proposal to mitigate the
construction noise impact arising from the Project. The proposal shall indicate
the exact locations and details of the temporary noise barriers and the
arrangement of the number and type of equipment, procedure and sequence of
construction. The submission shall be certified by the ET leader and verified
by the IEC as conforming to the information and recommendations contained in
the EIA Report.
2.4
The
Permit Holder shall, within one month after the commencement of construction of
the Project, submit to the Director 3 sets of Waste Management Plan (WMP) for
approval. The WMP shall take into account the relevant findings and
recommendations in the waste management section of the EIA Report. Before
submission to the Director, the WMP shall be certified by the ET Leader and
verified by the IEC as conforming to the information and recommendations
contained in the EIA Report.
2.5
The Permit
Holder shall, within one month after the commencement of construction of the
Project, inform the Director in writing the management organization of the main
construction companies and/or any form of joint ventures associated with the
construction of the Project. The
submitted information shall include at least an organization chart, names of
responsible persons and their contact details.
2.6
The Permit
Holder shall, within one month after the commencement of construction of the
Project, deposit with the Director 3 sets of landscape proposal to mitigate the
potential landscape and visual impacts arising from the construction and
operation of the Project. The landscape
proposal shall include an explanatory statement, design drawings and layout
plans at a scale 1 to 1000 or other scale as agreed by the Director. The
submission shall include an implementation programme with clear identification
of the responsibility for funding, implementation, management and maintenance
of the landscape and visual mitigation measures as recommended in the EIA
Report. The submission shall be certified by the ET leader and verified by the
IEC as conforming to the information and recommendations contained in the EIA
Report. The Permit Holder shall make available additional copies to the
Director upon his request.
2.7
The construction work of the Project at the
section from Kung Um Road to Shap Pat Heung shall not be carried out
simultaneously with that of Yuen Long Bypass Floodway at the bottom of the
embankment. The Permit Holder shall, prior to commencement of construction
works, deposit with the Director a project implementation programme showing
details of the construction activities, site location and duration of the
Project and the Yuen Long Bypass Floodway.
3.
Measures for Construction and Operation of the Project
3.1
To
mitigate the construction noise impact arising from the Project, all measures
recommended in the construction noise mitigation proposal deposited under Condition 2.3 shall
be fully implemented.
3.2
The
Permit Holder shall fully implement all the measures
recommended in accordance with the requirements and time schedule(s) set out in
the approved WMP. Before obtaining the
Director’s approval on the WMP as required under Condition 2.4, no disposal of
waste, spoil, soil, excavation materials or materials obtained from the Project site shall be allowed at
any locations.
3.3
To
mitigate the traffic noise impact arising from the Project, the Permit Holder
shall complete the construction of noise barriers in
accordance with the details as shown in Table 1 and Figures 2 - 9 attached to
this Permit prior to the operation of the Project. The
noise barriers shall be continuous structures with no gap or opening except
where access road is required. The Permit Holder shall properly maintain the noise
barriers during the operation of the Project.
3.4
All measures recommended in the landscape
proposal deposited under Condition 2.6 of this Permit shall be fully
implemented and maintained.
3.5
To carry out the construction work in
accordance with the programme deposited under Condition 2.7.
4.
Environmental Monitoring and Audit Requirements during
Construction of the Project
4.1
The EM&A programme shall be implemented as
set out in the EM&A Manual. Any changes to the programme shall be justified
by the ET leader and verified by the IEC as conforming to the information and
requirements contained in the EM&A Manual before submission to the Director
for approval.
4.2
The Permit Holder shall take samples and
measurements in accordance with the requirements of the EM&A Manual by:
(a)
conducting baseline environmental monitoring on
noise, water and air quality; and
(b)
conducting impact monitoring on noise, water
and air quality.
4.3
The remedial actions described in the
Event/Action Plans of the EM&A Manual shall be fully and properly carried
out in accordance with the time frames set out in the Event/Action Plans, or as
agreed by the Director.
4.4
Records of measurements and actions taken under
Conditions 4.2 and 4.3 respectively of this Permit shall be logged and kept,
within 3 working days of the collection of data or completion of action, for
the purpose of preparing and submitting the EM&A reports and making the
information available for inspection on site.
4.5
Two hard copies and one electronic copy of the
Baseline Monitoring Report shall be submitted to the Director at least 2 weeks
before commencement of construction of the Project. The submission shall be
verified by the IEC. Additional copies of the submission shall be made
available to the Director upon his request.
4.6
Two hard copies and one electronic copy of
monthly EM&A Report shall be submitted to the Director within 2 weeks after
the end of the reporting month. The EM&A Reports shall include a summary of
all noncompliance (exceedances) of the environmental quality performance limits
(Action and Limit Levels). The submissions shall be verified by the IEC.
Additional copies of the submission shall be provided to the Director upon
request by the Director.
4.7
All environmental monitoring and audit data
submitted under this Permit shall be true, valid and correct.
5.
Environmental Monitoring and Audit Requirements during Operation of the
Project
5.1
The Permit Holder shall, at least 6 months
before the operation of the Project, deposit with the Director a monitoring
plan for the purpose of verification of traffic noise assessment, by comparing
the project noise impact predictions with the actual impacts. The monitoring
plan shall contain monitoring locations, monitoring schedules, methodology of
noise monitoring including noise measurement procedures, traffic counts and
speed checks, and methodology of comparison with the predicted levels. Monitoring
shall be conducted in accordance with the deposited monitoring plan unless with
prior justification. Monitoring details and results, including the comparison
between the measured noise levels and the predicted levels, shall be recorded
in a report. The report shall be certified by the Permit Holder before it is
deposited with the Director, within one month after the completion of the
monitoring.
5.2
The Permit Holder shall deposit with the
Director 3 copies of an audit report, certified by the ET Leader and verified
by the IEC, demonstrating the satisfactory completion of the measures
recommended in the landscape proposal as described in Conditions 2.6 and 3.4 of
this Permit. The audit report shall be deposited within 3 weeks after
completion of the mitigation measures.
5.3
The Permit Holder shall deposit with the
Director 3 copies of audit report, certified by the ET leader and verified by
the IEC, demonstrating the satisfactory completion of the noise measures
described in Condition 3.3 of this Permit. The audit report shall be deposited
within 3 weeks after completion of the mitigation measures.
6.
Electronic Reporting of EM&A Information
6.1
To facilitate public inspection of the Baseline
Monitoring Report and monthly EM&A Reports via the EIAO Internet Website and
at the EIAO Register Office, electronic copies of these Reports shall be
prepared in Hyper Text Markup Language (HTML) (version 4.0 or later) and in
Portable Document Format (PDF version 4.0 or later), unless otherwise agreed by
the Director and shall be submitted at the same time as the hardcopies as
described in Conditions 4 and 5 of this Permit. For the HTML version, a content
page capable of providing hyperlink to each section and sub-section of these
Reports shall be included in the beginning of the document. Hyperlinks to all
figures, drawings and tables in these Reports shall be provided in the main
text from where the respective references are made. All graphics in these
Reports shall be in interlaced GIF format unless otherwise agreed by the Director.
The content of the electronic copies of these Reports must be the same as the
hardcopies.
6.2
The
Permit Holder shall, set up a dedicated web site and notify the Director in
writing the Internet address where the environmental monitoring and project
data is to be placed, within six weeks after the commencement of construction
of the Project. All environmental monitoring data described in Condition 6.1
above shall be made available to the public via a dedicated web site to be set
up by the Permit Holder in the shortest possible time and in no event later
than 2 weeks after the relevant environmental monitoring data are collected or
become available, unless otherwise agreed with the Director.
6.3
The Internet website as described in Condition 6.2
above shall enable user-friendly public access to the monitoring and project
data including the EIA report and the environmental permit(s) and the project
profile of the Project. The Internet website shall have features capable of:
(a)
providing access to all environmental monitoring
data collected since the commencement of works;
(b)
searching by date;
(c)
searching by types of monitoring data (noise, water
and air quality); and
(d)
hyperlinks to relevant monitoring data after
searching;
or otherwise as agreed by the Director.
Notes :
1. This
Permit consists of three parts, namely, PART A (Main Permit), PART B
(Description of Designated Project) and PART C (Permit Conditions). Any person
relying on this Permit should obtain independent legal advice on the legal
implications under the Ordinance, and the following notes are for general
information only.
2. The
Permit Holder may apply under Section 13 of the Ordinance to the Director for a
variation of the conditions of this Permit. The Permit Holder shall replace the
original permit displayed on the construction site by the amended permit.
3. A
person who assumes the responsibility for the whole or a part of the designated
project may, before he assumes responsibility of the designated project, apply
under Section 12 of the Ordinance to the Director for a further environmental
permit.
4. Under
Section 14 of the Ordinance, the Director may with the consent of the Secretary
for the Environment and Food, suspend, vary or cancel this Permit. The suspended, varied or cancelled Permit
shall be removed from display at the construction site.
5. If
this Permit is cancelled or surrendered during construction or operation of the
Project, another environmental permit must be obtained under the Ordinance
before the construction or operation of the Project could be continued. It is
an offence under Section 26(1) of the Ordinance to construct or operate a
designated project listed in Part I of Schedule 2 of the Ordinance without a
valid environmental permit.
6. Any
person who constructs or operates the Project contrary to the conditions in the
Permit, and is convicted of an offence under the Ordinance, is liable: -
(i)
on a first conviction on indictment
to a fine of $2 million and to imprisonment for 6 months;
(ii)
on a second or subsequent
conviction on indictment to a fine of $5 million and to imprisonment for 2
years;
(iii)
on a first summary conviction to a
fine at level 6 and to imprisonment for 6 months;
(iv)
on a second or subsequent summary
conviction to a fine of $1 million and to imprisonment for 1 year; and
(v)
in any case where the offence is of
a continuing nature, the court or magistrate may impose a fine of $10,000 for
each day on which he is satisfied the offence continued.
7. The
Permit Holder may appeal against any condition of this Permit under Section 17
of the Ordinance within 30 days of receipt of this Permit.
Environmental Permit No. EP-141/2002
Table 1 – Schedule of Noise Barriers to be provided before the operation
of the Project
(extracted from
Appendix A of the EM&A Manual, and to be read in conjunction with Figures 2
– 9 attached to this Permit)
Height of
barrier (m) |
Location |
Description |
From Chainage |
To Chainage |
Length of
barrier (m) |
2m vertical barriers |
Yuen
Long Highway |
West bound |
7000 |
7270 |
270 |
Yuen
Long Highway |
West bound |
7341 |
7974 |
633 |
|
Slip
road joining Route 10 and YLH (East bound) to the north-west of main chainage
2482 |
- |
- |
- |
143 |
|
3m vertical barriers |
Yuen
Long Highway |
West bound |
6768 |
7000 |
232 |
Yuen
Long Highway |
West bound |
7270 |
7341 |
71 |
|
Slip
road joining Castle Peak Road and YLH (East bound) chainage 1440 at Lam Tei
Interchange |
- |
- |
- |
159 |
|
Slip road slip off YLH (East bound) from chainage 4336 at Tin Shui
Wai West Interchange merging Hung Tin Road |
- |
- |
- |
144 |
|
Slip road joining Route 10 and YLH (East bound) to the north-west of
main chainage 2582 |
- |
- |
- |
94 |
|
Slip road joining Route 10 and YLH (East bound) to the north-west
of main chainage 2735 |
- |
- |
- |
380 |
|
Slip road joining Route 10 and YLH (West bound) to the south of
main chainage 1800 |
- |
- |
- |
192 |
|
Yuen Long Highway |
West bound |
2800 |
2850 |
50 |
|
4m vertical barriers |
Yuen Long Highway |
West bound |
5900 |
6298 |
398 |
Yuen Long Highway |
East bound |
4700 |
4843 |
143 |
|
Hung Tin Road (West bound) to the
north-west of main chainage 4475 |
- |
- |
- |
63 |
|
Slip road slip off YLH (East bound) from
chainage 5746 at Tong Yan San Tsuen Interchange merging Long Tin Road |
- |
- |
- |
142 |
|
Slip road slip off YLH (West bound) from
chainage 5900 at Tong Yan San Tsuen Interchange merging Long Tin Road |
- |
- |
- |
124 |
|
Yuen Long Highway |
West bound |
950 |
1160 |
210 |
|
Slip road slip off YLH (West bound) at Tin
Shui Wai West Interchange merging Hung Tin Road to the south-east of main
chainage 4717 |
- |
- |
- |
59 |
|
Slip road slip off YLH (West bound) from
chainage 1339 at Lam Tei Interchange merging Castle Peak Road |
- |
- |
- |
106 |
|
Yuen Long Highway |
East bound |
7448 |
7940 |
480 |
|
Yuen Long Highway |
West bound |
2750 |
2800 |
50 |
|
5.5m vertical barrier plus 1.5m cantilever at 45∘ |
Yuen Long Highway |
West bound |
4857 |
5014 |
157 |
Slip road joining Long Tin Road and YLH
(East bound) chainage 5905 at Tong Yan San Tsuen Interchange |
- |
- |
- |
182 |
|
Slip road joining Long Tin Road and YLH
(West bound) at Tong Yan San Tsuen Interchange |
- |
- |
- |
115 |
|
Yuen Long Highway |
East bound |
4152 |
4336 |
184 |
|
Yuen Long Highway |
East bound |
4400 |
4562 |
172 |
|
Yuen Long Highway |
East bound |
6134 |
6247 |
113 |
|
5.5m vertical barrier plus 2.5m cantilever at 45∘ |
Yuen Long Highway |
West bound |
5014 |
5160 |
146 |
Slip road joining Route 10 and YLH (East
bound) chainage 3550 |
- |
- |
- |
445 |
|
Slip road joining Castle Peak Road and YLH
(East bound) at Lam Tei Interchange to the north of main chainage 1285 |
- |
- |
- |
93 |
|
Yuen Long Highway |
East bound |
5746 |
5881 |
135 |
|
Yuen Long Highway |
East bound |
1714 |
1955 |
241 |
|
Yuen Long Highway |
West bound |
1378 |
1800 |
422 |
|
Yuen Long Highway |
West bound |
3083 |
3318 |
235 |
|
Hung Tin Road (West bound) to the
north-west of main chainage 4470 |
- |
- |
- |
59 |
|
Yuen Long Highway |
West bound |
4160 |
4343 |
183 |
|
Yuen Long Highway |
East bound |
5905 |
6134 |
229 |
|
5m vertical barriers |
Yuen Long Highway |
East bound |
6774 |
7448 |
684 |
Slip road slip off YLH (West bound) from
chainage 4857 at Tin Shui Wai West Interchange merging Hung Tin Road |
- |
- |
- |
169 |
|
Yuen Long Highway |
Central divider |
1345 |
1800 |
455 |
|
Slip road joining Route 10 and YLH (East
bound) to the north-west of main chainage 2656 |
- |
- |
- |
82 |
|
Yuen Long Highway |
East bound |
5279 |
5742 |
468 |
|
Yuen Long Highway |
West bound |
4343 |
4440 |
97 |
|
Yuen Long Highway |
Central divider |
1200 |
1290 |
90 |
|
Yuen Long Highway |
East bound |
1440 |
1714 |
274 |
|
Slip road slip off YLH (West bound) from
chainage 3083 merging Route 10 |
- |
- |
- |
961 |
|
Yuen Long Highway |
West bound |
1224 |
1308 |
84 |
|
Yuen Long Highway |
East bound |
3550 |
4152 |
602 |
|
Slip road slip off YLH (East bound) at Tin
Shui Wai West Interchange merging Hung Tin Road to the north-west of main
chainage 4453 |
- |
- |
- |
50 |
|
Yuen Long Highway |
East bound |
4843 |
5023 |
180 |
|
Yuen Long Highway |
East bound |
6300 |
6506 |
206 |
|
Yuen Long Highway |
West bound |
2700 |
2750 |
50 |
|
6m vertical barriers |
Slip road slip off YLH (East bound) from
chainage 1955 merging Route 10 |
- |
- |
- |
78 |
Yuen Long Highway |
West bound |
3318 |
3446 |
128 |
|
Yuen Long Highway |
East bound |
6247 |
6300 |
53 |
|
Hung Tin Road |
Central divider |
- |
- |
76 |
|
Yuen Long Highway |
East bound |
5023 |
5279 |
256 |
|
Yuen Long Highway |
East bound |
6506 |
6774 |
268 |
|
Slip road off YLH (West bound) merging
Castle Peak Road to the south of main chainage 1378 |
- |
- |
- |
41 |
|
Yuen Long Highway |
West bound |
2167 |
2700 |
533 |
|
Slip road joining Long Tin Road and YLH
(West bound) chainage 5160 at Tong Yan San Tsuen Interchange |
- |
- |
- |
458 |
圖 1 |
圖 2 |
圖 3 |
圖 4 |
圖 5 |
圖 6 |
圖 7 |
圖 8 |
圖 9