Environmental Permit No. EP-330/2009
環境許可證編號No. EP-330/2009
ENVIRONMENTAL IMPACT ASSESSMENT ORDINANCE
(CHAPTER 499)
SECTION 10
環境影響評估條例
(第499章)
第10條
ENVIRONMENTAL PERMIT TO CONSTRUCT AND OPERATE
A DESIGNATED PROJECT
建造及營辦指定工程項目的環境許可證
A部 (許可證主要部分)
Pursuant to Section 10 of the Environmental Impact
Assessment Ordinance (EIAO), the Director of Environmental Protection (the
Director) grants this environmental permit to the Drainage Services
Department (hereinafter referred to as the
“Permit Holder”) to construct and operate the designated project
described in Part B subject to the conditions specified in Part C.
The issue of this environmental permit is based on the documents, approvals or
permissions described below:
根據《環境影響評估條例》(環評條例) 第10條的規定,環境保護署署長(署長)將本環境許可證批予渠務署 (下稱“許可證持有人”) 以建造及營辦B部所說明的指定工程項目,但須遵守C部所列明的條件。本環境許可證是依據下列文件、批准或許可而簽發﹕
Application No. 申請書編號 |
AEP-330/2009
|
|
Documents in
the Register: 登記冊上的文件: |
(1) (2) (3) |
Project Profile – “Western
Interceptor Sewer Sewage Pumping Station” (Register No.: PP-375/2008) 工程項目簡介 – “西部主幹污水泵房” (登記冊編號: PP-375/2008) The Director’s letter
of permission to apply directly for environmental permit dated 署長於 Application for
environmental permit submitted by the Permit Holder on 許可證持有人於 |
23February 2009
2009年2月23日
Date 日期 |
|
(WONG Hon-meng) Principal Environmental Protection Officer for Director of Environmental Protection 環境保護署署長 (首席環境保護主任黃漢明代行) |
PART B (DESCRIPTION OF DESIGNATED PROJECT)
B部 (指定工程項目的說明)
Hereunder is the description of the designated
project mentioned in Part A of this environmental permit (hereinafter referred to as the “Permit”):
下列為本環境許可證 (下稱“許可證”) A部所提述的指定工程項目的說明﹕
Title
of Designated Project 指定工程項目的名稱 |
Western Interceptor Sewer Sewage Pumping Station
[This designated project is hereinafter referred
to as “the Project”] 西部主幹污水泵房 [本指定工程項目下稱 “工程項目”] |
Nature of Designated Project |
A sewage pumping station with
an installed capacity of more than 污水泵水站,其裝置的泵水能力超過每天 |
Location
of Designated Project 指定工程項目的地點 |
At the junction of 屯門龍門路及皇珠路交界處。工程項目的位置載於本許可證夾附的圖1。 |
Scale and Scope of Designated Project 指定工程項目的規模和範圍 |
Construction
and operation of a sewage pumping station with a designed capacity (average
dry weather flow) of about 建造及營辦一個設計容量(平均旱季流量)約為每天 |
C部(許可證條件)
1. General
Conditions
一般條件
1.1 The Permit Holder and any
person working on the Project shall comply with all conditions set out in this
Permit. Any non-compliance by any person may constitute a contravention of the
Environmental Impact Assessment Ordinance (EIAO) (Cap. 499) and may become the
subject of appropriate action being taken under the EIAO.
許可證持有人及任何從事工程項目的人士必須符合本許可證載列的全部條件。任何人士如有不符合本許可證的情況,可能違反環境影響評估條例(環評條例)(第499章)的規定,而當局可根據條例採取適當行動。
1.2 The Permit Holder shall ensure
full compliance with all legislation from time to time in force including,
without limitation to, the Noise Control Ordinance (Cap. 400), Air Pollution
Control Ordinance (Cap. 311), Water Pollution Control Ordinance (Cap. 358) and Waste
Disposal Ordinance (Cap. 354). This Permit does not of itself constitute any
ground of defence against any proceedings instituted under any legislation or
imply any approval under any legislation.
許可證持有人須經常確保完全符合現行法例的規定,包括但不限於噪音管制條例(第400章),空氣污染管制條例(第311章),水污染管制條例(第358章)及廢物處置條例(第354章)。本許可證本身不會就根據任何法例提出的訴訟構成任何抗辯理由,或根據任何法例默示任何批准。
1.3 The Permit Holder shall make
copies of this Permit together with all documents referred to in this Permit and
the documents referred to in Part A of the Permit readily available at
all times for inspection by the Director or his authorised officers at all
sites/offices covered by this Permit. Any reference to the Permit shall include
all documents referred to in the Permit and also the relevant documents in the
Register.
許可證持有人須印製本許可證的複本,連同本許可證所述的所有文件及本許可證A部所述文件,以供署長或獲授權人員任何時間內在本許可證所涵蓋的所有工地/辦事處查閱。凡提述本許可證,須包括本許可證所述的所有文件及登記冊內的相關文件。
1.4 The Permit Holder shall give a
copy of this Permit to the person(s) in charge of the site(s) and ensure that
such person(s) fully understands all conditions and all requirements
incorporated by the Permit. The site(s) refers to site(s) of construction and operation
of the Project and shall mean the same hereafter.
許可證持有人須把本許可證的複本交予有關工地的負責人,並確保這些人士完全明白本許可證的所有條件與規定。工地是指建造及營辦工程項目的工地,下文所提及的工地亦屬同一意思。
1.5 The Permit Holder shall display
conspicuously a copy of this Permit on the Project site(s) at all vehicular
site entrances/exits or at a convenient location for public information at all
times. The Permit Holder shall ensure that the most updated information about
the Permit, including any amended Permit, is displayed at such locations.
If the Permit Holder surrenders a part or the whole of the Permit, the notice
he sends to the Director shall also be displayed at the same locations as the
original Permit. The suspended, varied or cancelled Permit shall be
removed from display at the Project site(s).
許可證持有人須在工程項目的工地的所有車輛進出口或一處方便地點,顯眼地展示本許可證的複本,以供公眾在任何時間內閱覽。許可證持有人須確保在這些地點展示關於本許可證(包括任何經修訂的許可證)的最新資料。許可證持有人如交回許可證的部分或全部,必須把其送交署長的通知書,在備有原有許可證的相同地點展示。遭暫時吊銷、更改或取消的許可證必須從工程項目的工地除下,不再展示。
1.6 The Permit Holder shall
construct and operate the Project in accordance with the project description in
Part B of this Permit.
許可證持有人須依據本許可證B部的工程項目說明,建造及營辦工程項目。
1.7 The
Permit Holder shall ensure that the Project is designed, constructed and
operated in accordance with the information and recommendations described in
the Project Profile (Register No. PP-375/2008), the Application for
Environmental Permit (Application No. AEP-330/2009), and the information and
mitigation measures described in this Permit. Where recommendations referred to in the
documents of the Register are not expressly referred to in this Permit, such
recommendations are nevertheless to be implemented unless expressly excluded or
impliedly amended in this Permit.
許可證持有人須確保工程項目的設計、建造及營辦是按照工程項目簡介(登記冊編號:PP-375/2008)所說明的資料及建議;環境許可證申請文件(申請書編號:AEP-330/2009);以及本許可證所說明的資料及緩解措施辦理。登記冊文件所述建議如沒有在本許可證明確表示,則仍須實施這些建議,除非獲本許可證明確豁除或默示修訂。
1.8 All submissions, as required
under this Permit, shall be rectified and resubmitted in accordance with the
comments, if any, made by the Director within one month of the receipt of the
Director’s comments or otherwise as specified by the Director.
所有按本許可證規定提交的文件,須在接獲署長的意見(如有者)後1個月內(除非署長另行指定),根據署長的意見加以修正並再向署長提交。
1.9 All submissions approved by the
Director, all submissions deposited without comments by the Director, or all
submissions rectified in accordance with comments by the Director under this
Permit shall be construed as part of the permit conditions described in Part
C of this Permit. Any variation of the submissions shall be approved by the
Director in writing or as prescribed in the relevant permit conditions. Any
non-compliance with the submissions may constitute a contravention of the Environmental
Impact Assessment Ordinance (Cap. 499).
署長批准的所有提交文件、署長沒有給予意見的所有存放文件、或根據本許可證規定由署長給予意見修正的所有提交文件,均須詮釋為本許可證
1.10 The Permit Holder shall release all
finalized submissions, as required under this Permit, to the public by
depositing copies in the EIAO Register Office, or in any other places, or any
internet websites as specified by the Director, or by any other means as
specified by the Director for public inspection. For this purpose, the Permit
Holder shall provide sufficient copies of the submissions.
許可證持有人須把所有按本許可證規定提交的文件定稿公開給公眾知道,方法是把有關文件複本存放於環評條例登記冊辦事處、署長指定的任何其他地方、署長指定的任何互聯網網站或採取署長指定的任何方法,以供公眾查閱。因此,許可證持有人須提供足夠數量的複本。
1.11 All submissions to the Director required
under this Permit shall be delivered either in person or by registered mail to
the EIAO Register Office (currently at 27/F, Southorn Centre,
本許可證規定向署長提交的所有文件,須親身送交或以掛號方式郵寄至環評條例登記冊辦事處(現址為:香港灣仔軒尼詩道130號修頓中心27樓)。所有按本許可證規定提交的文件定稿的電子版本,均須以超文本標示語言(HTML)(第4.0或較後版本)及便攜式文件格式(PDF)(第1.3或較後版本)製作,除非另獲署長同意,並須與硬複本同時提交。
1.12 The Permit Holder shall notify the Director
in writing the commencement date of construction of
the Project no later than two weeks before the commencement of
construction of the Project. The Permit Holder shall notify the Director in
writing immediately if there is any change of the commencement date of the
construction.
許可證持有人須在工程項目的建造工程展開前至少兩個星期,以書面方式把工程項目建造工程的施工日期通知署長。施工日期如有任何更改,許可證持有人必須立即以書面方式通知署長。
1.13 For the purpose of this Permit, “commencement of
construction” does not include works related to site clearance and preparation,
or other works as agreed by the Director.
為執行本許可證,「建造工程的展開」不包括有關工地清理和預備的工程,或署長同意的其他工程。
2.
Specific Conditions
特定條件
2.1 To
minimise odour impact during operation of the Project, the coarse screen house
and wet well shall be located underground and enclosed by a reinforced concrete
structure.
為盡量減低工程項目營辦期間的氣味影響,粗孔隔篩房及濕井須設於地底,並以鋼筋混凝土結構覆蓋。
2.2 To
minimise odour impact during operation of the Project, a deodorizer with a
forced ventilation system and a H2S removal efficiency of at least
99.5% shall be installed and properly maintained.
為盡量減低工程項目營辦期間的氣味影響,須安裝附有壓力通風系統及具備消除至少99.5%硫化氫效能的除臭器,並予以妥善保養維修。
2.3 To
minimise noise impact during operation of the Project, the pump sets and
screening facilities of the pumping station shall be located underground and
enclosed by a reinforced concrete structure with acoustic louvers. Silencers shall be provided for the
exhaust fans.
為盡量減低工程項目營辦期間的噪音影響,泵房的水泵組及隔篩設施均須設於地底,並以附有隔音百葉簾的鋼筋混凝土結構覆蓋。抽氣扇亦須裝設滅聲器。
2.4 To
minimise the chance of emergency sewage bypass during operation of the Project,
one standby pump and dual power supply shall be provided. A telemetry system shall be provided to
transmit signals showing irregularity or operational problem of the pumping
station to the Pillar Point Sewage Treatment Works.
為盡量減低工程項目營辦期間緊急排放污水的機會,泵房須設有一個備用水泵及雙重電力供應,並須裝設遙測警報系統,以便泵房一旦有異常情況或操作出現問題時可把信號傳送至望后石污水處理廠。
2.5 To
minimise landscape and visual impacts, green roof design, wall planter at the
top of the pumping station and screen planting shall be provided and properly
maintained during operation of the Project as shown in Figure 2 attached to
this Permit.
為盡量減低工程項目對景觀及視覺造成的影響,須如本許可證夾附的圖2所示,在工程項目營辦期間採用綠化屋頂設計、在屋頂栽設外牆花槽及設置屏蔽種植,並予以妥善保養。
2.6 To
minimise landscape and visual impacts, the entrance gate of the pumping station
shall be at least
為盡量減低工程項目對景觀及視覺造成的影響,須如本許可證夾附的圖2所示,泵房入口大閘須最少為
Notes:
註:
1. This Permit consists
of three parts, namely, Part A (Main Permit), Part B (Description
of Designated Project) and Part C (Permit Conditions). Any person relying on this permit should
obtain independent legal advice on the legal implications under the EIAO, and
the following notes are for general information only.
本許可證共有3部,即A部(許可證主要部分);B部(指定工程項目的說明)及C部(許可證條件)。任何援引本許可證的人士須就環評條例的法律含意徵詢獨立法律意見,下述註解只供一般參考用。
2. If there is a breach
of any condition of this Permit, the Director or his authorized officer may,
with the consent of the Secretary for the Environment, order the cessation of
associated work until the remedial action is taken in respect of the resultant
environmental damage, and in that case the Permit Holder shall not carry out
any associated works without the permission of the Director or his authorized
officer.
如違反本許可證的任何條件,署長或獲授權人員徵得環境局局長的同意後可勒令停止相關工程,直至許可證持有人為所造成的環境損害採取補救行動為止。在此情況下,許可證持有人未經署長或獲授權人員同意,不得進行任何相關工程。
3. The Permit Holder
may apply under Section 13 of the EIAO to the Director for a variation of the
conditions of this Permit. The Permit Holder shall replace the original permit
displayed on the Project site by the amended permit.
許可證持有人可根據環評條例第13條的規定向署長申請更改本環境許可證的條件。許可證持有人須把經修改的許可證替換在工地內展示的原有許可證。
4. A person who assumes
the responsibility for the whole or a part of the Project may, before he
assumes responsibility of the Project, apply under Section 12 of the EIAO to
the Director for a further environmental permit.
承擔工程項目整項或部分工程的責任的人,在承擔責任之前,可根據環評條例第12條的規定向署長申請新的環境許可證。
5. Under Section 14 of
the EIAO, the Director may with the consent of the Secretary for the
Environment, suspend, vary or cancel this Permit. The suspended, varied or cancelled Permit
shall be removed from display at the Project site.
根據環評條例第14條的規定,署長可在環境局局長的同意下暫時吊銷、更改或取消環境許可證。遭暫時吊銷、更改或取消的環境許可證必須從建造工地除下,不再展示。
6. If this Permit is
cancelled or surrendered during construction or operation of the Project,
another environmental permit must be obtained under the EIAO before the Project
could be continued. It is an
offence under Section 26(1) of the EIAO to construct or operate a designated
project listed in Part I of Schedule 2 of the EIAO without a valid
environmental permit.
如果本許可證在工程項目建造或營辦期間取消或交回,則在繼續進行工程項目之前,必須先根據環評條例規定取得另一份環境許可證。根據環評條例第26(1)條的規定,任何人在沒有有效環境許可證的情況下建造或營辦條例附表2所列明的指定工程項目,即屬犯罪。
7. Any
person who constructs or operates the Project contrary to the conditions in the
Permit, and is convicted of an offence under the EIAO, is liable:
如任何人在違反本許可證的條件下建造或營辦工程項目,根據環評條例,即屬犯罪:
(i) on a
first conviction on indictment to a fine of $2 million and to imprisonment for 6 months
一經循公訴程序首次定罪,可處罰款200萬元及監禁6個月;
(ii)
on a second or subsequent
conviction on indictment to a fine of $5 million and to imprisonment for 2
years;
一經循公訴程序第二次或其後每次定罪,可處罰款500萬元及監禁2年;
(iii)
on a first summary conviction to a
fine at level 6 and to imprisonment for 6 months;
一經循簡易程序首次定罪,可處第6級罰款及監禁6個月;
(iv)
on a second or subsequent summary
conviction to a fine of $1 million and to imprisonment for 1 year; and
一經循簡易程序第二次或其後每次定罪,可處罰款100萬元及監禁1年;及
(v)
in any case where the offence is of
a continuing nature, the court or magistrate may impose a fine of $10,000 for
each day on which he is satisfied the offence continued.
在任何情況下如該罪行屬連續性質,法院或裁判官可就其信納該罪行連續的每一天另處罰款10,000元。
8. The Permit Holder
may appeal against any condition of this Permit under Section 17 of the EIAO
within 30 days of receipt of this Permit.
許可證持有人可在接獲本許可證後30天內,根據環評條例第17條就本許可證的任何條件提出上訴。
9. The Notes are for
general reference only and that the Permit Holder should refer to the EIAO for
details and seek independent legal advice.
上述註解只供一般參考用,欲知有關詳情,許可證持有人須參閱環評條例及徵詢獨立法律意見。
Environmental Permit No. EP-330/2009
環境許可證編號EP-330/2009