Environmental
Permit No. EP-602/2021
環境許可證編號 EP-602/2021
ENVIRONMENTAL
IMPACT ASSESSMENT ORDINANCE
(CHAPTER
499)
Section
10
環境影響評估條例
(第499章)
第10條
ENVIRONMENTAL
PERMIT TO CONSTRUCT AND OPERATE
A DESIGNATED
PROJECT
建造及營辦指定工程項目的環境許可證
A部 (許可證主要部分)
Pursuant to Section 10 of the Environmental
Impact Assessment Ordinance (EIAO), the Director of Environmental Protection (the
Director) grants this environmental permit to the Water Supplies Department (hereinafter
referred to as the "Permit Holder") to construct and operate the
designated project described in Part B subject to the
conditions specified in Part C. The issue of this environmental permit
is based on the documents, approvals or permissions described below :-
根據《環境影響評估條例》(環評條例)第10條的規定,環境保護署署長(署長)將本環境許可證批予水務署(下稱“許可證持有人”)以建造及營辦B部所說明的指定工程項目,但須遵守C部所列明的條件。本環境許可證的發出,乃以下表所列的文件、批准或許可作為根據:
Application No. 申請書編號 |
AEP-602/2021 |
Document
in the Register |
(1) Relocation of Diamond Hill Fresh Water and Salt Water Service Reservoirs to Caverns (Register No.: AEIAR-232/2021) – Environmental Impact Assessment Report [Hereinafter referred to as the “EIA Report”] – 的Environmental Monitoring and Audit (EM&A) Manual [Hereinafter referred to as the “EM&A Manual”] – Executive Summary 搬遷鑽石山食水及海水配水庫往岩洞(登記冊編號: AEIAR-232/2021) –
環境影響評估報告[下稱“環評報告”] –
環境監察及審核手冊[下稱“環監手冊”] –
行政摘要 (2) The Director’s letter of approval of the EIA Report dated 16 November 2021 (Reference: (40) in EP2/K11/Q/236 Pt.3) 署長於2021年11月16日發出批准環評報告的信件(檔案編號:(40) in
EP2/K11/Q/236 Pt.3) (3) Application for an environmental permit submitted by the Permit Holder on 22 November 2021 (Application No.: AEP - 602/2021) 許可證持有人於2021年11月22日提交的環境許可證申請文件(申請書編號:AEP-602/2021) |
14 December 2021
2021年12月14日
Date 日期 |
|
(Sunny C. W. CHEUNG) Principal Environmental Protection Officer for Director of Environmental Protection 環境保護署署長 (首席環境保護主任張展華代行) |
PART B
(DESCRIPTIONS OF DESIGNATED PROJECT(S) )
B部 (指定工程項目的說明)
Hereunder is the description of the designated
project mentioned in Part A of this environmental permit (hereinafter referred to as the “Permit”)
:-
下列為本環境許可證(下稱“許可證”) A部所提述的指定工程項目的說明:
Title
of Designated Project 指定工程項目的名稱 |
Relocation of Diamond Hill Fresh Water and Salt Water Service
Reservoirs to Caverns [This designated project is hereinafter referred to as “the Project”] 搬遷鑽石山食水及海水配水庫往岩洞 [本指定工程項目下稱“工程項目”] |
Nature
of Designated Project 指定工程項目的性質 |
Underground rock caverns. 地下石洞。 |
Location
of Designated Project 指定工程項目的地點
|
Hillside northwest
of Ma Chai Hang Fresh Water Service Reservoir. The location of the Project is
shown in Figure 1 attached to this
Permit. 馬仔坑食水配水庫西北面的山坡。工程項目的地點載於本許可證夾附的圖1。 |
Scale
and Scope of Designated Project 指定工程項目的規模和範圍 |
The Project mainly includes : 工程項目主要包括: (i)
Construction of the relocated
Diamond Hill Fresh Water and Salt Water Service Reservoirs (DHSRs) and
associated pumping stations and water main laying works; 建造重置的鑽石山食水及海水配水庫和相關抽水站,並進行水管敷設工程; (ii) Construction of tunnels, adits, ventilation system and caverns for
accommodating the relocated DHSRs and the associated facilities; and 建造隧道、通道、通風系統及用以安置重置的鑽石山食水及海水配水庫和相關設施的岩洞;以及 (iii) Other associated works that are incidental to and necessary for the
completion of the Project. 為完成工程項目所附帶及需要的其他相關工程。 |
C部(許可證條件)
1.
General Conditions
一般條件
1.1
The Permit Holder and any person
constructing or operating on the Project shall comply with all conditions set
out in this Permit. Any
non-compliance by any person may constitute a contravention of the Environmental
Impact Assessment Ordinance (EIAO) (Cap. 499) and
may become the subject of appropriate action being taken under the EIAO.
許可證持有人及任何建造或營辦工程項目的人士必須完全符合本許可證載列的全部條件。任何人士如有不符合本許可證的情況,可能違反《環境影響評估條例》(環評條例) (第499章) 的規定,而當局可根據環評條例採取適當行動。
1.2
The Permit Holder and any person
constructing or operating the Project shall ensure full
compliance with all legislation from time to time in force including, without
limitation to, the Noise
Control Ordinance (Cap. 400), Air Pollution Control Ordinance (Cap. 311), Water Pollution Control Ordinance (Cap.
358) and Waste Disposal Ordinance (Cap. 354). This Permit does not of itself
constitute any ground of defence against any proceedings instituted under any
legislation or imply any approval under any legislation.
許可證持有人及任何建造或營辦工程項目的人士須確保完全符合現行法例的規定,包括但不限於《噪音管制條例》(第400章) 、《空氣污染管制條例》(第311章)、《水污染管制條例》(第358章)及《廢物處置條例》(第354章)。本許可證本身不會就根據任何法例提出的法律程序構成任何抗辯理由,或根據任何法例默示任何批准。
1.3
The Permit Holder shall make copies
of this Permit together with all documents referred to in this Permit and the
documents referred to in Part A of this Permit
readily available at all times for inspection by the Director or his authorised
officers at all sites covered by this Permit. Any reference to this Permit shall
include all documents referred to in this Permit and also the relevant
documents in the Register.
許可證持有人須印製本許可證的複本,連同本許可證所述的所有文件及本許可證A部 所述文件,以供署長或獲授權人員任何時間內在本許可證所涵蓋的所有工地查閱。凡提述本許可證,須包括本許可證所述的所有文件及登記冊內的相關文件。
1.4
The Permit Holder shall give a
copy of this Permit to the person(s) in charge of the site(s) and ensure that
such person(s) fully understands all conditions and all requirements
incorporated in this Permit. The
site(s) refers to site(s) of construction and operation of the Project and
shall mean the same hereafter.
許可證持有人須把本許可證的一份複本交予有關工地的負責人,並確保這些人士完全明白本許可證的所有條件與規定。工地是指建造及營辦工程項目的工地,下文所提及的工地亦屬同一意思。
1.5
The Permit Holder shall display
conspicuously a copy of this Permit on the construction site(s) at all
vehicular site entrances/exits or at a convenient location for public’s
information at all times. The
Permit Holder shall ensure that the most updated information about this Permit,
including any amended Permit, is displayed at such locations. If the Permit Holder surrenders a part
or the whole of this Permit, the notice he sends to the Director shall also be
displayed at the same locations as the original Permit. The suspended, varied or cancelled
Permit shall be removed from display at the construction site(s).
許可證持有人須在建造工地的所有車輛進出口或一處方便地點,顯眼地展示本許可證的複本,以供公眾在任何時間內閱覽。許可證持有人須確保在這些地點展示關於本許可證(包括任何經修訂的許可證)的最新資料。許可證持有人如交回本許可證的部分或全部,必須把其送交署長的通知書,在備有原有許可證的各處相同地點展示。遭暫時吊銷、更改或取消的許可證必須從建造工地除下,不再展示。
1.6
The Permit Holder and any person constructing or operating
the Project shall construct and operate the Project in
accordance with the project description in Part B
of this Permit.
許可證持有人及任何建造或營辦工程項目的人士須依據本許可證B部的工程項目說明,建造及營辦工程項目。
1.7
The Permit Holder and any person constructing or operating
the Project shall ensure that the Project is designed, constructed
and operated in accordance with the information and recommendations described
in the approved EIA Report (Register No.: AEIAR-232/2021); the application
documents for environmental permits; other relevant documents in the
Register; the information and mitigation measures described in this Permit;
mitigation measures to be recommended in submissions that shall be deposited
with or approved by the Director as a result of permit conditions contained in
this Permit; and mitigation measures to be recommended under on-going
surveillance and monitoring activities during all stages of the Project. Where recommendations referred to in the
documents of the Register are not expressly referred to in this Permit, such
recommendations are nevertheless to be implemented unless expressly excluded in
this Permit or otherwise agreed by the Director.
許可證持有人及任何建造或營辦工程項目的人士須確保工程項目按照下述資料設計、建造及營辦:核准環評報告(登記冊編號:AEIAR-232/2021)所說明的資料及相關建議;環境許可證的申請文件;登記冊內的其他相關文件;本許可證所說明的資料及緩解措施;根據本許可證所載的條件須提交予署長存放或獲署長批准的文件所建議的緩解措施;以及在工程項目各階段進行的持續監察及監測工作所建議的緩解措施。登記冊文件所述建議如沒有在本許可證明確表示,則仍須實施這些建議,除非獲本許可證明確豁除或另獲署長同意。
1.8
All submissions, as required
under this Permit, shall be rectified and resubmitted in accordance with the
comments, if any, made by the Director within 1 month of the receipt of the
Director’s comments or otherwise as specified by the Director.
所有按本許可證規定提交的文件,須在接獲署長的意見(如有者)後1個月內或署長另行指定的期限內,根據署長的意見加以修正及重新提交。
1.9
All submissions approved by the
Director, all submissions deposited without comments by the Director, or all
submissions rectified in accordance with comments by the Director under this
Permit shall be construed as part of the permit conditions described in Part C of this Permit.
Any variation of the submissions shall be approved by the Director in writing
or as prescribed in the relevant permit conditions. Any non-compliance with the submissions
may constitute a contravention of the EIAO (Cap. 499). All submissions or any variation of the submissions
shall be certified by the Environmental Team (ET) Leader and verified by the
Independent Environmental Checker (IEC) referred to in Conditions 2.3 and 2.7
below before submitting to the Director under this Permit.
所有提交署長並獲批准的文件、所有提交署長存放而沒有收到署長意見的文件或根據本許可證提交並已依照署長的意見作出修訂的所有文件,將詮釋為本許可證C部 所說明的許可證條件的一部分。對提交文件所作的任何修訂,均須獲得署長的書面批准,或符合有關許可證條件所述。凡與所提交的文件有不符合的情況,均可能構成違反環評條例 (第499章)。所有提交文件或提交文件的任何修訂本,均須按下文條件第2.3及2.7項所述的環境小組組長核證及獨立環境查核人核實,然後才按本許可證規定向署長提交。
1.10
The Permit Holder shall release
all finalised submissions as required under this Permit to the public by
depositing copies in the Environmental
Impact Assessment Ordinance Register Office, or in
any other places, or any internet websites as specified by the Director, or by
any means as specified by the Director, for public inspection. For this purpose, the Permit Holder
shall provide sufficient copies of the submissions.
許可證持有人須把所有按本許可證規定提交的文件定稿公開給公眾人士知道,方法是把有關文件複本存放於環境影響評估條例登記冊辦事處,或署長指定的任何其他地方,或署長指定的任何互聯網網站,或署長指定的任何方法,以供公眾查閱。為此,許可證持有人須提供足夠數量的複本。
1.11
The Permit Holder shall submit
and / or deposit all submissions within the time as specified in the Conditions
of this Permit. All submissions to
the Director required under this Permit shall be delivered either in person or
by registered mail to the Environmental Impact Assessment Ordinance Register
Office (currently at 27/F, Southorn Centre, 130 Hennessy Road, Wanchai, Hong
Kong). Electronic copies of all
finalised submissions required under this Permit shall be prepared in Hyper Text
Markup Language (HTML) (version 4.0 or later) and in Portable Document Format
(PDF version 1.3 or later), unless otherwise agreed by the Director and shall
be submitted at the same time as the hard copies.
許可證持有人須在本許可證條件所列明的時間內,提交及/或存放所有文件。本許可證規定向署長提交的所有文件,須親身送交或以掛號方式郵寄至環境影響評估條例登記冊辦事處(現址為:香港灣仔軒尼詩道130號修頓中心27樓)。所有按本許可證規定提交的文件定稿的電子複本,均須以超文本標示語言(HTML)(第4.0或較後版本)和便攜式文件格式(PDF)(第1.3或較後版本)製作,除非另獲署長同意,電子複本須與硬複本同時提交。
1.12
The Permit Holder shall notify
the Director in writing the commencement date of construction of the Project no
later than 1 month prior to the commencement of construction of the
Project. The Permit Holder shall
notify the Director in writing immediately if there is any change of the
commencement date of the construction.
許可證持有人須在工程項目建造工程展開前最少1個月,以書面方式把工程項目建造工程的展開日期通知署長。建造工程的展開日期如有任何更改,許可證持有人必須立即以書面方式通知署長。
1.13
For the purpose of this Permit,
“commencement of construction” does not include works related to site clearance
and preparation, or other works as agreed by the Director.
為執行本許可證,「建造工程的展開」不包括有關工地清理和預備的工程,或署長同意的其他工程。
1.14
The Permit Holder shall
notify the Director in writing the commencement date of operation of the
Project no later than 1 month prior to the commencement of operation of the
Project. The Permit Holder shall
notify the Director in writing immediately if there is any change of the
commencement date of operation.
許可證持有人須在工程項目開始營辦前最少1個月,以書面方式把工程項目開始營辦的日期通知署長。開始營辦的日期如有任何更改,許可證持有人須立即以書面方式通知署長。
2.
Specific Conditions
特定條件
Employment
or Submissions before Construction of the Project
工程項目施工前須聘用的人員或提交的文件
Employment
of ET
聘用環境小組
2.1
An ET shall be established by the
Permit Holder no later than 1 month before the commencement of construction of
the Project. The ET shall not be in
any way an associated body of the Contractor or the IEC for the Project. The ET shall be headed by an ET
Leader. The ET Leader shall be a
person who has at least 7 years of experience in environmental monitoring and
auditing (EM&A) or environmental management.
許可證持有人須在工程項目建造工程展開前最少1個月成立一個環境小組。環境小組不得與工程項目的承辦商或獨立環境查核人有任何關聯。環境小組須由一名環境小組組長帶領。該名環境小組組長須在環境監察及審核(「環監」)或環境管理方面至少有7年經驗。
2.2
The ET Leader, or an ET Leader
representative who shall be a member of the ET with at least 5 years of
experience in EM&A or environmental management, shall work full time
on-site during construction stage of the Project.
環境小組組長或環境小組組長代表(須為環境小組成員,並在環監或環境管理方面具備至少5年經驗)須在工程項目的建造階段全職駐工地工作。
2.3
The ET and the ET Leader shall be
responsible for duties defined in the EM&A Manual and this Permit,
including implementation of the EM&A programme in accordance with the
EM&A requirements as contained in the EM&A Manual of the Project; and
site inspections to audit the Contractor’s site practice and work methodologies
with respect to environmental mitigation measures contained in the EM&A
Manual of the Project and/or as required under this Permit and to take
pro-active actions to pre-empt environmental problems. The ET Leader shall be responsible for:
環境小組及環境小組組長須負責執行環監手冊及本許可證所列明的職務,包括按工程項目的環監手冊所載的環監規定執行環監計劃;及進行實地視察,以便就工程項目的環監手冊所載及/或按本許可證規定的環境緩解措施,審核承辦商的工地作業方式及工作方法,並採取積極行動,防止環境問題出現。環境小組組長須負責:
(i)
certifying the environmental
acceptability of permanent and temporary works, relevant plans and submissions
required in the EM&A Manual and/or under this Permit. Certification(s) shall be documented in
the upcoming EM&A monthly report;
核證永久及臨時工程在環境上的可接受程度、相關的設計圖則和根據環監手冊及/或本許可證規定提交的文件。核證須記錄於每月環監報告;
(ii)
notifying the IEC within 1
working day of the occurrence of each and every instance or circumstance or
change of circumstances, which may affect the compliance with the
recommendations of the approved EIA Report (Register No. AEIAR-232/2021) and/or
this Permit. Notification(s)
shall be documented in the upcoming EM&A monthly report; and
在發生可能會影響核准環評報告(登記冊編號:
AEIAR-232/2021)的建議及/或本許可證的合規情況的每宗事件、每種情況或每次情況變化後1個工作天內通知獨立環境查核人。通知須記錄於每月環監報告;以及
(iii)
keeping a contemporaneous
log-book of any such instance or circumstance or change of circumstances, which
may affect the compliance with the EIA Report (Register No. AEIAR-232/2021)
and/or this Permit. The format of
the log-book shall be certified and approved by the IEC. The log-book shall be kept readily
available for inspection by all persons assisting in supervision of the
implementation of the recommendations of the approved EIA Report (Register No.
AEIAR-232/2021) and this Permit or by the Director or his authorised officers.
保存一本記錄冊,即時記載可能會影響核准環評報告(登記冊編號:AEIAR-232/2021)的建議及/或本許可證的合規情況的每宗事件、每種情況或每次情況變化。記錄冊的格式須得到獨立環境查核人的核證和批准。記錄冊須加以保存,以供協助督導執行核准環評報告(登記冊編號:AEIAR-232/2021)及本許可證的建議的所有人士、署長或獲授權人員隨時查閱。
2.4
Failure to maintain records in
the log-book or failure to discharge the duties of the ET Leader as defined in
the EM&A Manual or failure to comply with Condition 2.3 above would entitle
the Director to require the Permit Holder by notice in writing to replace the
ET Leader. Failure by the Permit
Holder to make replacement or further failure to keep contemporaneous records
in the log-book despite the employment of a new ET Leader may render this
Permit liable to suspension, cancellation or variation.
環境小組組長如未能在記錄冊保存記錄、未能執行環監手冊所列明的環境小組組長職務或未能符合上文條件第2.3項的規定,署長有權藉書面通知要求許可證持有人撤換環境小組組長。許可證持有人如未能安排人選替補,或在聘用新環境小組組長後仍未能在記錄冊保存即時記錄,或會導致本許可證遭暫時吊銷、取消或更改。
Employment
of IEC
聘用獨立環境查核人
2.5
An IEC shall be employed by the
Permit Holder no later than 1 month before commencement of construction of the
Project. The IEC shall not be in
any way an associated body of the Contractor or the ET for the Project. The IEC shall be a person who has at
least 7 years of experience in EM&A or environmental management.
許可證持有人須在工程項目建造工程展開前最少1個月聘用一名獨立環境查核人。獨立環境查核人不得與工程項目的承辦商或環境小組有任何關聯,而該名獨立環境查核人須在環監或環境管理方面至少有7年經驗。
2.6
The appointment of IEC shall be
approved by the Director before being appointed by the Permit Holder. The IEC, or an IEC representative who
shall be a person with at least 5 years of experience in EM&A or
environmental management, shall work full time on-site during construction
stage of the Project. The Permit
Holder shall also provide supporting team to the IEC or to the IEC
representative. The IEC or the IEC
representative shall report directly to the Director on matters relating to the
EM&A programme and environmental impacts of the Project.
獨立環境查核人須經署長批准才可獲許可證持有人聘用。獨立環境查核人或獨立環境查核人代表(須在環監或環境管理方面具備至少5年經驗)須在工程項目的施工階段全職駐工地工作。許可證持有人須為獨立環境查核人或獨立環境查核人代表提供支援小組。獨立環境查核人或獨立環境查核人代表須就環監計劃及工程項目造成的環境影響的相關事宜直接向署長匯報。
2.7
The IEC shall be responsible for
duties defined in the EM&A Manual and this Permit, including the following:
獨立環境查核人須執行環監手冊及本許可證所列明的職務,包括以下:
(i)
auditing the overall EM&A
performance, including the implementation of all environmental mitigation
measures and monitoring activities on site, submissions required in the
EM&A Manual, and/or under this Permit.
Finding(s) of the audit(s) shall be documented in the upcoming EM&A
monthly report;
審核整體環監工作的表現,包括實施所有環境緩解措施和執行現場的監察工作、提交環監手冊及/或本許可證所規定的文件。審核結果須記錄於每月環監報告;
(ii)
verifying the environmental
acceptability of permanent and temporary works, relevant design plans and
submissions required in the EM&A Manual and under this Permit. Verification(s) shall be documented in
the upcoming EM&A monthly report;
核實永久及臨時工程在環境上的可接受程度、相關的設計圖則和根據環監手冊及本許可證規定提交的文件。核實結果須記錄於每月環監報告;
(iii)
verifying the log-book(s) mentioned
in Condition 2.3(iii). The
IEC shall sign off with a date on the log-book after verification;
核實條件第2.3(iii)項所述的記錄冊。核實後獨立環境查核人須於記錄冊上簽署並填上日期;
(iv)
notifying the Director by fax or
email, within 1 working day of receipt of notification from the ET Leader, or
identification by the IEC and his team, of each and every change of
circumstances or suspected and/or potential non-compliance with the
recommendations (such as construction methods, mitigation measures and
environmental standards) of the approved EIA Report (Register No.
AEIAR-232/2021), the EM&A Manual and this Permit, which might affect the
monitoring or control of adverse environmental impacts arising from the
Project. Notification by the Permit
Holder is the same as notification by the IEC for the purpose of this
Condition;
在每次出現情況變化或懷疑及/或可能不符合核准環評報告(登記冊編號:AEIAR-232/2021)的建議(例如施工方法、緩解措施及環境標準)、環監手冊及本許可證的情況,而可能會妨礙對工程項目所造成的不良環境影響作出監察或控制時,獨立環境查核人須在接獲環境小組組長通知或獨立環境查核人及其支援小組確定情況後1個工作天內以傳真或電郵方式通知署長。為執行本條件,許可證持有人的通知等同獨立環境查核人的通知;
(v)
liaising closely with the
Director;
與署長密切聯繫;
(vi)
accompanying the Director in
carrying out site inspections and attending meetings when requested;
按要求陪同署長進行實地視察及出席會議;
(vii)
offering objective and
professional advice on environmental issues, when requested, and to respond to
questions and enquiries from the Director on the project, the EM&A
programme and duties discharged by the IEC, with the support of relevant
information, documents and records as appropriate; and
按要求就環境問題提供客觀及專業意見,並提供合適的相關資料、文件和記錄,以回應署長就工程項目、環監計劃及獨立環境查核人所執行之職務提出的問題及查詢;以及
(viii)
allocating adequate resources,
including any necessary specialist support, for discharging the duties required
in the EM&A Manual and/or this Permit.
分配足夠資源,包括所需的專業支援,以執行本許可證及/或環監手冊規定的各項職務。
2.8
If the Director considers the IEC
fails to discharge the duties of the IEC as defined in the EM&A Manual or
in this Permit, the Director may require the Permit Holder by notice in writing
to replace the IEC. Failure to
replace the IEC as directed or further failure to so notify the Director
despite employment of a new IEC may render this Permit liable to suspension, cancellation
or variation.
如署長認為獨立環境查核人未能執行環監手冊或本許可證所列明的獨立環境查核人職務,署長可藉書面通知要求許可證持有人撤換獨立環境查核人。如未能按指示撤換獨立環境查核人,或在聘用新獨立環境查核人後仍未能通知署長有關情況,則或會導致本許可證遭暫時吊銷、取消或更改。
Submission
of Management Organisation(s)
提交管理架構
2.9
The Permit
Holder shall, no later than 1 month before the commencement of construction of
the Project, inform the Director in
writing with the following information:
許可證持有人須在工程項目建造工程展開前最少1個月把以下資料,以書面通知署長:
(i)
the management organisation of
the main construction companies and /or any form of joint ventures associated
with the construction of the Project;
主要建造公司及/或以任何形式與工程項目建造工程相關的合營企業的管理架構;
(ii)
the management organisation of
the ET;
環境小組的管理架構;
(iii)
the management organisation of
the IEC and his supporting team; and
獨立環境查核人及其支援小組的管理架構;以及
(iv)
the submitted information
shall include at least an organization chart, names of responsible persons and
their contact details.
提交的資料須至少包括一份組織圖、負責人的姓名及聯絡資料。
Submission
of Environmental Permit (EP) Submission Schedule
提交環境許可證文件提交時間表
2.10
The
Permit Holder shall, no later than 1 month before the commencement of
construction of the Project, submit an EP Submission Schedule to set out a
timeline for EP submissions in this Permit and shall report the progress in
fulfilling the submission requirements in the Monthly EM&A Reports
submitted under Condition 3.4 of this Permit. The Permit Holder shall inform the
Director no later than 2 weeks before the scheduled submission date of the EP
submission in writing in case of any subsequent change(s) to the submitted EP
Submission Schedule. The EP
Submission Schedule or any subsequent change(s) to the submitted Schedule shall
be certified by the ET Leader and verified by the IEC referred to in Conditions
2.3 and 2.7 above, before submitting to the Director under this Permit.
許可證持有人須在工程項目的建造工程展開前至少提早1個月,向署長提交環境許可證文件提交時間表以制定本許可證所要求的文件的提交時間,並須在根據本許可證條件第3.4項提交的每月環監報告中,匯報文件提交的進度。倘若環境許可證文件提交時間表的內容在提交後有任何更改,許可證持有人須在提交文件的預定提交日期前至少提早2個星期,就有關更改以書面通知署長。環境許可證預計文件提交時間表或已提交的時間表其後有任何更改,均須按上文條件第2.3及2.7項所述的環境小組組長核證及獨立環境查核人核實,然後才按本許可證規定向署長提交。
Submission
of Construction Works Schedule and Location Plans
提交施工時間表及位置圖
2.11
The Permit Holder shall, no later than 1 month before
the commencement of construction of the Project, deposit with the Director 3
hard copies and 1 electronic copy of a work plan. The work plan shall include at least the
following information:
許可證持有人須在工程項目的建造工程展開前最少1個月,把施工計劃的3份硬複本及1份電子複本送交署長存放。施工計劃須至少包括下列資料:
(i)
a detailed phasing programme of all construction works
of the Project; and
工程項目所有建造工程的詳細分階段計劃;以及
(ii)
a location plan with scale of at least 1:1000 detailing
footprint of the Project, locations of the above ground structures of the
Project and boundaries of all construction works of the Project, with a view to
demonstrating that no footprint and construction works boundaries of the
Project will encroach on the Lion Rock Country Park and no above ground
structures of the Project will encroach on inland watercourses.
比例最低限度為 1:1000的位置圖,詳述工程項目的覆蓋範圍、地面建築物位置及所有建造工程的界線範圍,以證明工程項目的覆蓋範圍及建造工程的界線不會侵佔獅子山郊野公園,工程項目的地面建築物亦不會侵佔內陸水道。
Submission of Construction Noise Management Plan
提交建築噪音管理計劃
2.12
The Permit Holder shall, no later than 1 month before
the commencement of construction of the Project or
otherwise approved by the Director, deposit with the Director 3 hard copies and 1
electronic copy of a Construction Noise Management Plan (CNMP). The CNMP shall include layout plan(s)
detailing the locations and arrangements of the noise mitigation measures,
including but not limited to the use of movable noise barriers, enclosures and
quality powered mechanical equipment.
The CNMP shall include an implementation schedule in table form to
clearly list out the mitigation measures to be implemented, and the
implementation party, location, timing, and environmental performance required
for implementation of the mitigation measures. If there is any change to the
construction noise mitigation measures and/or plant inventory recommended in
the deposited CNMP, the Permit Holder shall, no later than 1 month before the
implementation of any such change, deposit with the Director 3 hard copies and
1 electronic copy of an updated CNMP.
The CNMP and updated CNMP shall be certified by the ET Leader and
verified by the IEC as conforming to the relevant information and
recommendations of the EIA Report (Register No. AEIAR-232/2021). All mitigation measures recommended and
requirements specified in the CNMP and the updated CNMP shall be fully
implemented.
許可證持有人須在工程項目的建造工程展開前最少1個月,或在署長另行批准的限期前,把建築噪音管理計劃的3份硬複本及1份電子複本送交署長存放。建築噪音管理計劃須包括以設計圖則詳列噪音緩解措施的位置及安排,包括但不限於使用可移動隔音屏障、隔音罩及優質機動設備。建築噪音管理計劃須包括以列表形式擬備的實施時間表,清楚列明將會實施的緩解措施、實施者、地點、時間,以及實施緩解措施時須達到的環保成效。如已存放的建築噪音管理計劃所建議的建築噪音緩解措施及/或設備清單有任何更改,許可證持有人須在落實任何更改事項前最少1個月,把已更新的建築噪音管理計劃的3份硬複本及1份電子複本送交署長存放。建築噪音管理計劃及已更新的建築噪音管理計劃須由環境小組組長核證及由獨立環境查核人核實,證明符合環評報告(登記冊編號:AEIAR-232/2021)所載的相關資料及建議。建築噪音管理計劃及已更新的建築噪音管理計劃所建議的各項緩解措施和訂明的規定均須全面予以實施。
Submission of Waste Management Plan
提交廢物管理計劃
2.13
The Permit Holder shall, no
later than 1 month before the commencement of construction of the Project or
otherwise approved by the Director, deposit with the Director 3 hard copies and
1 electronic copy of a Waste Management Plan (WMP). The WMP shall include
estimated volume of different types of waste, e.g. construction and demolition
(C&D) materials, chemical waste and general refuse, etc., and the
arrangements for avoidance, minimisation, recovery, recycling, reuse, storage,
collection, treatment and disposal of different categories of waste to be
generated from the construction activities at various works areas of the
Project at different times during the construction programme. The WMP shall include an implementation
schedule in table form to clearly list out the amount and disposal outlet for
the different types of waste arising, mitigation measures to be implemented,
and the implementation party, location, timing, and environmental performance
required for implementation of the mitigation measures. If there is any change to mitigation
measures as recommended in the deposited WMP, the Permit Holder shall, no later
than 1 month before the implementation of any such change, deposit with the
Director 3 hard copies and 1 electronic copy of an updated WMP. The WMP and updated WMP shall be
certified by the ET Leader and verified by the IEC as conforming to the
relevant information and recommendations of the EIA Report (Register No.
AEIAR-232/2021). All mitigation
measures recommended and requirements specified in the WMP and the updated WMP
shall be fully implemented.
許可證持有人須在工程項目的建造工程展開前最少1個月,或在署長另行批准的限期前,把廢物管理計劃的3份硬複本及1份電子複本送交署長存放。廢物管理計劃須包括在施工期間的不同時間內,於工程項目的各個施工區進行建築活動所產生的各種廢物(如建築和拆卸物料、化學廢物及一般垃圾)的估計數量,以及就避免、盡量減少、回收、循環再用、重用、貯存、收集、處理及處置各類廢物而作出的安排。廢物管理計劃須包括以列表形式擬備的實施時間表,清楚列明所產生的各類廢物的數量和處置方式、將會實施的緩解措施、實施者、地點、時間,以及實施緩解措施時須達到的環保成效。如已存放的廢物管理計劃所建議的緩解措施有任何更改,許可證持有人須在落實任何更改事項前最少1個月,把已更新的廢物管理計劃的3份硬複本及1份電子複本送交署長存放。廢物管理計劃及已更新的廢物管理計劃須由環境小組組長核證及由獨立環境查核人核實,證明符合環評報告(登記冊編號:AEIAR-232/2021)載列的相關資料及建議。廢物管理計劃及已更新的廢物管理計劃所建議的各項緩解措施和指明的規定,均須全面予以實施。
Submission of Landscape and Visual Mitigation Plan
提交景觀及視覺影響緩解計劃
2.14
The Permit Holder shall,
no later than 1 month before the commencement of the construction
of the
Project or otherwise approved by the Director, deposit
with the Director 4 hard copies and 1 electronic copy of landscape and visual
mitigation plan (LVMP). The LVMP shall show the
design details, including a compensatory planting proposal for the loss of
trees within the Project site, and implementation schedule, maintenance and
management schedules, and drawings in the scale of 1:1000 or other appropriate
scale of the landscape and visual mitigation measures of the Project. The implementation schedule shall be in
table form to clearly list out the mitigation measures to be implemented, and
the implementation party, location, timing, and environmental performance
required for implementation of the mitigation measures. If there is any change to the landscape
and visual mitigation measures as recommended in the deposited LVMP, the Permit
Holder shall, no later than 1 month before implementation of any such change,
deposit with the Director 4 hard copies and 1 electronic copy of the updated
LVMP. The LVMP and the updated LVMP
shall be certified by the ET Leader and verified by the IEC as conforming to
the relevant information and recommendations, including those described in the
approved EIA Report (Register No. AEIAR-232/2021). All landscape and visual mitigation
measures recommended in the LVMP and the updated LVMP shall be fully
implemented and maintained.
許可證持有人須在工程項目的建造工程展開前最少1個月,或在署長另行批准的限期前,把景觀及視覺影響緩解計劃的4份硬複本及1份電子複本送交署長存放。景觀及視覺影響緩解計劃須載列工程項目的景觀及視覺影響緩解措施的設計詳情(包括就工程項目工地內所損失的樹木提出補償植樹建議)、實施時間表、保養及管理時間表,以及採用1:1000的比例或其他合適比例繪畫的圖則。實施時間表須以列表形式擬備,清楚列明將會實施的緩解措施、實施者、地點、時間,以及實施緩解措施時須達到的環保成效。如已存放的景觀及視覺影響緩解計劃所建議的景觀及視覺影響緩解措施有任何更改,許可證持有人須在落實任何更改事項前最少1個月,把已更新的景觀及視覺影響緩解計劃的4份硬複本及1份電子複本送交署長存放。景觀及視覺影響緩解計劃和已更新的景觀及視覺影響緩解計劃須由環境小組組長核證及由獨立環境查核人核實,證明符合相關資料及建議,包括核准環評報告(登記冊編號:AEIAR-232/2021)所載的資料及建議。景觀及視覺影響緩解計劃及已更新的景觀及視覺影響緩解計劃所建議的各項景觀及視覺影響緩解措施,均須全面予以實施及維持。
Measures
during Construction of the Project
工程項目建造期間須採取的措施
Measures
to Minimise Construction Dust Impacts
減少建築塵埃影響的措施
2.15
The
Permit Holder shall implement the following measures to minimise the
construction dust impacts:
許可證持有人須實施以下減少建築塵埃影響的措施:
(i)
install
blast nets/canvas at the blasting area inside the cavern and tunnel of the
Project before blasting;
於爆破前在工程項目的岩洞及隧道爆破區安裝爆破護網/帆布;
(ii)
install
blast door near the blasting area and keep the blast door closed during
blasting;
在爆破區附近安裝爆破隔門及於爆破期間保持爆破隔門關閉;
(iii)
configure
the rock crushing plant for the construction of the Project as an enclosed
system and provide dust collector with dust removal efficiency of 95% or above
at the exhaust of the rock crusher; and
把工程項目的建造工程所使用的碎石設備配置為密封系統,以及在碎石機排放口設置除塵效能達95%或以上的集塵器;以及
(iv)
install
dust filter at the ventilation shafts of the tunnel portal with dust removal
efficiency of 80% or above.
在隧道口通風井安裝除塵效能達80%或以上的濾塵器。
Measures
during Operation of the Project
工程項目營辦期間須採取的措施
Measures to Prevent Hazardous Gas
防止有害氣體的措施
2.16
No
chlorination process shall be carried out in the caverns of the Project.
不得在工程項目的岩洞內進行加氯程序。
3
Environmental Monitoring and
Audit (EM&A) Requirements
環境監察及審核規定
3.1
The Permit Holder shall implement the EM&A programme in accordance with the procedures
and requirements as set out in the EM&A Manual. Any changes to the EM&A requirements
or programme or termination of the programme shall be justified by the ET
Leader and verified by the IEC as conforming to the relevant requirements as set out in the EM&A Manual
before submission to the Director for approval.
許可證持有人須按照環監手冊所載的程序及規定執行環監計劃。環監的規定或計劃如有更改或計劃如終止,須由環境小組組長提出理據並由獨立環境查核人核實,證明其符合環監手冊所載的資料及規定,然後才提交署長批准。
3.2
The Permit Holder shall take
samples, measurements and necessary remedial actions in accordance with the
requirements of the EM&A Manual by:
許可證持有人須按照環監手冊所載的規定,透過以下方法進行取樣、測量及所需的補救行動:
(i)
conducting baseline environmental
monitoring;
進行環境基線監測;
(ii) conducting
impact monitoring;
進行影響監測;
(iii) carrying
out remedial actions described in Event/Action Plans of the EM&A Manual in
accordance with the time frames set out in Event/Action Plans, or as agreed by
the Director, in case where specified criteria in the EM&A Manual are
exceeded; and
如超逾環監手冊內指定的標準,則按照環監手冊內的事件/行動計劃所訂明的時限或署長所同意的時限,執行事件/行動計劃所說明的補救行動;以及
(iv) logging and keeping records of
details of (i) to (iii) above for all parameters within 3 working days of
collection of data or completion of remedial action(s), for the purpose of
preparing and submitting the Monthly EM&A Reports and to make available for
inspection on site.
在收集數據或完成補救行動3個工作天內,須記錄及備存上文(i)至(iii)段所有參數的詳情,用作擬備及提交每月環監報告,並備妥有關資料以供在工地查閱。
3.3
The Permit Holder shall submit 1
hard copy and 1 electronic copy of Baseline Monitoring Report to the Director
at least 2 weeks before the commencement of construction of the Project. The submissions shall be certified by the ET
Leader and verified by the IEC as
having complied with the requirements as set out in the EM&A Manual before
submission to the Director. Additional copies of the Baseline
Monitoring Reports shall be provided upon request by the Director.
許可證持有人須在展開工程項目的建造工程前最少2個星期向署長提交基線監測報告的1份硬複本及1份電子版本。提交文件須由環境小組組長核證及獨立環境查核人核實,證明其符合環監手冊所載的規定,然後才提交署長。如署長要求,則須提交基線監測報告的額外複本。
3.4
The Permit Holder shall submit 1 hard copy and 1
electronic copy of the Monthly
EM&A Reports for the construction stage of the Project to the Director,
within 10 working days after the end of the reporting month. The Monthly EM&A Reports shall
include an executive summary of all environmental audit results, together with
actions taken in the event of non-compliance (exceedances) of the environmental
quality performance limits (Action and Limit Levels), complaints received and
emergency events relating to violation of environmental legislation. The
submissions
shall be certified by the ET Leader and verified by the IEC as having complied
with the requirements as set out in the EM&A Manual before submission to
the Director. Additional copies of
the Monthly EM&A Reports shall be provided upon request by the Director.
在每個提交報告的月份結束後10個工作天內,許可證持有人須向署長提交工程項目建築階段每月環監報告的1份硬複本及1份電子版本。每月環監報告須包括各項環境審核結果,以及在發生不符合(超出)環境質素表現規限(行動及極限水平)情況時所採取的行動、接獲有關違反環境法例的投訴及發生相關緊急事件的行政摘要。提交的報告須由環境小組組長核證及獨立環境查核人核實,證明其符合環監手冊所載的規定,然後才提交署長。如署長要求,則須向署長提交每月環監報告的額外複本。
3.5
All environmental monitoring and
audit data submitted under this Permit shall be true, valid and correct.
根據本許可證提交的所有環監數據,均須有效及真實無誤。
3.6
To ensure a high degree of
transparency regarding the monitoring data and results in view of the public
concern about the Project, all environmental monitoring and audit data and
results and all submissions and all performance test data and results required
by this Permit shall be made available by the Permit Holder to the public
through a dedicated website to be set up by the Permit Holder under Condition
4.2 below, in the shortest practicable time and in no event later than 10
working days after such information is available.
基於公眾對工程項目的關注,為確保監察數據和結果具高透明度,許可證持有人須盡快把各項環境監察及審核數據和結果、本許可證規定的所有提交文件及各項表現測試數據和結果,透過按下文條件第4.2項由許可證持有人設立的特定網站供公眾閱覽,在任何情況下均不得遲於這些資料可供閱覽後的10個工作天。
4. Electronic
Reporting of EM&A Information
環監資料的電子匯報
4.1 To
facilitate public inspection of the Baseline Monitoring Report and Monthly EM&A Reports via the EIAO
Internet Website and at the EIAO Register Office, electronic copies of these
Reports shall be prepared in Hyper Text Markup Language (HTML) (version 4.0 or
later) and in Portable Document Format (PDF version 1.3 or later), unless
otherwise agreed by the Director and shall be submitted at the same time as the
hard copies as described in Conditions 3.3 and 3.4 above. For the HTML version,
a content page capable of providing hyperlink to each section and sub-section
of these Reports shall be included in the beginning of the document. Hyperlinks to all figures, drawings and
tables in these Reports shall be provided in the main text from where the
respective references are made. All
graphics in these Reports shall be in interlaced GIF, JPEG or PDF format unless
otherwise agreed by the Director.
The content of the electronic copies of these Reports must be the same
as the hard copies.
為方便公眾透過環評條例互聯網網站及在環評條例登記冊辦事處查閱基線監測報告及每月環監報告,除非另獲署長同意,否則該等報告的電子複本須以超文本標示語言(HTML)(第4.0或較後版本)及便攜式文件格式(PDF)(第1.3或較後版本)擬備,並須與上文條件第3.3及3.4項所說明的硬複本同時提交。關於HTML的版本方面,須在文件開端加入可與報告各節及小節作出超文本連結的目錄。報告內的正文如有任何相關的參考資料,須建立超連結以連結至報告所載的相關數據和圖表。除非另獲署長同意,否則報告內所有圖像均須以交錯存取的GIF、JPEG或PDF格式制定。報告的電子複本內容,必須與硬複本的內容一致。
4.2 The Permit
Holder shall, within 1 month after the commencement of construction of the
Project, set up a dedicated Internet website and notify the Director in writing
the Internet address where the environmental monitoring data and project information is to be
placed. All environmental
monitoring results
described in Condition 4.1 above shall
be made available to the public via the
abovementioned dedicated Internet website in the shortest possible time and in any event no later
than 2 weeks
after the relevant environmental monitoring data are collected or become
available, unless otherwise agreed with the Director. All finalised submissions and plans
shall be made available to the public via the dedicated Internet website in the
shortest possible time and in any event no later than 2 weeks after the
submissions and plans are approved by or deposited with the Director, unless
otherwise agreed with the Director.
The Permit Holder shall maintain the dedicated website for public access
of the environmental monitoring data and reports throughout the entire
construction period and during the first 1-year period of operation of the
Project, or otherwise agreed by the Director.
許可證持有人須在工程項目的建造工程展開後1個月內,設立特定網站存放環境監察數據及工程項目資料,並以書面通知署長互聯網網址所在。除非另獲署長同意,上文條件第4.1項說明的所有環境監察數據,均須盡快透過上述特定互聯網網站供公眾閱覽,在任何情況下均不得遲於有關資料在收集或可供發放後的2個星期內上載至該特定網站。所有提交文件及圖則定稿,均須盡快透過該特定互聯網網站供公眾閱覽,在任何情況下均不得遲於有關提交文件及圖則獲署長核准或向署長存放後的2個星期,除非另獲署長同意。許可證持有人須在工程項目整個施工期內及首1年營辦期內,或署長同意的其他期間,維持該特定網站,供公眾接達有關環境監察數據及報告。
4.3 The internet website as described in Condition
4.2 above shall enable user-friendly public access to the monitoring and
project information
including the Project Profile, EIA Report and Environmental Permit(s). The Internet website shall have features
capable of:
上文條件第4.2項說明的互聯網網站,必須方便用戶使用,讓公眾容易接達環境監察數據及工程項目資料,當中包括工程項目簡介,環評報告及環境許可證。除非另獲署長同意,互聯網網站須具備部件,提供下述功能:
(i)
providing access to all
environmental monitoring data of this Project collected since the commencement
of construction and all
submissions under this Permit;
接達建造工程展開後所收集的全部環境監察數據及本許可證規定提交的所有文件;
(ii)
searching by date;
按日期搜尋;
(iii)
searching by types of monitoring
data; and
按監察數據類別搜尋;以及
(iv)
hyperlinks to relevant monitoring
data after searching;
在搜尋後與相關的監察數據作出超文本連結。
or otherwise as agreed by the
Director.
Notes:
註:
1.
This Permit consists of three
parts, namely, Part A (Main Permit), Part B (Description of Designated Project) and Part C (Permit Conditions). Any person relying on this Permit should obtain independent
legal advice on the legal implications under the EIAO, and the following notes
are for general information only.
本許可證共有3部,即
A部 (許可證主要部分);B部 (指定工程項目的說明) 及C部 (許可證條件)。任何援引本許可證的人士須就環評條例的法律含意徵詢獨立法律意見,下述註解只供一般參考用。
2.
If there is a breach of any
condition of this Permit, the Director or his authorised officer may, with the consent
of the Secretary for the Environment, order the cessation of associated works until the remedial action is
taken in respect of the resultant environmental damage, and in that case the
Permit Holder shall not carry out any associated works without the permission
of the Director or his authorised officer.
如違反本許可證的任何條件,署長或獲授權人員徵得環境局局長的同意後可勒令停止相關工程,直至許可證持有人為所造成的環境損害採取補救行動為止。在此情況下,許可證持有人未經署長或獲授權人員同意,不得進行任何相關工程。
3.
The Permit Holder may apply under
Section 13 of the EIAO to the Director for a variation of the conditions of
this Permit. The Permit Holder shall replace the original permit displayed on
the Project site by the amended permit.
許可證持有人可根據環評條例第13條的規定向署長申請更改本環境許可證的條件。許可證持有人須以經修改的許可證替換在工程項目工地內展示的原有許可證。
4.
A person who assumes the
responsibility for the whole or a part of the Project may, before he assumes
responsibility of the Project, apply under Section 12 of the EIAO to the
Director for a further environmental permit.
承擔工程項目整項或部分工程的責任的人,在承擔責任之前,可根據環評條例第12條的規定向署長申請新的環境許可證。
5.
Under Section 14 of the EIAO, the
Director may with the consent of the Secretary for the Environment suspend,
vary or cancel this Permit. The
suspended, varied or cancelled Permit shall be removed from display at the
Project site.
根據環評條例第14條的規定,署長可在取得環境局局長的同意下暫時吊銷、更改或取消本許可證。遭暫時吊銷、更改或取消的許可證必須從工程項目工地除下,不再展示。
6.
If this Permit is cancelled or
surrendered during construction or operation of the Project, another
environmental permit must be obtained under the EIAO before the Project could
be continued. It is an offence
under Section 26(1) of the EIAO to construct or operate a designated project
listed in Part I of Schedule 2 of the EIAO without a valid environmental
permit.
如果本許可證在工程項目建造或營辦期間取消或交回,則在繼續進行工程項目之前,必須先根據環評條例規定取得另一份環境許可證。根據環評條例第26(1)條的規定,任何人在沒有有效環境許可證的情況下建造或營辦環評條例附表2第1部所列明的指定工程項目,即屬犯罪。
7.
Any person who constructs or
operates the Project contrary to the conditions in the Permit, and is convicted
of an offence under the EIAO, is liable:
如任何人在違反本許可證的條件下建造或營辦工程項目,且被裁定觸犯環評條例所訂明的罪行,即屬犯罪:
(i)
on a first conviction on
indictment to a fine of $2 million and to imprisonment for 6 months;
一經循公訴程序首次定罪,可處罰款200萬元及監禁6個月;
(ii)
on a second or subsequent conviction
on indictment to a fine of $5 million and to imprisonment for 2 years;
一經循公訴程序第二次或其後每次定罪,可處罰款500萬元及監禁2年;
(iii)
on a first summary conviction to
a fine at level 6 and to imprisonment for 6 months;
一經循簡易程序首次定罪,可處第6級罰款及監禁6個月;
(iv)
on a second or subsequent summary
conviction to a fine of $1 million and to imprisonment for 1 year; and
一經循簡易程序第二次或其後每次定罪,可處罰款100萬元及監禁1年;以及
(v)
in any case where the offence is of
a continuing nature, the court or magistrate may impose a fine of $10,000 for
each day on which he is satisfied the offence continued.
在任何情況下如該罪行屬持續性質,法院或裁判官可就其信納該罪行持續的每天另處罰款10,000元。
8.
The Permit Holder may appeal
against any condition of this Permit under Section 17 of the EIAO within 30
days of receipt of this Permit.
許可證持有人可在接獲本許可證後30天內,根據環評條例第17條就本許可證的任何條件提出上訴。
9.
The Notes are for general
reference only and that the Permit Holder should refer to the EIAO for details
and seek independent legal advice.
上述註解只供一般參考用,欲知有關詳情,許可證持有人須參閱環評條例及徵詢獨立法律意見。
Environmental Permit No. EP-602/2021
環境許可證編號:EP-602/2021
| 圖 1 |