Environmental Permit No. EP-634/2023
環境許可證編號 EP-634/2023
ENVIRONMENTAL IMPACT ASSESSMENT
ORDINANCE
(CHAPTER 499)
SECTION 10
環境影響評估條例
(第499章)
第10條
ENVIRONMENTAL PERMIT TO CONSTRUCT
AND OPERATE
A DESIGNATED PROJECT
建造及營辦指定工程項目的環境許可證
A部 (許可證主要部分)
Pursuant to Section 10 of the Environmental Impact
Assessment Ordinance (EIAO), the Director of Environmental Protection (the
Director) grants this environmental permit to the Highways Department (hereinafter referred to as the “Permit Holder”) to
construct and operate the designated project described in Part B subject
to the conditions specified in Part C. The issue of this environmental
permit is based on the documents, approvals or permissions described below:
根據《環境影響評估條例》(環評條例) 第10條的規定,環境保護署署長(署長)將本環境許可證批予路政署 (下稱“許可證持有人”) 以建造及營辦B部所說明的指定工程項目,但須遵守C部所列明的條件。本環境許可證的發出,乃以下表所列的文件、批准或許可作為根據﹕
Application No. 申請書編號 |
AEP-634/2023 |
Document in
the Register: 登記冊上的文件: |
(1)
Tuen Mun Bypass (Register No. AEIAR-256/2023): -
Environmental
Impact Assessment (EIA) Report [Hereafter referred to as “the EIA Report”] -
Environmental
Monitoring and Audit (EM&A) Manual [Hereafter referred to as “the EM&A Manual”] -
Executive
Summary 屯門繞道 (登記冊編號:AEIAR-256/2023): -
環境影響評估報告 [下稱“環評報告”] -
環境監察及審核手冊 [下稱“環監手冊”] -
行政摘要 (2) The Director’s
letter of approval of the EIA Report dated 1 December 2023
(Reference: (98) in Ax(2) to EP 2/N4/A/138) 署長於2023年12月1日發出批准環評報告的信件
(檔案編號:(98) in Ax(2) to EP 2/N4/A/138) (3) Application for Environmental Permit
submitted on 28 July 2023 (Application
No. AEP-634/2023) 於2023年7月28日提交的環境許可證申請文件 (申請書編號: AEP-634/2023) |
4 December 2023
2023年12月4日
Date 日期 |
|
(Ms. Clara U) Acting Principal Environmental Protection Officer for Director of
Environmental Protection 環境保護署署長 (署理首席環境保護主任余錦華代行) |
PART B (DESCRIPTION OF
DESIGNATED PROJECT)
B部 (指定工程項目的說明)
Hereunder is the description of the
designated project mentioned in Part A of this environmental permit (hereinafter referred to as the “Permit”):
下列為本環境許可證 (下稱“許可證”) A部所提述的指定工程項目的說明﹕
Title of Designated Project 指定工程項目的名稱 |
Tuen Mun Bypass [This
designated project is hereafter referred to as “the Project”] 屯門繞道 [本指定工程項目下稱 “工程項目”] |
Nature of Designated Project |
A carriageway for motor
vehicles that is an expressway, trunk road, primary distributor road or
district distributor road. 屬快速公路、幹道、主要幹路或地區幹路的汽車車道。 A road tunnel or railway
tunnel more than 800 m in length between portals. 入口之間的長度超過800米的行車隧道或鐵路隧道。 A depot for the storage of, or
a manufacturing plant for the manufacture of, explosives (as defined by
section 2 of the Dangerous Goods Ordinance (Cap. 295)). 儲存《危險品條例》(第295章)第2條所界定的爆炸品的倉庫,或製造該等爆炸品的製造廠。 All projects involving
earthworks, dredging works and other building works partly or wholly in an
existing or gazetted proposed country park. 所有涉及下述項目的工程項目:土木工事、挖泥工程及其他建築工程,而該等項目部分或全部位於現有的郊野公園。 |
Location of Designated Project 指定工程項目的地點 |
The Project is located at Tuen
Mun. The location of the Project is
shown in Figure 1 of this Permit. 工程項目位於屯門。 工程項目的位置載於本許可證圖1。 |
Scale and Scope of
Designated Project 指定工程項目的規模和範圍 |
The Project
includes: (i)
Construction of a road
tunnel of about 7.5 km long running through Tuen
Mun and Tai Lam Country Park, linking the Tuen Mun-Chek Lap Kok Tunnel and the
Yuen Long Highway and Kong Sham Western Highway; (ii)
Construction of tunnel
portals and associated facilities at Tuen Mun Area
40 and Lam Tei Quarry; (iii)
Construction of viaducts
/ at-grade roads from the southern tunnel portal to the roads under planning
near Lung Mun Road / Mong Fat Street, and Tuen Mun-Chek Lap Kok Tunnel at Tuen Mun Area 40; (iv)
Provision of associated
ventilation buildings, administration building and other tunnel operation
area; (v)
Re-provision of
facilities affected by the proposed works; (vi)
Provision of possible adits and associated connection with existing roads; (vii)
Construction of temporary
explosive magazines in Lam Tei Quarry, Siu Lam and
Pillar Point; and (viii) Associated geotechnical works, ground investigation works, drainage
works, natural terrain hazard mitigation works, sewerage works, traffic aids,
directional signs, street lightings, Traffic Control and Surveillance System,
Electrical and Mechanical works, environmental mitigation measures,
landscaping works, and services systems for inspection and maintenance. (i)
建造一條長約 7.5 公里的公路隧道,經過屯門和大欖郊野公園,並連接屯門–赤鱲角隧道,以及元朗公路和港深西部公路; (ii)
於屯門第 40 區和藍地石礦場建造隧道出入口和相關設施; (iii)
從南面的隧道出入口延伸至規劃中位於龍門路/望發街附近的道路,以及屯門第 40 區的屯門–赤鱲角隧道建造高架/地面道路; (iv)
提供相關的通風大樓、行政大樓和其他隧道營運區; (v)
重置受各項擬建工程影響的設施; (vi)
提供可能需要的隧道入口通道和接駁現有道路的相關設施; (vii) 於藍地石礦場、小欖和望后石建造臨時炸藥庫;以及 (viii) 相關的岩土工程、土地勘測工程、排水工程、自然地形災害緩解工程、污水工程、交通輔助設施、路線指示標誌、道路照明、交通管制及監視系統、機電工程、環境緩解措施、環境美化工程,以及檢查和維護的服務系統。 |
C部 (許可證條件)
1. General Conditions
一般條件
1.1 The Permit Holder and any person
constructing or operating the Project shall comply with all conditions set out
in this Permit. Any non-compliance by any person may constitute a contravention
of the Environmental Impact Assessment Ordinance (EIAO) (Cap. 499) and may become
the subject of appropriate action being taken under the EIAO.
許可證持有人及任何建造或營辦工程項目的人士必須完全符合本許可證載列的全部條件。任何人士如有不符合本許可證的情況,可能違反《環境影響評估條例》(環評條例) (第499章) 的規定,而當局可根據環評條例採取適當行動。
1.2 The Permit Holder and any person
constructing or operating the Project shall ensure full compliance with all
legislation from time to time in force including, without limitation to, the
Noise Control Ordinance (Cap. 400), Air Pollution Control Ordinance (Cap. 311),
Water Pollution Control Ordinance (Cap. 358), Dumping at Sea Ordinance (Cap.
466) and Waste Disposal Ordinance (Cap. 354). This Permit does not of itself
constitute any ground of defence against any proceedings instituted under any
legislation or imply any approval under any legislation.
許可證持有人及任何建造或營辦工程項目的人士須確保完全符合現行法例的規定,包括但不限於《噪音管制條例》(第400章) 、《空氣污染管制條例》(第311章)、《水污染管制條例》(第358章) 、《海上傾倒物料條例》(第466章) 及《廢物處置條例》(第354章)。本許可證本身不會就根據任何法例提出的法律程序構成任何抗辯理由,或根據任何法例默示任何批准。
1.3 The Permit Holder shall make copies of
this Permit together with all documents referred to in this Permit and the
documents referred to in Part A of this Permit readily available at all
times for inspection by the Director or his authorized officers at all sites
covered by this Permit. Any reference to this Permit shall include all
documents referred to in this Permit and also the relevant documents in the
Register.
許可證持有人須印製本許可證的複本,連同本許可證所述的所有文件及本許可證A部所述文件,以供署長或獲授權人員任何時間內在本許可證所涵蓋的所有工地查閱。凡提述本許可證,須包括本許可證所述的所有文件及登記冊內的相關文件。
1.4 The Permit Holder shall give a copy of
this Permit to the person(s) in charge of the site(s) and ensure that such
person(s) fully understands all conditions and all requirements incorporated in
this Permit. The site(s) refers to site(s) of construction and operation of the
Project and shall mean the same hereafter.
許可證持有人須把本許可證的一份複本交予有關工地的負責人,並確保這些人士完全明白本許可證的所有條件與規定。工地是指建造及營辦工程項目的工地,下文所提及的工地亦屬同一意思。
1.5 The Permit Holder shall display
conspicuously a copy of this Permit on the construction site(s) at all
vehicular site entrances/exits or at a convenient location for public’s
information at all times. The Permit Holder shall ensure that the most updated
information about this Permit, including any amended Permit, is displayed at
such locations. If the Permit Holder surrenders a part or the whole of
this Permit, the notice he sends to the Director shall also be displayed at the
same locations as the original Permit. The suspended, varied or cancelled
Permit shall be removed from display at the construction site(s).
許可證持有人須在建造工地的所有車輛進出口或一處方便地點,顯眼地展示本許可證的複本,以供公眾在任何時間內閱覽。許可證持有人須確保在這些地點展示關於本許可證(包括任何經修訂的許可證)的最新資料。許可證持有人如交回本許可證的部分或全部,必須把其送交署長的通知書,在備有原有許可證的各處相同地點展示。遭暫時吊銷、更改或取消的許可證必須從建造工地除下,不再展示。
1.6 The Permit Holder and any person
constructing or operating the Project shall construct and operate the Project
in accordance with the project description in Part B of this Permit.
許可證持有人及任何建造或營辦工程項目的人士須依據本許可證B部的工程項目說明,建造及營辦工程項目。
1.7 The Permit Holder and any person
constructing or operating the Project shall ensure that the Project is designed, constructed and operated in accordance with
the information and recommendations described in the approved EIA Report (Register No.: AEIAR-256/2023);
the application documents for
environmental permits; other relevant document(s) in the
Register; the information and mitigation measures described in this Permit;
mitigation measures to be recommended in submissions that shall be deposited
with or approved by the Director as a result of permit conditions contained in
this Permit, and mitigation measures to be recommended under on-going
surveillance and monitoring activities during all stages of the Project. Where
recommendations referred to in the documents of the Register are not expressly
referred to in this Permit, such recommendations are nevertheless to be
implemented unless expressly excluded in this Permit or otherwise agreed by the
Director.
許可證持有人及任何建造或營辦工程項目的人士須確保工程項目按照下述資料設計、建造及營辦:核准環評報告(登記冊編號:AEIAR-256/2023)所說明的資料及相關建議;環境許可證的申請文件;登記冊內的其他相關文件;本許可證所說明的資料及緩解措施;根據本許可證所載的條件須提交予署長存放或獲署長批准的文件所建議的緩解措施;以及在工程項目各階段進行的持續監察及監測工作所建議的緩解措施。登記冊文件所述建議如沒有在本許可證明確表示,則仍須實施這些建議,除非獲本許可證明確豁除或另獲署長同意。
1.8 All
submissions, as required under this Permit, shall be rectified and resubmitted
in accordance with the comments, if any, made by the Director within 1 month of
the receipt of the Director’s comments or otherwise as specified by the
Director.
所有按本許可證規定提交的文件,須在接獲署長的意見(如有者)後1個月內或署長另行指定的期限內,根據署長的意見加以修正及重新提交。
1.9 All submissions approved by the Director, all submissions
deposited without comments by the Director, or all submissions rectified in
accordance with comments by the Director under this Permit shall be construed
as part of the permit conditions described in Part C of this Permit. Any
variation of the submissions shall be approved by the Director in writing or as
prescribed in the relevant permit conditions. Any non-compliance with the
submissions may constitute a contravention of the EIAO (Cap. 499). All submissions
or any variation of submissions shall be certified by the Environmental Team
(ET) Leader and verified by the Independent Environmental Checker (IEC)
referred to in Conditions 2.1 and 2.7 below before submitting to the Director
under this Permit.
所有提交署長並獲批准的文件、所有提交署長存放而沒有收到署長意見的文件或根據本許可證提交並已依照署長的意見作出修訂的所有文件,將詮釋為本許可證C部所說明的許可證條件的一部分。對提交文件所作的任何修訂,均須獲得署長的書面批准,或符合有關許可證條件所述。凡與所提交的文件有不符合的情況,均可能構成違反環評條例 (第499章)。所有提交文件或提交文件的任何修訂本,均須按下文條件第2.1及2.7項所述的環境小組組長核證及獨立環境查核人核實,然後才按本許可證規定向署長提交。
1.10 The
Permit Holder shall release all finalized submissions as required under this
Permit to the public by depositing copies in the Environmental Impact
Assessment Ordinance Register Office, or in any other places, or any internet
websites as specified by the Director, or by any means as specified by the
Director, for public inspection. For this purpose, the Permit Holder shall
provide sufficient copies of the submissions.
許可證持有人須把所有按本許可證規定提交的文件定稿公開給公眾人士知道,方法是把有關文件複本存放於環境影響評估條例登記冊辦事處,或署長指定的任何其他地方,或署長指定的任何互聯網網站,或署長指定的任何方法,以供公眾查閱。為此,許可證持有人須提供足夠數量的複本。
1.11 The
Permit Holder shall submit and / or deposit all submissions within the time as
specified in the Conditions of this Permit. All submissions to the Director required under this Permit
shall be delivered either in person or by registered mail to the Environmental
Impact Assessment Ordinance Register Office (currently at 27/F, Southorn Centre, 130 Hennessy Road, Wanchai,
Hong Kong). Electronic copies of all finalized submissions required under this
Permit shall be prepared in Hyper Text Markup
Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF
version 1.3 or later), unless otherwise agreed by the Director and shall be
submitted at the same time as the hard copies.
許可證持有人須在本許可證條件所列明的時間內,提交及/或存放所有文件。本許可證規定向署長提交的所有文件,須親身送交或以掛號方式郵寄至環境影響評估條例登記冊辦事處(現址為:香港灣仔軒尼詩道130號修頓中心27樓)。所有按本許可證規定提交的文件定稿的電子複本,均須以超文本標示語言(HTML)(第4.0或較後版本)和便攜式文件格式(PDF)(第1.3或較後版本)製作,除非另獲署長同意,電子複本須與硬複本同時提交。
1.12 The Permit Holder shall
notify the Director in writing the commencement date of construction of the corresponding
parts of the Project no later than
3 months prior to the commencement of construction of the corresponding parts of the Project. The Permit Holder shall notify the
Director in writing immediately if there is any change of the commencement date
of the construction.
許可證持有人須在工程項目相關部分建造工程展開前最少3個月,以書面方式把工程項目該部分建造工程展開日期通知署長。建造工程的展開日期如有任何更改,許可證持有人必須立即以書面方式通知署長。
1.13 For the purpose of this Permit,
“commencement of construction” does not include works related to site clearance
and preparation, or other works as agreed by the Director.
為執行本許可證,「建造工程的展開」不包括有關工地清理和預備的工程,或署長同意的其他工程。
1.14 The Permit Holder shall notify the Director
in writing the commencement date of operation of the corresponding parts of the Project no later than 1 month prior to the commencement of operation of the corresponding parts of the Project. The Permit Holder
shall notify the Director in writing immediately if there is any change of the
commencement date of operation.
許可證持有人須在工程項目相關部分開始營辦前最少1個月,以書面方式把工程項目該部分開始營辦的日期通知署長。開始營辦的日期如有任何更改,許可證持有人須立即以書面方式通知署長。
2. Specific Conditions
特定條件
Employment
or Submissions before Construction of the Project
工程項目施工前須聘用的人員或提交的文件
Employment of Environmental Team(s) (ET)
聘用環境小組
2.1 An ET shall be established by the Permit Holder no later than 4 months
before the commencement of construction of the corresponding parts of the
Project. The ET shall not be in any way an associated body of the
Contractor or the IEC for the Project. The ET shall be headed by an ET Leader. The ET Leader shall be a person who has at least 7 years of
experience in environmental monitoring and auditing (EM&A) or environmental
management.
許可證持有人須在工程項目相關部分的建造工程展開前最少4個月成立一個環境小組。環境小組不得與工程項目的承辦商或獨立環境查核人有任何關聯。環境小組須由一名環境小組組長帶領。該名環境小組組長須在環境監察及審核(“環監”)或環境管理方面至少有7年經驗。
2.2 The ET Leader, or an ET
Leader representative who shall be a member of the ET with at least 5 years of
experience in EM&A or environmental management, shall work full time
on-site during construction stage of the corresponding parts of the Project.
環境小組組長或環境小組組長代表 (須為環境小組成員,並在環監或環境管理方面具備至少有5年經驗) 須在工程項目相關部分的建造階段全職駐工地工作。
2.3 The ET and the ET Leader
shall be responsible for duties defined in the EM&A Manual and this Permit,
including implementation of the EM&A programme in
accordance with the EM&A requirements as contained in the EM&A Manual
of the Project; and site inspections to
audit the Contractor’s site practice and work methodologies with respect to
environmental mitigation measures contained in the EM&A Manual of the
Project and/or as required under this Permit and to take pro-active actions to
pre-empt environmental problems. The ET Leader shall
be responsible for:
環境小組及環境小組組長須負責執行環監手冊及本許可證所列明的職務,包括按工程項目的環監手冊所載的環監規定執行環監計劃;以及進行實地視察,以便就工程項目的環監手冊所載及/或按本許可證規定的環境緩解措施,審核承辦商的工地作業方式及工作方法,並採取積極行動,防止環境問題出現。環境小組組長須負責:
(i)
certifying
the environmental acceptability of permanent and temporary works, relevant
plans and submissions required in the EM&A Manual and/or under this Permit.
Certification(s) shall be documented in the upcoming EM&A monthly report;
核證永久及臨時工程在環境上的可接受程度、相關的設計圖則和根據環監手冊及/或本許可證規定提交的文件。核證須記錄於每月環監報告;
(ii)
notifying the IEC within one
working day of the occurrence of each and every instance or circumstance or
change of circumstances, which may affect the compliance with the
recommendations of the approved EIA Report (Register No. AEIAR-256/2023) and/or
this Permit. Notification(s) shall be documented in the
upcoming EM&A monthly report; and
在發生可能會影響核准環評報告 (登記冊編號: AEIAR-256/2023) 的建議及/或本許可證的合規情況的每宗事件、每種情況或每次情況變化後1個工作天內通知獨立環境查核人。通知須記錄於每月環監報告;以及
(iii)
keeping a contemporaneous
log-book of any such instance or circumstance or change of circumstances, which may affect the
compliance with the approved EIA Report (Register
No. AEIAR-256/2023) and/or this Permit. The format of the log-book shall be certified
and approved by the IEC. The log-book shall be kept
readily available for inspection by all persons assisting in supervision of the
implementation of the recommendations of the approved EIA Report (Register No.
AEIAR-256/2023) and this Permit or by the Director or his authorized officers.
保存一本記錄冊,即時記載可能會影響核准環評報告 (登記冊編號:
AEIAR-256/2023) 的建議及/或本許可證的合規情況的每宗事件、每種情況或每次情況變化。記錄冊的格式須得到獨立環境查核人的核證和批准。記錄冊須加以保存,以供協助督導執行核准環評報告 (登記冊編號:AEIAR-256/2023) 及本許可證的建議的所有人士、署長或獲授權人員隨時查閱。
2.4 Failure
to maintain records in the log-book, failure to discharge the duties of the ET
Leader as defined in the EM&A Manual or failure to comply with Condition 2.3 above
would entitle the Director to require the Permit Holder by notice in
writing to replace the ET Leader. Failure by the Permit Holder to make
replacement or further failure to keep contemporaneous records in the log-book
despite the employment of a new ET Leader may render this
Permit liable to suspension, cancellation or variation.
環境小組組長如未能在記錄冊保存記錄、未能執行環監手冊所列明的環境小組組長職務或未能符合上文條件第2.3項的規定,署長有權藉書面通知要求許可證持有人撤換環境小組組長。許可證持有人如未能安排人選替補,或在聘用新環境小組組長後仍未能在記錄冊保存即時記錄,或會導致本許可證遭暫時吊銷、取消或更改。
Employment of Qualified Ecologist(s) / Arborist(s) / Botanist(s)
聘用合資格的生態學家/樹藝師/植物學家
2.5 The
Permit Holder shall, no later than 3 months before the commencement of the
construction works of the corresponding parts of the Project, appoint Qualified
Ecologist(s) / Arborist(s) / Botanist(s) to form part of the ET to carry out
work relating to ecological aspects including but not limited to preparing the
submissions required under Conditions 2.17 to 2.20 of this Permit (i.e. Plant
Preservation and Transplantation Proposal(s), Translocation Proposal(s) for
Freshwater Crabs, and Woodland Compensation Implementation Plan(s)). The
Qualified Ecologist(s) / Arborist(s) / Botanist(s) shall also audit the
implementation of ecological mitigation measures to ensure compliance with
Conditions, and the recommendations of the submissions under Conditions 2.17 to
2.20 and the approved EIA Report (Register No. AEIAR-256/2023).
Each Qualified Ecologist / Arborist / Botanist shall be a person who has at
least 5 years of relevant experience. The qualification and experience of the
Qualified Ecologist(s) / Arborist(s) / Botanist(s) shall be certified by the ET
Leader and verified by the IEC.
許可證持有人須在工程項目相關部分的建造工程展開前最少3個月,聘用一名(或多名)合資格的生態學家/樹藝師/植物學家作為環境小組成員,以進行生態方面的工作,包括但不限於按照本許可證條件第2.17項至第2.20項的規定擬備須提交的文件 (即植物保護及移植建議書、淡水蟹遷移建議書及林地補償實施計劃),並審核生態緩解措施的執行情況,以確保已遵從本許可證條件第2.17項至第2.20項提交的文件和核准環評報告 (登記冊編號:AEIAR-256/2023)
載述的建議。每名合資格的生態學家/樹藝師/植物學家均須具備至少5年相關經驗,其資格及經驗須由環境小組組長核證,並經獨立環境查核人核實。
Employment
of Registered Landscape Architect(s)
聘用註冊園境師
2.6 The
Permit Holder shall, no later than 3 months before the commencement of the construction of
the corresponding parts of the Project,
appoint a Registered Landscape Architect to form part of the ET to carry out
work relating to landscape aspects including but not limited to preparing
submissions of the Landscape and Visual Mitigation Plan(s) for the Project as
required under Condition 2.22 of this Permit, and to audit the implementation of
landscape mitigation measures to ensure compliance with the recommendations of
the submissions under Condition 2.22 of this Permit and the approved EIA Report
(Register No. AEIAR-256/2023). The qualification and experience of the
Registered Landscape Architect shall be certified by the ET Leader and verified
by the IEC.
許可證持有人須在工程項目相關部分的建造工程展開前最少3個月,聘用一名註冊園境師作為環境小組成員,以進行與景觀有關的工作,包括但不限於按照本許可證條件第2.22項的規定,就工程項目擬備景觀及視覺影響緩解計劃,並審核景觀影響緩解措施的執行情況,確保已遵從按照本許可證條件第2.22項規定提交的文件和核准環評報告 (登記冊編號: AEIAR-256/2023) 載述的建議。註冊園境師的資格及經驗須由環境小組組長核證,並經獨立環境查核人核實。
Employment of Independent Environmental Checker(s) (IEC)
聘用獨立環境查核人
2.7 An
IEC shall be employed by the Permit Holder no
later than 4 months
before the commencement of construction of the corresponding parts of the
Project. The IEC shall not be in any way an associated
body of the Contractor or the ET for the Project. The IEC shall be a person
who has at least 7 years of experience in EM&A or environmental management.
許可證持有人須在工程項目相關部分的建造工程展開前最少4個月聘用一名獨立環境查核人。獨立環境查核人不得與工程項目的承辦商或環境小組有任何關聯,而該名獨立環境查核人須在環監或環境管理方面至少有7年經驗。
2.8 The appointment of IEC
shall be approved by the Director before being appointed by the Permit Holder. The
IEC, or an IEC representative who shall be a person with at least 5 years of
experience in EM&A or environmental management, shall work full time
on-site during construction stage of
the corresponding parts of the Project. The Permit Holder shall also
provide supporting team to the IEC or to the IEC representative. The IEC or the
IEC representative shall report directly to the Director on matters relating to
the EM&A programme and environmental impacts of the Project.
獨立環境查核人須經署長批准才可獲許可證持有人聘用。獨立環境查核人或獨立環境查核人代表 (須在環監或環境管理方面具備至少有5年經驗) 須在工程項目相關部分的施工階段全職駐工地工作。許可證持有人須為獨立環境查核人或獨立環境查核人代表提供支援小組。獨立環境查核人或獨立環境查核人代表須就環監計劃及工程項目造成的環境影響的相關事宜直接向署長匯報。
2.9 The IEC shall be responsible for duties
defined in the EM&A Manual and this Permit, including the following:
獨立環境查核人須執行環監手冊及本許可證所列明的職務,包括以下:
(i)
auditing the overall EM&A
performance, including the implementation of all environmental mitigation
measures and monitoring activities on site, submissions required in the
EM&A Manual, and/or under this Permit.
Finding(s) of the audit(s) shall be documented in the upcoming EM&A
monthly report;
審核整體環監工作的表現,包括實施所有環境緩解措施和執行現場的監察工作、提交環監手冊及/或本許可證所規定的文件。審核結果須記錄於每月環監報告;
(ii)
verifying the environmental acceptability of
permanent and temporary works, relevant design plans and submissions required
in the EM&A Manual and under this Permit. Verification(s) shall be
documented in the upcoming EM&A monthly report;
核實永久及臨時工程在環境上的可接受程度、相關的設計圖則和根據環監手冊及本許可證規定提交的文件。核實結果須記錄於每月環監報告;
(iii)
verifying the log-book(s) mentioned in Condition 2.3(iii). The IEC shall sign off with a date on the
log-book after verification.
核實條件第2.3 (iii) 項所述的記錄冊。核實後獨立環境查核人須於記錄冊上簽署;
(iv)
notifying the Director by fax or email, within one
working day of receipt of notification from the ET Leader, or identification by
the IEC and his team, of each and every change of circumstances or suspected
and/or potential non-compliance with the recommendations (such as construction
methods, mitigation measures, and environmental standards) of the approved EIA
Report (Register No. AEIAR-256/2023), the EM&A Manual and this Permit,
which might affect the monitoring or control of adverse environmental impacts
arising from the Project. Notification by the Permit Holder is the same
as notification by the IEC for the purpose of this Condition;
在每次出現情況變化或懷疑及/或可能不符合核准環評報告 (登記冊編號: AEIAR-256/2023) 的建議 (例如施工方法、緩解措施及環境標準)、環監手冊及本許可證的情況,而可能會妨礙對工程項目所造成的不良環境影響作出監察或控制時,獨立環境查核人須在接獲環境小組組長通知或獨立環境查核人及其支援小組確定情況後1個工作天內以傳真或電郵方式通知署長。為執行本條件,許可證持有人的通知等同獨立環境查核人的通知;
(v)
liaising closely with the Director;
與署長密切聯繫;
(vi)
accompanying the Director in carrying out site
inspections and attending meetings when requested;
按要求陪同署長進行實地視察及出席會議;
(vii) offering objective and
professional advice on environmental issues, when requested, and to respond to
questions and enquiries from the Director on the project, the EM&A programme and
duties discharged by the IEC, with the support of relevant information,
documents and records as appropriate; and
按要求就環境問題提供客觀及專業意見,並提供合適的相關資料、文件和記錄,以回應署長就環監計劃及獨立環境查核人所執行之職務提出的問題及查詢;以及
(viii) allocating adequate
resources, including any necessary specialist support, for discharging the
duties required in the EM&A Manual and/or this Permit.
分配足夠資源,包括所需的專業支援,以執行本許可證及/或環監手冊規定的各項職務。
2.10 If the
Director considers the IEC fails to discharge the duties of the IEC as defined
in the EM&A Manual or in this Permit, the Director may require the Permit
Holder by notice in writing to replace the IEC. Failure to replace the
IEC as directed or further failure to so notify the Director despite employment
of a new IEC may render this Permit liable to suspension, cancellation or
variation.
如署長認為獨立環境查核人未能執行環監手冊或本許可證所列明的獨立環境查核人職務,署長可藉書面通知要求許可證持有人撤換獨立環境查核人。如未能按指示撤換獨立環境查核人,或在聘用新獨立環境查核人後仍未能通知署長有關情況,則或會導致本許可證遭暫時吊銷、取消或更改。
Setting
up of Community Liaison Group(s)
設立社區聯絡小組
2.11 The Permit Holder shall, no
later than 1 month before the commencement of construction of the corresponding parts of the Project, set up a community liaison group, comprising representatives of affected parties,
including local committees, residents and schools in the affected areas along
the alignment, for maintaining regular communication with the
local and relevant stakeholders on issues concerning noise, air, waste
management and landscape, etc. arising from the Project, and handling
complaints on environmental issues related to the Project. The Permit Holder
shall take a proactive approach to disseminate information to the group,
promote community cooperation and participation and implement suitable local
environmental enhancement works. All relevant information of the Project
including the progress of construction and operation and environmental
monitoring and audit results should be provided to the group. Designated complaint hotlines
shall be set up for the project to address related concerns and enquiries in an
efficient manner. The Permit Holder shall
inform the Director in writing the membership and terms of reference of the
group.
許可證持有人須在工程項目相關部分的建造工程展開前最少1個月,設立一個由受影響各方的代表組成的社區聯絡小組,成員包括地區委員會及沿線受影響地區的居民和學校代表,以便就工程項目所帶來的噪音、空氣、廢物管理和景觀等問題,與地區及相關持份者保持定期溝通,以及處理與工程項目的環境問題有關的投訴。許可證持有人須採取積極主動的做法,向聯絡小組傳遞資訊、推動社區合作和參與,並進行適當的地區環境改善工程。工程項目的所有相關資料,包括建造及營辦進度、環境監察及審核結果,均須提供予聯絡小組。許可證持有人須為工程項目設立指定的投訴熱線,以便迅速處理公眾所關注的事宜和查詢。許可證持有人須以書面通知署長有關聯絡小組的成員名單和職權範圍。
Submission
of Construction Works Phasing Schedule(s)
提交施工分段時間表
2.12 The Permit Holder shall, no
later than 3 months before the commencement of construction of the corresponding parts of the Project, deposit 2 hard copies and 2 electronic copies of a Construction Works
Phasing Schedule (the Schedule) with the Director. The Schedule shall include
at least the following information:
許可證持有人須在工程項目相關部分的建造工程展開前最少3個月,把施工分段時間表(時間表)的2份硬複本及2份電子複本送交署長存放。時間表須至少包括下列資料:
(i)
a
detailed works programme showing the planned timing for the commencement and completion
of the major construction works including the phased implementation programme
for the project; and the number of Works Contract(s) involved under the
Project; and
詳細工作計劃,須顯示預計每個工作階段內主要建造工程的開始及完成時間,包括工程項目的階段性實施計劃;以及建造工程合約的數量;以及
(ii)
location
plan(s) in appropriate scale delineating the works boundary and works areas of
each Works Contract of the Project.
以合適比例繪製的位置圖,須描述工程項目每個建造工程合約的工地界線及工程範圍。
Submission
of Environmental Permit (EP) Submission Schedule(s)
提交環境許可證文件的提交時間表
2.13 The
Permit Holder shall, no later than 3 months before the commencement of
construction of the corresponding
parts of the Project, submit an EP Submission Schedule to the Director to set out a
timeline for EP submissions in this Permit, and shall report the progress in
fulfilling the submission requirements in the monthly Environmental Monitoring
and Audit (EM&A) reports submitted under Condition 3.4 of this Permit. The
Permit Holder shall inform the Director no later than 2 weeks before the
scheduled submission date of the EP submission in writing in case of any
subsequent change(s) to the submitted EP Submission Schedule. The EP Submission
Schedule or any subsequent change(s) to the submitted Schedule shall be
certified by the ET Leader and verified by the IEC before submitting to the
Director under this Permit.
許可證持有人須在工程項目相關部分的建造工程展開前至少提早3個月,向署長提交環境許可證文件的提交時間表,以制定本許可證所要求的文件的提交時間,並須在根據本許可證條件第3.4項提交的每月環監報告中,匯報文件提交的進度。倘若環境許可證文件的提交時間表的內容在提交後有任何更改,許可證持有人須在提交文件的預定提交日期前至少提早2個星期,就有關更改以書面通知署長。環境許可證文件的提交時間表或已提交的時間表其後有任何更改,均須由環境小組組長核證及獨立環境查核人核實,然後才按本許可證規定向署長提交。
Submission of Management Organization(s)
提交管理架構
2.14 The Permit Holder shall, no later than 1
month before the commencement of construction of the corresponding parts of the Project, inform the Director in writing with the following information:
許可證持有人須在工程項目相關部分建造工程展開前最少1個月把以下資料,以書面通知署長:
(i)
the management organization of the main
construction companies and/or any form
of joint ventures associated with the construction of the Project;
主要建造公司及/或以任何形式與工程項目建造工程相關的合營企業的管理架構;
(ii)
the management organization of the ET;
環境小組的管理架構;
(iii)
the management organization of the IEC
and his supporting team; and
獨立環境查核人及其支援小組的管理架構;以及
(iv)
the submitted information shall
include at least an organization chart, names of responsible persons and
their contact details.
提交的資料須至少包括一份組織圖、負責人的姓名及聯絡資料。
Submission of Construction Noise Management Plan(s)
提交建築噪音管理計劃
2.15 The
Permit Holder shall, no later than 2 months before the issuance of the tender
invitation of any part of the Project, if any, and before the commencement of
any construction works for that part of the Project, deposit with the Director
2 hard copies and 2 electronic copies of a
Construction Noise Management Plan (CNMP). Any CNMP deposited before the
issuance of the tender invitation shall be included in the tender document
unless otherwise agreed by the Director. If there is any change to the
construction noise mitigation measures and/or plant inventory in the CNMP, the
Permit Holder shall, no later than 1 month before the implementation of any
such change, deposit with the Director 2 hard copies and 2 electronic copies of an updated CNMP. The CNMP / updated CNMP shall identify the noise
source inventory, assess the effectiveness of construction noise mitigation
measures as recommended in the approved EIA Report (Register No. AEIAR-256/2023),
and include an implementation schedule in table form to list out the mitigation
measures to be implemented as well as the responsible party, location, timing
and environmental performance required for the implementation of the mitigation
measures. The CNMP / updated CNMP shall be prepared and checked by a Certified
Noise Modelling Professional as recognized by the Hong Kong Institute of
Qualified Environmental Professionals Limited (HKIQEP), or other professional
as agreed by the Director. The CNMP / updated CNMP shall be certified by the ET
Leader and verified by the IEC as conforming to the relevant information and
recommendations of the approved EIA Report (Register No. AEIAR-256/2023). All mitigation measures recommended and
requirements specified in the CNMP / updated CNMP shall be fully implemented.
許可證持有人須在工程項目的任何部分發出招標文件之前(如有),以及在該部分的建造工程展開前,最少2個月,把建築噪音管理計劃的2份硬複本及2份電子複本送交署長存放。除非另獲署長同意,任何在發出招標文件之前送交署長存放的建築噪音管理計劃均應包含在招標文件中。如已提交的建築噪音管理計劃內的建築噪音緩解措施及/或設備清單有任何更改,許可證持有人須在落實任何更改事項前最少1個月把更新的建築噪音管理計劃的2份硬複本及2份電子複本送交署長存放。建築噪音管理計劃/更新的建築噪音管理計劃須確定噪音源清單、評估核准環評報告 (登記冊編號: AEIAR-256/2023) 所建議的建築噪音緩解措施的成效,並提供一份實施時間表,以列表形式列出將會實施的緩解措施,以及實施緩解措施的負責方、地點、時間和須達到的環境表現規定。建築噪音管理計劃/更新的建築噪音管理計劃須由香港合資格環保專業人員學會(香港環專會)的認可噪音模擬專業人員或由署長同意的其它專業人員擬備及查核。建築噪音管理計劃/更新的建築噪音管理計劃須由環境小組組長核證,並經獨立環境查核人核實,確定符合核准環評報告(登記冊編號: AEIAR-256/2023)載列的相關資料及建議。建築噪音管理計劃/更新的建築噪音管理計劃中建議的所有緩解措施及指明的規定均須全面予以實施。
Submission of Fixed Noise Sources Management Plan(s)
提交固定噪音管理計劃
2.16 The Permit Holder shall,
no later than 2 months before the issuance of tender invitation of the
corresponding parts of the Project, if any, and before commencement of
implementation of the corresponding parts of the Project, deposit with the
Director 2 hard copies and 2 electronic copies of a Fixed Noise Sources
Management Plan (FNMP). Any FNMP deposited before the issuance of tender
invitation shall be included in the tender document unless otherwise agreed by
the Director. If there is any change to the specifications of the planned fixed
plant, layout design, operation modes, mitigation measures, or any other changes that could have adverse
implications on the fixed noise sources impact as concluded in the FNMP, the
Permit Holder shall, no later than 1 month before the implementation of any
such change, deposit with the Director 2 hard copies and 2 electronic copies of
an updated FNMP. The FNMP / updated FNMP shall identify the noise source
inventory, assess the effectiveness of fixed noise mitigation measures as
recommended in the approved EIA Report (Register No. AEIAR-256/2023), including
(i) louvres shall be orientated away from adjacent noise
sensitive receivers, and (ii) façade for these ventilation shafts shall have
adequate sound insulation properties. The
FNMP / updated FNMP shall include an implementation schedule in table form to
list out the mitigation measures to be implemented, as well as the responsible
party, location, timing and environmental performance required for the
implementation of the mitigation measures. The FNMP / updated FNMP shall be
prepared and checked by a Certified Noise Modelling Professional as recognized
by the HKIQEP, or other professional as agreed by the Director. The FNMP /
updated FNMP shall be certified by the ET Leader and verified by the IEC as
conforming to the relevant information and recommendations of the approved EIA
Report (Register No. AEIAR-256/2023). All mitigation measures recommended and
requirements specified in the FNMP / updated FNMP shall be fully implemented.
許可證持有人須在工程項目的相關部分發出招標文件之前(如有),以及在工程項目相關部分開始營運前,最少2個月,把固定噪音源管理計劃的2份硬複本及2份電子複本送交署長存放。除非另獲署長同意,任何在發出招標文件前送交署長存放的固定噪音源管理計劃均應包含在招標文件中。如已提交的固定噪音源管理計劃內的固定噪音設備規格、佈局設計、運作模式、緩解措施有任何更改,或有任何其他更改會令計劃中得出的固定噪音源影響造成不良影響,許可證持有人須在落實任何更改事項前最少1個月把更新的固定噪音源管理計劃的2份硬複本及2份電子複本送交署長存放。固定噪音源管理計劃/更新的固定噪音源管理計劃須確定噪音源清單、評估核准環評報告(登記冊編號: AEIAR-256/2023)所建議的固定噪音緩解措施的成效,包括(i)百葉窗板的朝向須離開鄰近噪音感應強的地方的方向;以及(ii)通風井的外牆須有足夠的隔聲功能。固定噪音源管理計劃/更新的固定噪音源管理計劃須提供一份實施時間表,以列表形式列出將會實施的緩解措施,以及實施緩解措施的負責方、地點、時間和須達到的環境表現規定。固定噪音源管理計劃/更新的固定噪音源管理計劃須由香港環專會的認可噪音模擬專業人員或由署長同意的其它專業人員擬備及查核。固定噪音源管理計劃/更新的固定噪音源管理計劃須由環境小組組長核證,並經獨立環境查核人核實,確定符合核准環評報告(登記冊編號: AEIAR-256/2023)載列的相關資料及建議。固定噪音源管理計劃/更新的固定噪音源管理計劃中建議的所有緩解措施及指明的規定均須全面予以實施。
Submission
of Plant Preservation and Transplantation Proposal(s)
提交植物保護及移植建議書
2.17 The Permit Holder shall, no later than 1 month
before commencement of site clearance works of the corresponding parts of the
Project, deposit with the Director 2 hard copies and 2 electronic copies of a Plant Preservation and Transplantation
Proposal (PPTP). The PPTP shall (i) report the
detailed vegetation survey methodology and results (including the updated
condition, number, locations, species and habitat types of potentially affected
individuals of flora species of conservation importance within the works area, e.g. Diospyros vaccinioides and Gnetum luofuense within mixed woodland at Pillar Point and
near Wah Fat Playground respectively); and (ii) propose
preservation, transplantation and/or compensation plan for each affected
individual of flora species of conservation importance (including methodology,
suitable receptor site and implementation, monitoring and maintenance programme). The Permit Holder shall consult Agriculture,
Fisheries and Conservation Department (AFCD) on the survey methodology before
conducting the survey.
許可證持有人須在工程項目相關部分的開始工地清理前最少1個月,把植物保護及移植建議書的2份硬複本及2份電子複本送交署長存放。植物保護及移植建議書須 (i)
報告詳細植物調查的方法及結果 (包括在施工範圍裡受潛在影響的具保育價值的植物的最新狀況、數量、位置、物種及生境類別,例如分別位於望后石及華發遊樂場附近混合林地的小果柿及羅浮買麻藤);以及 (ii) 就個別受工程影響的具保育價值的植物建議原址保育、移植及/或補償方案 (包括方法、合適的接收地點及其執行、監察及保養計劃等)。許可證持有人須在進行調查前就調查方法徵詢漁農自然護理署 (“漁護署”) 意見。
2.18 The PPTP submitted
under Condition 2.17 shall include an implementation schedule in table form to
clearly list out the mitigation measures to be implemented, and the
implementation party, location, timing, and environmental performance required
for implementation of the mitigation measures. The PPTP shall be prepared by
the qualified ecologist/botanist as appointed under Condition 2.5 and shall be
certified by the ET Leader and verified by the IEC as conforming to the
information and recommendations contained in the approved EIA Report (Register
No. AEIAR-256/2023). All measures recommended in the PPTP shall be fully
implemented.
本許可證條件第2.17項規定提交的植物保護及移植建議書須包括以列表形式列出的實施時間表,清楚列明將會執行的緩解措施、實施者、地點、時間,以及實施緩解措施時須達到的環境表現規定。植物保護及移植建議書須由按上文條件第2.5項規定聘用的合資格生態學家/植物學家擬備,並須由環境小組組長核證及獨立環境查核人核實,證明其符合核准環評報告 (登記冊編號:AEIAR-256/2023) 所載的資料及建議。植物保護及移植建議書中建議的所有措施均須全面予以實施。
Submission
of Translocation Proposal(s) for Freshwater Crabs
提交淡水蟹遷移建議書
2.19 The
Permit Holder shall, no later than 1 month before the commencement of
construction of the corresponding parts of the Project, deposit with the
Director 2 hard copies and 2 electronic copies of a Translocation Proposal for
Freshwater Crabs (Translocation Proposal) for Watercourse S2 to be directly
impacted. The Translocation Proposal shall (i) report
the pre-construction freshwater crab survey methodology and results; and (ii)
propose translocation plan for any individual(s) of freshwater crab species of conservation importance
to be directly impacted. The translocation plan should include capture and
translocation methodology, suitable receptor site, implementation programme, post-translocation monitoring programme and contingency plan. The translocation exercise
should be implemented prior to the commencement of watercourse diversion. The Translocation
Proposal shall be prepared by the qualified ecologist as appointed under
Condition 2.5, certified by the ET Leader and verified by the IEC as conforming
to the relevant information and recommendations of the approved EIA Report
(Register No. AEIAR-256/2023). All
measures recommended in the Translocation Proposal shall be fully implemented.
The Permit Holder shall consult AFCD on the survey methodology before
conducting the survey.
許可證持有人須在工程項目相關部分建造工程展開前最少1個月,把將會直接受影響的S2水道的淡水蟹遷移建議書(遷移建議書)的2份硬複本及2份電子複本送交署長存放。遷移建議書須 (i) 報告在施工前淡水蟹調查的方法及結果;以及 (ii) 就任何會受直接影響的具保育價值淡水蟹建議遷移方案。遷移方案須包括捕撈及遷移方法、合適的接收地點、實施計劃、遷移後的監察計劃及應變計劃。遷移行動須在水道改道展開前實施。遷移建議書須由按上文條件第2.5項聘用的合資格生態學家擬備,並由環境小組組長核證及獨立環境查核人核實,以確定符合核准環評報告 (登記冊編號:AEIAR-256/2023) 載列的相關資料及建議。遷移建議書的所有建議的措施,均須全面予以實施。許可證持有人須在進行調查前,就調查方法徵詢漁護署意見。
Submission of Woodland Compensation Implementation Plan(s)
提交林地補償實施計劃
2.20 The
Permit Holder shall, no later than 1 month before the commencement of
construction of the Project or otherwise agreed by the Director, deposit with
the Director 2 hard copies and 2 electronic copies of a Woodland Compensation
Implementation Plan. The Woodland Compensation Implementation Plan shall
provide details of the woodland compensation for the permanent loss of mixed
woodland under the Project in a ratio of no less than 1:1 in terms of area. The
Woodland Compensation Implementation Plan shall include an implementation
schedule in table form to clearly list out the mitigation measures to be
implemented, and the implementation party, location, timing, and environmental
performance required for implementation of the mitigation measures. The
Woodland Compensation Implementation Plan shall be prepared by the qualified
ecologist/arborist as appointed under Condition 2.5, certified by the ET Leader
and verified by the IEC as conforming to the relevant information and
recommendations of the approved EIA Report (Register No. AEIAR-256/2023). The
Permit Holder shall consult AFCD on the details of woodland compensation prior
to submission to the Director. If there is any subsequent change to the
Woodland Compensation Implementation Plan, the Permit Holder shall, no later
than 1 month before the implementation of any such change, deposit with the
Director 2 hard copies and 2 electronic copies of an updated Woodland
Compensation Implementation Plan. All measures recommended in the Woodland
Compensation Implementation Plan / updated Woodland Compensation Implementation
Plan shall be fully implemented.
許可證持有人須在工程項目的建造工程展開前最少1個月或另獲署長同意,把林地補償實施計劃的2份硬複本及2份電子複本送交署長存放。林地補償實施計劃須詳述就面積不少於1:1的比例,補償工程項目所造成的永久性混合林地損失的方案。林地補償實施計劃須包括以列表形式列出的實施時間表,清楚列明將會執行的緩解措施、實施者、地點、時間,以及實施緩解措施時須達到的環境表現規定。林地補償實施計劃須由按上文條件第2.5項規定聘用的合資格生態學家/樹藝師擬備,並須由環境小組組長核證及獨立環境查核人核實,證明其符合核准環評報告 (登記冊編號:AEIAR-256/2023)
所載的資料及建議。許可證持有人須就林地補償的細節徵詢漁護署意見,然後才向署長提交林地補償實施計劃。如林地補償實施計劃其後有任何更改,許可證持有人須在落實任何更改事項前最少1個月,把更新的林地補償實施計劃的2份硬複本及2份電子複本送交署長存放。林地補償實施計劃/更新的林地補償實施計劃中所有建議的措施,均須全面予以實施。
Submission
of Land Contamination Assessment(s)
提交土地污染評估
2.21 The
Permit Holder shall carry out detailed land contamination assessment(s) at the
concerned facilities/areas identified in Appendix 7.1 of the approved EIA
Report (Register No. AEIAR-256/2023) and any area identified with potential
contamination issues (concerned areas). The Permit Holder shall submit 2 hard
copies and 2 electronic copies of supplementary Contamination Assessment
Plan(s) (CAP(s)), including a site re-appraisal for the whole Project Boundary,
to the Director for approval no later than 1 month before the commencement of
site investigation (SI) at the concerned areas. Further assessment(s) and
remediation works recommended in the approved supplementary CAP(s) shall be
implemented. All submissions shall be certified by the ET Leader and verified
by the IEC as conforming to the relevant information and recommendations
contained in the approved EIA Report (Register No. AEIAR-256/2023). No construction works (except demolition works of aboveground
structures) at the concerned areas shall be commenced before the approval of
supplementary CAP(s) by the Director and the satisfactory completion of
necessary decontamination works.
許可證持有人須在核准環評報告 (登記冊編號:AEIAR-256/2023) 附錄7.1所示的相關設施/地方以及任何發現有潛在污染問題的地方(有關地方)進行詳細土地污染評估。許可證持有人須在有關地方進行工地勘察前最少1個月向署長提交補充污染評估計劃(包括對整個工程項目範圍重新進行場地評估)的2份硬複本及2份電子複本,以供審批。許可證持有人須按照核准補充污染評估計劃的建議進行額外評估及清理工作。所有提交的文件須由環境小組組長核證及獨立環境查核人核實,證明其符合核准環評報告 (登記冊編號:AEIAR-256/2023) 所載的資料及建議。在補充污染評估計劃書獲署長批准及所需的除污工程圓滿完成前,不得在有關地方展開建造工程 (地面構築物的拆卸工程除外)。
Submission
of Landscape and Visual Mitigation Plan(s)
提交景觀及視覺影響緩解計劃
2.22 The
Permit Holder shall, no later than 2 months before the commencement of
construction of the corresponding parts of the Project, deposit with the
Director 4 hard copies and 2 electronic copies of a Landscape and Visual
Mitigation Plan (LVMP). If there is any change to the landscape and visual
mitigation measures in the deposited LVMP, the Permit Holder shall, no later
than 1 month before the implementation of such change, deposit with the
Director 4 hard copies and 2 electronic copies of an updated LVMP with clear
indication of the proposed change(s). The LVMP / updated LVMP shall show the
design details, locations, implementation programme,
maintenance and management schedules, and drawings in the scale of 1:1,000 or
other appropriate scale of the landscape and visual mitigation measures of the
Project. The LVMP / updated LVMP shall include an implementation schedule in
table form to clearly list out the mitigation measures to be implemented, and
the implementation party, location, timing, and environmental performance
required for implementation of the mitigation measures. The LVMP / updated LVMP
shall be prepared by the Registered Landscape Architect appointed under
Condition 2.6, certified by the ET Leader and verified by the IEC as conforming
to the relevant information and recommendations contained in the approved EIA
Report (Register No. AEIAR-256/2023), and provide adequate and relevant
justifications to support the change(s). All recommended measures and
requirements specified in the LVMP / updated LVMP shall be fully implemented.
許可證持有人須在工程項目相關部分的建造工程展開前最少2個月,把景觀及視覺影響緩解計劃(緩解計劃)的4份硬複本及2份電子複本送交署長存放。如已存放的緩解計劃所建議的景觀及視覺影響緩解措施有任何更改,許可證持有人須在實施有關更改前最少1個月,把已更新的緩解計劃的4份硬複本及2份電子複本送交署長存放,並清楚顯示擬議更改。緩解計劃/已更新的緩解計劃須包括工程項目的景觀及視覺影響緩解措施的設計詳情、所涉地點、實施計劃、保養及管理時間表,以及採用1:1,000的比例或署長同意的其他合適比例繪畫的圖則。緩解計劃/已更新的緩解計劃亦須包括以列表形式擬備的實施時間表,清楚列明將會實施的緩解措施、實施者、地點、時間,以及實施緩解措施時須達到的環境表現規定。緩解計劃/已更新的緩解計劃須由根據上文條件第2.6項聘用的註冊園境師擬備,並由環境小組組長核證和獨立環境查核人核實,確定符合核准環評報告 (登記冊編號: AEIAR-256/2023) 載列的相關資料及建議,以及提供充分的相關理據支持在已更新的緩解計劃中的更改的事項。緩解計劃/已更新的緩解計劃中所有建議的緩解措施及列明的規定,均須全面予以實施。
Measures
to be Implemented during Construction of the Project
工程項目建造期間須實施的措施
Measures to
Avoid Terrestrial Ecological Impact
避免陸上生態影響的措施
2.23 No aboveground construction works shall be
carried out at Tai Lam Country Park,
Siu Lang Shui Site of Special Scientific Interest and Lam Tei
and Yick Yuen Conservation Area to avoid direct ecological impact on these area.
工程項目建造期間不可在大欖郊野公園、小冷水具特殊科學價值地點和藍地及亦園自然保育區進行地面建造工程,以避免對這些地方造成直接生態影響。
Measures to Minimize Construction Dust Impacts
減少建築塵埃影響的措施
2.24 Drill-and-blast tunnelling activities shall be conducted in a fully
enclosed environment to minimize the construction dust impact.
鑽爆隧道爆破工程須在全封閉環境進行,以減少建築塵埃影響。
2.25 Particulate Matter (PM)
sensors shall be installed at construction dust monitoring locations in
construction sites, as specified in EM&A Manual or updated EM&A Manual
(if any), to conduct monitoring of Respirable Suspended Particulates (RSP) and Fine
Suspended Particulates (FSP) during the construction stage.
工程項目建造期間須根據環監手冊或更新的環監手冊(如有)所示的建造工地建築塵埃監測地點安裝懸浮粒子感應器,以監測施工階段的可吸入懸浮粒子及微細懸浮粒子。
Waste
Management Measures
廢物管理措施
2.26 All dump trucks and
vessels for waste transportation and disposal under the Project shall be
equipped with Global Positioning System (GPS) or equivalent automatic
identification system for real time tracking and monitoring of their travel
routings and parking locations in order to avoid illegal dumping or landfilling
of construction and demolition (C&D) materials.
所有用於工程項目運送和處置廢物的泥頭車和船隻,均須配備全球衞星定位系統或同等的自動識別系統,以實時追蹤及監察其行駛路線及停泊地點,防止非法棄置或堆填建築和拆卸物料。
3. Environmental Monitoring
and Audit (EM&A) Requirements
環境監察及審核規定
3.1 The Permit Holder shall
implement the EM&A programme in accordance with the procedures and requirements
as set out in the EM&A Manual. Any changes to the EM&A requirements or programme or termination of
the programme shall be justified by the ET Leader and verified by the IEC as
conforming to the information and requirements contained in the EM&A Manual
before submission to the Director for approval.
許可證持有人須按照環監手冊所載的程序及規定執行環監計劃。環監的規定或計劃如有更改或計劃如終止,須由環境小組組長提出理據並由獨立環境查核人核實,證明其符合環監手冊所載的資料及規定,然後才提交署長批准。
3.2 The Permit Holder shall take samples,
measurements and necessary remedial actions in accordance with the requirements
of the EM&A Manual by:
許可證持有人須按照環監手冊所載的規定,透過以下方法進行取樣、測量及所需的補救行動:
(i)
conducting baseline environmental monitoring;
進行環境基線監測;
(ii)
conducting impact monitoring;
進行影響監測;
(iii)
carrying out remedial actions described in the
Event/Action Plans of the EM&A Manual in accordance with the time frame set
out in the Event/Action Plans, or as agreed by the Director, in case where
specified criteria in the EM&A Manual are exceeded; and
如超逾環監手冊內指定的標準,則按照環監手冊內的事件/行動計劃所訂明的時限或署長所同意的時限,執行事件/行動計劃所說明的補救行動;以及
(iv)
logging and keeping records of the details of (i) to (iii) above for all parameters within 3 working days
of the collection of data or completion of remedial action(s), for the purpose
of preparing and submitting the monthly EM&A Reports and to make available
the information for inspection on site.
在收集數據或完成補救行動3個工作天內,須記錄及備存上文(i)至(iii)段所有參數的詳情,用作擬備及提交每月環監報告,並備妥有關資料以供在工地查閱。
3.3 The Permit Holder shall submit 1 hard copy and 1 electronic copy of Baseline Monitoring Reports to the
Director at least 2 weeks before the commencement of construction of the corresponding
parts of the Project. The
submissions shall be certified by the ET Leader and verified by the IEC as
having complied with the requirements as set out in the EM&A Manual before
submission to the Director. Additional copies of the Baseline Monitoring
Reports shall be provided upon request by the Director.
許可證持有人須在展開工程項目相關部分的建造工程前最少2個星期向署長提交基線監測報告的1份硬複本及1份電子版本。提交文件須由環境小組組長核證及獨立環境查核人核實,證明其符合環監手冊所載的規定,然後才提交署長。如署長要求,則須提交基線監測報告的額外複本。
3.4 The Permit Holder shall
submit 1 hard copy and 1 electronic
copy of Monthly EM&A Reports for the construction stage of the Project to
the Director, within 10 working days after the end of the reporting
month. The monthly EM&A Reports shall include an executive summary of all environmental audit results, together with
actions taken in the event of non-compliance
(exceedances) of the environmental quality performance limits (Action and Limit
Levels),
complaints received and emergency events relating to violation of environmental
legislation. The submissions shall
be certified by the ET Leader and verified by the IEC as having complied with
the requirements as set out in the EM&A Manual before submission to the
Director. Additional copies of the Monthly EM&A Reports shall be
provided upon request by the Director.
在每個提交報告的月份結束後10個工作天內,許可證持有人須向署長提交工程項目建築階段每月環監報告的1份硬複本及1份電子版本。每月環監報告須包括各項環境審核結果,以及在發生不符合(超出)環境質素表現規限(行動及極限水平)情況時所採取的行動、接獲有關違反環境法例的投訴及發生相關緊急事件的行政摘要。提交的報告須由環境小組組長核證及獨立環境查核人核實,證明其符合環監手冊所載的規定,然後才提交署長。如署長要求,則須向署長提交每月環監報告的額外複本。
3.5 All
environmental monitoring and audit data submitted under this Permit shall be
true, valid and correct.
根據本許可證提交的所有環監數據,均須有效及真實無誤。
3.6 To ensure a high degree of transparency
regarding the monitoring data and results in view of the public concern about
the Project, all environmental monitoring and audit data and results and all
submissions and all performance test data and results required by this Permit
shall be made available by the Permit Holder to the public through a dedicated
website to be set up by the Permit Holder under Condition 4.2 below, in the
shortest practicable time and in no event later than 10 working days after such
information is available.
基於公眾對工程項目的關注,為確保監察數據和結果具高透明度,許可證持有人須盡快把各項環境監察及審核數據和結果、本許可證規定的所有提交文件及各項表現測試數據和結果,透過按下文條件第4.2項由許可證持有人設立的特定網站供公眾閱覽,在任何情況下均不得遲於這些資料可供閱覽後的10個工作天。
4. Electronic Reporting of EM&A Information
環監資料的電子匯報
4.1 To facilitate public inspection of the
Baseline Monitoring Report and Monthly EM&A Reports via the EIAO Internet
Website and at the EIAO Register Office, electronic copies of these Reports
shall be prepared in Hyper Text Markup Language
(HTML) (version 4.0 or later) and in Portable Document Format (PDF version 1.3
or later), unless otherwise agreed by the Director and shall be submitted at
the same time as the hard copies as described in Conditions 3.3 and 3.4 above. For the HTML
version, a content page capable of providing hyperlink to each section and
sub-section of these Reports shall be included in the beginning of the
document. Hyperlinks to all figures, drawings and tables in these Reports shall
be provided in the main text from where the respective references are
made. All graphics in these Reports shall be in interlaced GIF, JPEG or PDF format unless otherwise agreed by the Director. The content of
the electronic copies of these Reports must be the same as the hard copies.
為方便公眾透過環評條例互聯網網站及在環評條例登記冊辦事處查閱基線監測報告及每月環監報告,除非另獲署長同意,否則該等報告的電子複本須以超文本標示語言(HTML)(第4.0或較後版本)及便攜式文件格式(PDF)(第1.3或較後版本)擬備,並須與上文條件第3.3及3.4項所說明的硬複本同時提交。關於HTML的版本方面,須在文件開端加入可與報告各節及小節作出超文本連結的目錄。報告內的正文如有任何相關的參考資料,須建立超連結以連結至報告所載的相關數據和圖表。除非另獲署長同意,否則報告內所有圖像均須以交錯存取的GIF、JPEG或PDF格式制定。報告的電子複本內容,必須與硬複本的內容一致。
4.2 The Permit Holder shall,
within 4 weeks after the commencement of construction of the corresponding
parts of the Project, set up a
dedicated Internet website and notify the Director in writing the Internet
address where the environmental monitoring data and project information is to be placed. All environmental monitoring data described in
Condition 4.1 above shall be made available to the public via the
abovementioned dedicated Internet website in the shortest possible time and in
any event no later than 2 weeks after the relevant environmental monitoring
data are collected or become available, unless otherwise agreed with the
Director. All finalized submissions and plans shall be made available to the
public via the dedicated Internet website in the shortest possible time and in
any event no later than 2 weeks after the submissions and plans are approved by
or deposited with the Director, unless otherwise agreed with the Director. The Permit Holder shall maintain the dedicated
website for public access of the environmental monitoring data and reports
throughout the entire construction period and during the first 3-year period of
operation of the Project, or otherwise as agreed by the Director.
許可證持有人須在工程項目相關部分的建造工程展開後4個星期內,設立特定網站存放環境監察數據及工程項目資料,並以書面通知署長互聯網網址所在。除非另獲署長同意,上文條件第4.1項說明的所有環境監察數據,均須盡快透過上述特定互聯網網站供公眾閱覽,在任何情況下均不得遲於有關資料在收集或可供發放後的2個星期內上載至該特定網站。所有提交文件及圖則定稿,均須盡快透過該特定互聯網網站供公眾閱覽,在任何情況下均不得遲於有關提交文件及圖則獲署長核准或向署長存放後的2個星期,除非另獲署長同意。許可證持有人須在工程項目整個施工期內及首3年營辦期內,或署長同意的其他期間,維持該特定網站,供公眾接達有關環境監察數據及報告。
4.3 The Internet
website as described in Condition 4.2 above shall enable user-friendly public
access to the environmental monitoring data and project information including
the Project Profile, EIA Report and Environmental Permit(s). The Internet website shall have features capable of:
上文條件第4.2項說明的互聯網網站,必須方便用戶使用,讓公眾容易接達環境監察數據及工程項目資料,當中包括工程項目簡介,環評報告及環境許可證。除非另獲署長同意,互聯網網站須具備部件,提供下述功能:
(i)
providing access to all environmental monitoring data
of this Project collected since the commencement of construction;
接達建造工程展開後所收集的全部環境監察數據;
(ii)
searching by date;
按日期搜尋;
(iii)
searching by types of
monitoring data; and
按監察數據類別搜尋;以及
(iv)
hyperlinking to relevant
monitoring data after searching
在搜尋後與相關的監察數據作出超文本連結。
or otherwise as agreed
by the Director.
Notes:
註:
1. This Permit consists of three parts,
namely, Part A (Main Permit), Part B (Description of Designated
Project) and Part C (Permit Conditions).
Any person relying on this Permit should obtain independent legal advice
on the legal implications under the EIAO, and the following notes are for
general information only.
本許可證共有3部,即 A部 (許可證主要部分);B部 (指定工程項目的說明) 及C部 (許可證條件)。任何援引本許可證的人士須就環評條例的法律含意徵詢獨立法律意見,下述註解只供一般參考用。
2. If there is a breach of any condition
of this Permit, the Director or his authorized officer may, with the consent of
the Secretary for Environment and Ecology,
order the cessation of associated work until the remedial action is taken in
respect of the resultant environmental damage, and in that case the Permit
Holder shall not carry out any associated works without the permission of the
Director or his authorized officer.
如違反本許可證的任何條件,署長或獲授權人員徵得環境及生態局局長的同意後可勒令停止相關工程,直至許可證持有人為所造成的環境損害採取補救行動為止。在此情況下,許可證持有人未經署長或獲授權人員同意,不得進行任何相關工程。
3. The Permit Holder may apply under
Section 13 of the EIAO to the Director for a variation of the conditions of
this Permit. The Permit Holder shall replace the original permit displayed on
the Project site by the amended permit.
許可證持有人可根據環評條例第13條的規定向署長申請更改本環境許可證的條件。許可證持有人須以經修改的許可證替換在工程項目工地內展示的原有許可證。
4. A person who assumes the responsibility
for the whole or a part of the Project may, before he assumes responsibility of
the Project, apply under Section 12 of the EIAO to the Director for a further
environmental permit.
承擔工程項目整項或部分工程的責任的人,在承擔責任之前,可根據環評條例第12條的規定向署長申請新的環境許可證。
5. Under Section 14 of the EIAO, the
Director may with the consent of the Secretary
for Environment and Ecology, suspend, vary or cancel this Permit. The
suspended, varied or cancelled Permit shall be removed from display at the
Project site.
根據環評條例第14條的規定,署長可在取得環境及生態局局長的同意下暫時吊銷、更改或取消本許可證。遭暫時吊銷、更改或取消的許可證必須從工程項目工地除下,不再展示。
6. If this Permit is cancelled or
surrendered during construction or operation of the Project, another
environmental permit must be obtained under the EIAO before the Project could
be continued. It is an offence under Section
26(1) of the EIAO to construct or operate a designated project listed in Part I
of Schedule 2 of the EIAO without a valid environmental permit.
如果本許可證在工程項目建造或營辦期間取消或交回,則在繼續進行工程項目之前,必須先根據環評條例規定取得另一份環境許可證。根據環評條例第26(1)條的規定,任何人在沒有有效環境許可證的情況下建造或營辦環評條例附表2第I部所列明的指定工程項目,即屬犯罪。
7. Any person who constructs or operates
the Project contrary to the conditions in this Permit, and is convicted of an
offence under the EIAO, is liable:
(i)
on a first conviction on indictment to a fine of $2 million
and to imprisonment for 6 months;
(ii)
on a second or subsequent conviction on indictment to a
fine of $5 million and to imprisonment for 2 years;
(iii)
on a first summary conviction to a fine at level 6 and to
imprisonment for 6 months;
(iv)
on a second or subsequent summary conviction to a fine of
$1 million and to imprisonment for 1 year; and
(v)
in any case where the offence is of a continuing nature,
the court or magistrate may impose a fine of $10,000 for each day on which he
is satisfied the offence continued.
如任何人在違反本許可證的條件下建造或營辦工程項目,且被裁定觸犯環評條例所訂明的罪行,即屬犯罪:
(i)
一經循公訴程序首次定罪,可處罰款200萬元及監禁6個月;
(ii)
一經循公訴程序第二次或其後每次定罪,可處罰款500萬元及監禁2年;
(iii)
一經循簡易程序首次定罪,可處第6級罰款及監禁6個月;
(iv)
一經循簡易程序第二次或其後每次定罪,可處罰款100萬元及監禁1年;以及
(v)
在任何情況下如該罪行屬持續性質,法院或裁判官可就其信納該罪行持續的每天另處罰款10,000元。
8. The Permit Holder may appeal against
any condition of this Permit under Section 17 of the EIAO within 30 days of
receipt of this Permit.
許可證持有人可在接獲本許可證後30天內,根據環評條例第17條就本許可證的任何條件提出上訴。
9. The Notes are for
general reference only and that the Permit Holder should refer to the EIAO for
details and seek independent legal advice.
上述註解只供一般參考用,欲知有關詳情,許可證持有人須參閱環評條例及徵詢獨立法律意見。