Further Environmental Permit No. FEP-03/004/1999
新的環境許可證編號FEP-03/004/1999
ENVIRONMENTAL IMPACT ASSESSMENT ORDINANCE
環境影響評估條例
(第499章)
第12條
FURTHER ENVIRONMENTAL PERMIT TO CONSTRUCT A PART OF THE DESIGNATED PROJECT
就建造指定工程項目其中部分而發出新的環境許可證
PART A (MAIN PERMIT)
A 部 (許可證主要部分)
Pursuant to section 12 of the Environmental Impact Assessment Ordinance, the Director of Environmental Protection (the Director) grants this Further Environmental Permit to DRAGAGES-ZEN PACIFIC JOINT VENTURE (the "Permit Holder") to construct a part of the designated project described in Part B subject to the conditions described in or attached to Part C. The issue of this Further Environmental Permit is based on the documents, approvals or permissions described below:
根據環境影響評估條例第12條的規定,環境保護署署長(署長)將本新的環境許可證批予DRAGAGES-ZEN PACIFIC JOINT VENTURE(許可證持有人)以建造B部所說明的指定工程項目其中部分,但須遵守C部所說明或附載的條件。本新的環境許可證的發出,乃以下表所列的文件、批准或許可作為根據:
Application No.
|
FEP-003/1998 |
Documents in the Register :
|
|
___________________
|
______________________________________
|
PART B (DESCRIPTION OF THE PART OF THE DESIGNATED PROJECT)
Hereunder is the description of the part of the designated project mentioned in Part A of this further environmental permit :-
下列為本新的環境許可證A部所提述的指定工程項目本部分的說明:—
Title of the Part of the Designated Project
|
Kowloon-Canton Railway Corporation-West Rail Phase I Contract No. DB320 Kwai Tsing Tunnels
九廣鐵路公司─西鐵第一期
|
Nature of the part of the Designated Project
|
Construction of railway alignment in tunnel between Mei Foo Station and Tsuen Wan Station of the West Rail Phase I 建造西鐵第一期美孚站與荃灣站之間的隧道鐵路段 |
Location of the Part of the Designated Project
|
From Chainage Ch 14269 in Tsuen Wan to Ch 10679.334 in Mei Foo
由荃灣鏈距Ch 14269 至美孚鏈距Ch 10679.334
|
Scale and Scope of the Part of the Designated Project
|
The works involve railway alignment in tunnels, but excluding any non-railway development above the railway property. The 4 sections of the DB320 Kwai Tsing Tunnels are described below: Cheung Ching Tunnel: This short section of tunnel forms the interface between DB320 and the adjacent CC400 Mei Foo Station Contract. Ha Kwai Chung Tunnel: Ha Kwai Chung Tunnel runs from just north of Mei Foo Station to south of Kwai Chung Road in the north. Kwai Chung Nullah Tunnel: The section runs beneath Kwai Chung Road and passes below a five cell nulllah and a single cell box culvert that runs parallel with the road. Tsing Tsuen Tunnel: The Tunnel runs from Kwai Chung Road in Kwai Fong area to the north of the Wah Kai Industrial Building. 工程涉及在隧道內的鐵路路線,但不包括在鐵路物業上蓋與鐵路無關的發展。DB320葵青隧道的4段說明如下:
長青隧道:這段短的隧道,構成 下葵涌隧道:下葵涌隧道是從貼近美孚站以北向北伸延至葵涌道以南。
葵涌明渠隧道:這隧道段沿葵涌道之下伸延,在一條五格明渠以及與葵涌道平行伸延的單格箱形暗渠之下穿過。
青荃隧道:這隧道從葵芳區葵涌道伸延至華基工業大廈以北。
|
PART C (PERMIT CONDITIONS)
1. General Conditions
1.1 The Permit Holder shall ensure full compliance with all conditions of this Further Environmental Permit (the Permit). Any non-compliance with this Permit may constitute a contravention of the Environmental Impact Assessment Ordinance (Cap. 499) and shall be definite ground for enforcement action or permit cancellation where applicable.
1.2 This Permit shall not remove the responsibility of the Permit Holder to comply with any legislation currently in force such as Noise Control Ordinance (Cap.400), Air Pollution Control Ordinance (Cap.311), Water Pollution Control Ordinance (Cap.358), Dumping at Sea Ordinance (Cap.466), the Waste Disposal Ordinance (Cap.354) and others.
1.3 The Permit Holder shall make copies of this Permit available at all times for inspection by the Director at all sites covered by this Permit.
1.4 The Permit Holder shall give a copy of this Permit to the person(s) in charge of the site(s).
1.5 The Permit Holder shall display a copy of this Permit on the construction site(s) at all vehicular site entrances/exits for public information at all times. The Permit Holder shall ensure that the most updated information about the environmental permit, including any amended permit, is displayed at such locations. If the Permit Holder surrenders a part or the whole of the Permit, the notice he sends to the Director of Environmental Protection shall also be displayed at the same locations as the original Permit.
1.6 The Permit Holder shall construct the Project in accordance with the project descriptions in Part B of this Permit.
1.7 The Permit Holder shall ensure that the Project is designed and constructed in accordance with the information and recommendations contained in the EIA report.
1.8 This Permit shall not remove the responsibility of any person to comply with the conditions set out in Part C of the Environmental Permit No. EP-004/1998.
1.9 The requirements of Environmental Manager and Independent Environmental Checker, as required under this Permit, are described in conditions 2.1 and 2.2 of the Environmental Permit No. EP-004/1998.
1.10 Approved plans, schedules, reports, drawings or programmes mentioned in this Permit shall refer to those that have been approved by the Director.
1.11 All deposited submissions, as required under this permit, shall be rectified in accordance with the comments, if any, made by the Director within one month of the receipt of the Director's comments or otherwise specified by the Director.
1.12 All finalised submissions, as required under this permit, shall be released to the public if requested by the Director, by depositing copies in the Environmental Impact Assessment Ordinance Register Office or any other places or by any other means as specified by the Director for public inspection. For this purpose, the Permit Holder shall provide sufficient copies of submissions.
2. Submissions or Measures before Commencement of Construction of Certain Sections of the Project
2.1 An Environmental Team as recommended is the EM&A Manual shall be in place prior to the commencement of construction of the Project, described in Part B of this Permit. The Environmental Team shall be headed by a team leader who has at least 7 years experience in environmental monitoring or environmental management.
2.2 Before the commencement of construction of the Project described in Part B of this Permit, 3 sets of 1 to 1000 scale layout drawing shall be made available to and deposited with the Director. The layout drawings shall include an explanatory statement showing the works boundary, railway and tunnel alignment, environmental mitigation measures recommended in the EIA report, and any other facilities assessed in the EIA report. The drawings shall be certified by the Environmental Manager and verified by the Independent Environmental Checker as conforming to the findings and recommendations of the EIA report. The Project shall be constructed in accordance with the information and recommendations contained in the EIA report and the drawings deposited with the Director. All measures set out in the drawings shall be fully implemented.
2.3 Before the commencement of the construction on or in potential contaminated sites, the Permit Holder shall submit and obtain approval of the Director for the Contamination Assessment Plans (CAP) of the potentially contaminated sites in accordance with the information and recommendations contained in the EIA report and Annex 19, Section 3 of the Technical Memorandum on Environmental Impact Assessment Process (TM). Before submission to the Director, the Contamination Assessment Plans shall be certified by the Environmental Manager and verified by the Independent Environmental Checker as conforming to the information and recommendations contained in the EIA report.
2.4 Before the commencement of the construction on or in potential contaminated sites, the Permit Holder shall submit and obtain the approval of the Director Contamination Assessment Reports (CAR) based on the endorsed Contaminated Assessment Plans in accordance with Annex 19, Section 3 of the TM. During the preparation of the Contamination Assessment Report, if land contamination is confirmed, Remediation Action Plans (RAP) are required in accordance with Annex 19, Section 3 of the TM and shall be submitted as a combined report with the CAR to the Director for approval. Before submission to the Director, the results of the Contamination Assessment Reports and any Remediation Action Plans shall be certified by the Environmental Manager and verified by the Independent Environmental Checker as conforming to the information and recommendations contained in the EIA repot. All measures recommended in the approved Remediation Action Plans shall be fully implemented in accordance with the requirements and time schedule set out in the approved Remediation Action Plans.
2.5 Before the commencement of construction, the Permit Holder shall deposit with the Director a waste management plan for the Project as recommended in the EIA report. Before submission to the Director, the waste management plan shall be certified by the Environmental Manager and verified by the Independent Environmental Checker as conforming to the information and recommendations of the EIA report. Measures covered by the Waste Disposal Ordinance shall not be included in the waste management plan(s). All measures recommended in the deposited waste management plan(s) shall be fully implemented in accordance with the requirements and time schedule(s) set out in the waste management plan(s).
2.6 A detailed construction risk assessment report of the work site located south west of Kwai Hei Street, Kwai Fong as recommended in the EIA report shall be made available to the Director prior to the commencement of construction of the Tsing Tsuen / Kwai Fuk Road tunnels. The report shall, with reference to Appendix A, address the risks of landfill gas accumulation in temporary structures, storage facilities and the processes and activities to be undertaken at the site and shall be certified by the Environmental Manager, and verified by the Independent Environmental Checker as conforming to the information and recommendations contained in the EIA report. All measures recommended in the detailed construction risk assessment report shall be fully implemented in accordance with the requirements and the time schedule set out in the report deposited with the Director.
3. Submissions or Measures during the Construction Period
3.1 Within two months of commencement of construction of the Project, an environmental management plan as recommended in the EIA report shall be deposited with the Director. Before its submission to the Director, the environmental management plan shall be certified by the Environmental Manager and verified by the Independent Environmental Checker as conforming to the information and recommendations of the EIA report.
3.2 The Permit Holder shall fully implement all design or construction measures described in the approved or deposited submissions mentioned in section 2 and condition 3.1 above. Any changes to the measures including the design and construction of railway tunnel as identified in Part E of the application (No. FEP 003/1998) for this Permit shall be justified by Environmental Manager and verified by the Independent Environmental Checker as conforming to the information and recommendations contained in the EIA report.
3.3 The Permit Holder shall implement measures described in Appendix B to mitigate environmental impacts from site run-off and drainage.
3.4 The Permit Holder shall implement measures described in Appendix C to mitigate water quality impacts during tunneling and station construction.
3.5 To mitigate the cultural heritage and archaeological impacts during construction, the Permit Holder shall inform the Director immediately if any antiquities are discovered during the course of the construction works to further assess the cultural value of the items.
4. Environmental Monitoring and Audit During Construction
4.1 The Permit Holder shall keep a copy of the EM&A Manual, as described in Part A of this Permit, at his office on site for reference.
4.2 Any changes to the EM&A arrangements, including all methodologies and criteria, monitoring equipment, monitoring locations, baseline monitoring, impact monitoring, compliance assessment and event contingency plan, as required under the EM&A Manual or under the Implementation Schedule, shall be justified by the Environmental Manager, and verified by the Independent Environmental Checker in the monthly EM&A Reports and submitted to the Director under condition 4.6.
4.3 The EM&A requirements shall be implemented, including all methodologies and criteria, monitoring equipment, monitoring locations, baseline monitoring, impact monitoring, compliance assessment and event contingency plans, as set out in the EM&A Manuals and monthly EM&A Reports, unless the changes are justified in the monthly EM&A Reports submission, verified by the Independent Environmental Checker and approved by the Director.
4.4 Samples and measurements shall be taken in accordance with the requirements of noise, air quality and water quality monitoring in the EM&A Manual by:
4.5 Ten copies of the Baseline Monitoring Report certified by the Environmental Manager, and verified by the Independent Environmental Checker shall be made available to the Director one month before the commencement of any major construction works that would affect the monitoring results.
4.6 Ten copies of monthly EM&A Reports certified by the Environmental Manager, and verified by the Independent Environmental Checker shall be made available to the Director within 10 working days from the end of the reporting month.
4.7 Actions described in the action plan(s) / contingency plan(s) of the EM&A Manual shall be properly carried out, in accordance with the time frame set out in the action plan(s) / contingency plan(s), or as agreed by the Director.
5. Measures upon Completion of Construction
5.1 Upon completion of the construction of the Project, an audit shall be carried out to confirm that all the agreed environmental measures for the construction of the Project have been properly implemented. The audit shall cover all measures recommended in the EIA report, or described in approved or deposited submissions. The result of the audit shall be documented in an Audit Report certified by the Environmental Manager and verified by the Independent Environmental Checker to the information and recommendations contained in the EIA report prior to submission to the Director.
5.2 Five sets of the as-built drawings of scale 1 to 1000 with an explanatory statement showing the alignment and mitigation measures covered by this Permit, shall be deposited with the Director within three months after the completion of the construction of the Project.
Notes:
Further Environmental Permit No. FEP-03/004/1999
| Appendix A | Appendix B | Appendix C | Figure A |
Appendix A
Measures to Mitigate Landfill Gas Risk During Construction
The construction risk assessment is related to the Gin Drinker's Bay Landfill and shall include the temporary construction worksite located southwest of Kwai Hei Street at Kwai Chung. The worksite lies within 50m of the northeast perimeter of the former landfill site near to gas monitoring wells which have shown up to 20% v/v methane concentrations. Procedures and measures which can be made during the construction phase to reduce the risk of gas related problems :
Table 1 Actions to be carried out in the event of Landfill Gas Detection
Parameter |
Measurement |
Action |
O2 |
<19% |
Increase ventilation to restore O2 to >19% |
<18% |
Stop works
|
|
CH4 |
>10% LEL |
Prohibit hot works
|
>20% LEL |
Stop works
|
|
CO2 |
>0.5% |
Increase ventilation to restore CO2 to <0.5% |
>1.5% |
Stop works
|
Measures to Mitigate Environmental Impacts from Site Run-off and Drainage
To mitigate the environmental impacts from site run-off and drainage, the following shall be implemented:
Measures to Mitigate the Water Quality Impacts During Tunneling and Station Construction
To mitigate the water quality impacts during tunneling and station construction, the following shall be implemented: