Environmental Permit No. EP-260/2006/A
環境許可證編號EP-260/2006/A
ENVIRONMENTAL IMPACT ASSESSMENT ORDINANCE
(CHAPTER 499)
環境影響評估條例
(第499章)
第10及13條
ENVIRONMENTAL PERMIT TO CONSTRUCT AND OPERATE
建造及營辦指定工程項目的環境許可證
A部 (許可證主要部分)
Pursuant to Section 10 of the Environmental Impact Assessment Ordinance (the Ordinance), the Director of Environmental Protection (the Director) granted the Environmental Permit (No. EP-260/2006) to TELEVISION BROADCASTS LIMITED (hereinafter referred to as the "Permit Holder") on 20 November 2006. Pursuant to Section 13 of the Ordinance, the Director amends the Environmental Permit based on the Application No. VEP-322/2010. The amendments, described below, are incorporated into this Environmental Permit (No. EP-260/2006/A). This Environmental Permit as amended is for the construction and operation of the designated project described in Part B subject to the conditions specified in Part C. The issue of this environmental permit is based on the documents, approvals or permissions described below:
根據《環境影響評估條例》(環評條例)第10條的規定,環境保護署署長(署長)於2006年11月20日將環境許可證(編號EP-260/2006)批予電視廣播有限公司(下稱 “許可證持有人”)。根據條例第13條的規定,署長因應更改環境許可證的申請編號VEP-322/2010俢訂環境許可證編號。以下俢訂已包含在本環境許可證(編號EP-260/2006/A)內。本經俢訂的環境許可證作為建造及營運本許可證B部所說明的指定工程項目,但須遵守C部所列明的條件。本環境許可證的發出,乃以下表所列的文件、批准或許可作為根據:
Application No. 申請書編號
|
VEP-322/2010 |
|||
Document in the Register: 登記冊上的文件:
Document in the Register: 登記冊上的文件:
|
(1) Project Profile – “Hill-top Transposer Station Expansion at Castle Peak, Kowloon Peak and Cloudy Hill and Lamma Island ” (Register No.: PP-302/2006) 工程項目簡介 ― “青山、飛鵝山、九龍坑山及南丫島山頂轉播站擴建工程” (登記冊編號:PP-302/2006)
(2) The Director’s letter of permission to apply directly for environmental permit dated 20 November 2006 (Ref: EP2/G/Q/144) 署長於2006年11月20日 發出批准直接申請環境許可證的信件 (檔案編號 : EP2/G/Q/144)
(3) Application for Environmental Permit submitted on 19 December 2006 (Application No.: AEP-260/2006) 於2006年12月19日提交的環境許可證申請文件 (申請書編號:AEP-260/2006)
(4) Environmental Permit issued on 16 January 2007 (Permit No.: EP- 260/2006)
於2007年1月16日發出的環境許可證 (許可證編號: EP-260/2006)
(5) Application for Further Environmental Permit submitted on 13 August 2010 (Application No.: FEP-113/2010) 於2010年8月13日提交的新的環境許可證申請文件 (申請書編號 : FEP-113/2010)
(6) Application for Variation of Environmental Permit submitted on 13 August 2010 (Application No.: VEP-322/2010) 於2010年8月13日提交的更改環境許可證申請文件1 (申請書編號 : VEP-322/2010)
|
|||
|
25 August 2010 |
|
||
|
Date 日期 |
|
(Sam W. H. Wong) Principal Environmental Protection Officer (Regional Assessment) for Director of Environmental Protection 環境保護署署長 首席環境保護主任(區域評估) 黃偉康代行 |
|
PART B (DESCRIPTION OF DESIGNATED PROJECT)
B部 (指定工程項目的說明)
Hereunder is the description of the designated project mentioned in Part A of this environmental permit (hereinafter referred to as “the Permit”):
下列為本環境許可證(下稱“許可證”)A部所提述的指定工程項目的說明:
Title of Designated Project 指定工程項目的名稱
|
Hill-top Transposer Station Expansion at Castle Peak and Kowloon Peak (This designated project is hereafter referred to as “the Project”) 青山及飛鵝山山頂轉播站擴建工程 (本指定工程項目下稱“工程項目”)
|
Nature of Designated Project 指定工程項目的性質
|
Earthworks and building works wholly in the Castle Peak Site of Special Scientific Interest and Ma On Shan Country Park 於青山具有特別科學價值的地方及馬鞍山郊野公園內進行土木工事及建築工程
|
Location of Designated Project 指定工程項目的地點
|
The hill-top of Castle Peak at Tuen Mun and Kowloon Peak at Kowloon 屯門青山及九龍飛鵝山山頂
The locations of the Project are shown in Figure 1 and 2 of this Permit.
|
Scale and Scope of Designated Project |
The project is to construct and operate two transposer stations including: 工程項目涉及建造及營辦兩座轉播站。包括:
(a) a 2-storey building with an area of about 157m2 and an antenna tower about 34m in height on top of the building at Castle Peak; and 一座位於青山兩層高面積約157平方米的建築物,及一座在屋頂約34米高的天線塔;及
(b) a 2-storey building with an area of about 141m2 and an antenna tower about 47m in height on top of the building at Kowloon Peak. 一座位於飛鵝山兩層高面積約141平方米的建築物,及一座在屋頂約47米高的天線塔。
|
C部 (許可證條件)
1. General Conditions
一般條件
1.1 The Permit Holder and any person working on the Project shall comply with all conditions set out in this Permit. Any non-compliance by any person may constitute a contravention of the Environmental Impact Assessment Ordinance (Cap.499) and may become the subject of appropriate action being taken under the Ordinance.
許可證持有人和任何從事本工程項目的人士必須完全遵守本環境許可證的全部條件。如有不遵守本許可證條件的情況,可能違反環境影響評估條例 (第499章) 的規定,而當局可根據條例採取適當行動。
1.2 The Permit Holder shall ensure full compliance with all legislation from time to time in force including, without limitation to, the Noise Control Ordinance (Cap. 400), Air Pollution Control Ordinance (Cap. 311), Water Pollution Control Ordinance (Cap. 358), Waste Disposal Ordinance (Cap. 354), Country Parks Ordinance (Cap.208) and Waterworks Ordinance (Cap. 102). This Permit does not of itself constitute any ground of defense against any proceedings instituted under any legislation or imply any approval under any legislation.
許可證持有人須經常確保完全遵守現行法例的規定,包括但不限於噪音管制條例 (第400章)、空氣污染管制條例 (第311章)、水污染管制條例 (第358章)、廢物處置條例 (第354章)、郊野公園條例 (第208章),以及水務設施條例 (第102章)。本許可證本身不會就根據任何法例提出的訴訟構成任何抗辯理由,或根據任何法例默示任何批准。
1.3 The Permit Holder shall make copies of this Permit together with all documents referred to in this Permit and the documents referred to in Part A of the Permit readily available at all times for inspection by the Director or his authorized officers at all sites/offices covered by this Permit. Any reference to the Permit shall include all documents referred to in the Permit and also the relevant documents in the Register.
許可證持有人須印製本許可證的複本,連同本許可證所述的所有文件和本許可證A部所述的文件,以供署長或其授權人員任何時間內在本許可證所涵蓋的所有工地 / 辦事處查閱。凡提述本許可證,須包括本許可證所述的所有文件和登記冊內的相關文件。
1.4 The Permit Holder shall give a copy of this Permit to the person(s) in charge of the site(s) and ensure that such person(s) fully understands all conditions and all requirements incorporated by the Permit. The site(s) refers to site(s) of construction and operation of the Project and shall mean the same hereafter.
許可證持有人須把本許可證的一份複本交予有關工地的負責人,並確保這些人士完全明白本許可證內載的所有條件與規定。工地是指建造及營辦工程項目的工地,下文所提及的工地亦屬同一意思。
1.5 The Permit Holder shall display conspicuously a copy of this Permit on the Project site(s) at all vehicular site entrances/exits or at a convenient location for public’s information at all times. The Permit Holder shall ensure that the most updated information about the Permit, including any amended Permit, is displayed at such locations. If the Permit Holder surrenders a part or the whole of the Permit, the notice he sends to the Director shall also be displayed at the same locations as the original Permit. The suspended, varied or cancelled Permit shall be removed from display at the Project site(s).
許可證持有人須在工程項目的工地的所有車輛進出口或一處方便地點,顯眼地展示本許可證的複本,以供公眾在任何時間內閱覽。許可證持有人須確保在這些地點展示關於本許可證,包括任何經修訂的許可證的最新資料。許可證持有人如交回許可證的部分或全部,則其送交署長的通知書亦須在備有原有許可證的相同地點展示。遭暫時吊銷、更改或取消的許可證必須從工地除下,不再展示。
1.6 The Permit Holder shall construct and operate the Project in accordance with the project description in Part B of this Permit.
許可證持有人須依據本許可證B部的說明建造及營辦本工程項目。
1.7 The Permit Holder shall ensure that the Project is designed, constructed and operated in accordance with the information and all recommendations described in the Project Profile (Register No.: PP-302/2006), the application documents including all attachments for Environmental Permit (Application No. AEP-260/2006), the application documents including all attachments for variation of an environmental permit (Application No. VEP-322/2010), and the information and mitigation measures described in this Permit. Where recommendations referred to in the documents of the Register are not expressly referred to in this Permit, such recommendations are nevertheless to be implemented unless expressly excluded or impliedly amended in this Permit
許可證持有人,須確保工程項目的設計、建造及營辦,按照下述資料及措施辦理:工程項目簡介 (登記冊編號:PP302/2006);申請文件包括所有附件 (申請書編號: AEP-260/2006) 所說明的資料及所有建議,更改環境許可證申請文件包括所有附件(申請書編號: VEP-322/2010)所說明的資料及所有建議;及本許可證所說明的資料及緩解措施。登記冊文件所述建議如沒有在本許可證明確表示,則仍須實施這些建議,除非獲本許可證明確豁除或默示修訂。
1.8 All deposited submissions, as required under this Permit, shall be rectified and resubmitted in accordance with the comments, if any, made by the Director, within one month of the receipt of the Director’s comments or otherwise specified by the Director.
所有按本許可證規定存放的文件,須在接獲署長的意見 (如有者) 後1 個月內根據署長的意見加以修正並再提交署長,除非署長另行指示。
1.9 All submissions approved by the Director, all submissions deposited without comments by the Director, or all submissions rectified in accordance with comments by the Director under this Permit shall be construed as part of the permit conditions described in Part C of this Permit. Any variation of the submissions shall be approved by the Director in writing or as prescribed in the relevant permit conditions. Any non-compliance with the submissions may constitute a contravention of the Environmental Impact Assessment Ordinance (Cap.499).
署長按本許可證規定批准的所有提交文件、所有未經署長提出意見而存放的文件,或所有根據署長的意見加以修正後提交的文件,均須詮釋為本許可證C部的許可證條件的一部分。提交文件如有任何修訂,均須獲署長的書面批准,或符合有關許可證條件訂明的規定。如有不符合提交文件的情況,均可能違反環境影響評估條例 (第499章)。
1.10 The Permit Holder shall release all finalized submissions, as required under this Permit, to the public by depositing copies in the Environmental Impact Assessment Ordinance Register Office, or in any other places, or any internet websites as specified by the Director, or by any other means as specified by the Director for public inspection. For this purpose, the Permit Holder shall provide sufficient copies of the submissions.
許可證持有人須把所有按本許可證規定提交的文件定稿公開讓公眾人士知道,方法是把有關文件複本存放在環境影響評估條例登記冊辦事處,或署長指定的任何其他地方,或署長指定的任何互聯網網站,或採取署長指定的任何方法,供公眾查閱。因此,許可證持有人須提供足夠數量的複本。
1.11 All submissions to the Director required under this Permit shall be delivered either in person or by registered mail to the Environmental Impact Assessment Ordinance Register Office (currently at 27/F, Southorn Centre, 130 Hennessy Road, Wanchai, Hong Kong). Electronic copies of all finalized submissions required under this Permit shall be prepared in Hyper Text Markup Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF version 4.0 or later), unless otherwise agreed by the Director and shall be submitted at the same time as the hard copies.
本許可證規定向署長提交的所有文件,須親身送交或以掛號方式郵寄至環境影響評估條例登記冊辦事處 (現址為香港灣仔軒尼詩道130號修頓中心27樓)。所有按本許可證規定提交的文件定稿的電子版本,均須以超文本標示語言 (HTML) (第4.0或較後版本) 和便攜式文件格式 (PDF) (第4.0或較後版本) 製作,除非另獲署長同意,並須與硬複本同時提交。
1.12 The Permit Holder shall notify the Director in writing the commencement date of construction of the Project no later than two weeks prior to the commencement of construction of the Project. The Permit Holder shall notify the Director in writing immediately if there is any change of the commencement date of the construction.
許可證持有人須在工程項目的建造工程展開前,至少提早2星期以書面方式把建造工程的施工日期通知署長。施工日期如有任何更改,許可證持有人必須立即以書面方式通知署長。
1.13 For the purpose of this Permit, “commencement of construction” does not include works related to site clearance and preparation, or other works as agreed by the Director.
為執行本許可證,「建造工程的展開」不包括有關工地清理和預備的工程,或署長同意的其他工程。
2. Specific Conditions
特定條件
2.1 The Project shall only be constructed and operated at the locations as indicated in Figure 1and Figure 2 of this Permit.
許可證持證人只可在本許可證圖1及圖2所示的地點建造及營辦本工程項目。
2.2 No temporary access or haul road shall be formed for construction of the Project. Construction materials, equipments and surplus excavated materials for the Project shall be transported to and away from the Project sites through the existing route(s) or by helicopters.
不得為進行本工程項目搭建臨時通道或運料路。工程所需的建造材料、器材及多餘的挖出物料,須經現有路線或以直升機運往及搬離工程項目的建造工地。
2.3 No tree felling shall be carried out for the Project.
不得為進行本工程項目而砍伐樹木。
2.4 Before commencement of construction of the Project, field survey shall be conducted to ascertain any presence of rare or protected plant species within and close to the Project site. The Permit Holder shall, no later than two weeks after the completion of field survey, deposit with the Director four hard copies and one soft copy of the field survey report on the survey findings. If rare or protected plant species that will be affected by the Project were identified, these plant species shall be transplanted to suitable location(s) outside the Project site(s) before commencement of construction of the Project. The Permit Holder shall, no later than two weeks before commencement of transplantation, deposit with the Director four hard copies and one soft copy of transplantation proposal with the following details :
工程項目開始施工前,須進行實地調查,以確定施工範圍內及附近是否有任何稀有或受保護的植物品種。許可證持有人須於實地調查完成後2個星期內,向署長存放調查報告的4份硬複本及1份軟複本。如果確定建造工程會影響稀有或受保護的植物品種,許可證持有人須在工程項目開始施工前,把受影響的植物品種移植到工地範圍外的合適地點。許可證持有人須在進行移植前,至少提早2星期向署長存放載有下列資料移植建議的4份硬複本及1份軟複本:
(a) species and locations of plants to be transplanted;
須進行移植的植物品種及位置;
(b) recipient site for the transplanted plants;
移植地點;
(c) methodology and implementation programme of transplantation; and
移植方法及執行計劃;以及
(d) post-transplanting monitoring.
移植後的監察工作。
2.5 Chemical toilets shall be provided during the construction stage.
須在建造工程期間設置化學廁所。
2.6 Temporary drains with silt traps shall be constructed at the boundaries of the Project sites to direct all construction site run-off to sand/silt removal facilities before discharges.
在進行排污前,必須在工程項目的工地周邊修建附有泥沙收集器的臨時排水道,以便把所有工地徑流引入清除沙 / 泥的設施。
2.7 No earth, building materials, fuel, oil or toxic materials and other materials which may cause contamination shall be stockpiled on the Project sites. No waste, spoil, excavated materials or materials alike arising from the Project shall be dumped in any environmentally sensitive areas including any country park, site of special scientific interest and conservation area.
工程項目的工地不得堆積任何可能造成污染的土壤、建築材料、燃料、燃油或有毒物質,以及其他物質。工程項目產生的廢物、棄土、挖出物料或類似物料,不得傾倒於環境易受破壞的地區內。這些地區包括郊野公園、具有特別科學價值的地點,以及自然保育區。
2.8 Diesel storage in each transposer station shall not be more than 2,500 litres. All diesel storage tanks shall be housed in a fuel tight structure with holding capacity of not less than 2,500 litres to fully retain any accidentally spilled diesel.
每個轉播站所貯存的柴油不得逾2 500公升。所有柴油貯存缸必須存放於容量不少於2 500公升的密封防漏結構物內,以擋隔所有意外溢出的柴油。
2.9 Grease trap and perimeter drains shall be provided to retain any leakages of diesel/chemicals during both construction and operation stages.
須設置隔油池及周邊水渠,以擋隔在建造及營運階段溢出的柴油 /化學品。
2.10 Visually unobtrusive or sensitive architectural finishes and recessive chromatic treatments shall be incorporated into the design of the Transposer Stations for implementation. The Permit Holder shall, no later than three months after completion of construction of the Project, deposit with the Director four hard copies and one electronic copy of the as-built drawings and photo records showing the completed visual and landscape mitigation works.
轉播站的設計須融入不礙眼或視覺感應強的建築批盪及不顯眼的色彩美化元素,並予以執行。許可證持有人須於工程項目的建造工程竣工後3個月內,向署長存放竣工圖及照片記錄的4份硬複本及1份電子版本,展示已竣工的視覺及景觀防護工程。
2.11 All temporary works areas shall be reinstated and landscaped with vegetation within two months after the completion of construction of the Project. Construction plants and equipments which may cause pollution due to leakage of oil or fuel shall be removed from the Project site immediately after completion of construction of the Project
所有臨時工地須於工程項目竣工後2個月內恢復原狀及完成栽種有助美化景觀植物的工程。工程項目竣工後,所有可能因燃油或燃料滲漏而造成污染的建築機器及設備,須立即移離工地。
Notes :
註:
1. This Permit consists of three parts, namely, Part A (Main Permit), Part B (Description of Designated Project) and Part C (Permit Conditions). Any person relying on this permit should obtain independent legal advice on the legal implications under the Ordinance, and the following notes are for general information only.
本許可證共有3部,即A部(許可證主要部分),B部 (指定工程項目的說明) 及C部(許可證條件)。任何援引本許可證的人士須就環境影響評估條例 (「條例」) 的法律含意徵詢獨立法律意見,下述註解只供一般參考用。
2. If there is a breach of any conditions of this Permit, the Director or his authorized officer may, with the consent of the Secretary for the Environment, Transport and Works, order the cessation of associated work until the remedial action is taken in respect of the resultant environmental damage, and in that case the Permit Holder shall not carry out any associated works without the permission of the Director or his authorized officer.
如違反本許可證的任何條件,署長或其授權人員在徵得環境運輸及工務局局長的同意後可勒令停止相關工程,直至許可證持有人為所造成的環境損害採取補救行動為止。在此情況下,許可證持有人未經署長或其授權人員同意,不得進行任何相關工程。
3. The Permit Holder may apply under Section 13 of the Environmental Impact Assessment Ordinance (the “Ordinance”) to the Director for a variation of the conditions of this Permit. The Permit Holder shall replace the original permit displayed on the Project site by the amended permit.
許可證持有人可根據條例第13條的規定向署長申請更改本許可證的條件。許可證持有人須把經修改的許可證替換在工程項目的工地內展示的原有許可證。
4. A person who assumes the responsibility for the whole or a part of the Project may, before he assumes responsibility of the Project, apply under Section 12 of the Ordinance to the Director for a further environmental permit.
承擔工程項目整項或部分工程的責任的人,在承擔責任之前,可根據條例第12條的規定向署長申請新的環境許可證。
5. Under Section 14 of the Ordinance, the Director may with the consent of the Secretary for the Environment, Transport and Works, suspend, vary or cancel this Permit. The suspended, varied or cancelled Permit shall be removed from display at the Project sites.
根據條例第14條的規定,署長可在環境運輸及工務局局長的同意下暫時吊銷、更改或取消環境許可證。遭暫時吊銷、更改或取消的許可證必須從工程項目的工地除下,不再展示。
6. If this Permit is cancelled or surrendered during construction and operation of the Project, another environmental permit must be obtained under the Ordinance before the Project could be continued. It is an offence under Section 26 (1) of the Ordinance to construct and operate a designated project listed in Schedule 2 of the Ordinance without a valid environmental permit.
如本許可證在工程項目建造期間被取消或交回,則在繼續進行工程項目之前,必須先根據條例規定取得另一份環境許可證。根據條例第26(1)條的規定,任何人在沒有有效環境許可證的情況下建造條例附表2所列明的指定工程項目,即屬違法。
7. Any person who constructs or operates the Project contrary to the conditions in the Permit, and is convicted of an offence under the Ordinance, is liable:
如任何人在違反本許可證的條件下建造工程項目,根據環評條例,即屬違法:
(i) on a first conviction on indictment to a fine of $2 million and to imprisonment for 6 months;
一經循公訴程序首次定罪,可處罰款200萬元及監禁6個月;
(ii) on a second or subsequent conviction on indictment to a fine of $5 million and to imprisonment for 2 years;
一經循公訴程序第二次或其後每次定罪,可處罰款500萬元及監禁2年;
(iii) on a first summary conviction to a fine at level 6 and to imprisonment for 6 months;
一經循簡易程序首次定罪,可處第6級罰款及監禁6個月;
(iv) on a second or subsequent summary conviction to a fine of $1 million and to imprisonment for 1 year; and
一經循簡易程序第二次或其後每次定罪,可處罰款100萬元及監禁1年;及
(v) in any case where the offence is of a continuing nature, the court or magistrate may impose a fine of $10,000 for each day on which he is satisfied the offence continued.
在任何情況下如該罪行屬持續性質,則法院或裁判官可就其信納該罪行持續的每一天另處罰款10,000元。
8. The Permit Holder may appeal against any condition of this Permit under Section 17 of the Ordinance within 30 days of receipt of this Permit.
許可證持有人在接獲本許可證後30天內,可根據條例第17條就本許可證的任何條件提出上訴。
9. The Notes are for general reference only and that the Permit Holder should refer to the EIA Ordinance for details and seek independent legal advice.
上述註解只供一般參考用,欲知有關詳情,許可證持有人須參閱環評條例及徵詢獨立法律意見。
Environmental Permit No.: EP-260/2006/A
環境許可證編號: EP-260/2006/A