Permit No. EP-438/2012/L
環境許可證編號 EP-438/2012/L
ENVIRONMENTAL IMPACT ASSESSMENT ORDINANCE
(CHAPTER
499)
SECTIONS 10
and 13
環境影響評估條例
(第499章)
第10條及13條
ENVIRONMENTAL PERMIT TO CONSTRUCT AND OPERATE
A DESIGNATED PROJECT
建造及營辦指定工程項目的環境許可證
A部 (許可證主要部分)
Pursuant to
Section 10 of the Environmental Impact Assessment Ordinance (the Ordinance),
the Director of Environmental Protection (the Director) granted
the environmental permit (No. EP-438/2012) to the MTR
Corporation Limited (hereinafter referred to as the “Permit Holder”)
on 22 March 2012. Pursuant to Section 13 of the EIAO, the Director amends the
environmental permit (No. EP-438/2012/K) based
on the Application No. VEP-638/2024. The
amendments, described below, are incorporated into this environmental permit
(No. EP-438/2012/L). This
environmental permit as amended is for the construction and operation of the
designated project described in Part B subject to the conditions
specified in Part C. The issue of
this environmental permit is based on the documents, approvals or permissions
described below:
根據《環境影響評估條例》(環評條例)第10條的規定,環境保護署署長(署長)於2012年3月22日將環境許可證(No. EP-438/2012)批予香港鐵路有限公司(下稱 “許可證持有人”)。根據環評條例第13條的規定,署長因應更改環境許可證的申請編號VEP-638/2024修訂環境許可證(No. EP-438/2012/K)。以下修訂已包含在本環境許可證內(編號EP-438/2012/L)。本經修訂的環境許可證作為建造及營辦B部所說明的指定工程項目,但須遵守C部所列明的條件。本環境許可證是依據下列文件、批准或許可而簽發:
Application No. 申請書編號 |
VEP-638/2024 |
Document in the Register: 登記冊上的文件: |
1. Shatin to
Central Link (SCL) - Tai Wai to Hung Hom Section (Register No. AEIAR-167/2012) : -
Environmental Impact Assessment (EIA) Report
(October 2011) [Hereafter referred to as “the SCL(TAW-HUH)
EIA Report”] -
Environmental Monitoring and Audit (EM&A)
Manual (October 2011)
[Hereafter referred to as “the SCL(TAW-HUH)
EM&A Manual”] -
Executive Summary (October 2011) 1. 沙中線-大圍至紅磡段(登記冊檔號:AEIAR-167/2012): -
環境影響評估報告 (2011年10月) [下稱“SCL(TAW-HUH)環評報告”] -
環境監察審核手冊 (2011年10月) [下稱“SCL(TAW-HUH)環監手冊”] -
行政摘要(2011年10月) 2. Shatin to Central Link
(SCL) – Stabling Sidings at Hung Hom Freight Yard (Register No.
AEIAR-164/2012) : -
Environmental Impact Assessment (EIA) Report
(October 2011) [Hereafter referred to as “the SCL(HHS) EIA
Report"] -
Environmental Monitoring and Audit (EM&A)
Manual (October 2011)
[Hereafter referred to as “the SCL(HHS)EM&A
Manual”] - Executive
Summary (October 2011) |
|
2. 沙中線-位於紅磡貨運站的列車停放處 (登記冊檔號:AEIAR-164/2012): -
環境影響評估報告 (2011年10月) [下稱“SCL(HHS)環評報告”] -
環境監察審核手冊 (2011年10月) [下稱“SCL(HHS)環監手冊”] -
行政摘要(2011年10月) 3. The Director’s letter of approval of the SCL(TAW-HUH) EIA
Report dated 17 February 2012, (ref. (28) in Ax (2) to EP 2/G/A/124 Pt.7) 3. 署長於2012年2月17日發出SCL(TAW-HUH)環評報告的批准信,檔案編號: ((28) in Ax (2)
to EP 2/G/A/124 Pt.7) 4. The
Director’s letter of approval of the SCL(HHS) EIA Report dated 17
February 2012, (ref. (30) in EP 2/G/A/160 Pt.3) 4. 署長於2012年2月17日發出SCL(HHS)環評報告的批准信,檔案編號: ((30) in EP 2/G/A/160
Pt.3) 5. Application for
Environmental Permit submitted on 23 February 2012 (Application No.
AEP-438/2012) [Hereinafter referred to as the “Application”] 5. 於2012年2月23日 提交的環境許可證申請文件 (申請書編: AEP-438/2012) [下 稱 「 申 請 書 」] 6.
Environmental Permit issued
on 22 March 2012 (Permit No. EP-438/2012) 6. 於2012年3月22日簽發的環境許可證 (許可證編號EP-438/2012) 7.
Application for Variation of Environmental Permit
including all attachments submitted by the Permit Holder on 28 June 2012
(Application No. VEP-370/2012) 7. 許可證持有人於2012年6月28日提交的更改環境許可證申請包括所有附件(申請書編號VEP-370/2012) 8.
Environmental Permit issued
on 12 July 2012 (Permit No. EP-438/2012/A) 8. 於2012年7月12日簽發的環境許可證 (許可證編號EP-438/2012/A) 9.
Application for Variation of Environmental
Permit including all attachments submitted by the Permit Holder on 17 October
2012 (Application No. VEP-382/2012) 9. 許可證持有人於2012年10月17日提交的更改環境許可證申請包括所有附件(申請書編號VEP-382/2012) 10.
Environmental Permit issued
on 26 October 2012 (Permit No. EP- 438/2012/B) 10. 於2012年10月26日簽發的環境許可證 (許可證編號EP-438/2012/B) 11. Application for Variation
of Environmental Permit including all attachments submitted by the Permit
Holder on 15 April 2013 (Application No. VEP-401/2013) 11. 許可證持有人於2013年4月15日提交的更改環境許可證申請包括所有附件(申請書編號VEP-401/2013) 12.
Environmental Permit issued
on 30 April 2013 (Permit No. EP-438/2012/C) 12. 於2013年4月30日簽發的環境許可證 (許可證編號EP-438/2012/C) 13.
Application for
Variation of Environmental Permit including all attachments submitted by the
Permit Holder on 30 August 2013 (Application No. VEP-412/2013) 13. 許可證持有人於2013年8月30日提交的更改環境許可證申請包括所有附件(申請書編號VEP-412/2013) 14.
Environmental Permit issued
on 13 September 2013 (Permit No. EP-438/2012/D) 14.
於2013年9月13日簽發的環境許可證 (許可證編號EP-438/2012/D) 15.
Application for
Variation of Environmental Permit including all attachments submitted by the
Permit Holder on 19 March 2014 (Application No. VEP-432/2014) 15. 許可證持有人於2014年3月19日提交的更改環境許可證申請包括所有附件(申請書編號VEP-432/2014) 16.
Environmental Permit issued
on 4 April 2014 (Permit No. EP-438/2012/E) 16.
於2014年4月4日簽發的環境許可證 (許可證編號EP-438/2012/E) 17. Application for Variation of Environmental Permit including all
attachments submitted by the Permit Holder on 20
June 2014 (Application No. VEP-444/2014) 17. 許可證持有人於2014年6月20日提交的更改環境許可證申請包括所有附件(申請書編號VEP-444/2014) 18.
Environmental Permit issued
on 15 July 2014 (Permit No. EP-438/2012/F) 18.
於2014年7月15日簽發的環境許可證 (許可證編號EP-438/2012/F) 19. Application for Variation of Environmental Permit including all
attachments submitted by the Permit Holder on 29
July 2014 (Application No. VEP-450/2014) 19. 許可證持有人於2014年7月29日提交的更改環境許可證申請包括所有附件(申請書編號VEP-450/2014) 20.
Environmental Permit issued
on 14 August 2014 (Permit No. EP-438/2012/G) 20.
於2014年8月14日簽發的環境許可證 (許可證編號EP-438/2012/G) 21. Application for Variation of Environmental Permit including all
attachments submitted by the Permit Holder on 26
August 2014 (Application No. VEP-453/2014) 21. 許可證持有人於2014年8月26日提交的更改環境許可證申請包括所有附件(申請書編號VEP-453/2014) 22.
Environmental Permit issued
on 10 September 2014 (Permit No. EP-438/2012/H) 22.
於2014年9月10日簽發的環境許可證 (許可證編號EP-438/2012/H) 23. Application for Variation of Environmental Permit including all
attachments submitted by the Permit Holder on 18
September 2015 (Application No. VEP-484/2015) 23. 許可證持有人於2015年9月18日提交的更改環境許可證申請包括所有附件(申請書編號VEP-484/2015) 24.
Environmental Permit issued
on 14 October 2015 (Permit No. EP-438/2012/I) 24.
於2015年10月14日簽發的環境許可證 (許可證編號EP-438/2012/I) 25. Application for Variation of Environmental Permit including all
attachments submitted by the Permit Holder on 4
February 2016 (Application No. VEP-495/2016) 25. 許可證持有人於2016年2月4日提交的更改環境許可證申請包括所有附件(申請書編號VEP-495/2016) 26.
Environmental Permit issued
on 29 February 2016 (Permit No. EP-438/2012/J) 26.
於2016年2月29日簽發的環境許可證 (許可證編號EP-438/2012/J) 27. Application for Variation of Environmental Permit including all
attachments submitted by the Permit Holder on 7
September 2016 (Application No. VEP-506/2016) 27. 許可證持有人於2016年9月7日提交的更改環境許可證申請包括所有附件(申請書編號VEP-506/2016) 28. Environmental Permit issued on 4 October 2016 (Permit No. EP-438/2012/K) 28. 於2016年10月4日簽發的環境許可證 (許可證編號EP-438/2012/K) 29. Application for Variation of Environmental Permit including all attachments
submitted by the Permit Holder on 19 July 2024 (Application No. VEP-638/2024) 29. 許可證持有人於2024年7月19日提交的更改環境許可證申請包括所有附件(申請書編號VEP-638/2024) |
Application
No. 申請書編號 |
Date
of Application 申請日期 |
List
of Amendments Incorporated into Environmental Permit 已包含在環境許可證內的修訂項目 |
Date
of Amendment 修訂日期 |
|||||
VEP-370/2012 |
28 June 2012 2012年6月28日 |
Vary
Figures 1,3,4,5 and 11 of Environmental Permit No. EP-438/2012 更改環境許可證編號EP-438/2012的圖1,3,4,5及11 |
12 July 2012 2012年7月12日 |
|||||
VEP-382/2012 |
17 October 2012 2012年10月17日 |
Vary
Conditions 2.21 and 2.22 in Part C of Environmental Permit No. EP-438/2012/A 更改環境許可證編號EP-438/2012/A
C部條件第 2.21 及 2.22項 |
26 October 2012 2012年10月26日 |
|||||
VEP-401/2013 |
15 April 2013 2013年4月15日 |
Vary
Figures 3 and 4 of Environmental Permit No. EP-438/2012/B |
30 April 2013 2013年4月30日 |
|||||
VEP-412/2013 |
30 August
2013 2013年8月30日 |
Vary
Figures 3 and 4 of Environmental Permit No. EP-438/2012/C |
13
September 2013 2013年9月13日 |
|||||
VEP-432/2014 |
19 March 2014 2014年3月14日 |
Vary Figures 3, 4 and 6 of Environmental Permit
No. EP-438/2012/D 更改環境許可證編號
EP-438/2012/D的圖3 ,4
及6 |
4 April 2014 2014年4月4日 |
|||||
VEP-444/2014 |
20 June 2014 2014年6月20日 |
Vary Figures 3 and 4 of Environmental Permit No. EP-438/2012/E |
15 July 2014 2014年7月15日 |
|||||
VEP-450/2014 |
29 July 2014 2014年7月29日 |
Vary Condition 1.7 of Environmental Permit
No. EP-438/2012/F to include the installation and
operation of a Mobile Batching Machinery Equipment at Diamond Hill during the
construction of SCL (TAW-HUH) 更改環境許可證編號EP-438/2012/F的條件第1.7項,以加入在沙中線-大圍至紅磡段建造工程期間在鑽石山安裝及運作流動配料機設備 |
14 August 2014 2014年8月14日 |
|||||
VEP-453/2014 |
26 August 2014 2014年8月26日 |
Vary Figure 11 of Environmental Permit No. EP-438/2012/G 更改環境許可證編號 EP-438/2012/G 的圖11 |
10 September 2014 2014年9月10日 |
|||||
VEP-484/2015 |
18 September 2015 2015年9月18日 |
Vary Figures 1 and 4 of Environmental Permit No. EP-438/2012/H Vary Condition 2.13 of Environmental Permit
No. EP-438/2012/H 更改環境許可證編號EP-438/2012/H的條件第2.13項 |
14 October 2015 2015年10月14日 |
|||||
VEP-495/2016 |
4 February 2016 2016年2月4日 |
Vary Part B of the Environmental Permit No. EP-438/2012/I to include
the decommissioning of temporary magazine site at Tseung Kwan O (TKO) Area
137 更改環境許可證編號EP-438/2012/I的B部,以加入解除運作將軍澳第137區的臨時爆炸品倉庫。 Add Conditions 2.35 and 2.36 to Environmental Permit No. EP-438/2012/I 在環境許可證編號EP-438/2012/I加入條件第2.35及第2.36項 |
29 February 2016 2016年2月29日 |
|||||
VEP-506/2016 |
7 September 2016 2016年9月7日 |
Vary Figure 2 of Environmental Permit No. EP-438/2012/J 更改環境許可證編號 EP-438/2012/J 的圖2 Vary Condition 2.32 of Environmental Permit
No. EP-438/2012/J 更改環境許可證編號EP-438/2012/J的條件第2.32項 |
4 October 2016 2016年 10月4日 |
|||||
VEP-638/2024 |
19 July 2024 2024年7月19日 |
Vary Condition 2.26 of Environmental Permit
No. EP-438/2012/K 更改環境許可證編號EP-438/2012/K的條件第2.26項 |
16 August 2024 2024年8月16日 |
|||||
14 August 2024 2024年8月14日 |
|
|||||||
Date 日期 |
|
(Queenie Y.C. NG) Acting Principal Environmental Protection Officer for Director of Environmental Protection 環境保護署署長 (署理首席環境保護主任 吳沅清代行) |
||||||
|
|
|
|
|
|
|
||
PART B (DESCRIPTIONS OF
DESIGNATED PROJECT)
B部 (指定工程項目的說明)
Hereunder is the
description of the designated project mentioned in Part A of this
environmental permit:
下列為本環境許可證A部所提及的指定工程項目的說明:
Title
of Designated Project 指定工程項目的名稱 |
Shatin to Central Link (SCL) - Tai Wai to
Hung Hom Section [The project is
hereinafter referred to as “the Project”.] 沙中線 - 大圍至紅磡段 [上述工程項目下稱 “工程項目” ] |
Nature of Designated Project |
The Project covers
the following Designated Project elements under Part I, Schedule 2
of the EIAO : -
A railway and its associated stations (Item A.2 of
Part 1 of Schedule 2 of the EIAO); -
A railway siding (Item A.4 of Part 1 of
Schedule 2 of the EIAO); -
A railway tunnel more than 800 m in length between portals
(Item
A.7 of Part 1 of Schedule 2 of the EIAO); -
A railway bridge more than 100m in length between
abutments (Item A.8 of Part 1 of Schedule 2 of the EIAO); -
An explosive depot in a stand-alone, purpose built building (Item K.10 of Part 1 of
Schedule 2 of the EIAO); -
Decommissioning of an
explosive depot (Item 11 of Part II of Schedule 2 of the EIAO). 根據環評條例,本工程項目包含了下列屬於指定工程項目的元素: -
鐵路及其相聯車站 (「環評條例」附表2第1部A.2項); -
鐵路側線 (「環評條例」附表2第1部A.4項); -
入口之間的長度超過800米的鐵路隧道(「環評條例」附表2第1部A.7項); -
橋 台 之 間 的 長 度 超 過 100米 的 鐵 路 橋 樑 (「環評條例」附表2第1部A.8項); -
在某一單獨、特建的建築物內的爆炸品倉庫 (「環評條例」附表2第1部K.10項) ; -
解除運作一個爆炸品倉庫(「環評條例」附表2第II部第11項). |
Location
of Designated Project 指定工程項目的地點 |
General layout of the railway alignment and
location of the railway stations and the works sites of the Project are shown
in Figures 1,2, 3, 4 and 5 attached to this Permit. 工程項目及其工地的位置見載於本許可證夾附的圖1,2,3,4及5。 |
Scale and Scope of Designated Project 指定工程項目的規模和範圍 |
Construction and operation of the following
key elements: (i)
a railway of approximately 11km long from Tai Wai to Hung Hom; (ii)
seven
railway stations at Hin Keng, Diamond Hill, Kai Tak, To Kwa Wan, Ma Tau Wai,
Ho Man Tin and Hung Hom; (iii)
stabling
sidings at the former Hung Hom Freight Yard and associated
launching/retrieval tracks; (iv)
associated
ventilation
building, ventilation shafts, emergency access, emergency escape access and
emergency egress point; and (v)
supporting works areas, access roads, barging
facilities and temporary explosive magazine during the construction of the Project. Decommissioning of the following element: (i)
temporary magazine
site at Tseung Kwan O (TKO) Area 137. 建造和營辦以下的主要部份: (i)
長約11公里的鐵路,路線由大圍至紅磡; (ii)
7個位於顯徑、鑽石山、啓德、土瓜灣、馬頭圍、何文田及紅磡的車站; (iii)
位於前紅磡貨運站的列車停放處和相關的進出站路軌; (iv)
與鐵路相關的通風大樓、通風管道及緊急救援通道;及 (v)
於施工期間的後勤施工區、幹道支路、躉船轉運設施、臨時爆炸品倉庫。 解除運作以下部份: (i)
將軍澳第137區的臨時爆炸品倉庫。 Remarks : For Ho Man Tin (HOM) Station and Hung Hom (HUH)
Station, the civil construction works will be carried out under the Kwun Tong
Line Extension (KTE) Project and the SCL (Mong Kong East to Hung Hom Section)
Project respectively. The construction works to be carried out under this
Project will mainly include internal fitting-out works, track laying works
and provision of other station facilities. 建造何文田站及紅磡站的土木工程主要分別納入在「觀塘線延線」和「沙中線(旺角東至紅磡段)」的工程項目內,而本工程項目會在何文田站及紅磡站進行內部裝修、舖設路軌及提供其他車站設施。 |
C部 (許可證條件)
1.
General
Conditions
一般條件
1.1
The Permit Holder and any person working on the
Project shall comply with all conditions set out in this Permit. Any
non-compliance by any person may constitute a contravention of the
Environmental Impact Assessment Ordinance (Cap. 499) and may become the subject
of appropriate action being taken under the Ordinance.
許可證持有人及任何從事工程項目的人士必須完全符合本許可證載列的全部條件。任何人士如有不符合本許可證的情況,可能違反《環境影響評估條例》(第499章)的規定,而當局可根據條例採取適當行動。
1.2
The Permit
Holder shall ensure full compliance with all legislation from time to time in
force including, without limitation to, the Noise Control Ordinance (Cap. 400),
Air Pollution Control Ordinance (Cap. 311), Water Pollution Control Ordinance
(Cap. 358), Dumping at Sea Ordinance (Cap. 466) and Waste Disposal Ordinance
(Cap. 354). This Permit does not of itself constitute any ground of defence
against any proceedings instituted under any legislation or imply any approval
under any legislation.
許可證持有人須經常確保完全符合現行法例的規定,包括但不限於《噪音管制條例》(第400章)、《空氣污染管制條例》(第311章)、《水污染管制條例》(第358章)、《海上傾倒物料條例》 (第466章)及《廢物處置條例》(第354章)。本許可證本身不會就根據任何法例提起的法律程序構成任何抗辯理由,或根據任何法例默示任何批准。
1.3
The Permit
Holder shall make copies of this Permit together with all documents referred to
in this Permit or the documents referred to in Part A of the Permit
readily available at all times for inspection by the Director or his authorised
officers at all sites/offices covered by this Permit. Any reference to the
Permit shall include all documents referred to in the Permit and also the
relevant documents in the Register.
許可證持有人須印製本許可證的複本,連同本許可證所述的所有文件或本許可證A部所述文件,以供署長或獲授權人員任何時間內在本許可證所涵蓋的所有工地/辦事處查閱。凡提述本許可證,須包括本許可證所述的所有文件及登記冊內的相關文件。
1.4
The Permit
Holder shall give a copy of this Permit to the person(s) in charge of the
site(s) and ensure that such person(s) fully understands all conditions and all
requirements incorporated by the Permit. The site(s) refers to site(s) of
construction and operation of the Project and shall mean the same hereafter.
許可證持有人須把本許可證的一份複本交予工程項目工地的負責人,並確保這些人士完全明白本許可證的所有條件與規定。工地是指工程項目的建造及營辦工地,下文所提及的工地亦屬同一意思。
1.5
The Permit Holder shall display conspicuously a copy
of this Permit on the construction site(s) at all vehicular site
entrances/exists or at a convenient location for public’s information at all
times. The Permit Holder shall ensure that the most updated information
about the Permit, including any amended permit, is displayed at such
location. If the Permit Holder surrenders a part or the whole of the
Permit, the notice he sends to the Director shall also be displayed at the same
location as the original Permit. The suspended, varied or cancelled
Permit shall be removed from display at the construction site(s).
許可證持有人須在建造工地所有車輛進出口或一處方便地點,顯眼地展示本許可證的複本,以供公眾在任何時間內閱覽。許可證持有人須確保在這些地點展示關於本許可證(包括任何經修訂的許可證)的最新資料。許可證持有人如交回許可證的部分或全部,必須把其送交署長的通知書,在備有原有許可證的各處相同地點展示。遭暫時吊銷、更改或取消的許可證必須從建造工地除下,不再展示。
1.6
The Permit
Holder shall construct and operate the Project in accordance with the project
descriptions in Part B of this Permit.
許可證持有人須依據本許可證B部的工程項目說明,建造及營辦本工程項目。
1.7
The Permit
Holder shall ensure that the Project is designed, constructed and operated in
accordance with the information and all recommendations described in the SCL(TAW-HUH) EIA Report (Register No. AEIAR-167/2012); the SCL(HHS) EIA Report (Register No.
AEIAR-164/2012); the application document (Application No. AEP-438/2012);
other relevant documents in the Register; and the information or mitigation measures described in this Permit and the
applications for variation of Environmental Permits as listed in Part A of this
Permit, mitigation measures to be recommended in submissions
that shall be deposited with or approved by the Director as a result of permit conditions contained in this Permit, and
mitigation measures to be recommended under ongoing surveillance and monitoring
activities during all stages of the Project. Where recommendations referred to
in the documents of the Register are not expressly referred to in this Permit,
such recommendations are nevertheless to be implemented unless expressly
excluded or impliedly amended in this Permit.
許可證持有人須確保工程項目按照下述資料設計、建造及營辦:SCL(TAW-HUH)環評報告(登記冊檔號:AEIAR-167/2012);SCL(HHS)環評報告(登記冊檔號:AEIAR-164/2012)所說明的資料及各項建議;申請文件(申請書編號:AEP-438/2012);登記冊內的其他相關文件;本許可證所說明的資料或緩解措施及本許可證A部所臚列的更改環境許可證的申請文件;根據本許可證內載的條件須向署長存放或獲署長批准的提交文件所建議的緩解措施;以及在工程項目各階段進行的持續監察及監測工作所建議的緩解措施。登記冊文件所述建議如沒有在本許可證明確表示,則仍須實施這些建議,除非獲本許可證明確豁除或默示修訂。
1.8
All deposited
submissions, as required under this Permit, shall be rectified and resubmitted in
accordance with the comments, if any made by the Director within one month of
the receipt of the Director’s comments or otherwise specified by the Director.
所有按本許可證規定提交的存放文件,須在接獲署長的意見(如有者)後1個月內(除非署長另行指定),根據署長的意見加以修正及重新提交。
1.9
All submissions
approved by the Director, all submissions deposited without comments by the
Director, or all submissions rectified in accordance with comments by the
Director under this Permit shall be construed as part of the permit conditions
described in Part C of this Permit. Any variations of the
submissions shall be approved by the Director in writing or as prescribed in
the relevant permit conditions. Any non-compliance with the submissions may
constitute a contravention of the EIA Ordinance (Cap. 499). All submissions or
any variation of the submissions shall be certified by the Environmental Team
(ET) Leader and verified by the Independent Environmental Checker (IEC)
referred to in Conditions 2.1 and 2.2 below, before submitting to the Director
under the Permit.
署長批准的所有提交文件、署長沒有給予意見的所有存放文件,或根據本許可證規定由署長給予意見修正的所有提交文件,均須詮釋為本許可證C部說明的許可證條件的一部分。提交文件如有任何修訂,均須獲署長的書面批准,或符合有關許可證條件訂明的規定。如有不符合提交文件的情況,則可能違反《環境影響評估條例》(第499章)的規定。所有提交文件或提交文件的任何修訂本,均須由下文條件第2.1及2.2項所述的環境小組組長核證及獨立環境查核人核實,然後才按本許可證規定向署長提交。
1.10
The Permit
Holder shall release all finalized submissions, as required under this Permit,
to the public by depositing copies in the EIA Ordinance Register Office, or in
any other places, or any internet websites as specified by the Director, or by
any other means as specified by the Director for public inspection. For
this purpose, the Permit Holder shall provide sufficient copies of the submissions.
許可證持有人須把所有按本許可證規定提交的文件定稿公開給公眾人士知道,方法是把有關文件複本存放於環境影響評估條例登記冊辦事處,或署長指定的任何其他地方,或署長指定的任何互聯網網站,或署長指定的任何其他方法,以供公眾查閱。因此,許可證持有人須提供足夠數量的複本。
1.11
All submissions to the
Director required under this Permit shall be delivered either in person or by
registered mail to the EIA Ordinance Register Office (currently at 27/F,
Southorn Centre, 130 Hennessy Road, Wanchai, Hong
Kong). Electronic copies of all finalized submissions required under this
Permit shall be prepared in Hyper Text Markup Language (HTML) (version 4.0 or
later) and in Portable Document Format (PDF version 1.3 or later), unless
otherwise agreed by the Director and shall be submitted at the same time as the
hard copies.
本許可證規定向署長提交的所有文件,須親身送交或以掛號方式郵寄至環境影響評估條例登記冊辦事處(現址為:香港灣仔軒尼詩道130號修頓中心27樓)。所有按本許可證規定提交的文件定稿的電子版本,均須以超文本標示語言(HTML)(第4.0或較後版本)和便攜式文件格式(PDF)(第1.3或較後版本)製作,除非另獲署長同意,並須與硬複本同時提交。
1.12
The Permit
Holder shall notify the Director in writing the commencement date of construction
of the Project no later than one month prior to the commencement of
construction of the Project. The Permit Holder shall notify the Director in
writing immediately if there is any change of the commencement date of the
construction.
許可證持有人在工程項目的建造工程展開前,須至少提早1個月以書面方式通知署長工程項目建造工程的施工日期。建造工程的施工日期如有任何更改,許可證持有人須立即以書面方式通知署長。
1.13
For the purpose of this Permit, “commencement of
construction” does not include works related to site clearance and preparation,
or other works as agreed by the Director.
為執行本許可證,「建造工程的展開」不包括有關工地清理和預備工程,或署長同意的其他工程。
1.14
The Permit Holder notify the Director in writing the commencement date of operation of the
Project no later than two months prior to the commencement of operation of the
Project. The Permit Holder shall notify the Director in writing immediately if
there is any change of the commencement date of the operation.
許可證持有人在工程項目的營辦展開前,須至少提早2個月以書面方式通知署長工程項目開始營辦的日期。開始營辦的日期如有任何更改,許可證持有人須立即以書面方式通知署長。
2.
Special Conditions
特定條件
Submissions and
Measures before Commencement of Construction of the Project
工程項目施工前須提交的文件及採取的措施
Employment of Environmental Monitoring and Audit
(EM&A) Personnel
聘用環境監察及審核(環監)人員
2.1
An Environmental Team (ET) shall be established by
the Permit Holder no later than one month before the commencement of
construction of the Project. The ET shall not be in any way an associated body
of the Contractor or the Independent Environmental Checker (IEC) for the
Project. The ET shall be headed by an ET Leader. The ET Leader shall be a
person who has at least 7 years of experience in environmental monitoring and
auditing (EM&A) or environmental management. The ET and the ET Leader shall
be responsible for the implementation of the EM&A programme in accordance
with the EM&A requirements as contained in the SCL(TAW-HUH) EM&A Manual
and SCL(HHS) EM&A Manual. The ET Leader shall keep a contemporaneous
log-book of each and every instance or circumstance or change of circumstances,
which may affect the compliance with the recommendations of the SCL(TAW-HUH)
EIA Report (Register No. AEIAR-167/2012) and SCL(HHS) EIA Report (Register No.
AEIAR-164/2012) and this Permit. The ET
Leader shall notify the IEC within one working day of the occurrence of any
such instance or circumstance or change of circumstances. The ET Leader’s
log-book shall be kept readily available for inspection by all persons
assisting in supervision of the implementation of the recommendations of the SCL(TAW-HUH)
EIA Report (Register No. AEIAR-167/2012) and SCL(HHS) EIA Report (Register No.
AEIAR-164/2012) and this Permit or by the Director or his authorized officers.
Failure to maintain records in the log-book, failure to discharge the duties of
the ET Leader as defined in the EM&A Manual or failure to comply with this
Condition would entitle the Director to require the Permit Holder by notice in
writing to replace the ET Leader. Failure by the Permit Holder to make
replacement, or further failure to keep contemporaneous records in the log-book
despite the employment of a new ET Leader may render the Permit liable to suspension,
cancellation or variation.
在工程項目的建造工程展開前,許可證持有人須至少提早1個月成立一個環境小組。環境小組不得與工程項目的承辦商或獨立環境查核人有任何聯繫。環境小組須由一名環境小組組長帶領。環境小組組長須在環境監察及審核(環監)或環境管理方面至少有7年經驗。環境小組及環境小組組長須按SCL(TAW-HUH)及SCL(HHS)環監手冊內載的環監要求,執行環監計劃。環境小組組長須保存一本記錄冊,同時記載可能會影響SCL(TAW-HUH) 環評報告(登記冊檔號:AEIAR-167/2012)及SCL(HHS) 環評報告(登記冊檔號:AEIAR-164/2012)的建議及本許可證的符合情況的每宗事件、每種情況或每次情況變化。環境小組組長須在發生任何類似事件、情況或情況變化後1個工作天內通知獨立環境查核人。存放這本環境小組組長的記錄冊的地方,須可供協助督導執行SCL(TAW-HUH) 環評報告(登記冊檔號:AEIAR-167/2012)及SCL(HHS) 環評報告(登記冊檔號:AEIAR-164/2012)的建議及本許可證的所有人士、署長或獲授權人員隨時查閱。環境小組組長如未能在記錄冊保存記錄、未能執行環監手冊所列明的環境小組組長職務,或未能符合本條件的規定,署長有權以書面要求許可證持有人撤換環境小組組長。許可證持有人如未能安排人選替補,或在聘用新環境小組組長後仍未能在記錄冊保存同期的記錄,或會導致許可證遭暫時吊銷、取消或更改。
2.2
An IEC shall be employed by
the Permit Holder no later than one month before commencement of construction
of the Project. The IEC shall not be in any way an associated body of the
Contractor or the ET for the Project. The IEC shall be a person who has at
least 7 years of experience in EM&A or environmental management. The IEC
shall be responsible for duties defined in the SCL(TAW-HUH) EM&A
Manual and SCL(HHS) EM&A Manual and shall audit the
overall EM&A performance, including the implementation of all environmental
mitigation measures, submissions required in the SCL(TAW-HUH) EM&A Manual
and SCL(HHS) EM&A Manual, and any other submissions
required under this Permit. In addition, the IEC shall be responsible for
verifying the environmental acceptability of permanent and temporary works,
relevant design plans and submissions under this Permit. The IEC shall verify
the log-book(s) mentioned in Condition 2.1 of this Permit. The IEC shall notify
the Director by fax, within one working day of receipt of notification from the
ET Leader of each and every occurrence, change of circumstances or
non-compliance with the SCL(TAW-HUH) EIA Report (Register No. AEIAR-167/2012)
and SCL(HHS) EIA Report (Register No. AEIAR-164/2012) and
this Permit, which might affect the monitoring or control of adverse
environmental impacts from the Project. In the case where the IEC fails to so
notify the Director of the same, fails to discharge the duties of the IEC as
defined in the EM&A Manual or fails to comply with this Condition, the
Director may require the Permit Holder by notice in writing to replace the IEC.
Failure to replace the IEC as directed or further failure to so notify the
Director despite employment of a new IEC may render the Permit liable to
suspension, cancellation or variation. Notification by the Permit Holder is the
same as notification by the IEC for the purpose of this Condition.
在工程項目的建造工程展開前,許可證持有人須至少提早1個月聘用一名獨立環境查核人。獨立環境查核人不得與工程項目的承辦商或環境小組有任何聯繫。獨立環境查核人須在環監或環境管理方面至少有7年經驗。獨立環境查核人須執行SCL(TAW-HUH)及SCL(HHS)環監手冊所列明的職務,以及審核整體的環監表現,包括實施所有環境緩解措施、提交SCL(TAW-HUH)及SCL(HHS)環監手冊規定的文件,以及提交本許可證所要求的其他文件。此外,獨立環境查核人須核實永久及臨時工程在環境上的可接受程度、相關的設計圖則和根據本許可證提交的文件,並須核實本許可證條件第2.1項所述的記錄冊。在每次發生事件、出現情況變化或不符合SCL(TAW-HUH) 環評報告(登記冊檔號:AEIAR-167/2012)及SCL(HHS) 環評報告(登記冊檔號:AEIAR-164/2012)及本許可證的情況,而可能會妨礙就工程項目所造成不良環境影響而進行的監察或控制工作時,獨立環境查核人須在接獲環境小組組長通知後1個工作天內以傳真方式通知署長。獨立環境查核人如未能通知署長有關情況,未能執行環監手冊所列明的獨立環境查核人職務,或未能符合本條件的規定,署長可以書面要求許可證持有人撤換獨立環境查核人。如未能按指示撤換獨立環境查核人,或在聘用新獨立環境查核人後仍未能通知署長有關情況,則或會導致許可證遭暫時吊銷、取消或更改。為執行本條件,許可證持有人的通知等同獨立環境查核人的通知。
Community Liaison Groups
社區聯絡小組
2.3
Before the commencement of construction of the
Project, the Permit Holder shall set up Community Liaison Groups comprising
representatives of concerned and affected parties, including owners’
corporations, management offices, local committees, residents and schools in
the affected areas along the railway alignment, to facilitate communications,
enquiries and complaint handlings on environmental issues related to the Project and maintain the
Community Liaison Groups throughout the entire construction period of the
Project. The Permit Holder shall follow
up with the Community Liaison Groups on the implementation of mitigation
measures and other initiatives proposed by the Permit Holder such as Indirect
Technical Remedies in the form of upgraded glazing and air-conditioning for
eligible dwellings affected by air-borne construction noise impact, as well as
arrangement of continuous construction noise monitoring. The Permit Holder shall notify the Director
the date of setting up the Community Liaison Groups, the membership, the terms
of reference and the contact details at least one month before the commencement of
construction of the Project.
在工程項目的建造工程展開前,許可證持有人須成立社區聯絡小組,由相關及受影響團體代表組成,包括位於鐵路路線上受影響地區的業主立案法團、管理公司、地區委員會、居民及學校,以便在整段建造期間內就工程項目的所有環境問題加強與有關人士的溝通,處理有關的查詢和投訴,並與社區聯絡小組保持聯絡。許可證持有人須與社區聯絡小組跟進許可證持有人所建議的緩解措施及其他措施的實施情況,例如實施間接技術補救措施,為受經空氣傳送建築噪音影響的合資格住宅安裝厚玻璃窗和空調設備,以及持續噪音監測的安排等。在工程項目的建造工程展開前,許可證持有人須至少提早1個月通知署長社區聯絡小組的確實成立日期、成員名單、職權範圍及聯絡詳情。
2.4
The Permit Holder shall set up a designated complaint
hotline for the Project to address the environmental concerns and complaints in
an efficient manner before the commencement of construction of the Project and
maintain the designated complaint hotline throughout the entire construction
period of
the Project.
在工程項目的建造工程展開前,許可證持有人須為工程項目設立特定電話投訴熱線,以迅速回應及處理公眾關注的環境事宜和投訴。特定電話投訴熱線須於工程項目的整段建造期間維持運作。
Employment
of Certified Arborist
聘請註冊樹藝師
2.5
The Permit Holder shall appoint a Certified Arborist for the Project to advise
on, monitor and ensure proper implementation of measures for protecting trees
affected by the Project as well as trees to be transplanted, and to prepare
submissions as required under Condition 2.13 of this Permit.
許可證持有人須就工程項目委聘一名註冊樹藝師,以提供意見及進行監察,並確保各項保護受工程項目影響的樹木和將予移植樹木的措施能妥善執行,以及擬備根據本許可證條件第2.13項規定提交的文件。
Employment of Qualified
Archaeologist
聘請合資格的考古學家
2.6
The Permit Holder shall appoint a
qualified archaeologist to conduct further archaeological investigation at
former Tai Hom Village site and the Sacred Hill (North) study area and to
conduct rescue excavation to preserve any archaeological remains as required
under Condition 2.16 of this Permit.
許可證持有人須聘請一名合資格的考古學家,根據本許可證條件第2.16項的規定,在前大磡村用地及聖山(北)的研究範圍作進一步考古勘探及進行搶救發掘,以保存任何考古遺物。
Management
Organization of Main Construction Companies
主要建造公司的管理架構
2.7
The Permit Holder shall, no later than two weeks
before the commencement of construction of the Project, inform the Director in
writing the management organization of the main construction companies and/or
any form of joint ventures associated with the construction of the
Project. The submitted information shall
include at least an organization chart, names of responsible persons and their
contact details.
許可證持有人須在工程項目的建造工程展開前,至少提早2個星期把主要建造公司及/或以任何形式與建造工程項目相關的合營企業的管理架構,以書面通知署長。提交的資料須至少包括一份組織圖、負責人的姓名及聯絡資料。
Submission of Construction
Programme and Environmental Permit (EP) Submission Schedule
提交建造工程計劃及環境許可證文件提交時間表
2.8
The Permit Holder shall, no later than two weeks
before the commencement of the construction of the Project, deposit with the
Director four hard copies and one electronic copy of the construction programme
showing the commencement and completion dates of major items of construction
works; together with the anticipated schedule of submissions for fulfilling the
submission requirements as contained in this Permit. The Permit Holder shall inform the Director
accordingly in writing in case of any subsequent changes of items contained in
this submitted construction programme and EP Submission Schedule.
許可證持有人在工程項目的建造工程展開前,須至少提早2個星期向署長存放建造工程計劃的4份硬複本及1份電子版本,展示建造工程主要項目的施工及竣工日期,以及為符合本許可證提交文件的規定的預計文件提交時間表。倘若已提交的建造工程計劃及環境許可證文件提交時間表其後如有任何項目更改,許可證持有人須以書面方式通知署長。
Submission of
Construction Noise Mitigation Measures Plan (CNMMP)
提交建築噪音緩解措施計劃
2.9
To further reduce the air-borne construction noise
impacts on the 19 noise sensitive receivers (NSRs) shown in Table 1 of this Permit
with exceedance after mitigation as predicted in the SCL(TAW-HUH) EIA Report (Register
No. AEIAR-167/2012) and SCL(HHS) EIA Report (Register No. AEIAR-164/2012), the Permit
Holder shall, no later than one month before the commencement of the construction of
the Project, submit to the Director for approval four hard copies and one
electronic copy of an updated Construction Noise Mitigation Measures Plan
(CNMMP) and other initiatives proposed by the Permit Holder. The Plan shall include:-
為進一步減少經空氣傳送建築噪音對SCL(TAW-HUH) 環評報告(登記冊檔號:AEIAR-167/2012)及SCL(HHS) 環評報告(登記冊檔號:AEIAR-164/2012)內預計本許可證表1所示超標的19個噪音敏感受體在採取緩解措施後所受的影響,許可證持有人須在工程項目的建造工程展開前,至少提早1個月向署長提交許可證持有人建議的經更新的建築噪音緩解措施計劃和的其他措施的4份硬複本及1份電子版本,以供審批。有關計劃須包括:
(a)
a
schedule of construction works to be carried out at the works areas of the
Project within 300m from the NSRs;
距離噪音敏感受體300米範圍內的工程項目工地進行的建造工程時間表;
(b)
an
updated construction methodology of the construction works;
建造工程經更新的施工方法;
(c)
an
updated powered mechanical equipment (PME) list for the construction works;
建造工程經更新的機動設備名單;
(d)
an
updated proposal of air-borne noise mitigation measures for the 19 NSRs as
shown in Table 1 of this Permit, including the provision of noise barriers,
enclosures and Indirect Technical Remedies;
為本許可證表1所示的19個噪音敏感受體提供經更新的經空氣傳送噪音緩解建議措施,包括設置隔音屏障和隔音罩及間接技術補救措施;以及
(e)
an
updated prediction of noise levels in accordance with the above updated
information and mitigation proposals in place.
根據上述經更新的資料及採取建議緩解措施後作出的更新噪音水平預測。
Before submission to the Director, the CNMMP shall be certified
by the ET Leader and verified by the IEC as conforming to the relevant
information and recommendations contained in the approved SCL(TAW-HUH) EIA
Report (Register No. AEIAR-167/2012) and SCL(HHS) EIA Report (Register No.
AEIAR-164/2012). All measures recommended in the approved CNMMP shall be fully and properly
implemented.
建築噪音緩解措施計劃在提交署長前,須由環境小組組長核證及獨立環境查核人核實,證明其符合核准的SCL(TAW-HUH) 環評報告(登記冊檔號:AEIAR-167/2012)及SCL(HHS) 環評報告(登記冊檔號:AEIAR-164/2012)的有關資料及建議。核准的建築噪音緩解措施計劃所建議的全部措施均須徹底及妥善執行。
2.10
Submission
of Continuous Noise Monitoring Plan
提交持續噪音監測計劃
The Permit Holder
shall, no later than one month before the commencement of construction of the
Project, submit to the Director for approval four hard copies and one
electronic copy of a Continuous Noise Monitoring Plan for the Project.
The Plan shall include:
在工程項目的建造工程展開前,許可證持有人須至少提早1個月把工程項目持續噪音監測計劃的4份硬複本及1份電子版本,提交署長批核。有關計劃須包括:
(a)
updated
environmental monitoring and audit requirements relating to continuous noise
monitoring at the NSRs shown in Table 1 of this Permit with exceedance after
mitigation in air-borne construction noise impact as predicted in the approved SCL(TAW-HUH) EIA
Report (Register No. AEIAR-167/2012) and SCL(HHS) EIA Report (Register No.
AEIAR-164/2012) and as updated in the CNMMP approved under Condition 2.9;
就核准的SCL(TAW-HUH)環評報告(登記冊檔號:AEIAR-167/2012)及SCL(HHS) 環評報告(登記冊檔號:AEIAR-164/2012)內預計及根據條件第2.9項核准的經更新建築噪音緩解措施計劃所指:為經空氣傳送建築噪音對本許可證表1所示超標的噪音敏感受體在採取緩解措施後所受的影響而實施有關持續噪音監測的經更新環境監測及審核規定;
(b)
drawings
in the scale of 1:5,000 or other appropriate scale as agreed by the Director
showing the proposed locations for conducting continuous noise monitoring;
用1:5 000或署長同意的其他合適比例繪製的圖則,展示建議進行持續噪音監測的地點;
(c)
monitoring
methodology and measurement parameters;
監測方法及測量參數;
(d)
a
system to report the continuous noise monitoring results on a website within a
period of 2 working days after the relevant noise monitoring data are collected
or become available; and
在有關噪音監測數據收集或可供瀏覽後的2個工作天內於網站匯報持續噪音監測結果的系統;以及
(e)
an
Event and Action Plan giving details of the immediate active remedial measures
in the event that the measured noise levels exceed the worst-case scenario
predicted in the approved SCL(TAW-HUH) EIA Report (Register No. AEIAR-167/2012) and SCL(HHS) EIA
Report (Register No. AEIAR-164/2012) or the levels as updated by the CNMMP
approved under Condition 2.9.
事件及行動計劃,闡述倘若量度的噪音水平超逾核准的SCL(TAW-HUH) 環評報告(登記冊檔號:AEIAR-167/2012)及SCL(HHS)環評報告(登記冊檔號:AEIAR-164/2012)預計的最壞情況或根據條件第2.9項核准的建築噪音緩解措施計劃經更新的噪音水平時所採取的即時補救措施。
Before submission to
the Director, the Continuous Noise Monitoring Plan shall be certified by the ET
and verified by the IEC as conforming to the relevant information and
recommendations contained in the approved SCL(TAW-HUH) EIA Report (Register
No. AEIAR-167/2012) and SCL(HHS) EIA Report (Register No. AEIAR-164/2012) or the updated prediction of noise levels
as contained in the CNMMP approved under Condition 2.9. All measures
recommended in the Continuous Noise Monitoring Plan approved under this
Condition shall be fully and properly implemented.
持續噪音監測計劃在提交署長前,須由環境小組核證及獨立環境查核人核實,證明其符合核准的SCL(TAW-HUH) 環評報告(登記冊檔號:AEIAR-167/2012)及SCL(HHS)環評報告(登記冊檔號:AEIAR-164/2012)的有關資料及建議,或根據條件第2.9項核准的建築噪音緩解措施計劃載述經更新的噪音水平預測。根據本條件核准的持續噪音監測計劃所建議的措施全部均須徹底及妥善執行。
Submission of Construction and Demolition Materials
Management Plan (C&DMMP)
提交拆建物料管理計劃
2.11
The
Permit Holder shall, no later than one month before commencement of
construction of the Project, submit to the Director for approval four hard
copies and one electronic copy of a construction and demolition (C&D)
materials management plan (C&DMMP). The
C&DMMP shall describe the arrangements for avoidance, reuse, recovery and
recycling, storage, collection, treatment and disposal of C&D materials to
be generated from the construction of the Project. The C&DMMP shall indicate the disposal location(s) of all surplus excavated spoil
and other wastes. A trip ticket system shall be included in the C&DMMP.
Surplus excavated spoil and other wastes shall only be disposed of at
designated disposal locations unless otherwise approved by the Director.
許可證持有人須在工程項目的建造工程展開前,至少提早1個月,向署長提交拆建物料管理計劃的4份硬複本及1份電子版本,以供審批。拆建物料管理計劃須說明建造工程項目時所產生的拆建物料在避免產生、再使用、回收、循環再造、貯存、收集、處理和棄置方面的安排。拆建物料管理計劃須顯示所有剩餘挖出棄土及其他廢物的棄置地點。拆建物料管理計劃亦須包括運載記錄制度。除非另獲署長批准,剩餘挖出棄土及其他廢物,只可在指定的棄置地點棄置。
Before submission to the Director, the C&DMMP
shall be certified by the ET Leader and verified by the IEC as conforming to
the relevant information and recommendations contained in the approved SCL(TAW-HUH) EIA
Report (Register No. AEIAR-167/2012) and SCL(HHS) EIA Report (Register No.
AEIAR-164/2012). All measures recommended in the approved C&DMMP shall be fully and properly
implemented.
拆建物料管理計劃在提交署長前,須由環境小組組長核證及獨立環境查核人核實,證明其符合核准的SCL(TAW-HUH) 環評報告(登記冊檔號:AEIAR-167/2012)及SCL(HHS)環評報告(登記冊檔號:AEIAR-164/2012)所載的相關資料及建議。核准的拆建物料管理計劃建議的所有措施均須徹底及妥善執行。
Submission of Sediment Management Plan
提交沉積物管理計劃
2.12
The
Permit Holder shall, no later than one month before the commencement of
construction works which involves dredging / excavating sediments, submit to
the Director for approval four hard copies and one electronic copy of a
sediment management plan. The sediment
management plan shall include, but not limited to, details of proper treatment
and handling of sediments to be generated from the construction of the Project
before disposal.
在涉及疏浚/挖掘沉積物的建造工程展開前,許可證持有人須至少提早1個月把沉積物管理計劃的4份硬複本及1份電子版本提交署長審批。沉積物管理計劃須包括但不限於建造工程項目所釋出的沉積物在棄置前的妥善處理方法。
Before submission to the Director, the sediment
management plan shall be certified by the ET Leader and verified by the IEC as
conforming to the relevant information and recommendations contained in the
approved SCL(TAW-HUH) EIA Report (Register No. AEIAR-167/2012) and SCL(HHS) EIA
Report (Register No. AEIAR-164/2012). All measures recommended in the approved sediment management plan shall be fully and
properly implemented.
沉積物管理計劃在提交署長前,須由環境小組組長核證及獨立環境查核人核實,證明其符合核准的SCL(TAW-HUH) 環評報告(登記冊檔號:AEIAR-167/2012)及SCL(HHS)環評報告(登記冊檔號:AEIAR-164/2012)所載的相關資料及建議。核准的沉積物管理計劃建議的所有措施均須徹底及妥善執行。
Submission of Visual,
Landscape, Tree Planting & Tree Protection Plan
提交視覺、景觀及植樹與樹木保護計劃
2.13
The
Permit Holder shall, no later than one month before the commencement of construction
of the Project, submit six hard copies and one electronic copy of the visual, landscape,
tree planting & tree protection plan to the Director for approval. The plan, with drawings in the scale of 1:1000 or
other appropriate scales as agreed by the Director shall show the visual, landscape,
tree planting & tree protection measures of the Project, and shall include
at least the following information:
在工程項目的建造工程展開前,許可證持有人須至少提早1個月把視覺、景觀及植樹與樹木保護計劃的6份硬複本及1份電子版本提交署長審批。 有關計劃須包括比例1:1 000或署長同意的其他合適比例繪製的圖則,展示工程項目的視覺、景觀及植樹與樹木保護措施,並須至少包括以下資料:
(a)
aesthetic landscape and architectural treatment for
above ground structures including stabling sidings at the former Hung Hom Freight Yard, stations,
entrances, ventilation building, ventilation shafts, portals, noise
barriers/enclosures and viaduct section at Hin Heng;
就地面建築物包括前紅磡貨運站的列車停放處、顯徑車站、出入口、通風大樓、通風井、入口、隔音屏障/隔音罩及高架橋段所採取的景觀及建築優化措施;
(b)
tree protection proposal showing locations, size, number and plant species of
trees to be retained; and detailed working method statement for protection of retained trees;
樹木保護建議,須顯示將予保留樹木的位置、大小、數量及品種;以及保護獲保留樹木的詳細作業方法說明;
(c)
transplantation
proposal showing locations, size, number and tree species to be transplanted and the
final locations for transplantation;
移植建議,須顯示將予移植樹木的位置、大小、數量及品種,以及樹木的最終移植地點;
(d)
tree felling proposal showing locations, size,
number and plant species to be felled;
樹木砍伐建議,須顯示將予砍伐的植物位置、大小、數量及品種;
(e)
tree compensation proposal showing locations, size,
number and plant species to be provided or compensated;
補償植樹建議,須顯示將予栽種或補償種植樹木的位置、大小、數量及品種;
(f)
post-planting care proposal showing the proposed
establishment period and associated maintenance care requirements and frequency
of transplanted trees and trees planted as compensation under this Condition; and
植樹後護理的建議,須顯示就本條件規定而補償移植和種植樹木的建議培植期、相關的保養護理要求及次數;以及
(g)
implementation programme, maintenance and management
schedules for measures proposed in (a) to (f) above.
上文(a)至(f)項建議措施的實施計劃、保養及管理時間表。
The
proposals under Condition 2.13(b) to (f) shall be prepared by the Certified
Arborist appointed under Condition 2.5.
The Plan shall be certified by the ET Leader and verified by the IEC
as conforming to the information and recommendations contained in the approved SCL(TAW-HUH) EIA
Report (Register No. AEIAR-167/2012), SCL(HHS) EIA
Report (Register No. AEIAR-164/2012) and the application for variation of Environmental
Permit as listed in Part A of this Permit. All measures
recommended in the approved Plan shall be fully and properly implemented and
maintained for the Project.
條件第2.13(b)至(f)項所指的建議須由條件第2.5項委聘的註冊樹藝師擬備。有關計劃須由環境小組組長核證及獨立環境查核人核實,證明其符合核准的SCL(TAW-HUH) 環評報告(登記冊檔號:AEIAR-167/2012)、SCL(HHS)環評報告(登記冊檔號:AEIAR-164/2012)及本許可證A部所臚列的更改環境許可證的申請文件所載的資料及建議。核准計劃建議的所有措施均須為工程項目徹底及妥善執行及維持。
提交具重要保護價值的植物品種移植建議
2.14
To mitigate the ecological impact due to the loss of
plant species of conservation importance, Aquilaria sinensis, the affected
plants within the works area shall be transplanted before the commencement of
construction. A detailed
pre-transplantation survey shall be carried out to ascertain the presence and
the locations of plant species, Aquilaria sinensis wthin the works
area. The Permit Holder shall, no later
than two months before commencement of transplanting works, deposit with the
Director four hard copies and one electronic copy of transplantation proposal. The detailed
transplantation proposal shall include the following information:
為減輕因損失具重要保護價值的植物品種而造成的生態影響,工程範圍內受影響的植物牙香樹須在建造工程展開前移植,並須進行移植前的詳細調查,以確定植物品種牙香樹在工程範圍內的存在及位置。許可證持有人須在移植工作展開前,至少提早2個月向署長存放移植建議書的4份硬複本及1份電子版本。詳細的移植建議書須包括下列資料:
(a)
qualification of the specialist(s) to carry out the
transplantation works;
負責移植工作的專家資歷;
(b)
number, locations and photographs of plants to be
transplanted;
將予移植的植物數量、位置及照片;
(c)
locations of the receptor sites for transplantation;
接收移植植物地點的位置;
(d)
methodology and implementation programme; and
方法及執行計劃;以及
(e)
detailed schedule for post-transplantation maintenance
and monitoring of plants.
移植後詳細的植物保養及監察程序。
Before submission to the Director, the transplantation proposal shall
be certified by the ET Leader and verified by the IEC as conforming to the
information and recommendations contained in the approved SCL(TAW-HUH) EIA
Report (Register No. AEIAR-167/2012) and SCL(HHS) EIA Report (Register No.
AEIAR-164/2012).
移植建議書在提交署長前,須由環境小組組長核證及獨立環境查核人核實,證明其符合核准的SCL(TAW-HUH) 環評報告(登記冊檔號:AEIAR-167/2012)及SCL(HHS)環評報告(登記冊檔號:AEIAR-164/2012)所載的資料及建議。
Submission of Conservation
Plan
提交保護計劃
2.15
The Permit Holder shall, no
later than two months before the commencement of construction works affecting
the two historic buildings, namely Former Royal Air Force Hangar and the Old
Pillbox at the former Tai Hom Village site, submit four hard copies and one electronic copy of the
conservation plan for the said two historic buildings to the Director for
approval. The conservation plan shall include at least
the following information:
在影響兩座歷史建築物(即位於前大磡村用地的前皇家空軍飛機庫及機槍堡)的建造工程展開前,許可證持有人須至少提早2個月把該兩座歷史建築物保護計劃的4份硬複本及1份電子版本提交署長審批。保護計劃須至少包括以下資料:
(a)
a detailed plan for dismantling and reinstating the
two said historic buildings; and
拆卸及重置該兩座歷史建築物的詳細計劃;以及
(b)
implementation programme, maintenance and management
schedules for actions recommended in the plan.
計劃所建議採取的執行計劃、保養及管理程序。
Before submission
to the Director, the conservation plan shall be certified by the ET Leader and verified
by the IEC as conforming to the information and recommendations contained in
the approved
SCL(TAW-HUH)
EIA Report (Register No. AEIAR-167/2012) and SCL(HHS) EIA Report (Register No.
AEIAR-164/2012). All
measures recommended in the approved conservation plan shall be fully and
properly implemented for the Project.
保護計劃在提交署長前,須由環境小組組長核證及獨立環境查核人核實,證明其符合核准的SCL(TAW-HUH) 環評報告(登記冊檔號:AEIAR-167/2012)及SCL(HHS)環評報告(登記冊檔號:AEIAR-164/2012)所載的資料及建議。核准的保護計劃建議的所有措施均須為工程項目徹底及妥善執行。
Submission
of Archaeological Action Plan(s) (AAP(s))
提交考古行動計劃
2.16
The Permit Holder shall, no later than two months
before the commencement of the further archaeological investigation at the former Tai Hom Village site or the Sacred Hill (North) study area, deposit with
the Director four hard copies and
one electronic copy of Archaeological Action Plan(s) for the sites. The Archaeological
Action Plan(s) shall include:
許可證持有人在前大磡村用地或聖山(北)的研究範圍作進一步考古勘探前,須至少提早2個月向署長存放有關土地的考古行動計劃的4份硬複本及1份電子版本。考古行動計劃須包括:
(a)
a detailed plan for further archaeological
investigation and rescue excavation at the former Tai Hom Village site and the
Sacred Hill (North) study area;
在前大磡村用地及聖山(北)的研究範圍作進一步考古勘探及搶救發掘的詳細計劃;
(b)
a contingency plan to address possible arrangement
when significant archaeological findings are unearthed during the further
archeological investigation and rescue excavation.
制訂應變計劃,應付當進一步考古勘探及搶救發掘進行期間有重大考古發現時的可能安排。
Before submission to the Director, the AAP(s) shall be certified by the
ET Leader and verified by the IEC as conforming to the information and
recommendations contained in the approved SCL(TAW-HUH) EIA Report (Register No. AEIAR-167/2012)
and SCL(HHS) EIA Report (Register No. AEIAR-164/2012). All measures
recommended in the deposited AAP(s) shall be fully and properly implemented for
the Project.
考古行動計劃在提交署長前,須由環境小組組長核證及獨立環境查核人核實,證明其符合核准的SCL(TAW-HUH) 環評報告(登記冊檔號:AEIAR-167/2012)及SCL(HHS)環評報告(登記冊檔號:AEIAR-164/2012)所載的資料及建議。經存放的考古行動計劃建議的所有措施均須為工程項目徹底及妥善執行。
Submissions or
Measures to be Implemented During Construction of the Project
建造工程項目期間須提交的文件或採取的措施
Measures for Avoiding
Impact on Lung Tsun Stone Bridge and Former Kowloon City Pier
為避免龍津石橋及前九龍城碼頭受影響而採取的措施
2.17
To avoid direct impact on the remains of Lung Tsun
Stone Bridge and Former Kowloon City Pier, no at-grade construction works of
the Project shall be carried out inside the “buffer zone” for the remains of
Lung Tsun Stone Bridge and Former Kowloon City Pier as shown in the Figure 6
of this Permit.
為避免對龍津石橋及前九龍城碼頭的遺址有直接影響,本許可證圖6所示的龍津石橋和前九龍城碼頭遺址之間的「緩衝距離」內不得進行工程項目的地面建造工程。
Measures for
Mitigating Construction Dust Impact
建築塵埃影響的緩解措施
2.18
In order to minimize the
construction dust impact, the following dust mitigation measures shall be implemented:-
為盡量減低建築塵埃影響,須實施以下的塵埃緩解措施:
(a)
watering once every working
hour for active works areas, exposed areas and paved haul roads in Kowloon area
to keep these active works areas, exposed areas and paved haul roads wet;
每1 個工作小時在九龍區施工中的工程區、露天地區和已鋪面的工地通道上灑水一次,以保持這些施工中的工程區、露天地區和已鋪面的工地通道濕潤;
(b)
watering once every 1.5 working hours for active
works areas, exposed areas and paved haul roads in Tai Wai area to keep these
active works areas, exposed areas and paved haul roads wet; and
每1.5個工作小時在大圍區施工中的工程區、露天地區和已鋪面的工地通道上灑水一次,以保持這些施工中的工程區、露天地區和已鋪面的工地通道濕潤;以及
(c)
enclosing the unloading process at any barging point
by a 3-sided screen with top tipping hall, and operating water spraying and flexible
dust curtains at the discharge point.
卸泥的過程須在有蓋三面圍封的躉船轉運站的卸貨區進行,並須在排放口灑水和加裝彈性擋塵幕。
Measures for Mitigating Aerial
Emissions from Construction Plant
建造機械空氣污染物排放的緩解措施
2.19
All diesel fuelled construction plant, including
marine vessels if possible, used by the contractors
within the works areas of the Project shall be powered by ultra low sulphur
diesel fuel.
承辦商在工程項目施工區內所使用的柴油推動建造機械,包括船隻(如可能的話),全部均須以超低含硫量柴油推動。
Measures for Mitigating
Water Quality Impact from Dredging Works
挖泥工程對水質影響的緩解措施
2.20
All dredging works for the Kai Tak Runway Barging
Point shall only be carried out within the site boundary as shown in Figure
7 of this Permit. No extension of the site boundary shall be permitted without the
written approval of the Director.
啓德機場跑道躉船轉運站的所有挖泥工程只限在本許可證圖7所示的地界內進行。未經署長的書面批准,不得擴展地界。
2.21
Dredging shall only be carried out by closed grab
dredger or backhoe dredger with closed bucket. The dredging rate shall not exceed 500 m3
per day. The dredging rate shall not
exceed 41.7m3 per hour for closed grab dredger or 33.3 m3 per
hour for backhoe dredger with closed bucket. Other than closed grab dredger or backhoe
dredger with closed bucket, the use of other type of dredger and
the dredging rate shall be approved in writing by the Director before use.
挖泥工程只可採用密封式抓斗挖泥機或閉合式鏟斗反鏟挖泥機進行。挖泥量每日不得超過500立方米。密封式抓斗挖泥機的挖泥量每小時不得超過 41.7立方米,而閉合式鏟斗反鏟挖泥機每小時不得超過33.3立方米。除密封式抓斗挖泥機或閉合式鏟斗反鏟挖泥機外,其他類型挖泥機的使用或挖泥量須在使用前事先獲署長書面批准。
2.22
Each closed grab dredger or backhoe dredger with closed
bucket or other type of dredger approved
by the Director shall be enclosed by silt curtain during dredging
works.
在挖泥工程進行期間,每部密封式抓斗挖泥機或閉合式鏟斗反鏟挖泥機或署長批准的其他類型挖泥機須以隔泥幕圍封。
Submission of Contamination Assessment Report and Remedial Action Plan
(SLCA)
提交污染評估報告和整治計劃書
2.23
Supplementary land contamination assessment (SLCA)
for the New Territories South Animal Centre in Hin Keng as shown in Figure 8
of this Permit for soil sampling and analysis of cyanide (free) shall be
carried out after the site is handed over to the Permit Holder. The Permit Holder shall, no later than one
month after the completion of the land contamination investigation, deposit
with the Director three hard copies and one electronic copy of Contamination
Assessment Report (CAR) to document the SLCA findings. If land contamination is
confirmed, the Permit Holder shall also submit to the Director for approval
three hard copies and one electronic copy of Remedial Action Plan (RAP) to formulate
necessary remedial measures. Before
submission to the Director, the CAR and RAP shall be certified by the ET Leader
and verified by the IEC as conforming to the information and recommendations
contained in the approved SCL(TAW-HUH) EIA Report (Register No. AEIAR-167/2012).
在土地移交許可證持有人後,許可證持有人須就本許可證圖8所示位於顯徑的新界南動物管理中心的泥土取樣和氰化物(游離)分析進行附加土地污染評估。許可證持有人須在完成土地污染調查工作後1個月內,向署長存放污染評估報告的3份硬複本及1份電子版本,該報告須記錄附加土地污染評估的結果。倘若土地證實受到污染,許可證持有人須制訂所需的整治措施,並把整治計劃書的3份硬複本及1份電子版本提交署長審批。污染評估報告及整治計劃書在提交署長前,須由環境小組組長核證及獨立環境查核人核實,證明其符合核准的SCL(TAW-HUH) 環評報告(登記冊檔號:AEIAR-167/2012)所載的資料及建議。
Measures for Mitigating
Land Contamination and Submission of Remediation Works Report
土地污染緩解措施及提交整治工程報告
2.24
If land contamination is confirmed, all remedial
measures described in the RAP approved under Condition 2.23 of this Permit
shall be fully implemented.
倘若土地證實受到污染,許可證持有人須徹底執行按本許可證條件第2.23項核准的整治計劃書載述的所有整治措施。
2.25
If remediation is required, the Permit Holder
shall deposit three hard copies and one electronic copy of Remediation Report
(RR) to the Director, no later than one month after the completion of the
remediation works. The RR shall provide
details on the remediation works carried out, types and volume of contaminated
soil, standards and levels of treatment, and locations of all on-site and
off-site disposal sites (including record of disposal). The RR shall be certified by the ET Leader
and verified by the IEC to demonstrate that Condition 2.24 is fulfilled. No construction
works at the New Territories South Animal Centre in Hin Keng shall be carried out prior to the EPD's endorsement of the said RR.
如須進行整治,許可證持有人須在整治工程完成後1個月內,向署長存放整治報告的3份硬複本及1份電子版本。整治報告須提供所進行的整治工程詳情、受污染泥土的類別及數量、處理標準及水平,以及所有工地及工地以外的棄置地點位置(連同棄置記錄)。整治報告須由環境小組組長核證及獨立環境查核人核實,證明已履行條件第2.24項的規定。該整治報告獲環保署通過前,許可證持有人不得在位於顯徑的新界南動物管理中心進行建造工程。
Submissions
and Measures Before and During Operation of the Project
在工程項目營辦之前及期間須提交的文件及採取的措施
Submissions and Measures for Mitigating
Operational Noise Impacts
就運作噪音影響提交的文件及採取的緩解措施
2.26
The Permit Holder shall operate 8-car type SP 1900
/ SP 1950 train or other train type with equivalent or better noise performance
supported with justifications by the ET Leader and verified by the IEC as
conforming to the information, requirements and recommendations as set out in
the approved SCL(TAW-HUH) EIA Report (Register No. AEIAR-167/2012) and SCL(HHS)
EIA Report (Register No. AEIAR-164/2012).
許可證持有人營辦工程項目須採用8節車廂的SP1900/SP1950型列車,或其他在噪音表現方面相等或較佳的列車型號,惟須由環境小組組長提出理據支持及由獨立環境查核人核實,證明其符合核准的SCL(TAW-HUH) 環評報告(登記冊檔號:AEIAR-167/2012)及SCL(HHS)環評報告(登記冊檔號:AEIAR-164/2012)所載的資料、規定及建議。
2.27
The Permit Holder shall, no
later than one month after completion of corresponding parts of the tunnel
excavation of the Project, deposit with the Director four hardcopies and one
electronic copy of an Operational Ground-borne Noise Mitigation Measures Plan
to justify the adequacy of the operational ground-borne noise mitigation
measures for the Project. The Plan shall include the review and
verification of the assumptions adopted in the approved SCL(TAW-HUH) EIA
Report (Register No. AEIAR-167/2012) and SCL(HHS) EIA Report (Register No.
AEIAR-164/2012), such as line source response and ground
vibration conditions, and shall also include justifications and recommendations
for any contingency noise mitigation measures found necessary, including but
not limited to:
許可證持有人須在工程項目隧道挖掘工程的相關部分竣工後1個月內,向署長存放地層傳導運作噪音緩解措施計劃的4份硬複本及1份電子版本,以證明就工程項目的地層傳導運作噪音所建議的緩解措施是否足夠。該計劃須檢討及核實核准的SCL(TAW-HUH) 環評報告(登記冊檔號:AEIAR-167/2012)及SCL(HHS)環評報告(登記冊檔號:AEIAR-164/2012)內採用的假設,例如線狀震源傳遞性及地層震動的情況,並須包括實施所需的任何額外噪音緩解措施的理據及建議,包括但不限於:
(a)
resilent baseplates (type 1)
彈性底板 (類別1)
(b)
isolated slab track (type 4)
隔離式道床 (類別 4)
Before submission to the Director, the
Operational Ground-borne Noise Mitigation Measures Plan shall be certified by the
ET Leader and verified by the IEC as conforming to the information and
recommendations contained in the approved SCL(TAW-HUH) EIA Report (Register
No. AEIAR-167/2012) and SCL(HHS) EIA Report (Register No. AEIAR-164/2012).
地層傳導運作噪音緩解措施計劃在提交署長前,須由環境小組組長核證及獨立環境查核人核實,證明其符合核准的SCL(TAW-HUH) 環評報告(登記冊檔號:AEIAR-167/2012)及SCL(HHS)環評報告(登記冊檔號:AEIAR-164/2012)所載的資料及建議。
2.28
The Permit Holder shall, no later than one month
after completion of installation of rail tracks, deposit with the Director four
hard copies and one electronic copy of a set of as-built drawing(s) for the
operational ground-borne noise mitigation measures as recommended in the
Operational Ground-borne Noise Mitigation Measures Plan deposited under
Condition 2.27 above. Before submission to the Director, the set of
as-built drawing(s) shall be certified by the ET Leader and verified by
the IEC to demonstrate that measures as set out in the Plan deposited under
Condition 2.27 above has been fully and properly implemented.
許可證持有人須在鐵路路軌安裝工程竣工後1個月內,根據上文條件第2.27項存放的地層傳導運作噪音緩解措施計劃內建議的地層傳導運作噪音緩解措施,向署長存放整套竣工圖的4份硬複本及1份電子版本。整套竣工圖在提交署長前,須由環境小組組長核證及獨立環境查核人核實,證明按條件第2.27項存放的計劃所列明的措施已徹底及妥善執行。
2.29
To mitigate the operational air-borne noise from the
viaduct section between Tai Wai Station and Hin Keng Station and from the
operation of the stabling sidings at Hung Hom, noise mitigation measures as
shown in Table 2 and Figures 9a, 9b, 10 and 11 of this Permit
shall be installed.
為緩解大圍站至顯徑站的一段高架橋段及紅磡列車停放處運作時產生經空氣傳導的運作噪音,許可證持有人須設置本許可證表2和圖9a、9b、10及11所示的噪音緩解措施。
2.30
The Permit Holder shall, no later than one month
after the completion of installation of noise mitigation measures as required
under Condition 2.29 above, deposit with the Director four hard copies and one
electronic copy of a set of as-built drawings showing:-
許可證持有人須在按上文條件第2.29項規定完成設置噪音緩解措施後的1個月內,向署長存放整套竣工圖的4份硬複本及1份電子版本,當中須顯示:
(a)
the operational air-borne noise mitigation measures
under Condition 2.29 above; and
按上文條件第2.29項規定設置的空氣傳導運作噪音緩解措施;以及
(b)
any additional or changes in measures if required.
任何額外措施或修訂措施(如有需要)。
Before submission to the Director, the as-built drawings for
operational air-borne noise mitigation measures shall be certified by the ET
Leader and verified by the IEC as conforming to the information and
recommendations contained in the approved SCL(TAW-HUH) EIA Report (Register No. AEIAR-167/2012)
and SCL(HHS) EIA Report (Register No. AEIAR-164/2012). All measures
recommended in the deposited as-built drawings shall be fully and properly
implemented and maintained for the Project.
空氣傳導運作噪音緩解措施的整套竣工圖在提交署長前,須由環境小組組長核證及獨立環境查核人核實,證明其符合核准的SCL(TAW-HUH) 環評報告(登記冊檔號:AEIAR-167/2012)及SCL(HHS)環評報告(登記冊檔號:AEIAR-164/2012)所載的資料及建議。已存放的竣工圖所建議的全部措施,均須為工程項目徹底及妥善執行與維持。
2.31
At least one month before commencement of operation
of the Project, the Permit Holder shall carry out noise performance test and
deposit with the Director four hard copies and one electronic copy of a Noise
Performance Test Report to confirm the compliance of the operational air-borne
and ground-borne noise levels in accordance with the approved SCL(TAW-HUH) EIA
Report (Register No. AEIAR-167/2012) and SCL(HHS) EIA Report (Register No.
AEIAR-164/2012). Before submission to the
Director, the Noise Performance Test Report shall be certified by the ET Leader
and verified by the IEC as conforming to the information and recommendations
contained in the approved SCL(TAW-HUH) EIA
Report (Register No. AEIAR-167/2012) and SCL(HHS) EIA Report (Register No.
AEIAR-164/2012). Any necessary measure(s) as
recommended in the Noise Performance Test Report shall be fully and properly
implemented and maintained for the Project.
在工程項目展開營辦前,許可證持有人須至少提早1個月進行噪音水平測試,並向署長存放噪音水平測試報告的4份硬複本及1份電子版本,以確定空氣和地層傳導運作噪音水平符合核准的SCL(TAW-HUH) 環評報告(登記冊檔號:AEIAR-167/2012)及SCL(HHS)環評報告(登記冊檔號:AEIAR-164/2012)的規定。噪音水平測試報告在提交署長前,須由環境小組組長核證及獨立環境查核人核實,證明其符合核准的SCL(TAW-HUH) 環評報告(登記冊檔號:AEIAR-167/2012)及SCL(HHS)環評報告(登記冊檔號:AEIAR-164/2012)所載的資料及建議。噪音水平測試報告建議的所需措施,均須為工程項目徹底及妥善執行與維持。
2.32
At least one month before commencement of operation
of the Project, the Permit Holder shall carry out fixed plant noise audit and
deposit with the Director four hardcopies and one
electronic copy of an audit report showing the design of the fixed plant noise
sources associated with the Project complies with the maximum sound power
levels determined in the approved SCL(TAW-HUH) EIA Report (Register No. AEIAR-167/2012)
and SCL(HHS) EIA Report (Register No. AEIAR-164/2012)
and all relevant documents in the Register, or otherwise approved by the
Director in compliance with the requirements in Technical Memorandum on
Environmental Impact Assessment Process having due regard to the
characteristics of tonality, impulsiveness and intermittency. The audit
report shall be certified by the ET Leader and verified by the IEC as conforming to the
information and recommendations contained in the approved SCL(TAW-HUH) EIA Report (Register No. AEIAR-167/2012)
and SCL(HHS) EIA Report (Register No. AEIAR-164/2012)
and all relevant documents in the Register.
在工程項目展開營辦前,許可證持有人須至少提早1個月進行機房設備噪音審核,並向署長存放審核報告的4份硬複本及1份電子版本,顯示與工程項目有關的機房設備的設計令噪音源符合核准的SCL(TAW-HUH) 環評報告(登記冊檔號:AEIAR-167/2012)及SCL(HHS)環評報告(登記冊檔號:AEIAR-164/2012) 及登記冊內的所有相關文件訂定的最高聲功率級;或署長批准的其他最高聲功率級,而該最高聲功率級須符合環境影響評估程序的技術備忘錄的要求,並須適當考慮噪音音調、脈衝和斷續因素的特性。審核報告須由環境小組組長核證及獨立環境查核人核實,證明其符合核准的SCL(TAW-HUH) 環評報告(登記冊檔號:AEIAR-167/2012)及SCL(HHS)環評報告(登記冊檔號:AEIAR-164/2012)及登記冊內的所有相關文件所載的資料及建議。
Submissions of
As-Built Drawings of Measures for Mitigating Landscape and Visual Impacts
提交景觀及視覺影響緩解措施的竣工圖
2.33
At least one month before the Project commences
operation, four hard copies and one electronic copy of as-built drawing(s) on landscape
and visual mitigation measures with an explanatory statement showing the final
locations, size, number and species of planting to demonstrate compliance with
the approved submissions under Condition 2.13 of this Permit shall be deposited
with the Director. This as-built
submission shall be certified by the ET Leader and verified by the IEC that the
Visual, Landscape and Tree Planting & Tree Protection Plan approved under
Condition 2.13 has been fully and properly implemented.
在工程項目展開營辦前,許可證持有人須至少提早1個月向署長存放景觀及視覺緩解措施竣工圖的4份硬複本及1份電子版本。竣工圖須附有說明,詳述植樹的最終位置、大小、數量及品種,以展示符合根據本許可證條件第2.13項提交的核准文件。所提交的竣工圖須由環境小組組長核證及獨立環境查核人核實,證明根據條件第2.13項核准的視覺、景觀及植樹與樹木保護計劃已徹底及妥善執行。
Measures for Mitigating Impacts on Water
Quality from Track Run-off
鐵路路軌徑流對水質影響的緩解措施
2.34
To mitigate water quality impact from tunnel run-off
from rail track :-
為緩解鐵路路軌的隧道徑流對水質的影響:
(a)
track drainage discharges shall pass through
oil/grit interceptors/chambers to remove oil, grease and sediment before
discharging into public storm drainage/foul sewerage systems;
路軌排水渠排出的污水應先經過油污/砂礫截流管/池,以清除油污、油脂及沉積物,然後排進公眾雨水渠/公共污水渠系統;
(b)
the silt traps and oil interceptors shall be cleaned
and maintained regularly; and
淤泥收集器及集油器應定期清潔及保養;以及
(c)
oily contents of the oil interceptors shall be
transferred to an appropriate disposal facility, or to be collected for reuse,
if possible.
集油器內收集的油污應轉移到適當的處置設施或在可能時回收利用。
Submissions and Measures for Decommissioning of the Temporary Magazine Site at TKO Area 137
須就解除運作將軍澳第137區臨時爆炸品倉庫提交的文件及採取的措施
Measure for Decommissioning of the
Temporary Magazine Site at TKO Area 137
須就解除運作將軍澳第137區臨時爆炸品倉庫採取的措施
2.35
The
Permit Holder shall ensure that there is no explosive being stored in the
magazine and the “Licence to Possess Category 1 Dangerous Goods” has been
returned and accepted by Mines Division of Civil Engineering and Development
Department before the commencement of the decommissioning works.
許可證持有人須確保在解除運作工程展開前,該爆炸品倉庫並無貯存任何炸藥,並已交還「第一類危險品管有牌照」及獲土木工程拓展署礦務部接納。
Submissions and Measures for Land
Contamination Assessment
須就土地污染評估提交的文件及採取的措施
2.36
Land
contamination assessment for the temporary explosive magazine site as shown in
Figure 5 of this Permit shall be carried out. The Permit Holder shall,
許可證持有人須就本許可證圖5所示的臨時爆炸品倉庫進行土地污染評估。許可證持有人須:
(a)
no
later than one month before the commencement of the land contamination site
investigation, submit three hard copies and one electronic copy of
Contamination Assessment Plan (CAP) to the Director for approval. The CAP shall
include proposal with details of representative sampling and analysis required
to determine the nature and extent of contamination;
在土地污染場地勘察工作展開前,至少提早1個月向署長提交污染評估計劃書的3份硬複本及1份電子版本,以供批准。污染評估計劃書須提出建議,連同為確定污染性質及範圍所須進行代表性取樣及分析的詳情;
(b)
no
later than one month after the completion of the land contamination site
investigation works, submit three hard copies and one electronic copy of
Contamination Assessment Report (CAR) to the Director for approval which shall
document the land contamination assessment findings.
在土地污染場地勘察工作完成後1個月內,向署長提交污染評估報告的3份硬複本及1份電子版本,載述土地污染評估結果,以供批准;
(c)
If
land contamination and the need for remediation is confirmed, the Permit Holder
shall submit to the Director for approval three hard copies and one electronic
copy of Remediation Action Plan (RAP) to formulate necessary remedial measures.
All remedial measures described in the approved RAP shall be fully implemented.
The Permit Holder shall also submit three hard copies
and one electronic copy of
Remediation
Report (RR) to the Director for approval, no later than one month after the completion of the remediation works. The RR shall provide details on the remediation works carried out, types
and volume of contaminated soil, standards and levels of treatment, and
location(s) of disposal site(s)
(including record of disposal).
倘若證實土地受到污染及有需要進行整治,許可證持有人須制訂所需整治措施並向署長提交整治計劃書的3份硬複本及1份電子版本,以供批准。核准整治計劃書載述的所有整治措施必須徹底執行。在整治工程完成後1個月內,許可證持有人亦須向署長提交整治報告的3份硬複本及1份電子版本,以供批准。整治報告須提供所進行整治工程的詳情、受污染泥土的類別及數量、處理標準及水平,以及棄置地點的位置(包括棄置記錄)。
Before submission to the Director, the CAP,
CAR, RAP and RR shall be certified by the ET Leader and verified by the IEC as
conforming to the information and recommendations contained in the application
for Variation of Environmental Permit (No. VEP-495/2016).
污染評估計劃書、污染評估報告、整治計劃書及整治報告在提交署長前,須由環境小組組長核證及獨立環境查核人核實,證明其符合更改環境許可證申請文件(編號:VEP-495/2016)所載的資料及建議。
3.
Environmental
Monitoring and Audit (EM&A) Requirements
環境監察及審核規定
3.1
The EM&A programme shall be implemented in
accordance with the procedures and requirements in the SCL(TAW-HUH) EM&A Manual,
SCL(HHS) EM&A Manual and the Continuous Noise Monitoring Plan approved
under Condition 2.10 of this Permit. The
Permit Holder shall review the EM&A requirements or programme based on the
submitted construction programme required under Condition 2.8. Any changes to the EM&A requirements or programme and termination of
the EM&A programme shall be supported with justifications by the ET leader
and verified by the IEC as conforming to the requirements set out in the SCL(TAW-HUH) EM&A
Manual, SCL(HHS) EM&A Manual and the Continuous Noise Monitoring Plan
approved under Condition 2.10 of this Permit, and prior
approval from the Director shall be sought before their implementation.
環監計劃須按SCL(TAW-HUH)環監手冊、SCL(HHS)環監手冊及按本許可證條件第2.10項核准的持續噪音監測計劃所載的程序及規定執行。許可證持有人須根據條件第2.8項提交的建造工程計劃檢討有關環監規定或計劃。環監規定或計劃如有任何更改,或環監計劃如需終止,須由環境小組組長提出充分理由支持,並由獨立環境查核人核實,證明其符合SCL(TAW-HUH)環監手冊、SCL(HHS)環監手冊及按本許可證條件第2.10項核准的持續噪音監測計劃所載規定,並須事先取得署長的批准,方可執行。
3.2
Samples, measurements and
necessary remedial actions shall be taken in accordance with the requirements
of the SCL(TAW-HUH)
EM&A Manual and SCL(HHS) EM&A Manual by:
取樣、測量及所需的補救行動,均須按照SCL(TAW-HUH)環監手冊及SCL(HHS)環監手冊所載規定進行:
(a)
conducting baseline
environmental monitoring;
進行環境基線監測;
(b)
conducting impact
monitoring;
進行影響監測;
(c)
carrying out remedial actions
described in the Event/Action Plans of the SCL(TAW-HUH) EM&A Manual
and SCL(HHS) EM&A Manual in accordance with the time
frame set out in the Event/Action Plans, or as agreed by the Director, in case
where specified criteria in the SCL(TAW-HUH) EM&A Manual and SCL(HHS) EM&A
Manual are exceeded; and
如超逾SCL(TAW-HUH)環監手冊及SCL(HHS)環監手冊內指定的標準,則按照SCL(TAW-HUH)環監手冊及SCL(HHS)環監手冊內的事件/行動計劃所訂明的時限或署長所同意的時限,執行事件
/ 行動計劃所說明的補救行動;以及
(d)
logging and keeping records
of the details of (a) to (c) above for all parameters within 3 working days of
the collection of data or completion of remedial action(s), for the purpose of
preparing and submitting the monthly EM&A Reports and to make available the
information for inspection on site.
在收集數據或完成補救行動3個工作天內,記錄及備存上文(a)至(c)項所有參數的詳情,用作擬備並提交每月環監報告,並備妥有關資料以供在工地查閱。
3.3
Four hard copies and one
electronic copy of the Baseline Monitoring Report shall be submitted to the
Director at least 2 weeks before the commencement of construction of the
Project. The submission shall be certified by the ET Leader and verified
by the IEC. Additional copies of the submission shall be provided upon
request by the Director.
在工程項目的建造工程展開前,須至少提早2個星期向署長提交基線監測報告的4份硬複本及1份電子版本。提交文件須由環境小組組長核證及獨立環境查核人核實。如署長要求,則須提交文件的額外複本。
3.4
Four
hard copies and one electronic copy of monthly EM&A Report shall be
submitted to the Director within 2 weeks after the end of the reporting month.
The EM&A Reports shall include a summary of all non-compliance
(exceedances) of the environmental quality performance limits (Action and Limit
Levels). The submissions shall be certified by the ET Leader and verified
by the IEC as complying with the requirements set out in the SCL(TAW-HUH) EM&A
Manual, SCL(HHS) EM&A Manual. Additional copies of
the submission shall be provided to the Director upon request by the Director.
在規定提交報告的月份結束後2個星期內,須向署長提交每月環監報告的4份硬複本及1份電子版本。環監報告須包括各種不符合(超出)環境質素表現規限(行動及極限水平)情況的摘要。文件在提交署長前,須由環境小組組長核證及獨立環境查核人核實,證明符合SCL(TAW-HUH)環監手冊及SCL(HHS)環監手冊所載的規定。如署長要求,則須提交每月環監報告的額外複本。
3.5
All EM&A data submitted
under this Permit shall be true, valid and correct.
根據本許可證提交的所有環監數據,均須有效及真實無誤。
4.
Electronic Reporting
of EM&A Information
環監資料的電子匯報
4.1
To facilitate public inspection of the Baseline Monitoring Report and
monthly EM&A Reports via the EIAO Internet Website and at the EIAO Register
Office, electronic copies of these Reports shall be prepared in Hyper Text
Markup Language (HTML) (version 4.0 or later) and in Portable Document Format
(PDF version 1.3 or later), unless otherwise agreed by the Director and shall
be submitted at the same time as the hard copies as described in Condition 3.3
and 3.4 above of this Permit. For the HTML version, a content page
capable of providing hyperlink to each section and sub-section of these Reports
shall be included in the beginning of the document. Hyperlinks to all figures,
drawings and tables in these Reports shall be provided in the main text from
where the respective references are made. All graphics in these Reports
shall be in interlaced GIF format unless otherwise agreed by the Director.
The content of the electronic copies of these Reports must be the same as
the hard copies.
為方便公眾透過環評條例互聯網網站及在環評條例登記冊辦事處查閱基線監測報告及每月環監報告,以超文本標示語言 (HTML)
(第4.0或較後版本) 及便攜式文件格式 (PDF) (第1.3或較後版本) 製作的報告的電子版本,除非另獲署長同意,須與本許可證上文條件第3.3及3.4項所說明的硬複本同時提交。關於HTML的版本方面,可與報告各節及小節作出超文本連結的目錄須在文件開端加入。報告內各類圖表須在載有相關資料的正文內作出超文本連結。除非另獲署長同意,報告內所有圖形均須以交錯存取的GIF格式制定。報告的電子版本內容,必須與硬複本的內容一致。
4.2
The Permit Holder shall set up a dedicated website and notify the
Director in writing the internet address where the environmental monitoring
data and project information is to be placed within 1 month after the
commencement of construction of the Project. All environmental monitoring
data described in Condition 4.1 of this Permit and all submissions required by
this Permit shall made available to the public via this dedicated website to be
set up by the Permit Holder in the shortest time practicable, and in no event
later than 2 weeks after the relevant environmental monitoring data are collected
or become available, unless otherwise agreed with the Director. The
Permit Holder shall maintain the dedicated website for public access of the
environmental monitoring data and reports throughout the entire construction
period and during the first 3-year period of operation of the Project, or
otherwise as agreed by the Director.
許可證持有人須在工程項目的建造工程展開後1個月內,設立特定網站存放環境監察及工程項目數據,並以書面通知署長有關網址所在。上文條件第4.1項說明的所有環境監察結果及本許可證規定提交的所有文件,均須盡快透過許可證持有人設立的特定網站供公眾查閱,在任何情況下均不得遲於有關環境監察數據收集或可供閱覽後的2個星期,除非另獲署長同意。許可證持有人除非另獲署長同意,否則須在工程項目整段施工期及首3年的營辦期期間維持特定網站的運作,以供公眾查閱環境監察的數據及報告。
4.3
The internet
website as described in Condition 4.2 of this Permit shall enable user-friendly
public access to the environmental monitoring data and project information
including the approved SCL(TAW-HUH) EIA Report (Register No. AEIAR-167/2012)
and SCL(HHS) EIA Report (Register No. AEIAR-164/2012), the environmental
permit(s) and Project Profile of the Project. The internet website shall have
features capable of:
本許可證條件第4.2項說明的互聯網網站,必須方便用戶使用,讓公眾容易接達監察數據及工程項目資料,包括工程項目的核准SCL(TAW-HUH) 環評報告(登記冊檔號:AEIAR-167/2012)及SCL(HHS)環評報告(登記冊檔號:AEIAR-164/2012)、環境許可證和工程項目簡介。除非另獲署長同意,互聯網網站須具備部件,提供下述功能:
(a)
providing
access to all environmental monitoring data of this Project collected since the
commencement of construction;
在建造工程展開後,接達所收集的工程項目全部環境監察數據;
(b)
providing
access to all finalized submissions as required under this Permit;
接達所有本許可證內要求提交的文件及計劃的最終版本;
(c)
searching
by date;
按日期搜尋;
(d)
searching
by types of monitoring data (water quality, noise and air quality); and
按監察數據類別 (水質、噪音及空氣質素) 搜尋;以及
(e)
hyperlinking
to relevant monitoring data after searching;
在搜尋後與相關的監察數據作出超文本連結;
or otherwise as agreed by the Director.
Notes:
註:
1. This Permit consists of three parts, namely, PART A (Main
Permit), PART B (Descriptions of Designated Project) and PART
C (Permit Conditions). Any
person relying on this Permit should obtain independent legal advice on the
legal implications under the EIAO, and the following notes are for general
information only.
本許可證共有3部,即A部(許可證主要部分);B部(指定工程項目的說明)及 C部(許可證條件)。任何援引本許可證的人士須就環評條例的法律含意徵詢獨立法律意見,下述註解只供一般參考用。
2.
If there is a breach of any condition of this
Permit, the Director or his authorized officer may, with the consent of the
Secretary for Environment and Ecology, order the cessation of associated work
until the remedial action is taken in respect of the resultant environmental
damage, and in that case the Permit Holder shall not carry out any associated
works without the permission of the Director or his authorized officer.
如違反本許可證的任何條件,署長或獲授權人員徵得環境及生態局局長的同意後可勒令停止相關工程,直至許可證持有人為所造成的環境損害採取補救行動為止。在此情況下,許可證持有人未經署長或獲授權人員同意,不得進行任何相關工程。
3. The Permit Holder may apply under Section 13 of the EIAO to the Director
for a variation of the conditions of this Permit. The Permit Holder shall
replace the original permit displayed on the Project site by the amended
permit.
許可證持有人可根據環評條例第13條的規定向署長申請更改本環境許可證的條件。許可證持有人須把經修改的許可證替換在工程項目工地內展示的原有許可證。
4. A person who assumes responsibility for the whole or a part of the
Project may, before he assumes responsibility of the Project, apply under
Section 12 of the EIAO to the Director for a further environmental permit.
承擔工程項目整項或部分工程項目的責任的人,在承擔責任之前,可根據環評條例第12條的規定向署長申請新的環境許可證。
5. Under Section 14 of the EIAO, the Director may with the consent of the
Secretary for Environment and Ecology, suspend, vary or cancel this Permit. The
suspended, varied or cancelled Permit shall be removed from display at the
site.
根據環評條例第14條的規定,署長可在環境及生態局局長的同意下暫時吊銷、更改或取消環境許可證。遭暫時吊銷、更改或取消的環境許可證必須從工地除下,不再展示。
6. If this Permit is cancelled or surrendered during construction of the
Project, another environmental permit must be obtained under the EIAO before
the Project could be continued. It is an offence under Section 26(1) of the
EIAO to construct or operate a designated project listed in Part I of Schedule
2 of the EIAO without a valid environmental permit.
如果本許可證在工程項目建造期間取消或交回,則在繼續進行工程項目之前,必須先根據環評條例規定取得另一份環境許可證。根據環評條例第26(1)條的規定,任何人在沒有有效環境許可證的情況下建造或營辦環評條例附表2第I部所列明的指定工程項目,即屬犯罪。
7. Any person who constructs
the Project contrary to the conditions in the Permit, and is convicted of an
offence under the EIAO, is liable:
(i)
on a
first conviction on indictment to a fine of $2 million and to imprisonment for
6 months;
(ii)
on a
second or subsequent conviction on indictment to a fine of $5 million and to
imprisonment for 2 years;
(iii)
on a
first summary conviction to a fine at level 6 and to imprisonment for 6 months;
(iv)
on a
second or subsequent summary conviction to a fine of $1 million and to
imprisonment for 1 year; and
(v)
in any
case where the offence is of a continuing nature, the court or magistrate may
impose a fine of $10,000 for each day on which he is satisfied the offence
continued.
如任何人在違反本許可證的條件下建造工程項目,且被裁定觸犯環評條例所訂明的罪行,即屬犯罪:
(i)
一經循公訴程序首次定罪,可處罰款200萬元及監禁6個月;
(ii)
一經循公訴程序第二次或其後每次定罪,可處罰款500萬元及監禁2年;
(iii)
一經循簡易程序首次定罪,可處第6級罰款及監禁6個月;
(iv)
一經循簡易程序第二次或其後每次定罪,可處罰款100萬元及監禁1年;以及
(v)
在任何情況下如該罪行屬持續性質,法院或裁判官可就其信納該罪行持續的每天另處罰款10,000元。
7. The Permit Holder may appeal against any condition of this Permit under
Section 17 of the EIAO within 30 days of receipt of this Permit.
許可證持有人可在接獲本許可證後30天內,根據環評條例第17條就本許可證的任何條件提出上訴。
9. The Notes are for general reference only and that the Permit Holder
should refer to the EIAO for details and seek independent legal advice.
上述註解只供一般參考用,欲知有關詳情,許可證持有人須參閱環評條例及徵詢獨立法律意見。
Environmental
Permit No. EP-438/2012/L
環境許可證編號EP-438/2012/L
Table 1 - List of noise sensitive receivers (NSRs) with predicted residual air-borne
construction noise impacts exceeding noise criteria as listed in
Table 1B of EIAO-TM (to be read in conjunction with Condition 2.9
of this Permit)
表1 – 噪音敏感受體列表,其預計的剩餘經空氣傳送建築噪音影響超逾《環境影響評估條例技術備忘錄》表1B所列的噪音準則(須與本許可證條件第2.9項一併閱讀)
(Extracted from
Table 8.15 of the SCL(TAW-HUH) EIA Report (Register No. AEIAR-167/2012)
(摘自 SCL(TAW-HUH)環評報告(登記冊檔號: AEIAR-167/2012)的表8.15
NSR ID 噪音敏感受體編號 |
NSR Description 噪音敏感受體名稱 |
Uses[1] 用途[1] |
Criterion [2] dB(A) 準則 [2] 分貝(A) |
Predicted Maximum Noise
Level dB(A) 預計的最高噪音水平 分貝(A) |
Predicted Residual Noise
Impact dB(A) 預計的剩餘噪音影響 分貝(A) |
TAW-6-7 |
C.U.H.K.A.A.
Thomas Cheung School 香港中文大學校友會聯會張煊昌學校 |
E |
70 (65)
[2] |
68(67) |
0 (2) [3] |
DIH-9-1 |
Shek On
Building 錫安樓 |
E + W |
70 (65)
[2] |
70 (70) |
0(5) [3] |
DIH-13-1 |
Canossa Primary
School 嘉諾撒小學 |
E |
70 (65)
[2] |
67(66) |
0(1) [3] |
DIH-14-1 |
Rhythm Garden
Block 2 采頤花園第2座 |
R |
75 |
77 |
2 |
DIH-14-4 |
Canossa Primary
School (San Po Kong) 嘉諾撒小學(新蒲崗) |
E |
70 (65)
[2] |
69 (68) |
0 (3) [3] |
DIH-14-5 |
Rhythm Garden
Block 1 采頤花園第1座 |
R |
75 |
78 |
3 |
TKW-1-1 |
Parc 22 22居 |
R |
75 |
80 |
5 |
TKW-2-2 |
Skytower Tower
2 傲雲峰第2座 |
R |
75 |
76 |
1 |
TKW-3-2 |
Prosperity
House 寧興樓 |
R |
75 |
80 |
5 |
MTW-12-3 |
Lucky Mansion 好運樓 |
R |
75 |
80 |
5 |
MTW-12-4 |
352-354 Ma Tau Wai Rd (East Façade) 馬頭圍道352-354號(東面) |
R |
75 |
80 |
5 |
MTW-12-4-1 |
352-354 Ma Tau
Wai Rd (North Facade) 馬頭圍道352-354號 (北面) |
R |
75 |
84 |
9 |
MTW-12-10 |
Lucky Building
(South Facade) 七喜大廈(南面) |
R |
75 |
84 |
9 |
MTW-12-10-1 |
Lucky Building
(East Facade) 七喜大廈(東面) |
R |
75 |
80 |
5 |
MTW-12-11 |
Jing Ming
Building 晶明大廈 |
R |
75 |
82 |
7 |
MTW-16-1 |
SKH Good
Shepherd Primary School 聖公會牧愛小學 |
E |
70 (65)
[2] |
79 (79) |
9(14) [3] |
MTW-18-2 |
No. 2 Kowloon
City Road 九龍城道2號 |
R |
75 |
81 |
6 |
HOM-2-1-A |
Faerie Court
(East Facade) 富怡閣(東面) |
R |
75 |
78 |
3 |
HUH-1-3 |
Wing Fung
Building 榮豐大樓 |
R |
75 |
77 |
2 |
Notes:
註:
[1] R- Residential; E – Educational institution;
W-Worship
R- 住宅; E – 教育機構; W- 敬拜場所
[2] Values in parentheses
indicate the noise criterion during examination period (typical
examination period in May, June, November and December)
of educational institution.
括號中的數值顯示教育機構考試時段的噪音準則(在5月、6月、11月及12月的一般考試時段)。
[3] Residual impact is only expected during
the examination period (typical examination period in May, June,
November and December) of the
educational institution.
只預計教育機構在考試時段受到的剩餘影響(在5月、6月、11月及12月的一般考試時段)。
Table 2 – Details
of requirements on noise barriers/enclosures (to be read in conjunction with
Condition 2.29 and Figures 9a 9b,10 and 11 attached to this Permit)
表 2 – 隔音屏障/隔音罩的規定詳情(須與本許可證條件第2.29項及夾附的圖9a、9b、10及11一併閱讀)
Location 位置 |
Track Direction 路軌方向 |
Type of noise
Mitigation Measures 噪音緩解措施類別 |
Length (m) 長度 (米) |
Height (m) 高度 (米) |
Hin Keng 顯徑 |
||||
P1 as shown on
Figures 9a and 9b of this Permit 本許可證圖9a和9b 所示的P1 |
Up track 上行路軌 |
Noise barrier 隔音屏障 |
350 |
2 |
P2 as shown on
Figures 9a and 9b of this Permit 本許可證圖9a和9b 所示的P2 |
Up track 上行路軌 |
Noise barrier 隔音屏障 |
100 |
2 |
P3 as shown on
Figures 9a and 9b of this Permit 本許可證圖9a和9b 所示的P3 |
Down track 下行路軌 |
Noise barrier 隔音屏障 |
150 |
3 |
P4 as shown on
Figures 9a and 9b of this Permit 本許可證圖9a和9b 所示的P4 |
Tail track 尾軌 |
Noise barrier 隔音屏障 |
300 |
7 |
P5 as shown on
Figures 9a and 9b of this Permit 本許可證圖9a和9b 所示的P5 |
Up track 上行路軌 |
Noise barrier 隔音屏障 |
50 |
3 |
South-west of
TAW near Mei Tin Road as shown on Figure 10 of this Permit 本許可證圖10所示的大圍西南面近美田路 |
N/A 不適用 |
Noise cover 隔音蓋 |
15 |
N/A 不適用 |
Hung Hum 紅磡 |
||||
P1 as shown in
Figure 11 of this Permit 本許可證圖11所示的P1 |
N/A 不適用 |
Semi-enclosure半密封式隔音罩 |
N/A 不適用 |
7 |
P2 as shown in
Figure 11 of this Permit 本許可證圖11所示的P2 |
N/A 不適用 |
Noise barrier 隔音屏障 |
35 |
5 |
P3 as shown in
Figure 11 of this Permit 本許可證圖11所示的P3 |
N/A 不適用 |
Noise barrier 隔音屏障 |
45 |
5 |