Environmental
Permit No. EP-565/2019/A
環境許可證編號 EP-565/2019/A
ENVIRONMENTAL
IMPACT ASSESSMENT ORDINANCE
(CHAPTER 499)
SECTIONS 10 AND 13
環境影響評估條例
(第499章)
第10條及第13條
ENVIRONMENTAL
PERMIT TO CONSTRUCT AND OPERATE
A
DESIGNATED PROJECT
建造及營辦指定工程項目的環境許可證
A部 (許可證主要部分)
Pursuant to Section 10 of the Environmental Impact Assessment Ordinance (EIAO),
the Director of Environmental Protection (the Director) granted the Environmental
Permit (No. EP-565/2019) to the Drainage Services Department (hereinafter referred to as the “Permit Holder”) on 26 April 2019.
Pursuant to Section 13 of the EIAO, the Director amends the Environmental
Permit (No. EP-565/2019) based on the Application No. VEP-640/2024. The
amendments, described below, are incorporated into this Environmental Permit
(No. EP-565/2019/A).
This Environmental Permit as amended is for the construction and operation of
the designated project described in Part B subject
to the conditions specified in Part C. The issue of this environmental
permit is based on the documents, approvals or permissions described below:
根據《環境影響評估條例》(環評條例) 第10條的規定,環境保護署署長(署長)於2019年4月26日將環境許可證(編號:EP-565/2019)批予渠務署(下稱“許可證持有人”)。根據環評條例第13條的規定,署長因應更改環境許可證的申請編號:VEP-640/2024修訂環境許可證(編號:EP-565/2019)。以下修訂已包含在本環境許可證內(編號:EP-565/2019/A)。本經修訂的環境許可證作為建造及營辦B部所說明的指定工程項目,但須遵守C部所列明的條件。本環境許可證的發出,乃以下表所列的文件、批准或許可作為根據︰
Application No.: 申請書編號: |
VEP-640/2024 |
Document in the Register: 登記冊上的文件: |
(1) Yuen
Long Effluent Polishing Plant (Register No. AEIAR-220/2019) -Environmental
Impact Assessment Report [Hereinafter
referred to as the “EIA Report”] -EIA Executive
Summary [Hereinafter
referred to as the “EIA Executive Summary”] -Environmental
Monitoring and Audit Manual [Hereinafter
referred to as the “EM&A Manual”] 元朗淨水設施 (登記冊編號: AEIAR-220/2019) -環境影響評估報告 [下稱「環評報告」] -環境影響評估報告行政摘要 [下稱「環評行政摘要」] -環境監察及審核手冊 [下稱「環監手冊」] (2) The
Director’s letter of approval of the EIA Report dated 25 April 2019 (Reference :
(47) in
EP2/N6/F/151 Pt.2) 署長於2019年4月25日發出批准環評報告的信件(檔案編號: (47) in EP2/N6/F/151 Pt.2) (3) Application
for Environmental Permit submitted by the Permit Holder on 24 December 2018
(Application No. AEP-565/2018) 許可證持有人於2018年12月24日提交的環境許可證申請文件 (申請書編號:
AEP-565/2018) (4) Environmental
Permit No. EP-565/2019 issued on 26 April 2019 於2019年4月26日簽發的環境許可證編號EP-565/2019 (5) Application for Variation of
Environmental Permit submitted by the Permit Holder on 5 November 2024
(Application No. VEP-640/2024) 許可證持有人於2024年11月5日提交的更改環境許可證申請(申請書編號: VEP-640/2024) |
Application No. 申請書編號 |
Date of Application 申請日期 |
List of Amendments Incorporated into this
Environmental Permit 已包含在本環境許可證內的修訂項目 |
Date of Amendment 修訂日期 |
VEP-640/2024 |
5 November 2024 2024年11月5日 |
-
Vary condition 2.10 (ii) in Part C of
the Environmental Permit No. EP-565/2019 更改環境許可證編號EP-565/2019 C部的第2.10(ii)項條件 -
Add condition 2.10 (iii) in Part C of the Environmental
Permit No. EP-565/2019 在環境許可證編號EP-565/2019 C部加入第2.10(iii)項條件 -
Add Figure 2 in Part C of
the Environmental Permit No. EP-565/2019 |
26 November 2024 2024年11月26日 |
26 November 2024
2024年11月26日
Date 日期 |
|
(Billy CW MA) Acting Principal Environmental Protection Officer for Director of
Environmental Protection 環境保護署署長 (署理首席環境保護主任 馬志偉 代行) |
PART B (DESCRIPTION OF DESIGNATED PROJECT)
B部 (指定工程項目的說明)
Hereunder is the description of the designated project mentioned in Part
A of this environmental permit (hereinafter referred to as the “Permit”):
下列為本環境許可證 (下稱“許可證”) A部 所提述的指定工程項目的說明﹕
Title of Designated
Project 指定工程項目的名稱 |
Yuen Long Effluent Polishing Plant [This designated project is hereafter referred to as “the Project”] 元朗淨水設施 [本指定工程項目下稱 “工程項目”] |
Nature of Designated Project |
Sewage treatment works with an installed capacity of more than 15,000
m3 per day (Item F.1 of Part I of Schedule 2 of the EIAO) 裝置的污水處理能力超過每天15,000立方米的污水處理廠(環評條例附表2第I部F.1項) |
Location of Designated
Project 指定工程項目的地點 |
The Project is located at the
existing Yuen Long Sewage Treatment Works (YLSTW). The
location of the Project is shown in Figure 1 of this Permit. 工程項目位於現有的元朗污水處理廠。工程項目的位置載於本許可證圖1。 |
Scale and Scope of
Designated Project 指定工程項目的規模和範圍
|
The Project
scope comprises construction and operation of the following key elements:- 工程項目的範圍包括建造及營辦以下主要部份:- -
Upgrading of the existing YLSTW to an
effluent polishing plant of tertiary treatment with sewage treatment capacity
of no more than 180,000 m3 per day at Average Dry Weather Flow
(ADWF); 提升現有的元朗污水處理廠至三級處理及污水處理量不多於每天180,000立方米(以平均旱季流量計算)的淨水設施; -
Effluent reuse facilities and reuse of treated sewage
effluent
for non-potable purposes within the treatment plant; 廢水循環再用設施及循環再用經處理的污水,供作處理廠內非飲用用途; -
Co-digestion facility of organic wastes and
sewage sludge; and 有機廢物與污水淤泥共同消化設施;及 -
Ultraviolet (UV) disinfection facilities. 紫外線消毒設施。 |
C部 (許可證條件)
1.
General Conditions
一般條件
1.1
The Permit Holder and any person constructing or operating the Project
shall comply with all conditions set out in this Permit. Any non-compliance by
any person may constitute a contravention of the Environmental Impact
Assessment Ordinance (EIAO) (Cap. 499) and may become the subject of
appropriate action being taken under the EIAO.
許可證持有人及任何建造或營辦工程項目的人士必須完全符合本許可證載列的全部條件。任何人士如有不符合本許可證的情況,可能違反《環境影響評估條例》(環評條例) (第499章)的規定,而當局可根據條例採取適當行動。
1.2
The Permit Holder and any person constructing or operating the Project shall ensure
full compliance with all legislation from time to time in force including,
without limitation to, the Air Pollution Control Ordinance (Cap. 311), Waste
Disposal Ordinance (Cap. 354), Water Pollution Control Ordinance (Cap. 358), Noise Control Ordinance (Cap. 400)
and Dumping at Sea Ordinance (Cap. 466). This Permit does not of
itself constitute any ground of defence against any
proceedings instituted under any legislation or imply any approval under any
legislation.
許可證持有人及任何建造或營辦工程項目的人士須經常確保完全符合現行法例的規定,包括但不限於《空氣污染管制條例》(第311章)、《廢物處置條例》(第354章)、《水污染管制條例》(第358章)、《噪音管制條例》(第400章)及《海上傾倒物料條例》(第466章)。本許可證本身不會就根據任何法例提起的法律程序構成任何抗辯理由,或根據任何法例默示任何批准。
1.3
The Permit Holder shall make copies of this Permit together
with all documents referred to in this Permit and the documents referred to in Part
A of the Permit readily available at all times for inspection by the
Director or his authorised officers at all
sites/offices covered by this Permit. Any reference to the Permit shall include
all documents referred to in the Permit and also the relevant documents in the
Register.
許可證持有人須印製本許可證的複本,連同本許可證所述的所有文件及本許可證A部所述文件,以供署長或獲授權人員任何時間內在本許可證所涵蓋的所有工地/辦事處查閱。凡提述本許可證,須包括本許可證所述的所有文件及登記冊內的相關文件。
1.4
The Permit Holder shall give a copy of this Permit to the
person(s) in charge of the site(s) and ensure that such person(s) fully
understands all conditions and all requirements incorporated in this Permit.
The site(s) refers to site(s) of construction and operation of the Project and
shall mean the same hereafter.
許可證持有人須把本許可證的一份複本交予有關工地的負責人,並確保這些人士完全明白本許可證的所有條件與規定。工地是指建造及營辦工程項目的工地,下文所提及的工地亦屬同一意思。
1.5
The Permit Holder shall display conspicuously a copy of
this Permit on the construction site(s) at all vehicular site entrances/exits
or at a convenient location for public’s information at all times. The Permit
Holder shall ensure that the most updated information about the Permit,
including any amended Permit, is displayed at such locations. If the
Permit Holder surrenders a part or the whole of the Permit, the notice he sends
to the Director shall also be displayed at the same locations as the original
Permit. The suspended, varied or cancelled Permit shall be removed from display
at the construction site(s).
許可證持有人須在建造工地的所有車輛進出口或一處方便地點,顯眼地展示本許可證的複本,以供公眾在任何時間內閱覽。許可證持有人須確保在這些地點展示關於本許可證(包括任何經修訂的許可證)的最新資料。許可證持有人如交回許可證的部分或全部,必須把其送交署長的通知書,在備有原有許可證的各處相同地點展示。遭暫時吊銷、更改或取消的許可證必須從建造工地除下,不再展示。
1.6
The Permit Holder and any person constructing or
operating the Project shall construct and
operate the Project in accordance with the project description in Part B
of this Permit.
許可證持有人及任何建造或營辦工程項目的人士須依據本許可證B部的工程項目說明,建造及營辦工程項目。
1.7
The Permit Holder and any person constructing or operating the Project shall ensure
that the Project is designed, constructed and operated in accordance with the
information and relevant recommendations
described in the approved EIA Report (Register No: AEIAR-220/2019), the application documents for environmental permits; other relevant documents in the Register; the information and mitigation measures described in this Permit; mitigation measures to be
recommended in submissions that shall be deposited with or approved by the
Director as a result of permit conditions contained in this Permit, and
mitigation measures to be recommended under on-going surveillance and
monitoring activities during all stages of the Project. Where recommendations referred to in the
documents of the Register are not expressly referred to in this Permit, such
recommendations are nevertheless to be implemented unless expressly excluded in
this Permit or otherwise agreed by the Director.
許可證持有人及任何建造或營辦工程項目的人士須確保工程項目按照下述資料設計、建造及營辦:核准環評報告(登記冊編號:AEIAR-220/2019)所說明的資料及相關建議、環境許可證申請文件、登記冊內的其他相關文件、本許可證所說明的資料及緩解措施、根據本許可證內載的條件須向署長存放或獲署長批准的提交文件所建議的緩解措施、以及在工程項目各階段進行的持續監察及監測工作所建議的緩解措施。登記冊文件所述建議如沒有在本許可證明確表示,則仍須實施這些建議,除非獲本許可證明確豁除或另獲署長同意。
1.8
All submissions, as required under this Permit, shall
be rectified and resubmitted in accordance with the comments, if any, made by
the Director within one month of the receipt of the Director’s comments or
otherwise as specified by the Director.
所有按本許可證規定提交的文件,須在接獲署長的意見(如有者)後1個月內或署長另行指定的期限內,根據署長的意見加以修正及重新提交。
1.9
All submissions approved by the Director, all submissions deposited without
comments by the Director, and all submissions rectified in accordance with
comments by the Director under this Permit shall be construed as part of the
permit conditions described in Part C of this Permit. Any variation of
the submissions shall be approved by the Director in writing or as prescribed
in the relevant permit conditions. Any non-compliance with the submissions may
constitute a contravention of the EIAO (Cap. 499). All submissions or any variation of the submissions shall
be certified by the Environmental Team (ET) Leader and verified by the
Independent Environmental Checker (IEC) referred to in Conditions 2.1 and 2.4 below before submitting to the Director under
this Permit.
所有提交署長並獲批准的文件、所有提交署長存放而沒有收到署長意見的文件及根據本許可證規定已依照署長的意見作出修訂的文件,將詮釋為本許可證C部所說明的許可證條件的一部分。對提交文件如有任何修訂,均須獲署長的書面批准,或符合有關許可證條件所述。凡與所提交的文件有不符合的情況,均可能構成違反環評條例 (第499章)。所有提交文件或提交文件的任何修訂本,均須按下文條件第2.1及2.4項所述由環境小組組長核證及獨立環境查核人核實,然後才按本許可證規定向署長提交。
1.10
The Permit Holder shall release all finalized
submissions, as required under this Permit, to the public by depositing copies in the EIAO Register Office, or in any other places, or any internet websites as
specified by the Director, or by any other means as specified by the Director,
for public inspection. For this purpose, the Permit Holder shall
provide sufficient copies of the submissions.
許可證持有人須把所有按本許可證規定提交的文件定稿公開給公眾人士知道,方法是把有關文件複本存放於環境影響評估條例登記冊辦事處,或署長指定的任何其他地方,或署長指定的任何互聯網網站,或署長指定的任何其他方法,以供公眾查閱。因此,許可證持有人須提供足夠數量的複本。
1.11
The Permit Holder shall submit and/or deposit all
submissions within the time as specified in the Conditions of this Permit. All
submissions to the Director required under this Permit shall be delivered
either in person or by registered mail to the EIAO Register Office (currently
at 27/F, Southorn Centre, 130 Hennessy Road, Wanchai,
Hong Kong). Electronic copies of all finalized submissions required under this
Permit shall be prepared in Hyper Text Markup Language (HTML) (version 4.0 or
later) and in Portable Document Format (PDF version 1.3 or later), unless
otherwise agreed by the Director and shall be submitted at the same time as the
hard copies.
許可證持有人須在本許可證條件所列明的時間內,提交及/或存放所有文件。本許可證規定向署長提交的所有文件,須親身送交或以掛號方式郵寄至環境影響評估條例登記冊辦事處 (現址為:香港灣仔軒尼詩道130號修頓中心27樓)。所有按本許可證規定提交的文件定稿的電子版本,均須以超文本標示語言 (HTML)
(第4.0或較後版本) 和便攜式文件格式 (PDF) (第1.3或較後版本) 製作,除非另獲署長同意,並須與硬複本同時提交。
1.12
The Permit Holder shall notify the Director in writing
the commencement dates of construction and operation of the Project no later
than one month prior to the
commencement of construction and operation of the Project. The Permit Holder
shall notify the Director in writing immediately if there is any change of the
commencement dates of construction and operation.
許可證持有人須在展開工程項目的建造及營辦工程前最少1個月,以書面方式把工程項目建造及營辦工程的展開日期通知署長。建造及營辦工程的展開日期如有任何更改,許可證持有人必須立即以書面方式通知署長。
1.13
For the purpose of this Permit, “commencement of
construction” does not include works related to site investigation, clearance
and preparation, or other works as agreed by the Director.
為執行本許可證,「建造工程的展開」不包括有關工地勘探、清理和預備工程,或署長同意的其他工程。
2.
Special Conditions
特定條件
Submissions or Measures to
be Implemented before or during Construction of
the Project
工程項目施工前或期間須提交的文件或採取的措施
Employment
of ET
聘用環境小組
2.1
A single ET, unless otherwise approved by the
Director, shall be established by the Permit Holder no later than three months before the commencement of construction of
the Project. The ET shall be directly supervised by the Engineer’s
Representative of the Permit Holder (ER) and shall not be in any way an
associated body of the Contractor or the IEC for the Project. The Permit Holder
shall provide a site office to the ET for use. The ET shall be headed by an ET
Leader and supported by relevant specialists including Ecologist and Landscape
Architect or related professional. The ET Leader shall be a person who has at
least 7 years of experience in environmental monitoring and auditing (EM&A)
or environmental management. The ET Leader shall be working full time on-site throughout
the entire construction period
of the Project. The
minimum on-site time for the ET,
and the qualifications of the specialists in the ET shall be proposed with
justifications for the approval of the Director.
除非署長另行批准,否則許可證持有人須在展開工程項目的建造工程前最少3個月成立一個環境小組。環境小組須由許可證持有人的工程師代表直接監督,且不得是工程項目的承辦商或獨立環境查核人的相聯團體。許可證持有人須提供工地辦事處予環境小組使用。環境小組須由一名環境小組組長帶領,並須獲相關的專家包括生態學家及園境師或相關專業人士支援。環境小組組長須在環境監察及審核(「環監」)或環境管理方面至少有7年經驗。環境小組組長在工程項目的整個施工期內須全職實地工作。許可證持有人須就環境小組的最少駐工地時間以及環境小組內的專家的資歷向署長提交建議及理由,以供批准。
2.2
The ET and the ET Leader shall be responsible for:
環境小組及環境小組組長須負責:
(i)
implementing the EM&A programme in accordance
with the EM&A requirements as contained in the EM&A Manual of
the Project;
按工程項目的環監手冊內載的環監規定,執行環監計劃;
(ii)
certifying
the environmental acceptability of permanent and temporary works, relevant
design plans and submissions required in the EM&A Manual and under this
Permit;
核證永久及臨時工程在環境上的可接受程度、相關的設計圖則和根據環監手冊及本許可證規定提交的文件;
(iii)
carrying out site inspections to audit the
Contractor’s site practice and work methodologies with respect to environmental
mitigation measures contained in the EM&A Manual of the Project and to take
pro-active actions to pre-empt environmental problems;
進行實地視察,以便就工程項目的環監手冊內載的環境緩解措施審核承辦商的工地行為及工作方法,並採取積極行動預防產生環境問題;
(iv)
notifying the IEC within one working day of the
occurrence of each and every instance or circumstance or change of
circumstances, which may affect the compliance with the recommendations of the
approved EIA Report (Register No. AEIAR-220/2019) and this Permit; and
在發生可能會影響核准環評報告(登記冊編號: AEIAR-220/2019)的建議及本許可證的符合情況的每宗事件、每種情況或每次情況變化後1個工作天內通知獨立環境查核人;以及
(v)
keeping a contemporaneous log-book of any such
instance or circumstance or change of circumstances. The log-book shall be kept
readily available for inspection by all persons assisting in supervision of the
implementation of the recommendations of the approved EIA Report (Register No. AEIAR-220/2019) and this Permit or by
the Director or his authorized officers.
保存一本記錄冊,同時記載任何類似事件、情況或情況變化。存放記錄冊的地方,須可供協助督導執行核准環評報告(登記冊編號:AEIAR-220/2019)的建議及本許可證的所有人士、署長或獲授權人員隨時查閱。
2.3
Failure to maintain records in the log-book, failure
to discharge the duties of the ET Leader as defined in the EM&A Manual
or in this Permit would entitle the Director to require the Permit Holder by
notice in writing to replace the ET Leader. Failure by the Permit Holder to
replace the ET Leader or failure by the new ET Leader to keep contemporaneous
records in the log-book or to discharge the duties as defined in the EM&A
Manual or in this Permit may render the Permit liable to suspension,
cancellation or variation.
環境小組組長如未能在記錄冊保存記錄、未能執行環監手冊或本許可證所列明的職務,署長有權以書面要求許可證持有人撤換環境小組組長。許可證持有人如未能安排人選替補,或新聘用的環境小組組長未能在記錄冊保存同期的記錄、未能執行環監手冊或本許可證所列明的職務,或會導致許可證被暫時吊銷、取消或更改。
Employment
of IEC
聘用獨立環境查核人
2.4
A single IEC with a supporting team, unless otherwise approved by the Director, shall be
employed by the Permit Holder no later than three months before the commencement
of construction of the Project. The IEC and his team shall not be in any way an
associated body of the ER, the Contractor or the ET for the Project. The
IEC shall be approved by the Director before appointment by the Permit
Holder. The IEC shall be a
person who has at least 7 years of experience in EM&A or environmental
management. The IEC shall be working full time on-site throughout
the entire construction period
of the Project. The minimum on-site time for the supporting team of the IEC shall
be proposed with justifications for the approval of the Director.
除非署長另行批准,否則許可證持有人須在展開工程項目的建造工程前最少3個月聘用一名獨立環境查核人及其支援小組。獨立環境查核人及其支援小組不得是工程項目的工程師代表、承辦商或環境小組的相聯團體。獨立環境查核人須經署長批准,才可獲許可證持有人聘用。獨立環境查核人須在環監或環境管理方面至少有7年經驗。獨立環境查核人在工程項目的整個施工期內須全職實地工作。許可證持有人須就獨立環境查核人的支援小組的最少駐工地時間向署長提交建議及理由,以供批准。
2.5
The IEC shall report directly to the Director on
matters relating to the EM&A programme and environmental impacts from the
Project and shall submit to the Director for approval, no later than one month before the commencement of construction of
the Project, a proposal on the reporting mechanism covering the approaches for
the IEC and his team to report to the Director on:
獨立環境查核人須直接向署長報告有關環監計劃及工程項目的環境影響事宜,並須在展開工程項目的建造工程前最少1個月把有關報告機制的建議書提交署長批准,內容涵蓋獨立環境查核人及其小組就以下事項向署長報告的方法:
(i)
how to
discharge all the duties specified under the EM&A programme
and this Permit, taking into account the construction activities and programme of the Project;
如何在顧及工程項目的建造活動及計劃的情況下執行環監計劃及本許可證指明的各項職責;
(ii)
how to
handle each and every
change of circumstances, emergency events relating to violation of
environmental legislation (such as illegal dumping relating to the
Project) or non-compliance (including suspects of
non-compliance) with the recommendations (such as construction
methods, mitigation measures, and environmental standards) of
the approved EIA Report (Register No. AEIAR-220/2019), the EM&A
Manual and this Permit, which might affect the monitoring or control of
adverse environmental impacts from the Project; and
如何處理每次情況變化、與違反環境法例相關的緊急事件(例如與工程項目相關的非法棄置)或不遵行(包括懷疑不遵行的情況)核准環評報告(登記冊編號:AEIAR-220/2019)的建議(例如施工方法、緩解措施及環境標準)、環監手冊及本許可證的情況,而該等情況可能會妨礙工程項目所造成不良環境影響的監察或控制工作;以及
(iii)
how to
keep proper records in order to respond to questions and enquiries from the
Director on the EM&A programme and duties
discharged by the IEC.
如何備存合適記錄以回應署長就有關環監計劃及獨立環境查核人所執行職務的問題及查詢。
2.6
The IEC shall be responsible for duties defined in
the EM&A Manual and this Permit, including but not limited to the following:
獨立環境查核人須執行環監手冊及本許可證所列明的職務,包括但不限於以下各項:
(i)
to audit the overall EM&A performance, including
the implementation of all environmental mitigation measures and monitoring
activities on site;
審核整體環監工作的表現,包括執行所有環境緩解措施及現場的監察工作;
(ii)
to
verify the environmental
acceptability of permanent and temporary works, relevant design plans and
submissions required in the EM&A Manual and under this Permit;
核實永久及臨時工程在環境上的可接受程度、相關的設計圖則和根據環監手冊及本許可證規定提交的文件;
(iii)
to verify the log-book(s) mentioned in Condition 2.2(v) of this Permit;
核實本許可證條件第2.2(v)項所述的記錄冊;
(iv)
to notify the Director by fax or email, within one
working day of receipt of notification from the ET Leader, or identification by
the IEC and his team, of each and every change of circumstances, emergency events relating to violation of
environmental legislation (such as illegal dumping and landfilling) or
non-compliance (including suspects of non-compliance) with the recommendations
(such as construction methods, mitigation measures, and environmental
standards) of the approved EIA Report (Register No. AEIAR-220/2019), the EM&A Manual and this Permit, which
might affect the monitoring or control of adverse environmental impacts from
the Project. Notification by the Permit Holder is the same as notification by
the IEC for the purpose of this Condition;
在每次出現情況變化、與違反環境法例相關的緊急事件(例如與工程項目相關的非法棄置及堆填)或不遵行(包括懷疑不遵行的情況)核准環評報告(登記冊編號:AEIAR-220/2019)的建議(例如施工方法、緩解措施及環境標準)、環監手冊及本許可證的情況,而該等情況可能會妨礙監察或控制有關工程項目所造成的不良環境影響,須在接獲環境小組組長通知或獨立環境查核人及其支援小組確定情況後1個工作天內以傳真或電郵方式通知署長。為執行本條件,許可證持有人的通知等同獨立環境查核人的通知;
(v)
to liaise closely with the Director;
與署長密切聯繫;
(vi)
to
accompany the Director in carrying out site inspections and attending meetings
when requested;
按署長要求,陪同署長進行實地視察及出席會議;
(vii)
to
offer objective and professional advice on environmental issues, when requested,
and to respond to questions and enquiries from the Director on the EM&A programme and duties discharged by the IEC, with the
support of relevant information, documents and records as appropriate; and
按要求就環境問題提供客觀及專業意見,並提供合適的相關資料,文件和記錄以回應署長提出有關環監計劃和獨立環境查核人所執行職務的問題及查詢;以及
(viii)
to allocate adequate resources, including any
necessary specialist support, for discharging the duties required in this
Permit and the EM&A Manual.
分配足夠的資源,包括所需的專業支援,以執行本許可證及環監手冊規定的各項職責。
2.7
If the Director considers the IEC fails to discharge
the duties as defined in the EM&A Manual or in this Permit, the Director
may require the Permit Holder by notice in writing to replace the IEC. Failure
by the Permit Holder to replace the IEC or failure by the new IEC to discharge
the duties as defined in the EM&A Manual or in this Permit may render
the Permit liable to suspension, cancellation or variation.
如署長認為獨立環境查核人未能執行環監手冊或本許可證所列明的職務,署長可以書面要求許可證持有人撤換獨立環境查核人。如許可證持有人未能撤換獨立環境查核人,或新聘用的獨立環境查核人未能執行環監手冊或本許可證所列明的職務,或會導致許可證被暫時吊銷、取消或更改。
Submission
of Management Organizations
提交管理架構
2.8
The Permit Holder shall, no later than one month
before the commencement of construction of the Project, inform the Director in
writing the following information:
許可證持有人須在展開工程項目的建造工程前最少1個月把以下資料以書面通知署長:
(i)
the
management organization of the main construction companies and / or any form of
joint ventures associated with the construction of the Project;
主要建造公司及/或以任何形式與工程項目建造工程相關的合營企業的管理架構;
(ii)
the
management organization of the ET;
環境小組的管理架構;
(iii)
the
management organization of the IEC and his team; and
獨立環境查核人及其支援小組的管理架構;以及
(iv)
the
submitted information shall include an organization chart, names of responsible
persons and their contact details.
提交的資料須包括一份組織圖、負責人的姓名及聯絡資料。
Submission
of Construction Phase Emergency Response Plan
提交施工階段緊急應變計劃
2.9
The Permit Holder shall, no later than one month
before the commencement of construction of the Project, deposit with the
Director a Construction Phase Emergency Response Plan to minimize the chance of
sewage overflow throughout the entire construction period of the Project. The Emergency Response Plan shall include
mechanism to monitor the sewage flow build-up of the existing YLSTW, an Event
and Action Plan and any necessary remedial measures to ensure proper treatment
of sewage and sludge associated with the operation of the existing YLSTW throughout the entire construction
period of the Project.
許可證持有人須在展開工程項目的建造工程前最少1個月向署長存放施工階段緊急應變計劃,以盡量減低工程項目的整個施工期內污水溢流的可能性。緊急應變計劃須包括監察現有的元朗污水處理廠污水量增長情況的機制,事件及行動計劃,以及所需的補救措施以確保在工程項目的整個施工期內妥善處理與現有的元朗污水處理廠的運作有關的污水和污泥。
Measure
for Mitigating Ecological Impacts during Construction of the Project
工程項目施工期間生態影響的緩解措施
2.10
The
Permit Holder shall implement the following mitigation measures to minimize ecological
impact during construction of the Project:
許可證持有人必須採取以下的緩解措施以盡量減低工程項目施工期間的生態影響:
(i)
All
construction works shall be confined within the boundary of the existing YLSTW (as shown in Figure
1);
所有建造工程須限制在現有的元朗污水處理廠的範圍內(如圖1所示);
(ii) All percussive piling works, other than those
for the foundation construction of the Sludge Dewatering Building (SDB), and
demolition using excavator-mounted breakers shall not be carried out from
November to March to avoid construction noise impact to the overwintering /
migratory waterbirds;
所有撞擊式打樁工程(除污泥脫水大樓地基工程外)及使用裝在挖土機上的破碎機進行拆卸工程不得在11月至3月進行,避免建築噪音影響過冬/遷徙水鳥;
(iii) For the percussive piling works for the construction
of the SDB to be carried out
from November to March, the piles and piling rigs shall be installed with movable full height
U-shaped noise barrier of at least 12m with absorptive materials, while the boundary
of the construction area of SDB (as shown in Figure 2) shall also be erected
with noise barriers of at least 4m high with absorptive materials. No more than
two piling rigs for percussive piling shall be used concurrently within the
entire Project site. Moreover, the piling works will only be conducted between
8:30 am and 4:30 pm; and during high tides when the predicted tidal level is
higher than 1.5 mCD (as predicted by the Hong Kong Observatory
for the tidal station at Tsim Bei Tsui). The predicted tides for the upcoming month
will be presented in the monthly EM&A report; and
於11月至 3月就建造污泥脫水大樓進行的撞擊式打樁工程,樁柱及打樁機須設置至少12米高、可移動及附有吸音物料的U型隔音屏障。污泥脫水大樓的工地範圍邊界(如圖2所示)須豎立至少4米高附有吸音物料的隔音屏障。整個工程項目工地內不得同時使用超過兩台撞擊式打樁機。此外,撞擊式打樁工程只可在上午8時30分至下午4時30分內及在預計潮汐水位高於海圖基準面以上1.5米(根據香港天文台尖鼻咀潮汐站的預報資料)的漲潮期間進行。每月環監報告將記載隨後一個月的預計潮汐資料;及
(iv) Noise barriers with
absorptive materials of at least 4m high shall be erected along the northern,
eastern and western sides
of the Project boundary.
在工程項目邊界北側、東側和西側豎立至少4米高附有吸音物料的隔音屏障。
2.11
The
Permit Holder shall, in consultation with the Agriculture, Fisheries and
Conservation Department, conduct a pre-construction survey for areas within 100
m from the Project boundary to confirm the location(s) and status of ardeid
night roost(s); and, no later than one month before the commencement of
construction of the Project, submit a Pre-Construction Survey Report for approval by the
Director. Subject to the
findings of the survey, the Pre-Construction Survey Report shall list out
details of all measures, including the limitation of time and buffer distance
for use of powered mechanical equipment, to minimize impact on any ardeid night
roost during construction of the Project. The Pre-Construction Survey Report
shall be certified by the ET Leader and the Ecologist referred to in Condition
2.1 and verified by the IEC. All measure(s) as recommended in the approved Pre-Construction
Survey Report shall be fully implemented.
許可證持有人須諮詢漁農自然護理署的意見,在工程項目界線100米範圍內進行施工前期調查,以確認鷺鳥夜間棲息地的位置和狀況;並須在展開工程項目的建造工程前最少1個月向署長提交施工前期調查報告,以供審批。視乎施工前期調查的結果,施工前期調查報告須列出所有措施的詳情,包括限制使用機動設備的時間和緩衝距離,以盡量減低工程項目施工期間對任何鷺鳥夜間棲息地的影響。施工前期調查報告須由條件第2.1項提及的環境小組組長及生態學家核證,及由獨立環境查核人核實。核准施工前期調查報告建議的所有措施必須徹底執行。
2.12
The
Permit Holder shall, no later than one month before the commencement of
construction of the Project, deposit with the Director a Noise Mitigation
Measures Plan (NMMP) to list out details of all construction noise mitigation
measures, including but not limited to the use of low-noise technology and
equipment and provision of noise barriers, acoustic mats and enclosures to
minimize construction noise impacts on nearby ecological sensitive receivers. All
measures as recommended in the NMMP shall be fully implemented.
許可證持有人須在展開工程項目的建造工程前最少1個月向署長存放噪音緩解措施計劃,列出所有建築噪音緩解措施的詳情,包括但不限於使用低噪聲技術和設備及提供隔音屏障、隔音墊和隔音罩,以盡量減低建築噪音對附近生態敏感受體造成的影響。噪音緩解措施計劃建議的所有措施必須徹底執行。
2.13
The
Permit Holder shall, no later than one month before the commencement of
construction of the Project, deposit with the Director a proposal to list out
all measures to minimize overspill of light to ecological sensitive areas during construction
and operation of the Project.
The proposal shall include details of the use of directional down lighting,
control of lighting periods and intensity. All measures as recommended in the proposal
shall be fully implemented.
許可證持有人須在展開工程項目的建造工程前最少1個月向署長存放計劃書,列出工程項目施工及營辦期間所有盡量減低光線散射到生態敏感地方的措施。計劃書須包括使用向下的定向照明設備,控制照明時間及強度的詳情。計劃書建議的所有措施必須徹底執行。
Submissions
for Land Contamination Assessment
提交進行土地污染評估的文件
2.14
The
Permit Holder shall carry out detailed assessment of land contamination before
the commencement of construction works at the concerned facilities / areas identified
in Appendix 7.1 of the approved EIA Report (Register No. AEIAR-220/2019). The Permit Holder shall,
no later than three
months before the commencement of site investigation (SI) at the concerned
facilities / areas, submit supplementary Contamination Assessment Plan(s) [CAP(s)]
to the Director for approval. The Permit Holder shall conduct the SI in
accordance with the approved supplementary CAP(s) and submit Contamination
Assessment Report(s) [CAR(s)] to document the findings of the SI (with
Remediation Action Plan(s) [RAP(s)] if contamination is confirmed and
remediation is deemed necessary) for approval by the Director. If remediation is required, the Permit Holder
shall conduct the remediation in accordance with the approved RAP(s) and submit
Remediation Report(s) to document the remediation programme
for approval by the Director. No construction works at the concerned facilities/areas
shall be commenced before the approval of respective supplementary CAP(s) by
the Director and the satisfactory completion of necessary decontamination works.
許可證持有人須在核准環評報告(登記冊編號:AEIAR-220/2019)附錄7.1所示的有關設施/地方展開建造工程前進行詳細土地污染評估。許可證持有人須在有關設施/地方進行場地勘察前最少3個月向署長提交補充污染評估計劃書,以供審批。許可證持有人須按照核准補充污染評估計劃書進行場地勘察,並向署長提交詳細記錄勘察結果的污染評估報告 (如評估結果顯示土地受到污染而需要進行整治,須連同整治計劃書一併提交),以供審批。如需進行整治,許可證持有人須按照核准整治計劃書進行整治工作,並把詳細記錄整治過程的整治報告提交署長批准。在補充污染評估計劃書獲署長批准及必要的除污工程圓滿完成前,不得在有關設施/地方展開建造工程。
Submission
of Landscape and Visual Mitigation Plan(s)
提交景觀及視覺緩解計劃
2.15
The
Permit Holder shall, no later than one month before the
commencement of the corresponding parts of landscape and visual mitigation
measures of the Project, deposit with the Director Landscape and Visual Mitigation Plan(s). The
Landscape and Visual Mitigation Plan(s) shall show the design
details, recommendations of tree preservation including measures to retain and
protect the trees along east and north side of the Project boundary, confirmation
of the feasibility for proposed planting, locations, implementation programme,
maintenance and management schedules, and drawings in the scale of 1:1,000 or
other appropriate scale, as agreed with the Director, of the landscape and
visual mitigation measures of the Project. The Landscape and Visual Mitigation Plan(s)
shall be certified by the ET Leader and the Landscape Architect or
related professional
referred to in Condition 2.1 and verified by the IEC as conforming to the
relevant information and recommendations, including those described in the EIA
Report (Register No. AEIAR-220/2019). The
Permit Holder shall consult the Planning Department on the Landscape and Visual Mitigation Plan(s) before submission
to the Director.
許可證持有人須在工程項目的景觀及視覺影響緩解措施的相關部分展開前最少1個月向署長存放景觀及視覺緩解計劃。景觀及視覺緩解計劃須展示工程項目景觀及視覺影響緩解措施的設計詳情、樹木保育的建議,包括保留和保護工程項目邊界東側和北側樹木的措施、確認擬議種植的可行性、位置、實施計劃、保養及管理時間表,以及採用1:1,000的比例或署長同意的其他合適比例繪畫的圖則。景觀及視覺緩解計劃須由條件第2.1項提及的環境小組組長及園境師或相關專業人士核證,並由獨立環境查核人核實,證明符合相關資料及建議,包括環評報告(登記冊編號:AEIAR-220/2019)所載的資料及建議。許可證持有人須就景觀及視覺緩解計劃諮詢規劃署的意見,然後才提交署長。
Submissions
or Measures to be
Implemented before or during Operation of the Project
工程項目營辦前或期間須提交的文件或採取的措施
Submission
of Operation Phase Emergency Response Plan(s)
提交營辦階段緊急應變計劃
2.16
The Permit Holder shall, no
later than one year before the commencement of operation of the Project, submit Operation
Phase Emergency Response Plan(s) for approval by the Director. The Emergency Response
Plan(s) shall include, but not limited to, the following:
許可證持有人須在工程項目開始營辦前最少1年向署長提交營辦階段緊急應變計劃,以供審批。緊急應變計劃須包括但不限於以下各項:
(i)
Measures
to minimize emergency discharge during operation of the Project;
盡量減低工程項目營辦期間緊急排放的措施。
(ii) Establishment of an appropriate set of
baseline data and, if additional baseline monitoring is required, proposal of
baseline monitoring methodology;
編制一套合適的基線數據,如需額外的基線監察,則須建議基線監察的方法;
(iii) Proposal of emergency discharge follow-up
monitoring requirements, including the water quality monitoring locations;
建議緊急排放跟進監察的規定,包括水質監察位置;
(iv) List of relevant government departments, mariculturists
and stakeholders to be informed;
須通知的相關政府部門,海產養殖戶及持份者名單;
(v) Reporting procedures; and
通報程序;以及
(vi) Investigation arrangement of incidents that
affect nearby water body / sensitive receivers, including water sampling and
monitoring, assessing the impact, investigating the cause of incidents, determining necessary
remedial measures, and relevant departments to be consulted.
調查影響鄰近水體∕敏感受體事故的安排,包括抽取水質樣本及監察、評估影響、調查事故原因、釐定所需的補救措施,以及須諮詢的相關部門。
All measure(s) as
recommended in the approved Emergency Response Plan(s) shall be fully
implemented.
核准緊急應變計劃建議的所有措施必須徹底執行。
Submission
of Commissioning Test Report(s)
提交試行運作測試報告書
2.17
The
Permit Holder shall conduct the commissioning tests in accordance with the
requirements of the EM&A Manual and, no later than one month before the
commencement of operation of the Project, deposit with the Director Commissioning
Test Report(s) to demonstrate compliance with the design emission limits for
relevant air pollutants and noise standards for the fixed noise sources. The commissioning tests for the fixed noise sources
shall have due regard to the characteristics of tonality, impulsiveness
and intermittency. Any
measure(s) as recommended in the Commissioning Test Report(s) shall
be fully implemented.
許可證持有人須按照環監手冊所載的規定進行試行運作測試,並須在工程項目開始營辦前最少1個月向署長存放試行運作測試報告書,證明符合相關空氣污染物的設計排放限度及固定噪音源的噪音標準。有關固定噪音源的試行運作測試須適當考慮噪音音調、脈衝及斷續因素的特性。試行運作測試報告書建議的任何措施必須徹底執行。
Measures
for Mitigating Odour Impacts during Operation of the Project
工程項目營辦期間氣味影響的緩解措施
2.18
The
Permit Holder shall implement the following mitigation measures to minimize odour impact during operation of the Project:
許可證持有人必須採取以下的緩解措施以盡量減低工程項目營辦期間的氣味影響:
(i)
All facilities and areas with potential odour emission shall be fully enclosed and the
exhaust air shall be conveyed to deodourization (DO)
units for treatment before discharge to the environment; and
所有可能散發氣味的設施及地方須完全密封,而廢氣在排放到環境之前須先行傳送到除味裝置進行處理;及
(ii) Except for the DO units of the ancillary
buildings, all DO units as shown in Appendix 3.9 of the approved EIA Report
(Register No. AEIAR-220/2019)
shall have at least 95% odour removal efficiency. The
DO units of the ancillary buildings shall have at least 90% odour
removal efficiency. All DO units shall be properly operated and maintained for
treatment of exhaust air before discharge.
除了附屬建築物的除味裝置,所有在核准環評報告(登記冊編號:AEIAR-220/2019)附錄3.9所示的除味裝置須具備至少95%的除味效能。附屬建築物的除味裝置須具備至少90%的除味效能。所有除味裝置須予以妥善操作及保養維修,以處理廢氣後再排出。
(iii) Activated carbon filter with at least 70% odour removal
efficiency shall be installed at the ammonia stripping units. The
activated carbon filter shall be properly operated and maintained for
treatment of exhaust air before discharge.
除氨裝置須安裝具備至少70%除味效能的活性碳過濾器。活性碳過濾器須予以妥善操作及保養維修,以處理廢氣後再排出。
(iv)
Sludge shall be stored in sealed containers during
transportation.
污泥於運送途中須貯存於密封式容器內。
Measures
for Mitigating Water Quality Impact during Operation of the Project
工程項目營辦期間水質影響的緩解措施
2.19
Reuse of treated sewage effluent shall only be used within the treatment plant for chemical
preparation, water supplement to DO units and cleaning
of treatment equipment via automatic closed-loop system.
循環再用經處理的污水只能用於處理廠內,通過自動閉環系統供作化學製劑、除味裝置的補充水及清洗處理設備用途。
2.20
No maintenance dredging shall be carried out at the
outfalls at Shan Pui River.
不得在位於山貝河的排放渠口進行維修挖泥工程。
Measure for
Minimising Ecological Impacts during Operation of the Project
工程項目營辦期間盡量減低生態影響的措施
2.21
The
surface of solar panels shall adopt dark-colored and non-reflective materials.
太陽能電池板的表面須採用深色和非反光物料。
3.
Environmental Monitoring
and Audit (EM&A) Requirements
環境監察及審核(環監)規定
3.1
The
Permit Holder shall implement the EM&A programme
in accordance with the procedures and requirements as set out in the EM&A
Manual. Any major changes to the programme shall be
justified by the ET leader and verified by the IEC as conforming to the
requirements set out in the EM&A Manual, and shall seek the prior approval
from the Director before implementation.
許可證持有人須按照環監手冊所載的程序及規定執行環監計劃。計劃如有任何重大更改,須由環境小組組長提出理據,並由獨立環境查核人核實,證明其符合環監手冊所載的規定,並須事先獲署長批准才可執行。
3.2
The
Permit Holder shall take samples, measurements and necessary remedial actions
in accordance with the requirements of the EM&A Manual by:
許可證持有人須按照環監手冊所載的規定,透過以下方法進行取樣、測量及所需的補救行動:
a)
conducting
baseline environmental monitoring;
進行環境基線監測;
b)
conducting
impact monitoring;
進行影響監測;
c) carrying out remedial actions described in the
Event/Action Plans of the EM&A Manual in accordance with the time frame set out in
the Event/Action Plans, or as agreed by the Director, in case where specified
criteria in the EM&A Manual are exceeded; and
如超逾環監手冊內指定的標準,則按照環監手冊內的事件/行動計劃所訂明的時限或署長所同意的時限,執行事件/行動計劃所說明的補救行動;以及
d) logging and keeping records of the details of
(a) to (c) above for all parameters within 3 working days of the collection of
data or completion of remedial action(s), for the purpose of preparing and
submitting the monthly EM&A Reports and to make available the information
for inspection on site.
在收集數據或完成補救行動3個工作天內,須記錄及備存上文(a)至(c)項所有參數的詳情,用作擬備及提交每月環監報告,並備妥有關資料以供在工地查閱。
3.3
The
Permit Holder shall submit 4 hard copies and 1
electronic copy of Baseline Monitoring Report(s) to the Director at least 2
weeks before the commencement of construction of the Project. The
submission(s) shall be certified by the ET Leader and verified by the IEC as
having complied with the requirements as set out in the EM&A Manual before
submission to the Director. Additional copies of the Baseline Monitoring
Report(s) shall be provided upon request by the Director.
許可證持有人須在展開工程項目的建造工程前最少2個星期向署長提交有關基線監測報告的4份硬複本及1份電子版本。提交的文件須由環境小組組長核證及獨立環境查核人核實,證明其符合環監手冊所載的規定,然後才提交署長。如署長要求,則須提交基線監測報告的額外複本。
3.4
The
Permit Holder shall submit 1 hard copy and 1 electronic copy of monthly
EM&A Reports to the Director within 2 weeks after the end of the reporting
month during construction of the Project. The monthly EM&A
Reports shall include a summary of all non-compliance with the recommendations
in the approved EIA Report (Register No. AEIAR-220/2019) or this Permit. The submissions
shall be certified by the ET Leader and verified by the IEC as having complied
with the requirements as set out in the EM&A Manual before submission to
the Director. Additional copies of the monthly EM&A Reports shall
be provided to the Director upon request by the Director.
在工程項目施工期間每個提交報告的月份結束後2個星期內,許可證持有人須向署長提交每月環監報告的1份硬複本及1份電子版本。每月環監報告須包括所有不符合核准環評報告(登記冊編號:AEIAR-220/2019)的建議或本許可證情況的摘要。提交的文件須由環境小組組長核證及獨立環境查核人核實,證明其符合環監手冊所載的規定,然後才提交署長。如署長要求,則須提交每月環監報告的額外複本。
3.5
Unless
otherwise agreed by the Director, the Permit Holder shall submit 1 hard copy
and 1 electronic copy of quarterly EM&A Reports to the Director within 2
weeks after the end of the reporting month in accordance with the requirements
of the EM&A Manual for the first three years during operation of the
Project. The quarterly EM&A Reports shall include a summary of
all non-compliance with the recommendations in the approved EIA Report (Register
No. AEIAR-220/2019) or this Permit. The submissions shall
be certified by the ET Leader and verified by the IEC as having complied with
the requirements as set out in the EM&A Manual before submission to the
Director. Additional copies of the quarterly EM&A Reports shall
be provided to the Director upon request by the Director.
除非另獲署長同意,在工程項目營辦期間首3年每個提交報告的月份結束後2個星期內,許可證持有人須按照環監手冊所載的規定向署長提交季度環監報告的1份硬複本及1份電子版本。季度環監報告須包括所有不符合核准環評報告(登記冊編號:AEIAR-220/2019)的建議或本許可證情況的摘要。提交的文件須由環境小組組長核證及獨立環境查核人核實,證明其符合環監手冊所載的規定,然後才提交署長。如署長要求,則須提交季度環監報告的額外複本。
3.6
All
EM&A data submitted under this Permit shall be true, valid and correct.
根據本許可證提交的所有環監數據,均須有效及真實無誤。
4. Electronic
Reporting of EM&A Information
環監資料的電子匯報
4.1 To
facilitate public inspection of the Baseline Monitoring
Report(s) and
EM&A Reports via the EIAO Internet Website and at the EIAO Register Office,
electronic copies of these Reports shall be prepared in Hyper Text Markup
Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF
version 1.3 or later), unless otherwise agreed by the Director and shall be
submitted at the same time as the hard copies as described in Conditions 3.3, 3.4 and 3.5 above. For the HTML version, a
content page capable of providing hyperlink to each section and sub-section of
these Reports shall be included in the beginning of the document. Hyperlinks to
all figures, drawings and tables in these Reports shall be provided in the main
text from where the respective references are made. All graphics in
these Reports shall be in interlaced GIF,
JPEG or PDF format unless
otherwise agreed by the Director. The content of the electronic
copies of these Reports must be the same as the hard copies.
為方便公眾透過環評條例互聯網網站及在環評條例登記冊辦事處查閱基線監測報告及環監報告,除非另獲署長同意,這些報告的電子版本須以超文本標示語言(HTML)(第4.0或較後版本)及便攜式文件格式(PDF)(第1.3或較後版本)製作,並須與本許可證條件第3.3,3.4及3.5項所說明的硬複本同時提交。關於HTML的版本方面,須在文件開端加入已為報告各節及小節建立超連結的目錄,同時亦須為報告正文內的各類圖表建立超連結,連結到有關的參考資料。除非另獲署長同意,報告內所有圖形均須屬交錯存取的GIF,JPEG或PDF格式。報告的電子版本內容,必須與硬複本的內容一致。
4.2 The
Permit Holder shall, within 6 weeks after commencement of construction of the
Project, set up a dedicated Internet web site and notify the Director in
writing the Internet address where the environmental monitoring data and
project information is to be placed. All environmental monitoring
data described in Condition 4.1 above shall be made available to the public via
the dedicated Internet web site in the shortest possible time and in any event
no later than 2 weeks after the relevant environmental monitoring data are
collected or become available, unless otherwise agreed with the
Director. All finalized submissions and plans shall be made
available to the public via the dedicated Internet web site in the shortest
possible time and in any event no later than 2 weeks after the submissions and
plans are approved by or deposited with the Director, unless otherwise agreed
with the Director. The Permit Holder shall maintain the dedicated website for
public access of the environmental monitoring data and reports throughout the
entire construction period of the Project and until two months after the last
EM&A report is uploaded, or otherwise agreed by the Director.
許可證持有人須在工程項目的建造工程展開後6個星期內,設立特定網站存放環境監察數據及工程項目資料,並以書面通知署長互聯網網址所在。除非另獲署長同意,上文條件第4.1項說明的所有環境監察數據,均須盡快透過該特定網站供公眾閱覽,在任何情況下均不得遲於有關資料在收集或可供發放後的2個星期內上載至該特定網站。除非另獲署長同意,所有提交文件及圖則的定稿,均須盡快透過該特定網站供公眾閱覽,在任何情況下均不得遲於有關提交文件及圖則獲署長批准或向署長存放後的2個星期內上載至該特定網站。許可證持有人須在工程項目的整個施工期內及最後一份環監報告上載後的2個月內,或另獲署長同意,維持該特定網站,供公眾人士查閱環境監察數據及報告。
4.3 The
Internet web site as described in Condition 4.2 above shall enable
user-friendly public access to the environmental monitoring data and project
information including the Project Profile, EIA report, environmental permit(s)
and finalized submissions and plans required under this Permit. Unless otherwise agreed by the Director, the Internet web site shall have features
capable of:
上文條件第4.2項說明的互聯網網站,必須方便用戶使用,讓公眾容易接達環境監察數據及工程項目資料,當中包括工程項目簡介、環評報告、環境許可證及本許可證所規定提交文件及圖則的定稿。除非另獲署長同意,互聯網網站須具備部件,提供下述功能:
a) providing
access to all environmental monitoring data of this Project collected since the
commencement of construction;
接達建造工程展開後所收集的全部環境監察數據;
b) providing
access to all finalized submissions as required under this Permit;
接達本許可證所規定提交的所有文件定稿;
c) searching by
date;
按日期搜尋;
d) searching by
types of monitoring data; and
按監察數據類別搜尋;以及
e) hyperlinking
to relevant monitoring data after searching
在搜尋後與相關的監察數據作出超文本連結。
Notes:
1.
This Permit consists of three
parts, namely, Part A (Main Permit), Part B (Description of
Designated Project) and Part C (Permit Conditions). Any person relying on this Permit should obtain
independent legal advice on the legal implications under the EIAO, and the
following notes are for general information only.
本許可證共有3部,即A部 (許可證主要部分);B部 (指定工程項目的說明) 及C部 (許可證條件)。任何援引本許可證的人士須就環評條例的法律含意徵詢獨立法律意見,下述註解只供一般參考用。
2.
If there is a breach of any
condition of this Permit, the Director or his authorized officer may, with the
consent of the Secretary for the
Environment and Ecology, order
the cessation of associated work until the remedial action is taken in respect
of the resultant environmental damage, and in that case the Permit Holder shall
not carry out any associated works without the permission of the Director or
his authorized officer.
如違反本許可證的任何條件,署長或獲授權人員徵得環境及生態局局長的同意後可勒令停止相關工程,直至許可證持有人為所造成的環境損害採取補救行動為止。在此情況下,許可證持有人未經署長或獲授權人員同意,不得進行任何相關工程。
3.
The Permit Holder may apply under
Section 13 of the EIAO to the Director for a variation of the conditions of
this Permit. The Permit Holder shall replace the original permit displayed on
the Project site by the amended permit.
許可證持有人可根據環評條例第13條的規定向署長申請更改本許可證的條件。許可證持有人須將經修改的許可證替換在工程項目工地內展示的原有許可證。
4.
A person who assumes the
responsibility for the whole or a part of the Project may, before he assumes
responsibility of the Project, apply under Section 12 of the EIAO to the
Director for a further environmental permit.
承擔工程項目整項或部分工程的責任的人,在承擔責任之前,可根據環評條例第12條的規定向署長申請新的環境許可證。
5.
Under Section 14 of the EIAO, the
Director may, with the consent of the Secretary
for the Environment and Ecology,
suspend, vary or cancel this Permit. The suspended, varied or cancelled Permit
shall be removed from display at the Project site.
根據環評條例第14條的規定,署長可在環境及生態局局長的同意下暫時吊銷、更改或取消本許可證。遭暫時吊銷、更改或取消的許可證必須從工程項目工地除下,不再展示。
6.
If this Permit is cancelled or
surrendered during construction or operation of the Project, another
environmental permit must be obtained under the EIAO before the Project could
be continued. It is an offence under Section 26(1) of the EIAO to construct or
operate a designated project listed in Part I of Schedule 2 of the EIAO without
a valid environmental permit.
如果本許可證在工程項目建造或營辦期間取消或交回,則在繼續進行工程項目之前,必須先根據環評條例的規定取得另一份環境許可證。根據環評條例第26(1)條的規定,任何人在沒有有效環境許可證的情況下建造或營辦環評條例附表2第I部所列明的指定工程項目,即屬犯罪。
7.
Any person who constructs or
operates the Project contrary to the conditions in the Permit, and is convicted
of an offence under the EIAO, is liable:
如任何人在違反本許可證的條件下建造或營辦工程項目,且被裁定觸犯環評條例所訂明的罪行,即屬犯罪—
(i)
on a first conviction on indictment
to a fine of $2 million and to
imprisonment for 6 months;
一經循公訴程序首次定罪,可處罰款200萬元及監禁6個月;
(ii)
on a second or subsequent
conviction on indictment to a fine of $5 million and to imprisonment for 2
years;
一經循公訴程序第二次或其後每次定罪,可處罰款500萬元及監禁2年;
(iii)
on a first summary conviction to a
fine at level 6 and to imprisonment for 6 months;
一經循簡易程序首次定罪,可處第6級罰款及監禁6個月;
(iv)
on a second or subsequent summary
conviction to a fine of $1 million and to imprisonment for 1 year; and
一經循簡易程序第二次或其後每次定罪,可處罰款100萬元及監禁1年;及
(v)
in any case where the offence is of
a continuing nature, the court or magistrate may impose a fine of $10,000 for
each day on which he is satisfied the offence continued.
在任何情況下如該罪行屬持續性質,則法院或裁判官可就其信納該罪行持續的每天另處罰款10,000元。
8.
The Permit Holder may appeal
against any condition of this Permit under Section 17 of the EIAO within 30
days of receipt of this Permit.
許可證持有人可在接獲本許可證後30天內,根據環評條例第17條就本許可證的任何條件提出上訴。
9.
The
Notes are for general reference only and that the Permit Holder should refer to the EIAO for details and seek independent
legal advice.
上述註解只供一般參考用,欲知有關詳情,許可證持有人須參閱環評條例及徵詢獨立法律意見。