Monthly Update of Documents
Uploaded
Documents Uploaded to the EIAO Website
|
|
(for the period between 16 November 2021 to 15 December 2021)
|
|
|
|
|
|
|
Application
No. / Permit No.
|
Project
Title
|
Document
Name
|
Hyperlink
|
|
|
|
|
|
|
Application
for EIA Study Brief
|
|
|
|
|
|
|
Nil
|
|
|
|
|
|
|
Application
for Permission to Apply Directly for Environmental Permit
|
|
|
|
|
|
|
DIR-287/2021
|
Removal
of 132kV Overhead Line and Pylons for P-Line
|
Project
Profile
|
https://www.epd.gov.hk/eia/register/profile/latest/dir287/dir287.pdf
|
|
|
|
|
|
|
Application
for Approval of EIA Report
|
|
|
|
|
|
|
EIA-271/2021
|
Relocation
of Diamond Hill Fresh Water and Salt Water Service Reservoirs to Caverns
|
EIA Reports
Approved
|
https://www.epd.gov.hk/eia/register/report/conditions/aeiar2712021.pdf
|
|
|
|
|
|
|
EIA-274/2021
|
Mai
Po Nature Reserve Infrastructure Upgrade Project
|
EIA Reports
|
https://www.epd.gov.hk/eia/register/report/eiareport/eia_2742021/Content%20Page.html
|
|
|
|
|
|
|
Application
for Environmental Permit
|
|
|
|
|
|
|
AEP-601/2021
|
Desilting Works at Pui O River
|
Environmental
Permit issued (EP-601/2021)
|
https://www.epd.gov.hk/eia/register/permit/latest/ep6012021.htm
|
|
|
|
|
|
|
AEP-602/2021
|
Relocation
of Diamond Hill Fresh Water and Salt Water Service Reservoirs to Caverns
|
Environmental
Permit issued (EP-602/2021)
|
https://www.epd.gov.hk/eia/register/permit/latest/ep6022021.htm
|
|
|
|
|
|
|
Application
for Variation of an Environmental Permit
|
|
|
|
|
|
|
VEP-600/2021
|
Sludge
Treatment Facilities
|
Environmental
Permit issued (EP-334/2009/F)
|
https://www.epd.gov.hk/eia/register/permit/latest/vep6002021.htm
|
|
|
|
|
|
|
VEP-601/2021
|
Sludge
Treatment Facilities
|
Environmental
Permit issued (FEP-01/334/2009/F)
|
https://www.epd.gov.hk/eia/register/permit/latest/vep6012021.htm
|
|
|
|
|
|
|
VEP-602/2021
|
Yuen
Long Nullah Revitalisation
/ decking along Kung Um Road and Kiu Hing Road for Housing Sites in Yuen Long South
|
Environmental
Permit issued (EP-553/2008/A)
|
https://www.epd.gov.hk/eia/register/permit/latest/vep6022021.htm
|
|
|
|
|
|
|
VEP-603/2021
|
Fill
Bank at Tseung Kwan O Area 137
|
Environmental
Permit issued (EP-134/2002/O)
|
https://www.epd.gov.hk/eia/register/permit/latest/vep6032021.htm
|
|
|
|
|
|
|
Application
for Further Environmental Permit
|
|
|
|
|
|
|
Nil
|
|
|
|
|
|
|
Submission
as required by Environmental Permit Condition - Design / Environmental
Submissions
|
|
|
|
|
|
|
EP-457/2013/D
|
Central Kowloon Route - Central Tunnel
(HY/2018/08)
|
Certification of Construction Noise
Mitigation Measure Plan
|
https://www.epd.gov.hk/eia/english/register/index8/vep5942021hy201808.html
|
|
|
|
|
|
|
EP-464/2013
|
Expansion of
Ha Tsuen Sewage Pumping Station
|
Monthly Operational Phase Environmental
Monitoring and Audit Report No. 5
|
https://www.epd.gov.hk/eia/english/register/aep/ep4642013_content.html
|
|
|
|
|
|
|
EP-505/2015/A
|
Chai Wan
Government Complex and Vehicle Depot
|
Baseline Monitoring Report (Rev 1)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5702019_content.html
|
|
|
|
|
|
|
EP-581/2020
|
Airport City Link
|
Baseline Monitoring Report(Nov 2021)
|
https://www.epd.gov.hk/eia/english/register/aep/ep5812020_content.html
|
|
|
|
|
|
|
EP-477/2013/A
|
Development of Lok
Ma Chau Loop
|
Emergency Contingency Plan
|
https://www.epd.gov.hk/eia/english/register/index8/vep5952021_content.html
|
|
|
|
|
|
|
EP-014/1998/A
|
Outlying Islands Transfer Facilities at Sok Kwu Wan
|
Annual Environmental Audit Report(Operation)(Apr 2002 to Mar 2003)
|
https://www.epd.gov.hk/eia/english/register/index8/vep2692021_content.html
|
|
|
|
|
|
|
EP-014/1998/A
|
Outlying Islands Transfer Facilities at Sok Kwu Wan
|
Annual Environmental Audit Report(Operation)(Apr 2003 to Mar 2004)
|
https://www.epd.gov.hk/eia/english/register/index8/vep2692021_content.html
|
|
|
|
|
|
|
EP-014/1998/A
|
Outlying Islands Transfer Facilities at Sok Kwu Wan
|
Annual Environmental Audit Report(Operation)(Apr 2004 to Mar 2005)
|
https://www.epd.gov.hk/eia/english/register/index8/vep2692021_content.html
|
|
|
|
|
|
|
EP-014/1998/A
|
Outlying Islands Transfer Facilities at Sok
Kwu Wan
|
Annual Environmental Audit Report(Operation)(Apr 2005 to Mar 2006)
|
https://www.epd.gov.hk/eia/english/register/index8/vep2692021_content.html
|
|
|
|
|
|
|
EP-014/1998/A
|
Outlying Islands Transfer Facilities at Sok Kwu Wan
|
Annual Environmental Audit Report(Operation)(Apr 2006 to Mar 2007)
|
https://www.epd.gov.hk/eia/english/register/index8/vep2692021_content.html
|
|
|
|
|
|
|
EP-014/1998/A
|
Outlying Islands Transfer Facilities at Sok Kwu Wan
|
Annual Environmental Audit Report(Operation)(Apr 2007 to Mar 2008)
|
https://www.epd.gov.hk/eia/english/register/index8/vep2692021_content.html
|
|
|
|
|
|
|
EP-014/1998/A
|
Outlying Islands Transfer Facilities at Sok Kwu Wan
|
Annual Environmental Audit Report(Operation)(Apr 2008 to Mar 2009)
|
https://www.epd.gov.hk/eia/english/register/index8/vep2692021_content.html
|
|
|
|
|
|
|
EP-014/1998/A
|
Outlying Islands Transfer Facilities at Sok Kwu Wan
|
Annual Environmental Audit Report(Operation)(Apr 2009 to Mar 2010)
|
https://www.epd.gov.hk/eia/english/register/index8/vep2692021_content.html
|
|
|
|
|
|
|
EP-014/1998/A
|
Outlying Islands Transfer Facilities at Sok Kwu Wan
|
Annual Environmental Audit Report(Operation)(Apr 2010 to Mar 2011)
|
https://www.epd.gov.hk/eia/english/register/index8/vep2692021_content.html
|
|
|
|
|
|
|
EP-014/1998/A
|
Outlying Islands Transfer Facilities at Sok Kwu Wan
|
Annual Environmental Audit Report(Operation)(Apr 2011 to Mar 2012)
|
https://www.epd.gov.hk/eia/english/register/index8/vep2692021_content.html
|
|
|
|
|
|
|
EP-014/1998/A
|
Outlying Islands Transfer Facilities at Sok Kwu Wan
|
Annual Environmental Audit Report(Operation)(Apr 2012 to Mar 2013)
|
https://www.epd.gov.hk/eia/english/register/index8/vep2692021_content.html
|
|
|
|
|
|
|
FEP-01/470/2013
|
Utilization of Treated Sewage Effluent (TSE)
from Shek Wu Hui Sewage
Treatment Works
|
Baseline Monitoring Report
|
https://www.epd.gov.hk/eia/english/register/index7/fep2042021_content.html
|
|
|
|
|
|
|
EP-473/2013/A
|
Fanling Bypass Eastern Section
|
Detailed Design of Siu
Hang San Tsuen Watercourse
|
https://www.epd.gov.hk/eia/english/register/index8/vep5262016_content.html
|
|
|
|
|
|
|
EP-505/2015/A
|
Chai Wan Government Complex and Vehicle Depot
|
Construction Noise Management Plan (Rev E)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5702019_content.html
|
|
|
|
|
|
|
EP-071/2000/D
|
1,800MW Gas-Fired Power Station at Lamma Extension
|
Waste Management Plan
|
https://www.epd.gov.hk/eia/english/register/index8/vep5802020_content.html
|
|
|
|
|
|
|
Submission
as required by Environmental Permit Condition - EM&A Report
|
|
|
|
|
|
|
|
Island District
|
Central & Western District
|
|
|
|
|
|
|
|
|
North District
|
Wan Chai District
|
|
|
|
|
|
|
|
|
Sai Kung District
|
Eastern District
|
|
|
|
|
|
|
|
|
Sha Tin District
|
Southern District
|
|
|
|
|
|
|
|
|
Tai Po District
|
Kowloon City District
|
|
|
|
|
|
|
|
|
Tsuen Wan District
|
Kwun Tong District
|
|
|
|
|
|
|
|
|
Tuen Mun District
|
Sham Shui Po District
|
|
|
|
|
|
|
|
|
Yuen Long District
|
Wong Tai Sin District
|
|
|
|
|
|
|
|
|
Kwai Tsing District
|
Yau Tsim Mong District
|
|
|
|
|
|
|
|
- Island District
|
|
|
|
|
|
|
EP-555/2018/A
|
New Wang Tong River
Bridge
|
Monthly EM&A
Report(Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5852020_content.html
|
|
|
|
|
|
|
EP-519/2016
|
Tung Chung New Town
Extension
|
Monthly EM&A
Report(Aug 2021)
|
https://www.epd.gov.hk/eia/english/register/aep/ep5192016_content.html
|
|
|
|
|
|
|
EP-519/2016
|
Tung Chung New Town
Extension
|
Monthly EM&A Report(Sep 2021)
|
https://www.epd.gov.hk/eia/english/register/aep/ep5192016_content.html
|
|
|
|
|
|
|
EP-519/2016
|
Tung Chung New Town
Extension
|
Monthly EM&A Report(Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/aep/ep5192016_content.html
|
|
|
|
|
|
|
EP-489/2014
|
Expansion of Hong Kong
International Airport into a Three-Runway System
|
Construction Phase
Monthly EM&A Report No.70
|
https://www.epd.gov.hk/eia/english/register/aep/ep4892014_content.html
|
|
|
|
|
|
|
EP-489/2014
|
Expansion of Hong Kong
International Airport into a Three-Runway System
|
Quarterly EM&A
Report No.23 (Jul 2021 to Sep 2021)
|
https://www.epd.gov.hk/eia/english/register/aep/ep4892014_content.html
|
|
|
|
|
|
|
FEP-01/353/2009/K
|
Hong Kong - Zhuha - Macao Bridge (HZMB) Hong Kong Boundary Crossing
Facilities (HKBCF) - The Road Connection between HKBCF and the Airport, Chek Lap Kok
|
Construction Phase
Monthly EM&A Report No. 1 (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1902018_content.html
|
|
|
|
|
|
|
EP-083/2000
|
Conversion of Two
Existing Gas Turbines (GT5 & GT7) into a Combined Cycle Unit
|
Monthly Environmental
Monitoring And Audit Report (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/aep/ep0832000_content.html
|
|
|
|
|
|
|
FEP-01/558/2018/A
|
Hong Kong Offshore LNG Terminal - Works associated
with the double berth jetty at LNG Terminal
|
Monthly Environmental Monitoring and Audit (EM&A)
Report (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5832020_content.html
|
|
|
|
|
|
|
EP-532/2017/A
|
Mui Wo Lai Chi Yuen
Cemetery Extension
|
Monthly EM&A Report
(Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5582019_content.html
|
|
|
|
|
|
|
FEP-02/558/2018/A
|
Hong Kong Offshore LNG Terminal - Works associated
with the subsea gas pipeline for Lamma Power
Station (LPS) and the associated Gas Receiving Station (GRS) in LPS
|
Monthly Environmental Monitoring and Audit (EM&A)
Report (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5862020_content.html
|
|
|
|
|
|
|
FEP-03/558/2018/B
|
Hong Kong Offshore LNG Terminal - Works associated with
the subsea gas pipeline for Black Point Power Station (BPPS) and the
associated Gas Receiving Station (GRS) in BPPS
|
Monthly Environmental Monitoring and Audit (EM&A)
Report (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5972021_content.html
|
|
|
|
|
|
|
FEP-01/558/2018/A
|
Hong Kong Offshore LNG Terminal - Works associated
with the double berth jetty at LNG Terminal
|
Quarterly Environmental Monitoring and Audit
(EM&A) Report(Jul 2021 to Sep 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5832020_content.html
|
|
|
|
|
|
|
FEP-02/558/2018/A
|
Hong Kong Offshore LNG Terminal - Works associated
with the subsea gas pipeline for Lamma Power
Station (LPS) and the associated Gas Receiving Station (GRS) in LPS
|
Quarterly Environmental Monitoring and Audit (EM&A)
Report(Jul 2021 to Sep 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5862020_content.html
|
|
|
|
|
|
|
FEP-03/558/2018/B
|
Hong Kong Offshore LNG Terminal - Works associated
with the subsea gas pipeline for Black Point Power Station (BPPS) and the
associated Gas Receiving Station (GRS) in BPPS
|
Quarterly Environmental Monitoring and Audit
(EM&A) Report(Jul 2021 to Sep 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5972021_content.html
|
|
|
|
|
|
|
EP-488/2014/A
|
Upgrading of Cheung Chau Sewage Collection, Treatment and Disposal
Facilities
|
Monthly EM&A Report(Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5912021_content.html
|
|
|
|
|
|
|
EP-01/059/2000/C
|
The Theme Park at
Penny's Bay, Lantau
|
194th Monthly EM&A
Report (12 Oct 2021 – 11 Nov 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep3782012_content.html
|
|
|
|
|
|
|
EP-071/2000/D
|
1,800
MW Gas-Fired Power Station at Lamma Extension
|
Monthly Environmental Monitoring and Audit
Report Unit L11& L12 (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5802020_content.html
|
|
|
|
|
|
|
EP-071/2000/D
|
1,800
MW Gas-Fired Power Station at Lamma Extension
|
Environmental Monitoring and Audit Report
(Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5802020_content.html
|
|
|
|
|
|
|
EP-353/2009/K
|
Hong Kong - Zhuhai - Macao
Bridge Hong Kong Boundary Crossing Facilities
|
Monthly EM&A Report(Oct 2021)(HY/2019/01)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4982016_content.html
|
|
|
|
|
|
|
EP-353/2009/K
|
Hong Kong - Zhuhai - Macao
Bridge Hong Kong Boundary Crossing Facilities
|
Monthly EM&A Report(Oct 2021) (HY/2011/03)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4982016_content.html
|
|
|
|
|
|
|
EP-429/2012/A
FEP-01/429/2012/A
|
Development of the Integrated Waste
Management Facilities Phase 1
|
Monthly EM&A Report No.40(Rev A)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1772017_content.html
|
|
|
|
|
|
|
EP-352/2009/D
|
Hong Kong - Zhuhai - Macao
Bridge Hong Kong Link Road
|
Monthly
EM&A Report(Oct 2021) (HY/2011/03)
|
https://www.epd.gov.hk/eia/english/register/index8/vep4592014_content.html
|
|
|
|
|
|
|
EP-456/2013/B
|
Drainage Improvement Works at Ngong Ping
|
Monthly Environmental Monitoring And Audit
Report (Oct 2021)(DC/2019/06)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5992021_content.html
|
|
|
|
|
|
|
EP-560/2018
|
Intermodal Transfer Terminal – Bonded Vehicular
Bridge and Associated Roads
|
EM&A Report(Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/aep/ep5602018_content.html
|
|
|
|
|
|
|
EP-354/2009/D
|
Tuen Mun - Chek Lap Kok Link
|
EM&A Report (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep4692015_content.html
|
|
|
|
|
|
|
EP-535/2017
|
Improvement
Dredging for Lamma Power Station Navigation
Channel
|
Quality EM&A Report (Aug 2021 to Sep
2021)
|
https://www.epd.gov.hk/eia/english/register/aep/ep5352017_content.html
|
|
|
|
|
|
|
EP-312/2008/A
|
Disposal of Contaminated Sediment - Dredging,
Management and Capping of sediment Disposal Facility at Sha
Chau
|
Monthly Progress Report (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep2742009_content.html
|
|
|
|
|
|
|
FEP-01/395/2010/C
|
Organic Waste Treatment Facilities, Phase I
|
Seventy-seventh Monthly EM&A Report (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep4872015_content.html
|
|
|
|
|
|
|
EP-01/097/2001/C
|
Water
Recreation Centre at Penny's Bay (part & remaining part)
|
Monthly
Environmental Monitoring and Audit Report (No. 194)
|
http://www.epd.gov.hk/eia/english/register/index8/vep1992005_content.html
|
|
|
|
|
|
|
EP-01/097/2001/C
|
Water
Recreation Centre at Penny's Bay (part & remaining part)
|
Monthly
Environmental Monitoring and Audit Report (No. 195)
|
http://www.epd.gov.hk/eia/english/register/index8/vep1992005_content.html
|
|
|
|
|
|
|
- North District
|
|
|
|
|
|
|
EP-534/2017/A
|
Site Formation and Associated
Infrastructural Works for Development of Columbarium, Crematorium and
Related Facilities at Sandy Ridge Cemetery
|
Monthly EM&A Report (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5542018_content.html
|
|
|
|
|
|
|
EP-534/2017
|
Site Formation and Associated
Infrastructural Works for Development of Columbarium, Crematorium and
Related Facilities at Sandy Ridge Cemetery
|
Monthly EM&A Report (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/aep/ep5342017_content.html
|
|
|
|
|
|
|
FEP-01/534/2017
|
Site Formation and Associated
Infrastructural Works for Development of Columbarium, Crematorium and
Related Facilities at Sandy Ridge Cemetery
|
Monthly EM&A Report (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1802018_content.html
|
|
|
|
|
|
|
FEP-01/534/2017/A
|
Site Formation and Associated
Infrastructural Works for Development of Columbarium, Crematorium and
Related Facilities at Sandy Ridge Cemetery
|
Monthly EM&A Report (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5552018_content.html
|
|
|
|
|
|
|
EP-477/2013/A
|
Development of Lok
Ma Chau Loop
|
Monthly EM&A Report (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5952021_content.html
|
|
|
|
|
|
|
EP-329/2009
|
Provision of Cremators
at Wo Hop Shek
Crematorium
|
Monthly EM&A Report (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/aep/ep3292009_content.html
|
|
|
|
|
|
|
EP-324/2008/E
|
Widening of Tolo
Highway/Fanling Highway between Island House
Interchange and Fanling
|
Annual EM&A Report
(Nov 2020 - Sep 2021)(CV/2012/09)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5222016_content.html
|
|
|
|
|
|
|
EP-324/2008/E
|
Widening of Tolo
Highway/Fanling Highway between Island House
Interchange and Fanling
|
Quarterly EM&A
Report (Aug 2021- Sep 2021)(CV/2012/09)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5222016_content.html
|
|
|
|
|
|
|
EP-324/2008/E
|
Widening of Tolo
Highway/Fanling Highway between Island House
Interchange and Fanling
|
Annual EM&A Report
(Nov 2020 - Sep 2021) (HY/2012/06)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5222016_content.html
|
|
|
|
|
|
|
EP-517/2017/A
|
Expansion of Sha
Tau Kok Sewage Treatment Works
|
Monthly EM&A Report(Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5672019_content.html
|
|
|
|
|
|
|
EP-510/2016
|
Police Facilities in Kong Nga
Po
|
Monthly
EM&A Report(Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/aep/ep5102016_content.html
|
|
|
|
|
|
|
EP-510/2016
|
Police Facilities in Kong Nga
Po
|
Quarterly
EM&A Report (Jul 2021 to Sep 2021)
|
https://www.epd.gov.hk/eia/english/register/aep/ep5102016_content.html
|
|
|
|
|
|
|
FEP-02/474/2013
|
Shek Wu Hui Effluent Polishing Plant
|
Monthly EM&A Report(Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1792018_content.html
|
|
|
|
|
|
|
EP-470/2013
|
NENT - Utilization of Treated Sewage Effluent (TSE) from Shek Wu Hui Sewage Treatment
Works
|
Monthly EM&A Report(Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/aep/ep4702013_content.html
|
|
|
|
|
|
|
EP-475/2013/A
|
Reprovision of temporary Wholesale Market in Fanling North New Development Area
|
Monthly EM&A Report(Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5162016_content.html
|
|
|
|
|
|
|
EP-468/2013/A
|
Kwu Tung North New Development Area Road D1 to D5
|
Monthly EM&A Report(Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5232016_content.html
|
|
|
|
|
|
|
EP-466/2013
|
NENT - Castle Peak Road
Diversion
|
Monthly
EM&A Report(Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/aep/ep4662013_content.html
|
|
|
|
|
|
|
EP-467/2013/A
|
Kwu Tung North New Development Area
Road P1 and P2 and Associated New Kwu Tung
Interchange and Pak Shek Au Interchange
Improvement
|
Monthly EM&A
Report(Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5242016_content.html
|
|
|
|
|
|
|
EP-469/2013
|
NENT - Sewage Pumping Stations
in Kwu Tung North New Development Areaf
|
Monthly
EM&A Report(Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/aep/ep4692013_content.html
|
|
|
|
|
|
|
EP-473/2013/A
|
Fanling Bypass Eastern Section
|
Monthly
EM&A Report(Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5262016_content.html
|
|
|
|
|
|
|
EP-404/2011/D
|
Liantang / Heung Yuen Wai Boundary Control Point and Associated Works
|
Monthly EM&A Report (Oct 2021)
|
http://www.epd.gov.hk/eia/english/register/index8/vep5192016_content.html
|
|
|
|
|
|
|
EP-404/2011/D
|
Liantang / Heung Yuen Wai Boundary Control Point and Associated Works
|
Quarterly EM&A Report (Aug 2021 to Oct 2021)
|
http://www.epd.gov.hk/eia/english/register/index8/vep5192016_content.html
|
|
|
|
|
|
|
FEP-01/460/2013/A
|
Development of Organic Waste Treatment Facilities,
Phase 2
|
Monthly EM&A Report (Aug 2021) (Version
3)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5792020_content.html
|
|
|
|
|
|
|
FEP-01/460/2013/A
|
Development of Organic Waste Treatment
Facilities, Phase 2
|
Monthly EM&A Report (Sep 2021) (Version 3)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5792020_content.html
|
|
|
|
|
|
|
FEP-01/460/2013/A
|
Development of Organic Waste Treatment
Facilities, Phase 2
|
Monthly EM&A Report (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5792020_content.html
|
|
|
|
|
|
|
- Sai Kung
District
|
|
|
|
|
|
|
EP-134/2002/N
|
Fill Bank at Tseung
Kwan O Area 137
|
Monthly Environmental Monitoring and Audit
Report (Sep 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5632019_content.html
|
|
|
|
|
|
|
EP-134/2002/N
|
Fill Bank at Tseung
Kwan O Area 137
|
Quarterly Environmental Monitoring and Audit
Report (May 2021 to Jul 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5632019_content.html
|
|
|
|
|
|
|
EP-134/2002/N
|
Fill Bank at Tseung
Kwan O Area 137
|
Monthly Environmental Monitoring and Audit
Report (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5632019_content.html
|
|
|
|
|
|
|
FEP-01/308/2008/B
|
South-East New Territories Landfill Extension
|
Monthly EM&A Report No.34(Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1872018_content.html
|
|
|
|
|
|
|
FEP-01/308/2008/B
|
South-East New Territories Landfill Extension
|
Quarterly EM&A Report (Jul 2021 to Sep
2021)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1872018_content.html
|
|
|
|
|
|
|
EP-308/2008/B
|
South-East New Territories Landfill Extension
|
Monthly EM&A Report No.34(Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/aep/ep3082008_content.html
|
|
|
|
|
|
|
EP-308/2008/B
|
South-East New Territories Landfill Extension
|
Quarterly EM&A Report (Jul 2021 to Sep
2021)
|
https://www.epd.gov.hk/eia/english/register/aep/ep3082008_content.html
|
|
|
|
|
|
|
EP-513/2016
|
Development of Anderson Road Quarry site -
Road Improvement Works
|
Monthly EM&A Report (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/aep/ep5132016_content.html
|
|
|
|
|
|
|
EP-459/2013
|
Cross Bay Link, Tseung
Kwan O
|
Monthly EM&A Report (Oct 2021)(Version 2)
|
https://www.epd.gov.hk/eia/english/register/aep/ep4592013_content.html
|
|
|
|
|
|
|
EP-516/2016
|
Port Shelter Sewerage, Stage3 - Sewerage
Works at Po Toi O
|
Quality EM&A Report (Jun 2021 to Aug
2021)
|
https://www.epd.gov.hk/eia/english/register/aep/ep5162016_content.html
|
|
|
|
|
|
|
EP-516/2016
|
Port Shelter Sewerage, Stage3 - Sewerage
Works at Po Toi O
|
Monthly EM&A Report(Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/aep/ep5162016_content.html
|
|
|
|
|
|
|
EP-458/2013/C
|
Tseung Kwan O – Lam Tin Tunnel and Associated Works
|
Monthly EM&A Report (Oct 2021)(Version 1.0)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5272016_content.html
|
|
|
|
|
|
|
EP-458/2013/C
|
Tseung Kwan O - Lam Tin Tunnel and Associated Works ED/2018/04
- Cha Kwo Ling
|
Quarterly Environmental Monitoring And Audit Report (Feb 2021 to Apr
2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5272016ED201804_content.html
|
|
|
|
|
|
|
EP-319/2009/D
|
Development of a Biodiesel
Plant at Tseung Kwan O Industrial Estate
|
Monthly EM&A Report
(Oct 2021) (V.1)
|
https://www.epd.gov.hk/eia/english/register/index8/vep4242014_content.html
|
|
|
|
|
|
|
EP-458/2013/C
|
Tseung Kwan O - Lam Tin Tunnel and Associated Works ED/2018/04
- Cha Kwo Ling
|
Monthly EM&A Report (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5272016ED201804_content.html
|
|
|
|
|
|
|
FEP-01/503/2015/A
|
Desalination Plant at Tseung Kwan O
|
Monthly EM&A Report
(Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1922019_content.html
|
|
|
|
|
|
|
FEP-02/428/2011/A
|
Drainage Diversion Works
For the Comprehensive Residential Development At Various Lots In DD227
& DD229, Tai Po Tsai, Sai Kung
|
Monthly EM&A Report(Jan 2014)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1422012_content.html
|
|
|
|
|
|
|
FEP-02/428/2011/A
|
Drainage Diversion Works
For the Comprehensive Residential Development At Various Lots In DD227
& DD229, Tai Po Tsai, Sai Kung
|
Monthly EM&A Report(Feb 2014)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1422012_content.html
|
|
|
|
|
|
|
FEP-02/428/2011/A
|
Drainage Diversion Works
For the Comprehensive Residential Development At Various Lots In DD227
& DD229, Tai Po Tsai, Sai Kung
|
Monthly EM&A Report(Mar 2014)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1422012_content.html
|
|
|
|
|
|
|
FEP-02/428/2011/A
|
Drainage Diversion Works
For the Comprehensive Residential Development At Various Lots In DD227
& DD229, Tai Po Tsai, Sai Kung
|
Monthly EM&A Report(Apr 2014)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1422012_content.html
|
|
|
|
|
|
|
FEP-02/428/2011/A
|
Drainage Diversion Works
For the Comprehensive Residential Development At Various Lots In DD227
& DD229, Tai Po Tsai, Sai Kung
|
Monthly EM&A Report(May 2014)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1422012_content.html
|
|
|
|
|
|
|
FEP-02/428/2011/A
|
Drainage Diversion Works
For the Comprehensive Residential Development At Various Lots In DD227
& DD229, Tai Po Tsai, Sai Kung
|
Monthly EM&A Report(Jun 2014)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1422012_content.html
|
|
|
|
|
|
|
FEP-02/428/2011/A
|
Drainage Diversion Works
For the Comprehensive Residential Development At Various Lots In DD227
& DD229, Tai Po Tsai, Sai Kung
|
Monthly EM&A Report(Jul 2014)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1422012_content.html
|
|
|
|
|
|
|
FEP-02/428/2011/A
|
Drainage Diversion Works
For the Comprehensive Residential Development At Various Lots In DD227
& DD229, Tai Po Tsai, Sai Kung
|
Monthly EM&A Report(Aug 2014)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1422012_content.html
|
|
|
|
|
|
|
FEP-02/428/2011/A
|
Drainage Diversion Works
For the Comprehensive Residential Development At Various Lots In DD227
& DD229, Tai Po Tsai, Sai Kung
|
Monthly EM&A Report(Sep 2014)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1422012_content.html
|
|
|
|
|
|
|
FEP-02/428/2011/A
|
Drainage Diversion Works
For the Comprehensive Residential Development At Various Lots In DD227
& DD229, Tai Po Tsai, Sai Kung
|
Monthly EM&A Report(Oct 2014)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1422012_content.html
|
|
|
|
|
|
|
FEP-02/428/2011/A
|
Drainage Diversion Works
For the Comprehensive Residential Development At Various Lots In DD227
& DD229, Tai Po Tsai, Sai Kung
|
Monthly EM&A Report(Nov 2014)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1422012_content.html
|
|
|
|
|
|
|
FEP-02/428/2011/A
|
Drainage Diversion Works
For the Comprehensive Residential Development At Various Lots In DD227
& DD229, Tai Po Tsai, Sai Kung
|
Monthly EM&A Report(Dec 2014)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1422012_content.html
|
|
|
|
|
|
|
EP-428/2011/A
|
Drainage Diversion Works
For the Comprehensive Residential Development At Various Lots In DD227
& DD229, Tai Po Tsai, Sai Kung
|
Monthly EM&A Report(Jan 2014)
|
https://www.epd.gov.hk/eia/english/register/index8/vep3642012_content.html
|
|
|
|
|
|
|
EP-428/2011/A
|
Drainage Diversion Works
For the Comprehensive Residential Development At Various Lots In DD227
& DD229, Tai Po Tsai, Sai Kung
|
Monthly EM&A Report(Feb 2014)
|
https://www.epd.gov.hk/eia/english/register/index8/vep3642012_content.html
|
|
|
|
|
|
|
EP-428/2011/A
|
Drainage Diversion Works
For the Comprehensive Residential Development At Various Lots In DD227
& DD229, Tai Po Tsai, Sai Kung
|
Monthly EM&A Report(Mar 2014)
|
https://www.epd.gov.hk/eia/english/register/index8/vep3642012_content.html
|
|
|
|
|
|
|
EP-428/2011/A
|
Drainage Diversion Works
For the Comprehensive Residential Development At Various Lots In DD227
& DD229, Tai Po Tsai, Sai Kung
|
Monthly EM&A Report(Apr 2014)
|
https://www.epd.gov.hk/eia/english/register/index8/vep3642012_content.html
|
|
|
|
|
|
|
EP-428/2011/A
|
Drainage Diversion Works
For the Comprehensive Residential Development At Various Lots In DD227
& DD229, Tai Po Tsai, Sai Kung
|
Monthly EM&A Report(May 2014)
|
https://www.epd.gov.hk/eia/english/register/index8/vep3642012_content.html
|
|
|
|
|
|
|
EP-428/2011/A
|
Drainage Diversion Works
For the Comprehensive Residential Development At Various Lots In DD227
& DD229, Tai Po Tsai, Sai Kung
|
Monthly EM&A Report(Jun 2014)
|
https://www.epd.gov.hk/eia/english/register/index8/vep3642012_content.html
|
|
|
|
|
|
|
EP-428/2011/A
|
Drainage Diversion Works
For the Comprehensive Residential Development At Various Lots In DD227
& DD229, Tai Po Tsai, Sai Kung
|
Monthly EM&A Report(Jul 2014)
|
https://www.epd.gov.hk/eia/english/register/index8/vep3642012_content.html
|
|
|
|
|
|
|
EP-428/2011/A
|
Drainage Diversion Works
For the Comprehensive Residential Development At Various Lots In DD227
& DD229, Tai Po Tsai, Sai Kung
|
Monthly EM&A Report(Aug 2014)
|
https://www.epd.gov.hk/eia/english/register/index8/vep3642012_content.html
|
|
|
|
|
|
|
EP-428/2011/A
|
Drainage Diversion Works
For the Comprehensive Residential Development At Various Lots In DD227
& DD229, Tai Po Tsai, Sai Kung
|
Monthly EM&A Report(Sep 2014)
|
https://www.epd.gov.hk/eia/english/register/index8/vep3642012_content.html
|
|
|
|
|
|
|
EP-428/2011/A
|
Drainage Diversion Works
For the Comprehensive Residential Development At Various Lots In DD227
& DD229, Tai Po Tsai, Sai Kung
|
Monthly EM&A Report(Oct 2014)
|
https://www.epd.gov.hk/eia/english/register/index8/vep3642012_content.html
|
|
|
|
|
|
|
EP-428/2011/A
|
Drainage Diversion Works
For the Comprehensive Residential Development At Various Lots In DD227
& DD229, Tai Po Tsai, Sai Kung
|
Monthly EM&A Report(Nov 2014)
|
https://www.epd.gov.hk/eia/english/register/index8/vep3642012_content.html
|
|
|
|
|
|
|
EP-428/2011/A
|
Drainage Diversion Works
For the Comprehensive Residential Development At Various Lots In DD227
& DD229, Tai Po Tsai, Sai Kung
|
Monthly EM&A Report(Dec 2014)
|
https://www.epd.gov.hk/eia/english/register/index8/vep3642012_content.html
|
|
|
|
|
|
|
- Sha Tin
District
|
|
|
|
|
|
|
EP-494/2015
|
In-situ Reprovisioning of Sha
Tin Water Treatment Works - South Works
|
Monthly
EM&A Report No.68
|
http://www.epd.gov.hk/eia/english/register/aep/ep4942014_content.html
|
|
|
|
|
|
|
EP-463/2013/B
|
Widening and
Reconstruction of Tai Po Road (Sha Tin Section)
|
Monthly
EM&A Report (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5142016_content.html
|
|
|
|
|
|
|
EP-533/2017
|
Sha Tin Cavern Sewage
Treatment Works
|
Monthly
EM&A Report (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/aep/ep5332017_content.html
|
|
|
|
|
|
|
- Tai Po District
|
|
|
|
|
|
|
EP-324/2008/E
|
Widening of Tolo Highway/Fanling Highway between Island House Interchange and Fanling
|
Annual EM&A Report (Nov 2020 - Sep 2021)(CV/2012/09)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5222016_content.html
|
|
|
|
|
|
|
EP-324/2008/E
|
Widening of Tolo Highway/Fanling Highway between Island House Interchange and Fanling
|
Quarterly EM&A Report (Aug 2021- Sep
2021)(CV/2012/09)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5222016_content.html
|
|
|
|
|
|
|
EP-324/2008/E
|
Widening of Tolo Highway/Fanling Highway between Island House Interchange and Fanling
|
Annual
EM&A Report (Nov 2020 - Sep 2021) (HY/2012/06)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5222016_content.html
|
|
|
|
|
|
|
EP-470/2013
|
NENT -
Utilization of Treated Sewage Effluent (TSE) from Shek
Wu Hui Sewage Treatment Works
|
Monthly
EM&A Report(Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/aep/ep4702013_content.html
|
|
|
|
|
|
|
EP-475/2013/A
|
Reprovision of temporary Wholesale Market in Fanling North New Development Area
|
Monthly
EM&A Report(Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5162016_content.html
|
|
|
|
|
|
|
EP-468/2013/A
|
Kwu Tung North New Development Area Road D1 to D5
|
Monthly
EM&A Report(Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5232016_content.html
|
|
|
|
|
|
|
EP-466/2013
|
NENT
- Castle Peak Road Diversion
|
Monthly EM&A Report(Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/aep/ep4662013_content.html
|
|
|
|
|
|
|
EP-467/2013/A
|
Kwu Tung North New Development Area
Road P1 and P2 and Associated New Kwu Tung
Interchange and Pak Shek Au Interchange
Improvement
|
Monthly EM&A Report(Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5242016_content.html
|
|
|
|
|
|
|
EP-469/2013
|
NENT -
Sewage Pumping Stations in Kwu Tung North New
Development Areaf
|
Monthly EM&A Report(Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/aep/ep4692013_content.html
|
|
|
|
|
|
|
EP-473/2013/A
|
Fanling Bypass Eastern Section
|
Monthly EM&A Report(Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5262016_content.html
|
|
|
|
|
|
|
- Tsuen Wan District
|
|
|
|
|
|
|
EP-076/2000
|
Upgrading of Siu
Ho Wan Sewage Treatment Plant
|
Monthly Environmental Monitoring And Audit
Report (Oct 2021)
|
http://www.epd.gov.hk/eia/english/register/aep/ep0762000_content.html
|
|
|
|
|
|
|
EP-076/2000
|
Upgrading of Siu
Ho Wan Sewage Treatment Plant
|
Quarterly Environmental Monitoring And
Audit Report (Aug 2021 to Oct 2021)
|
http://www.epd.gov.hk/eia/english/register/aep/ep0762000_content.html
|
|
|
|
|
|
|
EP-489/2014
|
Expansion of Hong Kong International Airport
into a Three-Runway System
|
Construction Phase Monthly EM&A Report
No.70
|
https://www.epd.gov.hk/eia/english/register/aep/ep4892014_content.html
|
|
|
|
|
|
|
EP-489/2014
|
Expansion of Hong Kong International Airport
into a Three-Runway System
|
Quarterly EM&A Report No.23 (Jul 2021 to
Sep 2021)
|
https://www.epd.gov.hk/eia/english/register/aep/ep4892014_content.html
|
|
|
|
|
|
|
FEP-01/395/2010/C
|
Organic Waste Treatment
Facilities, Phase I
|
Seventy-seventh Monthly
EM&A Report (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep4872015_content.html
|
|
|
|
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report (Oct
2021)(DE/2018/17)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
|
|
|
|
- Tuen Mun District
|
|
|
|
|
|
|
EP-210/2005/D
|
Expansion and Extension
of Fill Bank at Tuen Mun
Area 38
|
Monthly EM&A Report
(Sep 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5772020_content.html
|
|
|
|
|
|
|
EP-210/2005/D
|
Expansion and Extension
of Fill Bank at Tuen Mun
Area 38
|
Monthly EM&A Report
(Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5772020_content.html
|
|
|
|
|
|
|
EP-210/2005/D
|
Expansion and Extension
of Fill Bank at Tuen Mun
Area 38
|
Quarterly EM&A
Report(May 2021 to Jul 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5772020_content.html
|
|
|
|
|
|
|
EP-489/2014
|
Expansion of Hong Kong
International Airport into a Three-Runway System
|
Construction Phase
Monthly EM&A Report No.70
|
https://www.epd.gov.hk/eia/english/register/aep/ep4892014_content.html
|
|
|
|
|
|
|
EP-489/2014
|
Expansion of Hong Kong
International Airport into a Three-Runway System
|
Quarterly EM&A
Report No.23 (Jul 2021 to Sep 2021)
|
https://www.epd.gov.hk/eia/english/register/aep/ep4892014_content.html
|
|
|
|
|
|
|
EP-429/2012/A
FEP-01/429/2012/A
|
Development of the Integrated Waste
Management Facilities Phase 1
|
Monthly EM&A Report No.40(Rev A)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1772017_content.html
|
|
|
|
|
|
|
FEP-01/558/2018/A
|
Hong
Kong Offshore LNG Terminal - Works associated with the double berth jetty
at LNG Terminal
|
Monthly
Environmental Monitoring and Audit (EM&A) Report (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5832020_content.html
|
|
|
|
|
|
|
FEP-02/558/2018/A
|
Hong Kong Offshore LNG Terminal - Works associated
with the subsea gas pipeline for Lamma Power
Station (LPS) and the associated Gas Receiving Station (GRS) in LPS
|
Monthly Environmental Monitoring and Audit (EM&A)
Report (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5862020_content.html
|
|
|
|
|
|
|
FEP-03/558/2018/B
|
Hong Kong Offshore LNG Terminal - Works associated
with the subsea gas pipeline for Black Point Power Station (BPPS) and the
associated Gas Receiving Station (GRS) in BPPS
|
Monthly Environmental Monitoring and Audit (EM&A)
Report (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5972021_content.html
|
|
|
|
|
|
|
FEP-01/558/2018/A
|
Hong Kong Offshore LNG Terminal - Works associated
with the double berth jetty at LNG Terminal
|
Quarterly Environmental Monitoring and Audit (EM&A)
Report(Jul 2021 to Sep 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5832020_content.html
|
|
|
|
|
|
|
FEP-02/558/2018/A
|
Hong Kong Offshore LNG Terminal - Works associated
with the subsea gas pipeline for Lamma Power
Station (LPS) and the associated Gas Receiving Station (GRS) in LPS
|
Quarterly Environmental Monitoring and Audit
(EM&A) Report(Jul 2021 to Sep 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5862020_content.html
|
|
|
|
|
|
|
FEP-03/558/2018/B
|
Hong Kong Offshore LNG Terminal - Works associated
with the subsea gas pipeline for Black Point Power Station (BPPS) and the
associated Gas Receiving Station (GRS) in BPPS
|
Quarterly Environmental Monitoring and Audit
(EM&A) Report(Jul 2021 to Sep 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5972021_content.html
|
|
|
|
|
|
|
EP-534/2017/A
|
Site Formation and Associated Infrastructural Works for
Development of Columbarium, Crematorium and Related Facilities at Sandy
Ridge Cemetery
|
Monthly EM&A Report (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5542018_content.html
|
|
|
|
|
|
|
EP-534/2017
|
Site Formation and Associated Infrastructural Works for
Development of Columbarium, Crematorium and Related Facilities at Sandy
Ridge Cemetery
|
Monthly EM&A Report (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/aep/ep5342017_content.html
|
|
|
|
|
|
|
FEP-01/534/2017
|
Site Formation and Associated Infrastructural Works for
Development of Columbarium, Crematorium and Related Facilities at Sandy
Ridge Cemetery
|
Monthly EM&A Report (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1802018_content.html
|
|
|
|
|
|
|
FEP-01/534/2017/A
|
Site Formation and Associated Infrastructural Works for
Development of Columbarium, Crematorium and Related Facilities at Sandy Ridge
Cemetery
|
Monthly EM&A Report (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5552018_content.html
|
|
|
|
|
|
|
EP-354/2009/D
|
Tuen Mun - Chek Lap Kok Link
|
EM&A Report (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep4692015_content.html
|
|
|
|
|
|
|
EP-441/2012/A
|
Enhanced Ash Utilisation and Water Management Facilities at the
Castle Peak Power Station (CPPS)
|
Monthly EM&A Report
(Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5432018_content.html
|
|
|
|
|
|
|
EP-507/2016/C
|
Installation of One
additional gas-fired generation unit (CCGT Unit No. 1) at the Black Point
Power Station
|
Monthly EM&A Report
no.59
|
https://www.epd.gov.hk/eia/english/register/index8/vep5752020_content.html
|
|
|
|
|
|
|
FEP-03/507/2016/C
|
Additional Gas-fired
Generation units Project - Installation of one additional gas-fired
generation unit (CCGT Unit No. 2) at the Black Point Power Station
|
Monthly EM&A Report
no.59
|
https://www.epd.gov.hk/eia/english/register/index7/fep2012020_content.html
|
|
|
|
|
|
|
FEP-04/507/2016/C
|
Additional Gas-fired
Generation units Project - Installation of one additional gas-fired generation
unit (CCGT Unit No. 2) at the Black Point Power Station
|
Monthly EM&A Report
no.59
|
https://www.epd.gov.hk/eia/english/register/index7/fep2062021_content.html
|
|
|
|
|
|
|
- Yuen Long District
|
|
|
|
|
|
|
EP-477/2013/A
|
Development of Lok Ma Chau Loop
|
Monthly EM&A Report (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5952021_content.html
|
|
|
|
|
|
|
EP-311/2008/E
|
Proposed
Comprehensive Development at Wo Shang Wai, Yuen Long
|
Monthly
EM&A Report (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5382017_content.html
|
|
|
|
|
|
|
EP-565/2019
|
Yuen Long Effluent Polishing Plant
|
Monthly EM&A Report(Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/aep/ep5652019_content.html
|
|
|
|
|
|
|
EP-464/2013
|
Expansion of Ha Tsuen Sewage
Pumping Station
|
Monthly EM&A Report (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/aep/ep4642013_content.html
|
|
|
|
|
|
|
EP-464/2013
|
Expansion of Ha Tsuen Sewage
Pumping Station
|
Quarterly EM&A Report (Aug 2021 to Oct
2021)
|
https://www.epd.gov.hk/eia/english/register/aep/ep4642013_content.html
|
|
|
|
|
|
|
- Kwai Tsing District
|
|
|
|
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report (Oct
2021)(DE/2018/17)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
|
|
|
|
EP-541/2017/A
|
Flyover from Kwai Tsing Interchange Upramp to Kwai Chung Road
|
Monthly EM&A Report(Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5842020_content.html
|
|
|
|
|
|
|
- Central & Western District
|
|
|
|
|
|
|
EP-122/2002/E
|
Central Reclamation Phase III
|
Quarterly EM&A Report (Aug 2021 to Oct 2021)
(HY/2019/18)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4832015_content.html
|
|
|
|
|
|
|
EP-364/2009
|
Central-Wanchai
Bypass (CWB) including its road tunnel and slip roads
|
Quarterly EM&A Report (May 2021 to Jul
2021)
|
https://www.epd.gov.hk/eia/english/register/aep/ep3642009_content.html
|
|
|
|
|
|
|
EP-376/2009
|
DP2-Road P2 and other roads which are classified as
primary/district distributor roads
|
Monthly EM&A Report (Oct
2021)(HY/2019/18)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3762009_content.html
|
|
|
|
|
|
|
EP-376/2009
|
DP2-Road P2 and other roads which are classified as
primary/district distributor roads
|
Quarterly EM&A Report (May 2021 to Jul
2021)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3762009_content.html
|
|
|
|
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report (Oct 2021)(DE/2018/17)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
|
|
|
|
EP-364/2009/H
|
Central-Wanchai Bypass (CWB) including its road tunnel and slip
roads
|
Monthly EM&A Report
(Oct 2021)(HY/2019/18)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5722020_content.html
|
|
|
|
|
|
|
EP-364/2009/H
|
Central-Wanchai Bypass (CWB) including its road tunnel and slip
roads
|
Quarterly EM&A
Report (Jun 2021 to Aug 2021)(HK/2019/18)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5722020_content.html
|
|
|
|
|
|
|
FEP-06/364/2009/A
|
Central - Wan Chai Bypass - Central Interchange (Contract No.
HY/2009/15)
|
Quarterly EM&A
Report (Jun 2021 to Aug 2021)(HK/2019/18)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1182010_content.html
|
|
|
|
|
|
|
FEP-07/364/2009/H
|
Central-Wanchai Bypass (CWB) including its road tunnel and slip
roads
|
Quarterly EM&A
Report (Jun 2021 to Aug 2021)(HK/2019/18)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5742020_content.html
|
|
|
|
|
|
|
FEP-10/364/2009/B
|
Wan Chai
Development Phase II - Central - Wan Chai Bypass
at Wan Chai West (Contract No. HY/2010/08) -
Tunnel Work
|
Quarterly EM&A
Report (Jun 2021 to Aug 2021)(HK/2019/18)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1482013_content.html
|
|
|
|
|
|
|
FEP-11/364/2009/E
|
Central-Wanchai Bypass (CWB) including its road tunnel and slip
roads
|
Quarterly EM&A
Report (Jun 2021 to Aug 2021)(HK/2019/18)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5132016_content.html
|
|
|
|
|
|
|
FEP-01/364/2009
|
Wan Chai
Development Phase II - Central - Wan Chai Bypass
at Wan Chai East(CWB Tunnel)
|
Quarterly EM&A
Report (Jun 2021 to Aug 2021)(HK/2019/18)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1062010_content.html
|
|
|
|
|
|
|
FEP-07/364/2009/H
|
Central-Wanchai Bypass
(CWB) including its road tunnel and slip roads
|
Monthly EM&A Report
(Oct 2021)(HY/2019/18)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5742020_content.html
|
|
|
|
|
|
|
FEP-01/436/2012/F
|
Shatin to Central Link - Hung Hom
to Admiralty Section
|
Monthly EM&A Report
(Oct 2021)(HY/2014/07)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1972020_content.html
|
|
|
|
|
|
|
EP-356/2009
|
Wan Chai
Development Phase II and Central-Wan Chai Bypass
|
Monthly EM&A Report
(Oct 2021)(HY/2019/18)
|
https://www.epd.gov.hk/eia/english/register/aep/ep3562009_content.html
|
|
|
|
|
|
|
EP-356/2009
|
Wan Chai
Development Phase II and Central-Wan Chai Bypass
|
Quarterly EM&A
Report (Jun 2021 to Aug 2021)(HY/2019/18)
|
https://www.epd.gov.hk/eia/english/register/aep/ep3562009_content.html
|
|
|
|
|
|
|
FEP-13/364/2009/H
|
Central-Wanchai Bypass (CWB) including its road tunnel and slip
roads
|
Monthly EM&A Report
(Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1992020_content.html
|
|
|
|
|
|
|
FEP-13/364/2009/H
|
Central-Wanchai Bypass (CWB) including its road tunnel and slip
roads
|
Quarterly EM&A
Report (May 2021 to Jul 2021)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1992020_content.html
|
|
|
|
|
|
|
- Wan Chai District
|
|
|
|
|
|
|
EP-122/2002/E
|
Central Reclamation Phase III
|
Quarterly EM&A Report (Aug 2021 to Oct 2021)
(HY/2019/18)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4832015_content.html
|
|
|
|
|
|
|
EP-364/2009
|
Central-Wanchai
Bypass (CWB) including its road tunnel and slip roads
|
Quarterly EM&A Report (May 2021 to Jul
2021)
|
https://www.epd.gov.hk/eia/english/register/aep/ep3642009_content.html
|
|
|
|
|
|
|
FEP-03/376/2009
|
DP2-Road P2 and other
roads which are classified as primary/district distributor roads
|
Monthly EM&A Report
(Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1982020_content.html
|
|
|
|
|
|
|
FEP-03/376/2009
|
DP2-Road P2 and other
roads which are classified as primary/district distributor roads
|
Quarterly EM&A
Report (May 2021 to Jul 2021)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1982020_content.html
|
|
|
|
|
|
|
EP-436/2012/F
|
Shatin to Central Link - Hung Hom
to Admiralty Section
|
Monthly EM&A Report
(Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5562018_content.html
|
|
|
|
|
|
|
EP-376/2009
|
DP2-Road P2 and other roads which are classified as
primary/district distributor roads
|
Monthly EM&A Report (Oct
2021)(HY/2019/18)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3762009_content.html
|
|
|
|
|
|
|
EP-376/2009
|
DP2-Road P2 and other roads which are classified as
primary/district distributor roads
|
Quarterly EM&A Report (May 2021 to Jul
2021)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3762009_content.html
|
|
|
|
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report (Oct 2021)(DE/2018/17)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
|
|
|
|
FEP-01/436/2012/F
|
Shatin to Central Link - Hung Hom
to Admiralty Section
|
Monthly EM&A Report
(Oct 2021)(HY/2014/07)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1972020_content.html
|
|
|
|
|
|
|
FEP-13/364/2009/H
|
Central-Wanchai Bypass (CWB) including its road tunnel and slip
roads
|
Monthly EM&A Report
(Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1992020_content.html
|
|
|
|
|
|
|
FEP-13/364/2009/H
|
Central-Wanchai Bypass (CWB) including its road tunnel and slip
roads
|
Quarterly EM&A
Report (May 2021 to Jul 2021)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1992020_content.html
|
|
|
|
|
|
|
EP-364/2009/H
|
Central-Wanchai Bypass (CWB) including its road tunnel and slip
roads
|
Monthly EM&A Report
(Oct 2021)(HY/2019/18)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5722020_content.html
|
|
|
|
|
|
|
EP-364/2009/H
|
Central-Wanchai Bypass (CWB) including its road tunnel and slip
roads
|
Quarterly EM&A
Report (Jun 2021 to Aug 2021)(HK/2019/18)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5722020_content.html
|
|
|
|
|
|
|
FEP-06/364/2009/A
|
Central - Wan Chai Bypass - Central Interchange (Contract No.
HY/2009/15)
|
Quarterly EM&A
Report (Jun 2021 to Aug 2021)(HK/2019/18)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1182010_content.html
|
|
|
|
|
|
|
FEP-07/364/2009/H
|
Central-Wanchai Bypass (CWB) including its road tunnel and slip
roads
|
Quarterly EM&A
Report (Jun 2021 to Aug 2021)(HK/2019/18)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5742020_content.html
|
|
|
|
|
|
|
FEP-10/364/2009/B
|
Wan Chai
Development Phase II - Central - Wan Chai Bypass
at Wan Chai West (Contract No. HY/2010/08) -
Tunnel Work
|
Quarterly EM&A
Report (Jun 2021 to Aug 2021)(HK/2019/18)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1482013_content.html
|
|
|
|
|
|
|
FEP-11/364/2009/E
|
Central-Wanchai Bypass (CWB) including its road tunnel and slip
roads
|
Quarterly EM&A
Report (Jun 2021 to Aug 2021)(HK/2019/18)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5132016_content.html
|
|
|
|
|
|
|
FEP-01/364/2009
|
Wan Chai
Development Phase II - Central - Wan Chai Bypass
at Wan Chai East(CWB Tunnel)
|
Quarterly EM&A
Report (Jun 2021 to Aug 2021)(HK/2019/18)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1062010_content.html
|
|
|
|
|
|
|
FEP-07/364/2009/H
|
Central-Wanchai Bypass
(CWB) including its road tunnel and slip roads
|
Monthly EM&A Report
(Oct 2021)(HY/2019/18)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5742020_content.html
|
|
|
|
|
|
|
EP-356/2009
|
Wan Chai
Development Phase II and Central-Wan Chai Bypass
|
Monthly EM&A Report
(Oct 2021)(HY/2019/18)
|
https://www.epd.gov.hk/eia/english/register/aep/ep3562009_content.html
|
|
|
|
|
|
|
EP-356/2009
|
Wan Chai
Development Phase II and Central-Wan Chai Bypass
|
Quarterly EM&A
Report (Jun 2021 to Aug 2021)(HY/2019/18)
|
https://www.epd.gov.hk/eia/english/register/aep/ep3562009_content.html
|
|
|
|
|
|
|
- Eastern District
|
|
|
|
|
|
|
EP-122/2002/E
|
Central Reclamation Phase III
|
Quarterly EM&A Report (Aug 2021 to Oct 2021)
(HY/2019/18)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4832015_content.html
|
|
|
|
|
|
|
EP-364/2009
|
Central-Wanchai
Bypass (CWB) including its road tunnel and slip roads
|
Quarterly EM&A Report (May 2021 to Jul
2021)
|
https://www.epd.gov.hk/eia/english/register/aep/ep3642009_content.html
|
|
|
|
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report (Oct 2021)(DE/2018/17)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
|
|
|
|
EP-376/2009
|
DP2-Road P2 and other roads which are classified as
primary/district distributor roads
|
Monthly EM&A Report (Oct
2021)(HY/2019/18)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3762009_content.html
|
|
|
|
|
|
|
EP-376/2009
|
DP2-Road P2 and other roads which are classified as
primary/district distributor roads
|
Quarterly EM&A Report (May 2021 to Jul
2021)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3762009_content.html
|
|
|
|
|
|
|
EP-458/2013/C
|
Tseung Kwan O – Lam Tin Tunnel and Associated Works
|
Monthly EM&A Report (Oct 2021)(Version 1.0)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5272016_content.html
|
|
|
|
|
|
|
EP-458/2013/C
|
Tseung Kwan O - Lam Tin Tunnel and Associated Works ED/2018/04
- Cha Kwo Ling
|
Quarterly Environmental Monitoring And Audit Report (Feb 2021 to Apr
2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5272016ED201804_content.html
|
|
|
|
|
|
|
EP-458/2013/C
|
Tseung Kwan O - Lam Tin Tunnel and Associated Works ED/2018/04
- Cha Kwo Ling
|
Monthly EM&A Report (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5272016ED201804_content.html
|
|
|
|
|
|
|
EP-459/2013
|
Cross Bay Link, Tseung Kwan O
|
Monthly EM&A Report
(Oct 2021)(Version 2)
|
https://www.epd.gov.hk/eia/english/register/aep/ep4592013_content.html
|
|
|
|
|
|
|
FEP-01/436/2012/F
|
Shatin to Central Link - Hung Hom
to Admiralty Section
|
Monthly EM&A Report
(Oct 2021)(HY/2014/07)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1972020_content.html
|
|
|
|
|
|
|
EP-356/2009
|
Wan Chai
Development Phase II and Central-Wan Chai Bypass
|
Monthly EM&A Report
(Oct 2021)(HY/2019/18)
|
https://www.epd.gov.hk/eia/english/register/aep/ep3562009_content.html
|
|
|
|
|
|
|
EP-356/2009
|
Wan Chai
Development Phase II and Central-Wan Chai Bypass
|
Quarterly EM&A
Report (Jun 2021 to Aug 2021)(HY/2019/18)
|
https://www.epd.gov.hk/eia/english/register/aep/ep3562009_content.html
|
|
|
|
|
|
|
FEP-13/364/2009/H
|
Central-Wanchai Bypass (CWB) including its road tunnel and slip
roads
|
Monthly EM&A Report
(Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1992020_content.html
|
|
|
|
|
|
|
FEP-13/364/2009/H
|
Central-Wanchai Bypass (CWB) including its road tunnel and slip
roads
|
Quarterly EM&A
Report (May 2021 to Jul 2021)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1992020_content.html
|
|
|
|
|
|
|
EP-308/2008/B
|
South-East New
Territories Landfill Extension
|
Monthly EM&A Report
No.34(Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/aep/ep3082008_content.html
|
|
|
|
|
|
|
EP-308/2008/B
|
South-East New
Territories Landfill Extension
|
Quarterly EM&A
Report (Jul 2021 to Sep 2021)
|
https://www.epd.gov.hk/eia/english/register/aep/ep3082008_content.html
|
|
|
|
|
|
|
EP-364/2009/H
|
Central-Wanchai Bypass (CWB) including its road tunnel and slip
roads
|
Monthly EM&A Report
(Oct 2021)(HY/2019/18)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5722020_content.html
|
|
|
|
|
|
|
EP-364/2009/H
|
Central-Wanchai Bypass (CWB) including its road tunnel and slip
roads
|
Quarterly EM&A
Report (Jun 2021 to Aug 2021)(HK/2019/18)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5722020_content.html
|
|
|
|
|
|
|
FEP-06/364/2009/A
|
Central - Wan Chai Bypass - Central Interchange (Contract No.
HY/2009/15)
|
Quarterly EM&A
Report (Jun 2021 to Aug 2021)(HK/2019/18)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1182010_content.html
|
|
|
|
|
|
|
FEP-07/364/2009/H
|
Central-Wanchai Bypass (CWB) including its road tunnel and slip
roads
|
Quarterly EM&A
Report (Jun 2021 to Aug 2021)(HK/2019/18)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5742020_content.html
|
|
|
|
|
|
|
FEP-10/364/2009/B
|
Wan Chai
Development Phase II - Central - Wan Chai Bypass
at Wan Chai West (Contract No. HY/2010/08) -
Tunnel Work
|
Quarterly EM&A
Report (Jun 2021 to Aug 2021)(HK/2019/18)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1482013_content.html
|
|
|
|
|
|
|
FEP-11/364/2009/E
|
Central-Wanchai Bypass (CWB) including its road tunnel and slip
roads
|
Quarterly EM&A
Report (Jun 2021 to Aug 2021)(HK/2019/18)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5132016_content.html
|
|
|
|
|
|
|
FEP-01/364/2009
|
Wan Chai
Development Phase II - Central - Wan Chai Bypass
at Wan Chai East(CWB Tunnel)
|
Quarterly EM&A
Report (Jun 2021 to Aug 2021)(HK/2019/18)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1062010_content.html
|
|
|
|
|
|
|
FEP-07/364/2009/H
|
Central-Wanchai Bypass
(CWB) including its road tunnel and slip roads
|
Monthly EM&A Report
(Oct 2021)(HY/2019/18)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5742020_content.html
|
|
|
|
|
|
|
- Southern District
|
|
|
|
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report (Oct 2021)(DE/2018/17)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
|
|
|
|
EP-537/2017
|
Proposed
Extension of Academic Block, The Swire Institute of Marine Science, Faculty
of Science, The University of Hong Kong, Cape D’Aguilar
Road, Shek O
|
Monthly
EM&A Report No.49
|
http://www.epd.gov.hk/eia/english/register/aep/ep5372017_content.html
|
|
|
|
|
|
|
FEP-01/436/2012/F
|
Shatin to Central Link - Hung Hom
to Admiralty Section
|
Monthly EM&A Report
(Oct 2021)(HY/2014/07)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1972020_content.html
|
|
|
|
|
|
|
FEP-11/364/2009/E
|
Central-Wanchai Bypass (CWB) including its road tunnel and slip
roads
|
Quarterly EM&A
Report (Jun 2021 to Aug 2021)(HK/2019/18)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5132016_content.html
|
|
|
|
|
|
|
EP-458/2013/C
|
Tseung Kwan O – Lam Tin Tunnel and Associated Works
|
Monthly EM&A Report (Oct 2021)(Version 1.0)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5272016_content.html
|
|
|
|
|
|
|
EP-458/2013/C
|
Tseung Kwan O - Lam Tin Tunnel and Associated Works ED/2018/04
- Cha Kwo Ling
|
Quarterly Environmental Monitoring And Audit Report (Feb 2021 to Apr
2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5272016ED201804_content.html
|
|
|
|
|
|
|
EP-458/2013/C
|
Tseung Kwan O - Lam Tin Tunnel and Associated Works ED/2018/04
- Cha Kwo Ling
|
Monthly EM&A Report (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5272016ED201804_content.html
|
|
|
|
|
|
|
- Kowloon City District
|
|
|
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak
Development
|
Monthly EM&A Report (Oct 2021) (ED/2018/01)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Monthly EM&A Report (Oct 2021) (ED/2018/05)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak
Development
|
Final EM&A Review Report (Feb 2016 to Mar
2021)(KL/2014/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak
Development
|
Monthly EM&A Report (Oct 2021)(KL/2016/05)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak
Development
|
Quarterly EM&A Report (Dec 2020 to Mar
2021)(KL/2014/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak
Development
|
Quarterly EM&A Report (Apr 2021 to Jun
2021)(KL/2014/01)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak
Development
|
Monthly EM&A Report (Aug
2021)(KL/2014/01)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak
Development
|
Monthly EM&A Report (Sep
2021)(KL/2014/01)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
|
|
|
EP-339/2009/A
|
Decommissioning of the Remaining Parts
(EX_GFS Building, Radar Station and Hong Kong Aviation Club) of the Former
Kai Tak Airport
|
Final EM&A Review Report (Feb 2016 to Mar
2021)(KL/2014/03)
|
https://www.epd.gov.hk/eia/english/register/index8/vep2882009_content.html
|
|
|
|
|
|
|
EP-339/2009/A
|
Decommissioning of the Remaining Parts
(EX_GFS Building, Radar Station and Hong Kong Aviation Club) of the Former
Kai Tak Airport
|
Quarterly EM&A Report (Dec 2020 to Mar
2021)(KL/2014/03)
|
https://www.epd.gov.hk/eia/english/register/index8/vep2882009_content.html
|
|
|
|
|
|
|
EP-544/2017
|
Kai Tak Sports Park
|
EM&A Report (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/aep/ep5442017_content.html
|
|
|
|
|
|
|
EP-451/2013
|
Trunk Road T2
|
Final EM&A Review Report (Feb 2016 to
Mar 2021)(KL/2014/03)
|
https://www.epd.gov.hk/eia/english/register/aep/ep4512013_content.html
|
|
|
|
|
|
|
EP-451/2013
|
Trunk Road T2
|
Monthly EM&A Report (Oct
2021)(ED/2018/04)
|
https://www.epd.gov.hk/eia/english/register/aep/ep4512013_content.html
|
|
|
|
|
|
|
EP-451/2013
|
Trunk Road T2
|
Quarterly EM&A Report (Dec 2020 to Mar
2021)(KL/2014/03)
|
https://www.epd.gov.hk/eia/english/register/aep/ep4512013_content.html
|
|
|
|
|
|
|
EP-445/2013/A
|
Kai Tak Development – Roads D3A
& D4A
|
Monthly EM&A Report (Oct 2021)
(ED/2018/01)
|
https://www.epd.gov.hk/eia/english/register/index8/vep4492014_content.html
|
|
|
|
|
|
|
EP-445/2013/A
|
Kai Tak Development – Roads D3A
& D4A
|
Monthly EM&A Report (Oct 2021) (ED/2018/05)
|
https://www.epd.gov.hk/eia/english/register/index8/vep4492014_content.html
|
|
|
|
|
|
|
EP-445/2013/A
|
Kai Tak Development – Roads D3A
& D4A
|
Quarterly EM&A Report (Apr 2021 to Jun
2021)(KL/2014/01)
|
https://www.epd.gov.hk/eia/english/register/index8/vep4492014_content.html
|
|
|
|
|
|
|
EP-445/2013/A
|
Kai Tak Development – Roads D3A
& D4A
|
Monthly EM&A Report (Aug 2021)(KL/2014/01)
|
https://www.epd.gov.hk/eia/english/register/index8/vep4492014_content.html
|
|
|
|
|
|
|
EP-445/2013/A
|
Kai Tak Development – Roads D3A
& D4A
|
Monthly EM&A Report (Sep 2021)(KL/2014/01)
|
https://www.epd.gov.hk/eia/english/register/index8/vep4492014_content.html
|
|
|
|
|
|
|
EP-563/2018
|
The Development of AFCD Animal Management and
Animal Welfare Building Complex in Kai Tak
Development
|
Monthly Audit Report No. 13
|
https://www.epd.gov.hk/eia/english/register/aep/ep5632018_content.html
|
|
|
|
|
|
|
FEP-02/457/2013/C
|
Central Kowloon Route - Yau
Ma Tei East (HY/2014/08)
|
Monthly EM&A Report (Oct
2021)(HY/2014/08)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1832018hy201408.html
|
|
|
|
|
|
|
FEP-01/457/2013/C
|
Central Kowloon Route - Kai Tak West (HY/2014/07)
|
Monthly EM&A Report (Oct
2021)(HY/2014/07)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1822018hy201407.html
|
|
|
|
|
|
|
EP-457/2013/D
|
Central Kowloon Route
|
Monthly EM&A Report (Oct
2021)(HY/2018/08)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5942021hy201808.html
|
|
|
|
|
|
|
EP-457/2013/D
|
Central Kowloon Route
|
Monthly EM&A Report (Oct 2021)(HY/2014/20)
(HY/2019/13)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5942021hy201420.html
|
|
|
|
|
|
|
EP-457/2013/D
|
Central Kowloon Route
|
Monthly EM&A Report (Oct
2021)(HY/2018/02)(HY/2019/13)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5942021hy201802.html
|
|
|
|
|
|
|
EP-457/2013/D
|
Central Kowloon Route
|
Monthly EM&A Report
(Oct 2021)(HY/2014/08)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5942021hy201408.html
|
|
|
|
|
|
|
- Kwun Tong
District
|
|
|
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak
Development
|
Monthly EM&A Report (Oct 2021) (ED/2018/01)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
|
|
|
EP-337/2009
|
New
Distributor Roads Serving the Planned Kai Tak
Development
|
Monthly
EM&A Report (Oct 2021)
(ED/2018/05)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak
Development
|
Final EM&A Review Report (Feb 2016 to Mar
2021)(KL/2014/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak
Development
|
Monthly EM&A Report (Oct 2021)(KL/2016/05)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak
Development
|
Quarterly EM&A Report (Dec 2020 to Mar
2021)(KL/2014/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak
Development
|
Quarterly EM&A Report (Apr 2021 to Jun
2021)(KL/2014/01)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak
Development
|
Monthly EM&A Report (Aug
2021)(KL/2014/01)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak
Development
|
Monthly EM&A Report (Sep
2021)(KL/2014/01)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
|
|
|
EP-339/2009/A
|
Decommissioning of the Remaining Parts
(EX_GFS Building, Radar Station and Hong Kong Aviation Club) of the Former
Kai Tak Airport
|
Final EM&A Review Report (Feb 2016 to Mar
2021)(KL/2014/03)
|
https://www.epd.gov.hk/eia/english/register/index8/vep2882009_content.html
|
|
|
|
|
|
|
EP-339/2009/A
|
Decommissioning of the Remaining Parts
(EX_GFS Building, Radar Station and Hong Kong Aviation Club) of the Former
Kai Tak Airport
|
Quarterly EM&A Report (Dec 2020 to Mar
2021)(KL/2014/03)
|
https://www.epd.gov.hk/eia/english/register/index8/vep2882009_content.html
|
|
|
|
|
|
|
EP-513/2016
|
Development of Anderson Road Quarry site -
Road Improvement Works
|
Monthly EM&A Report (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/aep/ep5132016_content.html
|
|
|
|
|
|
|
EP-544/2017
|
Kai Tak Sports Park
|
EM&A Report (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/aep/ep5442017_content.html
|
|
|
|
|
|
|
EP-564/2018
|
Lei Yue Mun Waterfront Enhancement Project
|
Monthly EM&A Report (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/aep/ep5642018_content.html
|
|
|
|
|
|
|
FEP-02/457/2013/C
|
Central Kowloon Route - Yau Ma Tei East (HY/2014/08)
|
Monthly EM&A Report
(Oct 2021)(HY/2014/08)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1832018hy201408.html
|
|
|
|
|
|
|
FEP-01/457/2013/C
|
Central Kowloon Route -
Kai Tak West (HY/2014/07)
|
Monthly EM&A Report
(Oct 2021)(HY/2014/07)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1822018hy201407.html
|
|
|
|
|
|
|
EP-457/2013/D
|
Central Kowloon Route
|
Monthly EM&A Report
(Oct 2021)(HY/2018/08)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5942021hy201808.html
|
|
|
|
|
|
|
EP-457/2013/D
|
Central Kowloon Route
|
Monthly EM&A Report
(Oct 2021)(HY/2014/20) (HY/2019/13)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5942021hy201420.html
|
|
|
|
|
|
|
EP-457/2013/D
|
Central Kowloon Route
|
Monthly EM&A Report
(Oct 2021)(HY/2018/02)(HY/2019/13)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5942021hy201802.html
|
|
|
|
|
|
|
EP-457/2013/D
|
Central Kowloon Route
|
Monthly EM&A Report
(Oct 2021)(HY/2014/08)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5942021hy201408.html
|
|
|
|
|
|
|
EP-458/2013/C
|
Tseung Kwan O - Lam Tin Tunnel and Associated Works ED/2018/04
- Cha Kwo Ling
|
Monthly EM&A Report (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5272016ED201804_content.html
|
|
|
|
|
|
|
EP-458/2013/C
|
Tseung Kwan O – Lam Tin Tunnel and Associated Works
|
Monthly EM&A Report (Oct 2021)(Version 1.0)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5272016_content.html
|
|
|
|
|
|
|
EP-458/2013/C
|
Tseung Kwan O - Lam Tin Tunnel and Associated Works ED/2018/04
- Cha Kwo Ling
|
Quarterly Environmental Monitoring And Audit Report (Feb 2021 to Apr
2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5272016ED201804_content.html
|
|
|
|
|
|
|
- Sham Shui Po
District
|
|
|
|
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report (Oct
2021)(DE/2018/17)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
|
|
|
|
- Wong Tai Sin District
|
|
|
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak
Development
|
Monthly EM&A Report (Oct 2021) (ED/2018/01)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
|
|
|
EP-337/2009
|
New
Distributor Roads Serving the Planned Kai Tak
Development
|
Monthly
EM&A Report (Oct 2021)
(ED/2018/05)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak
Development
|
Final EM&A Review Report (Feb 2016 to Mar
2021)(KL/2014/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak
Development
|
Monthly EM&A Report (Oct 2021)(KL/2016/05)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak
Development
|
Quarterly EM&A Report (Dec 2020 to Mar
2021)(KL/2014/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak
Development
|
Quarterly EM&A Report (Apr 2021 to Jun
2021)(KL/2014/01)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak
Development
|
Monthly EM&A Report (Aug
2021)(KL/2014/01)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak
Development
|
Monthly EM&A Report (Sep
2021)(KL/2014/01)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
|
|
|
EP-339/2009/A
|
Decommissioning of the Remaining Parts
(EX_GFS Building, Radar Station and Hong Kong Aviation Club) of the Former
Kai Tak Airport
|
Final EM&A Review Report (Feb 2016 to Mar
2021)(KL/2014/03)
|
https://www.epd.gov.hk/eia/english/register/index8/vep2882009_content.html
|
|
|
|
|
|
|
EP-339/2009/A
|
Decommissioning of the Remaining Parts
(EX_GFS Building, Radar Station and Hong Kong Aviation Club) of the Former
Kai Tak Airport
|
Quarterly EM&A Report (Dec 2020 to Mar
2021)(KL/2014/03)
|
https://www.epd.gov.hk/eia/english/register/index8/vep2882009_content.html
|
|
|
|
|
|
|
EP-544/2017
|
Kai Tak Sports Park
|
EM&A Report (Oct
2021)
|
https://www.epd.gov.hk/eia/english/register/aep/ep5442017_content.html
|
|
|
|
|
|
|
- Yau
Tsim Mong District
|
|
|
|
|
|
|
EP-453/2013/B
|
Underpass Road and Austin Road Flyover Serving the West
Kowloon Cultural District
|
Monthly EM&A Report (Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5032016_content.html
|
|
|
|
|
|
|
EP-453/2013/B
|
Underpass Road and Austin Road Flyover Serving the West
Kowloon Cultural District
|
Quarterly EM&A Report (Aug 2021 to Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5032016_content.html
|
|
|
|
|
|
|
EP-523/2016
|
Proposed Sewage Pumping Station and Dry
Weather Flow Interceptor at Cherry Street Box Culvert
|
Submission of Monthly EM&A Report No.46
|
https://www.epd.gov.hk/eia/english/register/aep/ep5232016_content.html
|
|
|
|
|
|
|
EP-436/2012/F
|
Shatin to Central Link - Hung Hom
to Admiralty Section
|
Monthly EM&A Report
(Oct 2021)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5562018_content.html
|
|
|
|
|
|
|
FEP-02/457/2013/C
|
Central Kowloon Route - Yau Ma Tei East (HY/2014/08)
|
Monthly EM&A Report
(Oct 2021)(HY/2014/08)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1832018hy201408.html
|
|
|
|
|
|
|
FEP-01/457/2013/C
|
Central Kowloon Route -
Kai Tak West (HY/2014/07)
|
Monthly EM&A Report
(Oct 2021)(HY/2014/07)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1822018hy201407.html
|
|
|
|
|
|
|
FEP-01/436/2012/F
|
Shatin to Central Link - Hung Hom
to Admiralty Section
|
Monthly EM&A Report
(Oct 2021)(HY/2014/07)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1972020_content.html
|
|
|
|
|
|
|
EP-457/2013/D
|
Central Kowloon Route
|
Monthly EM&A Report
(Oct 2021)(HY/2018/08)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5942021hy201808.html
|
|
|
|
|
|
|
EP-457/2013/D
|
Central Kowloon Route
|
Monthly EM&A Report
(Oct 2021)(HY/2014/20) (HY/2019/13)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5942021hy201420.html
|
|
|
|
|
|
|
EP-457/2013/D
|
Central Kowloon Route
|
Monthly EM&A Report
(Oct 2021)(HY/2018/02)(HY/2019/13)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5942021hy201802.html
|
|
|
|
|
|
|
EP-457/2013/D
|
Central Kowloon Route
|
Monthly EM&A Report
(Oct 2021)(HY/2014/08)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5942021hy201408.html
|
|
|
|
|
|
|
|
|
|
|
|
|
|