Monthly Update of
Documents Uploaded
Documents Uploaded to the EIAO Website
|
(for the period between 16 Jan 2017 to 15 Feb 2017)
|
|
|
Application
No. / Permit No.
|
Project
Title
|
Document
Name
|
Hyperlink
|
|
|
Application
for EIA Study Brief
|
|
|
Nil
|
|
|
Application
for Permission to Apply Directly for Environmental Permit
|
|
|
Nil
|
|
|
Application
for Approval of EIA Report
|
|
|
EIA-249/2016
|
A
Rooftop Helipad at the Proposed New Block of Queen Mary Hospital
|
EIA Report
|
http://www.epd.gov.hk/eia/register/report/eiareport/eia_2492016/Main%20Page.html
|
|
|
EIA-244/2016
|
Port
Shelter Sewerage, Stage3 - Sewerage Works at Po Toi O
|
Approval Conditions
|
http://www.epd.gov.hk/eia/register/report/conditions/aeiar2442016.pdf
|
|
|
EIA-245/2016
|
Expansion
of Sha Tau Kok Sewage Treatment Works
|
Approval Conditions
|
http://www.epd.gov.hk/eia/register/report/conditions/aeiar2452016.pdf
|
|
|
Application
for Environmental Permit
|
|
|
AEP-515/2016
|
Proposed
Low-rise and Low-density Residential Development at Various Lots and their
Adjoining Government Land in D.D. 104, East of
Kam Pok Road, Mai Po, Yuen
Long. New Territories
|
Environmental Permit issued (EP-515/2017)
|
http://www.epd.gov.hk/eia/register/permit/latest/ep5152016.htm
|
|
|
AEP-516/2016
|
Port Shelter
Sewerage, Stage3 - Sewerage Works at Po Toi O
|
Environmental Permit issued (EP-516/2016)
|
http://www.epd.gov.hk/eia/register/permit/latest/ep5162016.htm
|
|
|
AEP-517/2016
|
Expansion
of Sha Tau Kok Sewage Treatment Works
|
Environmental Permit issued (EP-517/2017)
|
http://www.epd.gov.hk/eia/register/permit/latest/ep5172016.htm
|
|
|
AEP-525/2017
|
Elevated
Pedestrian Corridor in Yuen Long Town Connecting with Long Ping Station
|
Environmental Permit issued (EP-525/2017)
|
http://www.epd.gov.hk/eia/register/permit/latest/ep5252017.htm
|
|
|
AEP-526/2017
|
Construction
of Four New Sewage Pumping Stations in Hung Shui Kiu
New Development Area
|
Environmental Permit issued (EP-526/2017)
|
http://www.epd.gov.hk/eia/register/permit/latest/ep5262017.htm
|
|
|
Application
for Variation of an Environmental Permit
|
|
|
VEP-516/2016
|
NENT - Reprovision of temporary Wholesale Market in Fanling North New Development Area
|
Environmental Permit issued (EP-475/2013/A)
|
http://www.epd.gov.hk/eia/register/permit/latest/vep5162016.htm
|
|
|
VEP-517/2016
|
Central Kowloon Route
|
Environmental Permit issued (EP-457/2013/C )
|
http://www.epd.gov.hk/eia/register/permit/latest/vep5172016.htm
|
|
|
VEP-518/2016
|
Deep Bay Link and Widening of Yuen Long Highway between
Lam Tei and Shap Pat
Heung Interchange ( Lam Tei to Tan Kwai Tsuen Section )
|
Environmental Permit issued (EP-163/2003/H )
|
http://www.epd.gov.hk/eia/register/permit/latest/vep5182016.htm
|
|
|
VEP-519/2016
|
Liantang / Heung Yuen Wai Boundary Control Point and Associated
Works
|
Environmental Permit issued (EP-404/2011/D )
|
http://www.epd.gov.hk/eia/register/permit/latest/vep5192016.htm
|
|
|
VEP-520/2016
|
NENT - San Tin Highway and Fanling
Highway Kwu Tung Section Widening (Between San
Tin Interchange and Po Shek Wu Interchange)
|
Environmental Permit issued (EP-465/2013/A )
|
http://www.epd.gov.hk/eia/register/permit/latest/vep5202016.htm
|
|
|
VEP-521/2016
|
South East New Territories (SENT) Landfill Extension
|
Environmental Permit issued (EP-308/2008/B )
|
http://www.epd.gov.hk/eia/register/permit/latest/vep5212016.htm
|
|
|
VEP-522/2016
|
Widening of Tolo Highway/Fanling Highway between Island House Interchange and Fanling
|
Environmental Permit issued (EP-324/2008/E )
|
http://www.epd.gov.hk/eia/register/permit/latest/vep5222016.htm
|
|
|
VEP-523/2016
|
NENT - Kwu Tung North New Development
Area Road P1 and P2 and Associated New Kwu Tung
Interchange and Pak Shek Au Interchange
Improvement
|
Environmental Permit issued (EP-467/2013/A)
|
http://www.epd.gov.hk/eia/register/permit/latest/vep5232016.htm
|
|
|
VEP-524/2016
|
NENT - Kwu Tung North New
Development Area Road D1 to D5
|
Environmental Permit issued (EP-468/2013/A )
|
http://www.epd.gov.hk/eia/register/permit/latest/vep5242016.htm
|
|
|
VEP-525/2016
|
NENT - Fanling Bypass Western
Section
|
Environmental Permit issued (EP-472/2013/A )
|
http://www.epd.gov.hk/eia/register/permit/latest/vep5252016.htm
|
|
|
VEP-526/2016
|
NENT - Fanling Bypass Eastern
Section
|
Environmental Permit issued (EP-473/2013/A)
|
http://www.epd.gov.hk/eia/register/permit/latest/vep5262016.htm
|
|
|
VEP-527/2016
|
Tseung Kwan O – Lam Tin Tunnel and Associated Works
|
Environmental Permit issued (EP-458/2013/C)
|
http://www.epd.gov.hk/eia/register/permit/latest/vep5272016.htm
|
|
|
VEP-528/2017
|
Dredging Works for Proposed Cruise Terminal at Kai Tak
|
Environmental Permit issued (EP-328/2009/B)
|
http://www.epd.gov.hk/eia/register/permit/latest/vep5282017.htm
|
|
|
Application
for Further Environmental Permit
|
|
|
FEP-175/2016
|
Hang
Hau Tsuen Channel at Lau Fau
Shan
|
Environmental Permit issued (FEP-01/343/2009)
|
http://www.epd.gov.hk/eia/register/permit/latest/fep1752016.htm
|
|
|
Submission
as required by Environmental Permit Condition - Design / Environmental
Submissions
|
|
|
EP-353/2009/K
|
Hong Kong -
Zhuhai - Macao Bridge Hong Kong Boundary Crossing Facilities
|
Annual
Review Report(Mar 2015 to Feb 2016)(HY/2010/02)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4982016_content.html
|
|
|
EP-427/2011/A
|
Dredging, Management and
Capping of Contaminated Sediment Disposal Facility to the South of The
Brothers
|
Monthly Progress Report
(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep3492011_content.html
|
|
|
EP-354/2009/D
|
Tuen Mun - Chek Lap Kok Link
|
Annual
Review Report(Mar 2015 to Feb 2016)(HY/2010/02)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4692015_content.html
|
|
|
EP-404/2011/C
|
Liantang / Heung Yuen Wai Boundary Control Point and
Associated Works
|
Ecological
Monitoring Report for the Woodland Compensation Area (Sep to Oct 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4662015_content.html
|
|
|
EP-404/2011/C
|
Liantang / Heung Yuen Wai Boundary Control Point and
Associated Works
|
Ecological
Monitoring Report for the Woodland Compensation Area (Nov to Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4662015_content.html
|
|
|
FEP-01/334/2009/E
|
Sludge
Treatment Facilities
|
Environmental
Monitoring Results in Operation Phase - Landfill Gas Monitoring (Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4932016_content.html
|
|
|
EP-427/2011/A
|
Dredging,
Management and Capping of Contaminated Sediment Disposal Facility to the
South of The Brothers
|
Monthly
Progress Report (Jan 2017)
|
http://www.epd.gov.hk/eia/english/register/index8/vep3492011_content.html
|
|
|
FEP-07/364/2009/D
|
Central-Wanchai Bypass (CWB)
including its road tunnel and slip roads
|
Landscape Plan Rev.5(HY/2009/19)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4862015_content.html
|
|
|
Submission
as required by Environmental Permit Condition - EM&A
Reports
|
|
|
|
Island District
|
Central & Western District
|
|
|
|
|
North District
|
Wan Chai District
|
|
|
|
|
Sai Kung District
|
Eastern District
|
|
|
|
|
Sha Tin District
|
Southern District
|
|
|
|
|
Tai Po District
|
Kowloon City District
|
|
|
|
|
Tsuen Wan District
|
Kwun Tong District
|
|
|
|
|
Tuen Mun District
|
Sham Shui Po District
|
|
|
|
|
Yuen Long District
|
Wong Tai Sin District
|
|
|
|
|
Kwai Tsing District
|
Yau Tsim Mong District
|
|
|
|
- Island District
|
|
|
FEP-01/507/2016
|
Installation of One additional gas-fired generation unit
(CCGT Unit No. 1) at the Black Point Power
Station
|
Monthly EM&A Report no.1
|
http://www.epd.gov.hk/eia/english/register/index7/fep1732016_content.html
|
|
|
EP-392/2010
|
Improvement of Fresh Water Supply to Cheung
Chau
|
Monthly EM&A Report
(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3922010_content.html
|
|
|
EP-354/2009/D
|
Tuen Mun - Chek Lap Kok Link
|
Monthly Environmental Monitoring and Audit Report (Dec
2016)(HY/2010/02)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4692015_content.html
|
|
|
EP-354/2009/D
|
Tuen Mun - Chek Lap Kok Link
|
Monthly Environmental Monitoring and Audit
Report (Dec 2016)(HY/2013/12)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4692015_content.html
|
|
|
EP-354/2009/D
|
Tuen Mun - Chek Lap Kok Link
|
Monthly Environmental Monitoring and Audit
Report (Dec 2016)(HY/2012/08)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4692015_content.html
|
|
|
EP-354/2009/D
|
Tuen Mun - Chek Lap Kok Link
|
Monthly Environmental Monitoring and Audit
Report (Jan 2017)(HY/2012/07)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4692015_content.html
|
|
|
EP-353/2009/K
|
Hong Kong - Zhuhai - Macao Bridge Hong Kong Boundary
Crossing Facilities
|
Monthly Environmental Monitoring and Audit
Report (Nov 2016)(HY/2013/03)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4982016_content.html
|
|
|
EP-353/2009/K
|
Hong Kong - Zhuhai - Macao Bridge Hong Kong Boundary
Crossing Facilities
|
Monthly Environmental Monitoring and Audit
Report (Oct 2016)(HY/2013/03)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4982016_content.html
|
|
|
EP-353/2009/K
|
Hong Kong - Zhuhai - Macao Bridge Hong Kong Boundary Crossing
Facilities
|
Quarterly Environmental Monitoring and
Audit Report (Jun 2016 to Aug 2016)(HY/2011/03)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4982016_content.html
|
|
|
EP-353/2009/K
|
Hong Kong - Zhuhai - Macao Bridge Hong Kong Boundary
Crossing Facilities
|
Monthly Environmental Monitoring and Audit
Report (Dec 2016)(HY/2010/02)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4982016_content.html
|
|
|
EP-353/2009/K
|
Hong Kong - Zhuhai - Macao Bridge Hong Kong Boundary Crossing
Facilities
|
Monthly EM&A
Report(Dec 2016) (HY/2011/03)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4982016_content.html
|
|
|
EP-353/2009/K
|
Hong Kong - Zhuhai - Macao Bridge Hong Kong Boundary
Crossing Facilities
|
Monthly Environmental Monitoring and Audit
Report (Dec 2016)(HY/2014/05)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4982016_content.html
|
|
|
EP-353/2009/K
|
Hong Kong - Zhuhai - Macao Bridge Hong Kong Boundary
Crossing Facilities
|
Quarterly Environmental Monitoring and
Audit Report (Sep 2016 to Nov 2016)(HY/2014/05)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4982016_content.html
|
|
|
EP-353/2009/K
|
Hong Kong - Zhuhai - Macao Bridge Hong Kong Boundary
Crossing Facilities
|
Monthly Environmental Monitoring and Audit
Report (Dec 2016)(HY/2013/01)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4982016_content.html
|
|
|
EP-353/2009/K
|
Hong Kong - Zhuhai - Macao Bridge Hong Kong Boundary
Crossing Facilities
|
Monthly Environmental Monitoring and Audit
Report (Sep 2016)(HY/2013/03)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4982016_content.html
|
|
|
EP-353/2009/K
|
Hong Kong - Zhuhai - Macao Bridge Hong Kong Boundary Crossing
Facilities
|
Monthly Environmental Monitoring and Audit
Report (Nov 2016)(HY/2013/01)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4982016_content.html
|
|
|
EP-353/2009/K
|
Hong Kong - Zhuhai - Macao Bridge Hong Kong Boundary
Crossing Facilities
|
Monthly Environmental Monitoring and Audit
Report (Dec 2016)(HY/2013/02)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4982016_content.html
|
|
|
EP-353/2009/K
|
Hong Kong - Zhuhai - Macao Bridge Hong Kong Boundary Crossing
Facilities
|
Monthly Environmental Monitoring and Audit
Report (Dec 2016)(HY/2013/03)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4982016_content.html
|
|
|
EP-352/2009/D
|
Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road
|
Monthly EM&A Report(Dec
2016) (HY/2011/09)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4592014_content.html
|
|
|
EP-352/2009/D
|
Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road
|
Quarterly Environmental Monitoring and Audit Report (Jun
2016 to Aug 2016)(HY/2011/03)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4592014_content.html
|
|
|
EP-352/2009/D
|
Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road
|
Monthly Environmental Monitoring and Audit Report (Dec
2016)(HY/2010/02)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4592014_content.html
|
|
|
FEP-01/395/2010/C
|
Organic Waste Treatment Facilities, Phase I
|
Nineteenth Monthly EM&A
Summary
Report(Nov 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4872015_content.html
|
|
|
EP-071/2000/C
|
1,800MW Gas-Fired Power Station at LammaExtension
|
Monthly Monthly Environmental
Monitoring and Audit Report Unit L10& L11 (Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep1742005_content.html
|
|
|
EP-071/2000/C
|
1,800MW Gas-Fired Power Station at LammaExtension
|
Monthly EM&A Report
(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep1742005_content.html
|
|
|
EP-083/2000
|
Conversion of Two Existing Gas Turbines (GT5 & GT7)
into a Combined Cycle Unit
|
Monthly Environmental Monitoring And Audit Report (Dec
2016)
|
http://www.epd.gov.hk/eia/english/register/aep/ep0832000_content.html
|
|
|
EP-237/2005/B
|
Drainage Improvements in Southern Lantau
|
Monthly Environmental Monitoring & Audit Report (Sep
2016) (DP 04/2012)
|
http://www.epd.gov.hk/eia/english/register/index8/vep2832007_content.html
|
|
|
EP-237/2005/B
|
Drainage Improvements in Southern Lantau
|
Final Environmental Monitoring & Audit Report (DP
04/2012)
|
http://www.epd.gov.hk/eia/english/register/index8/vep2832007_content.html
|
|
|
EP-489/2014
|
Expansion of Hong Kong International Airport into a
Three-Runway System
|
Quarterly EM&A Report No.4
(Oct to Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/aep/ep4892014_content.html
|
|
|
EP-01/097/2001/C
|
Water Recreation Centre at Penny's Bay (part &
remaining part)
|
Monthly Environmental Monitoring and Audit Report (No.
137)
|
http://www.epd.gov.hk/eia/english/register/index8/vep1992005_content.html
|
|
|
EP-01/059/2000/C
|
The Theme Park at Penny's Bay, Lantau
|
136th Monthly EM&A Report (12
Dec 2016 to 11 Jan 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep3782012_content.html
|
|
|
- North District
|
|
|
EP-404/2011/C
|
Liantang /
Heung Yuen Wai Boundary Control Point and Associated Works
|
Monthly EM&A Report
(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4662015_content.html
|
|
|
FEP-01/474/2013
|
NENT - Shek Wu Hui Sewage Treatment Works - Further
Expansion at Fanling North New
Development Area
|
Monthly EM&A Report
(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1522014_content.html
|
|
|
EP-347/2009/A
|
Construction of a Secondary Boundary Fence and new sections
of Primary Boundary Fence and Boundary Patrol Road
|
Monthly EM&A Report
(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep3142010_content.html
|
|
|
EP-502/2015/A
|
Operation of the Existing Tai Lam Explosives Magazine at
Tai Shu Ha, Yuen Long for Liantang /
Heung Yuen Wai Boundary Control Point Project
|
Monthly EM&A Report
(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep5052016_content.html
|
|
|
EP-324/2008/D
|
Widening of ToloHighway/FanlingHighway between Island House
Interchange and Fanling
|
Monthly EM&A Report
(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4802015_content.html
|
|
|
EP-450/2013/A
|
Construction of Cycle Tracks and the associated
Supporting Facilities from Sha Po Tsuen to Shek Sheung River
|
Monthly EM&A Report (Nov
2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4782015_content.html
|
|
|
EP-436/2012/E
|
Shatin to Central Link - Hung Hom
to Admiralty Section
|
Monthly EM&A
Report (Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep5102016_content.html
|
|
|
- Sai Kung District
|
|
|
EP-399/2010/D
|
Kwun Tong
Line Extension
|
Monthly EM&A Report (Dec
2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4922016_content.html
|
|
|
EP-435/2011/A
|
Sewerage Works at Pik
Shui Sun Tsuen
|
Monthly EM&A
Report (Oct 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4482014_content.html
|
|
|
EP-435/2011/A
|
Sewerage Works at Pik
Shui Sun Tsuen
|
Monthly EM&A
Report (Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4482014_content.html
|
|
|
EP-319/2009/D
|
Development of a Biodiesel Plant at Tseung Kwan
O Industrial Estate
|
Monthly EM&A Report (Oct
2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4242014_content.html
|
|
|
EP-319/2009/D
|
Development of a Biodiesel Plant at Tseung Kwan
O Industrial Estate
|
Monthly EM&A Report (Nov
2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4242014_content.html
|
|
|
EP-134/2002/K
|
Fill Bank at TseungKwan O Area 137
|
Monthly EM&A Report (Dec 2016)(CV/2013/06)
|
http://www.epd.gov.hk/eia/english/register/index8/vep3892013_content.html
|
|
|
EP-134/2002/K
|
Fill Bank at TseungKwan O Area 137
|
Quarterly EM&A
Report (Oct 2016 to Dec 2016)(CV/2013/06)
|
http://www.epd.gov.hk/eia/english/register/index8/vep3892013_content.html
|
|
|
EP-438/2012/K
|
Shatin to
Central Link - Tai Wai to Hung Hom Section
|
Monthly EM&A Report
(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep5062016_content.html
|
|
|
EP-458/2013/B
|
Tseung Kwan O – Lam Tin Tunnel and Associated Works
|
Monthly EM&A Report (Dec
2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4892015_content.html
|
|
|
- Sha Tin District
|
|
|
EP-494/2015
|
In-situ Reprovisioning of
Sha Tin Water Treatment Works - South Works
|
Monthly EM&A Report
No.10
|
http://www.epd.gov.hk/eia/english/register/aep/ep4942014_content.html
|
|
|
EP-438/2012/K
|
Shatin to Central Link -
Tai Wai to Hung Hom Section
|
Monthly EM&A Report
(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep5062016_content.html
|
|
|
- Tai Po District
|
|
|
FEP-01/474/2013
|
NENT - Shek Wu Hui Sewage Treatment Works - Further
Expansion at Fanling North New
Development Area
|
Monthly EM&A Report
(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1522014_content.html
|
|
|
EP-324/2008/D
|
Widening of ToloHighway/FanlingHighway between Island
House Interchange and Fanling
|
Monthly EM&A Report
(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4802015_content.html
|
|
|
- Tsuen
Wan District
|
|
|
FEP-01/395/2010/C
|
Organic Waste Treatment Facilities, Phase I
|
Nineteenth Monthly EM&A
Summary
Report(Nov 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4872015_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report(DC/2009/10)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Quarterly
EM&A Report(DC/2007/23)(Sep 2016 to Nov 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2007/23)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2009/23)(Jan 2017)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2009/23)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2009/20)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report
(DC/2009/18)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report(DC/2009/10,DC/2009/17,DC/2009/18)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2009/24)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2009/17)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-489/2014
|
Expansion of Hong Kong International Airport into a Three-Runway
System
|
Quarterly EM&A Report No.4
(Oct to Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/aep/ep4892014_content.html
|
|
|
- Tuen Mun District
|
|
|
FEP-01/497/2015
|
Decommissioning of West Portion of the Middle Ash Lagoon
at Tsang Tsui, Tuen Mun
|
Monthly EM&A Report(Dec
2016)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1692016_content.html
|
|
|
EP-354/2009/D
|
Tuen Mun - Chek Lap Kok Link
|
Monthly Environmental Monitoring and Audit Report (Dec
2016)(HY/2010/02)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4692015_content.html
|
|
|
EP-354/2009/D
|
Tuen Mun - Chek Lap Kok Link
|
Monthly Environmental Monitoring and Audit Report (Dec
2016)(HY/2013/12)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4692015_content.html
|
|
|
EP-354/2009/D
|
Tuen Mun - Chek Lap Kok Link
|
Monthly Environmental Monitoring and Audit Report (Dec
2016)(HY/2012/08)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4692015_content.html
|
|
|
EP-354/2009/D
|
Tuen Mun - Chek Lap Kok Link
|
Monthly Environmental Monitoring and Audit
Report (Jan 2017)(HY/2012/07)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4692015_content.html
|
|
|
EP-489/2014
|
Expansion of Hong Kong International Airport into a
Three-Runway System
|
Quarterly EM&A Report No.4
(Oct to Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/aep/ep4892014_content.html
|
|
|
EP-068/2000/A
|
Tuen Mun Sewerage
- Eastern Coastal Sewerage Extension
|
Monthly EM&A Report (Dec
2016)(DC/2014/01)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4712015_content.html
|
|
|
EP-381/2009
|
Tuen Mun Area
54 Sewage Pumping Station
|
Monthly EM&A Report
(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3812009_content.html
|
|
|
EP-210/2005/B
|
Expansion and Extension of Fill Bank at Tuen MunArea 38
|
Monthly EM&A Report
(Dec 2016) (CV/2013/06)
|
http://www.epd.gov.hk/eia/english/register/index8/vep3952013_content.html
|
|
|
EP-210/2005/B
|
Expansion and Extension of Fill Bank at Tuen MunArea 38
|
Quarterly EM&A Report (Oct
2016 to Dec 2016) (CV/2013/06)
|
http://www.epd.gov.hk/eia/english/register/index8/vep3952013_content.html
|
|
|
EP-331/2009
|
Widening of Tsing Lun Road, TuenMun
|
Monthly EM&A Report
(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3312009_content.html
|
|
|
EP-331/2009
|
Widening of Tsing Lun Road, TuenMun
|
Quarterly EM&A
Report (Sep 2016 to Nov 2016)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3312009_content.html
|
|
|
EP-354/2009/A
|
Tuen Mun - Chek Lap Kok Link
|
Monthly EM&A Report
(Dec 2016)(HY/2012/07)
|
http://www.epd.gov.hk/eia/english/register/index8/vep3312012_content.html
|
|
|
EP-507/2016
|
Installation of One additional gas-fired generation unit
(CCGT Unit No. 1) at the Black Point Power
Station
|
Monthly EM&A Report no.1
|
http://www.epd.gov.hk/eia/english/register/aep/ep5072016_content.html
|
|
|
FEP-01/507/2016
|
Installation of One additional gas-fired generation unit
(CCGT Unit No. 1) at the Black Point Power
Station
|
Monthly EM&A Report no.1
|
http://www.epd.gov.hk/eia/english/register/index7/fep1732016_content.html
|
|
|
EP-226/2005/D
|
Development of an EcoPark in Tuen Mun Area 38
|
Quarterly EM&A Report (Oct
2016 to Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4942016_content.html
|
|
|
EP-226/2005/D
|
Development of an EcoPark in Tuen Mun Area 38
|
Annual EM&A Report (2016)
issue 1
|
http://www.epd.gov.hk/eia/english/register/index8/vep4942016_content.html
|
|
|
FEP-01/334/2009/E
|
Sludge Treatment Facilities
|
Monthly EM&A Report(Jan
2017)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4932016_content.html
|
|
|
- Yuen Long District
|
|
|
EP-450/2013
|
Construction of Cycle Tracks and the associated
Supporting Facilities from Sha Po Tsuen to Shek SheungRiver
|
Monthly EM&A Report
(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/aep/ep4502013_content.html
|
|
|
EP-411/2011
|
Improvement to Pok Oi Interchange
|
Quarterly EM&A Report (Sep 2016
to Nov 2016)
|
http://www.epd.gov.hk/eia/english/register/aep/ep4112011_content.html
|
|
|
EP-347/2009/A
|
Construction of a Secondary Boundary Fence and new
sections of Primary Boundary Fence and Boundary Patrol Road
|
Monthly EM&A Report
(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep3142010_content.html
|
|
|
EP-502/2015/A
|
Operation of the Existing Tai Lam Explosives Magazine at
Tai Shu Ha, Yuen Long for Liantang /
Heung Yuen Wai Boundary Control Point Project
|
Monthly EM&A Report
(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep5052016_content.html
|
|
|
EP-311/2008/D
|
Proposed Comprehensive Development at Wo Shang Wai, Yuen
Long
|
Monthly EM&A Report
(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep3932013_content.html
|
|
|
FEP-01/507/2016
|
Installation of One additional gas-fired generation unit
(CCGT Unit No. 1) at the Black Point Power
Station
|
Monthly EM&A Report no.1
|
http://www.epd.gov.hk/eia/english/register/index7/fep1732016_content.html
|
|
|
EP-450/2013/A
|
Construction of Cycle Tracks and the associated Supporting
Facilities from Sha Po Tsuen to Shek Sheung River
|
Monthly EM&A Report (Nov
2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4782015_content.html
|
|
|
- Kwai Tsing
District
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report(DC/2009/10)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Quarterly
EM&A Report(DC/2007/23)(Sep 2016 to Nov 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report
(DC/2007/23)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2009/23)(Jan 2017)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2009/23)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2009/20)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2009/18)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report(DC/2009/10,DC/2009/17,DC/2009/18)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report
(DC/2009/24)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2009/17)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-426/2011/A
|
Providing Sufficient Water Depth for Kwai Tsing
Container Basin and its Approach Channel
|
Monthly Environmental Monitoring & Audit Report (Dec
2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep3692012_content.html
|
|
|
- Central & Western District
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report(DC/2009/10)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Quarterly
EM&A Report(DC/2007/23)(Sep 2016 to Nov 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2007/23)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2009/23)(Jan 2017)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2009/23)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2009/20)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2009/18)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report(DC/2009/10,DC/2009/17,DC/2009/18)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report
(DC/2009/24)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2009/17)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-122/2002/E
|
Central Reclamation Phase III
|
Monthly EM&A Report
(Dec 2016) (HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4832015_content.html
|
|
|
EP-376/2009
|
DP2-Road P2 and other roads which are classified as
primary/district distributor roads
|
Monthly EM&A Report (Dec
2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3762009_content.html
|
|
|
FEP-01/376/2009
|
DP2-Road P2 and other roads which are classified as primary/district
distributor roads
|
Monthly EM&A Report (Dec
2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1612015_content.html
|
|
|
FEP-02/376/2009
|
DP2-Road P2 and other roads which are classified as
primary/district distributor roads
|
Monthly EM&A Report (Dec
2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1702016_content.html
|
|
|
EP-408/2011/C
|
Central Police Station Conservation and RevitalisationProject
|
Monthly EM&A Report(Dec
2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4992016_content.html
|
|
|
EP-356/2009
|
Wan Chai Development Phase II and Central-Wan Chai Bypass
|
Monthly EM&A Report (Dec
2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3562009_content.html
|
|
|
FEP-02/356/2009
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Hong Kong Convention and Exhibition Centre
|
Monthly
EM&A Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1032010_content.html
|
|
|
FEP-03/356/2009
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Wan Chai East
|
Monthly
EM&A Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1052010_content.html
|
|
|
FEP-04/356/2009
|
Central - Wan Chai Bypass - Tunnel (Causeway Bay Typhoon shelter
section) Contract No. HY/2009/15 - Marine Works
|
Monthly
EM&A Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1172010_content.html
|
|
|
FEP-06/356/2009
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Wan Chai West (Contract No. HK/2012/08) - Marine Work
|
Monthly
EM&A Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1452013_content.html
|
|
|
FEP-07/356/2009
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Wan Chai West (Contract No. HK/2012/08) - Marine Work
|
Monthly
EM&A Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1492013_content.html
|
|
|
FEP-08/356/2009
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Wan Chai West (Contract No. HK/2012/08) - Marine Work
|
Monthly EM&A Report (Dec
2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1722016_content.html
|
|
|
EP-364/2009/E
|
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads
|
Monthly EM&A
Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index8/vep5122016_content.html
|
|
|
FEP-01/364/2009
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Wan Chai East(CWB Tunnel)
|
Monthly EM&A
Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1062010_content.html
|
|
|
FEP- 02/364/2009
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Hong Kong Convention and Exhibition Centre - Tunnel Works
|
Monthly EM&A Report
(Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1082010_content.html
|
|
|
FEP-05/364/2009/A
|
Central - Wan Chai Bypass - Central Interchange (Contract
No. HY/2009/18)
|
Monthly EM&A
Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1162010_content.html
|
|
|
FEP-06/364/2009/A
|
Central - Wan Chai Bypass - Central Interchange (Contract
No. HY/2009/18)
|
Monthly EM&A
Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1182010_content.html
|
|
|
FEP-07/364/2009/D
|
Central - WanchaiBypass Tunnel (North Point
Section) and Island Eastern Corridor Link
|
Monthly EM&A
Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4862015_content.html
|
|
|
FEP-09/364/2009/B
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Wan Chai West (Contract No. HK/2012/08) - Tunnel Work
|
Monthly EM&A
Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1442013_content.html
|
|
|
FEP-10/364/2009/B
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Wan Chai West (Contract No. HK/2012/08) - Tunnel Work
|
Monthly EM&A
Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1482013_content.html
|
|
|
FEP-11/364/2009/E
|
Central
- Wan Chai Bypass - Tunnel Buildings, Systems and Fittings, and Works
Associated with Tunnel Commissioning (Contract No. HY/2011/08)
|
Monthly EM&A
Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index8/vep5132016_content.html
|
|
|
FEP-12/364/2009/D
|
Central-Wanchai Bypass (CWB)
including its road tunnel and slip roads
|
Monthly EM&A
Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1712016_content.html
|
|
|
EP-407/2010/F
|
South Island Line (East)
|
Monthly EM&A Report
No.66
|
http://www.epd.gov.hk/eia/english/register/index8/vep5082016_content.html
|
|
|
EP-408/2011/B
|
Central Police Station Conservation and RevitalisationProject
|
20th Quarterly EM&A Report
|
http://www.epd.gov.hk/eia/english/register/index8/vep3572012_content.html
|
|
|
EP-436/2012/E
|
Shatin to Central Link - Hung Hom
to Admiralty Section
|
Monthly EM&A
Report (Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep5102016_content.html
|
|
|
- Wan Chai District
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report(DC/2009/10)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Quarterly
EM&A Report(DC/2007/23)(Sep 2016 to Nov 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2007/23)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2009/23)(Jan 2017)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2009/23)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2009/20)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report
(DC/2009/18)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report(DC/2009/10,DC/2009/17,DC/2009/18)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2009/24)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2009/17)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-356/2009
|
Wan Chai Development Phase II and Central-Wan Chai Bypass
|
Monthly EM&A Report (Dec
2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3562009_content.html
|
|
|
FEP-02/356/2009
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Hong Kong Convention and Exhibition Centre
|
Monthly
EM&A Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1032010_content.html
|
|
|
FEP-03/356/2009
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Wan Chai East
|
Monthly
EM&A Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1052010_content.html
|
|
|
FEP-04/356/2009
|
Central - Wan Chai Bypass - Tunnel (Causeway Bay Typhoon shelter
section) Contract No. HY/2009/15 - Marine Works
|
Monthly
EM&A Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1172010_content.html
|
|
|
FEP-06/356/2009
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Wan Chai West (Contract No. HK/2012/08) - Marine Work
|
Monthly
EM&A Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1452013_content.html
|
|
|
FEP-07/356/2009
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Wan Chai West (Contract No. HK/2012/08) - Marine Work
|
Monthly
EM&A Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1492013_content.html
|
|
|
FEP-08/356/2009
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Wan Chai West (Contract No. HK/2012/08) - Marine Work
|
Monthly EM&A Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1722016_content.html
|
|
|
EP-364/2009/E
|
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads
|
Monthly EM&A
Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index8/vep5122016_content.html
|
|
|
FEP-01/364/2009
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Wan Chai East(CWB Tunnel)
|
Monthly EM&A
Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1062010_content.html
|
|
|
FEP- 02/364/2009
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Hong Kong Convention and Exhibition Centre - Tunnel Works
|
Monthly EM&A Report
(Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1082010_content.html
|
|
|
FEP-05/364/2009/A
|
Central - Wan Chai Bypass - Central Interchange (Contract
No. HY/2009/18)
|
Monthly EM&A
Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1162010_content.html
|
|
|
FEP-06/364/2009/A
|
Central - Wan Chai Bypass - Central Interchange (Contract
No. HY/2009/18)
|
Monthly EM&A
Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1182010_content.html
|
|
|
FEP-07/364/2009/D
|
Central - WanchaiBypass Tunnel (North Point
Section) and Island Eastern Corridor Link
|
Monthly EM&A
Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4862015_content.html
|
|
|
FEP-09/364/2009/B
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Wan Chai West (Contract No. HK/2012/08) - Tunnel Work
|
Monthly EM&A
Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1442013_content.html
|
|
|
FEP-10/364/2009/B
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Wan Chai West (Contract No. HK/2012/08) - Tunnel Work
|
Monthly EM&A
Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1482013_content.html
|
|
|
FEP-11/364/2009/E
|
Central
- Wan Chai Bypass - Tunnel Buildings, Systems and Fittings, and Works
Associated with Tunnel Commissioning (Contract No. HY/2011/08)
|
Monthly EM&A
Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index8/vep5132016_content.html
|
|
|
FEP-12/364/2009/D
|
Central-Wanchai Bypass (CWB)
including its road tunnel and slip roads
|
Monthly EM&A Report
(Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1712016_content.html
|
|
|
EP-444/2012/A
|
MTR Wan Chai Station Lee Tung Street Subway
|
Monthly EM&A Report
(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4412014_content.html
|
|
|
EP-376/2009
|
DP2-Road P2 and other roads which are classified as primary/district
distributor roads
|
Monthly EM&A Report (Dec
2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3762009_content.html
|
|
|
FEP-01/376/2009
|
DP2-Road P2 and other roads which are classified as
primary/district distributor roads
|
Monthly EM&A Report (Dec
2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1612015_content.html
|
|
|
FEP-02/376/2009
|
DP2-Road P2 and other roads which are classified as
primary/district distributor roads
|
Monthly EM&A Report (Dec
2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1702016_content.html
|
|
|
EP-122/2002/E
|
Central Reclamation Phase III
|
Monthly EM&A Report
(Dec 2016) (HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4832015_content.html
|
|
|
EP-407/2010/F
|
South Island Line (East)
|
Monthly EM&A Report
No.66
|
http://www.epd.gov.hk/eia/english/register/index8/vep5082016_content.html
|
|
|
EP-436/2012/E
|
Shatin to Central Link - Hung Hom
to Admiralty Section
|
Monthly EM&A
Report (Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep5102016_content.html
|
|
|
- Eastern District
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report(DC/2009/10)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Quarterly
EM&A Report(DC/2007/23)(Sep 2016 to Nov 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2007/23)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2009/23)(Jan 2017)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2009/23)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2009/20)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report
(DC/2009/18)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report(DC/2009/10,DC/2009/17,DC/2009/18)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2009/24)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2009/17)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-356/2009
|
Wan Chai Development Phase II and Central-Wan Chai Bypass
|
Monthly EM&A Report (Dec
2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3562009_content.html
|
|
|
FEP-02/356/2009
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Hong Kong Convention and Exhibition Centre
|
Monthly
EM&A Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1032010_content.html
|
|
|
FEP-03/356/2009
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Wan Chai East
|
Monthly
EM&A Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1052010_content.html
|
|
|
FEP-04/356/2009
|
Central - Wan Chai Bypass - Tunnel (Causeway Bay Typhoon
shelter section) Contract No. HY/2009/15 - Marine Works
|
Monthly
EM&A Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1172010_content.html
|
|
|
FEP-06/356/2009
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Wan Chai West (Contract No. HK/2012/08) - Marine Work
|
Monthly
EM&A Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1452013_content.html
|
|
|
FEP-07/356/2009
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Wan Chai West (Contract No. HK/2012/08) - Marine Work
|
Monthly
EM&A Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1492013_content.html
|
|
|
FEP-08/356/2009
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Wan Chai West (Contract No. HK/2012/08) - Marine Work
|
Monthly EM&A Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1722016_content.html
|
|
|
EP-364/2009/E
|
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads
|
Monthly EM&A
Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index8/vep5122016_content.html
|
|
|
FEP-01/364/2009
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Wan Chai East(CWB Tunnel)
|
Monthly EM&A
Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1062010_content.html
|
|
|
FEP- 02/364/2009
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Hong Kong Convention and Exhibition Centre - Tunnel Works
|
Monthly EM&A Report
(Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1082010_content.html
|
|
|
FEP-05/364/2009/A
|
Central - Wan Chai Bypass - Central Interchange (Contract
No. HY/2009/18)
|
Monthly EM&A
Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1162010_content.html
|
|
|
FEP-06/364/2009/A
|
Central - Wan Chai Bypass - Central Interchange (Contract
No. HY/2009/18)
|
Monthly EM&A
Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1182010_content.html
|
|
|
FEP-07/364/2009/D
|
Central - WanchaiBypass Tunnel (North Point Section)
and Island Eastern Corridor Link
|
Monthly EM&A
Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4862015_content.html
|
|
|
FEP-09/364/2009/B
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Wan Chai West (Contract No. HK/2012/08) - Tunnel Work
|
Monthly EM&A
Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1442013_content.html
|
|
|
FEP-10/364/2009/B
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Wan Chai West (Contract No. HK/2012/08) - Tunnel Work
|
Monthly EM&A
Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1482013_content.html
|
|
|
FEP-11/364/2009/E
|
Central
- Wan Chai Bypass - Tunnel Buildings, Systems and Fittings, and Works
Associated with Tunnel Commissioning (Contract No. HY/2011/08)
|
Monthly EM&A
Report (Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index8/vep5132016_content.html
|
|
|
FEP-12/364/2009/D
|
Central-Wanchai Bypass (CWB)
including its road tunnel and slip roads
|
Monthly EM&A Report
(Dec 2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1712016_content.html
|
|
|
EP-407/2010/F
|
South Island Line (East)
|
Monthly EM&A Report
No.66
|
http://www.epd.gov.hk/eia/english/register/index8/vep5082016_content.html
|
|
|
EP-376/2009
|
DP2-Road P2 and other roads which are classified as primary/district
distributor roads
|
Monthly EM&A Report (Dec
2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3762009_content.html
|
|
|
FEP-01/376/2009
|
DP2-Road P2 and other roads which are classified as
primary/district distributor roads
|
Monthly EM&A Report (Dec
2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1612015_content.html
|
|
|
FEP-02/376/2009
|
DP2-Road P2 and other roads which are classified as
primary/district distributor roads
|
Monthly EM&A Report (Dec
2016)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1702016_content.html
|
|
|
EP-458/2013/B
|
Tseung Kwan O – Lam Tin Tunnel and Associated Works
|
Monthly EM&A Report (Dec
2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4892015_content.html
|
|
|
EP-436/2012/E
|
Shatin to Central Link - Hung Hom
to Admiralty Section
|
Monthly EM&A
Report (Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep5102016_content.html
|
|
|
- Southern District
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report(DC/2009/10)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Quarterly
EM&A Report(DC/2007/23)(Sep 2016 to Nov 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2007/23)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2009/23)(Jan 2017)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2009/23)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2009/20)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2009/18)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report(DC/2009/10,DC/2009/17,DC/2009/18)(Dec
2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2009/24)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2009/17)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-487/2014
|
Tai Shue Wan
Development at Ocean Park
|
Monthly EM&A Report No.18
|
http://www.epd.gov.hk/eia/english/register/aep/ep4872014_content.html
|
|
|
EP-407/2010/F
|
South Island Line (East)
|
Monthly EM&A Report
No.66
|
http://www.epd.gov.hk/eia/english/register/index8/vep5082016_content.html
|
|
|
EP-436/2012/E
|
Shatin to Central Link - Hung Hom
to Admiralty Section
|
Monthly EM&A
Report (Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep5102016_content.html
|
|
|
- Kowloon City District
|
|
|
EP-437/2012
|
Shatin to
Central Link - Mong KokEast to Hung HomSection
|
Monthly EM&A Report
(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/aep/ep4372012_content.html
|
|
|
EP-445/2013/A
|
Kai TakDevelopment – Roads D3A
& D4A
|
Quarterly EM&A Report (Oct
2016 to Dec 2016)(KL/2014/01)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4492014_content.html
|
|
|
EP-445/2013/A
|
Kai TakDevelopment – Roads D3A
& D4A
|
Monthly EM&A Report (Dec
2016)(KL/2014/01)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4492014_content.html
|
|
|
EP-451/2013
|
Trunk Road T2
|
Monthly EM&A Report (Dec
2016)(KL/2014/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep4512013_content.html
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Monthly EM&A Report (Dec
2016)(KL/2014/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
EP-339/2009/A
|
Decommissioning of the Remaining Parts (EX_GFSBuilding, Radar Station and
Hong Kong Aviation Club) of the Former Kai Tak Airport
|
Monthly EM&A Report (Dec
2016)(KL/2014/03)
|
http://www.epd.gov.hk/eia/english/register/index8/vep2882009_content.html
|
|
|
EP-451/2013
|
Trunk Road T2
|
Quarterly EM&A
Report (Sep 2016 to Nov 2016)(KL/2014/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep4512013_content.html
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Quarterly EM&A
Report (Sep 2016 to Nov 2016)(KL/2014/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
EP-339/2009/A
|
Decommissioning of the Remaining Parts (EX_GFSBuilding, Radar Station
and Hong Kong Aviation Club) of the Former Kai Tak Airport
|
Quarterly
EM&A Report (Sep 2016 to Nov
2016)(KL/2014/03)
|
http://www.epd.gov.hk/eia/english/register/index8/vep2882009_content.html
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Quarterly EM&A Report (Oct
2016 to Dec 2016)(KL/2014/01)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Monthly EM&A Report (Dec
2016)(KL/2014/01)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Monthly EM&A
Report (Dec 2016)(KL/2015/02)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
EP-344/2009
|
New Sewage Pumping Stations Serving Kai TakDevelopment
|
Monthly EM&A
Report (Dec 2016)(KL/2012/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3442009.html
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Monthly EM&A Report
(Dec 2016)(KL/2012/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
EP-399/2010/D
|
Kwun Tong
Line Extension
|
Monthly EM&A Report (Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4922016_content.html
|
|
|
EP-438/2012/K
|
Shatin to
Central Link - Tai Wai to Hung Hom Section
|
Monthly EM&A Report
(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep5062016_content.html
|
|
|
- Kwun Tong
District
|
|
|
EP-458/2013/B
|
Tseung Kwan O – Lam Tin Tunnel and Associated Works
|
Monthly EM&A Report (Dec
2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4892015_content.html
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Monthly EM&A Report (Dec
2016)(KL/2014/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
EP-339/2009/A
|
Decommissioning of the Remaining Parts (EX_GFSBuilding, Radar Station
and Hong Kong Aviation Club) of the Former Kai Tak Airport
|
Monthly EM&A Report (Dec
2016)(KL/2014/03)
|
http://www.epd.gov.hk/eia/english/register/index8/vep2882009_content.html
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Quarterly EM&A Report (Oct
2016 to Dec 2016)(KL/2014/01)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Monthly EM&A Report (Dec
2016)(KL/2014/01)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Quarterly EM&A
Report (Sep 2016 to Nov 2016)(KL/2014/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
EP-339/2009/A
|
Decommissioning of the Remaining Parts (EX_GFSBuilding, Radar Station and
Hong Kong Aviation Club) of the Former Kai Tak Airport
|
Quarterly
EM&A Report (Sep 2016 to Nov
2016)(KL/2014/03)
|
http://www.epd.gov.hk/eia/english/register/index8/vep2882009_content.html
|
|
|
EP-344/2009
|
New Sewage Pumping Stations Serving Kai TakDevelopment
|
Monthly EM&A
Report (Dec 2016)(KL/2012/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3442009.html
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Monthly EM&A
Report (Dec 2016)(KL/2012/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Monthly EM&A Report
(Dec 2016)(KL/2015/02)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
EP-140/2002
|
Planning and Engineering Feasibility Study for Development
at Anderson Road
|
Quarterly EM&A
Report (Oct to Dec 2016)(CV/2012/07)
|
http://www.epd.gov.hk/eia/english/register/aep/ep1402002_content.html
|
|
|
EP-140/2002
|
Planning and Engineering Feasibility Study for
Development at Anderson Road
|
Monthly EM&A
Report (Dec 2016)(CV/2012/07)
|
http://www.epd.gov.hk/eia/english/register/aep/ep1402002_content.html
|
|
|
EP-140/2002
|
Planning and Engineering Feasibility Study for
Development at Anderson Road
|
Monthly EM&A
Report (Dec 2016)(CV/2007/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep1402002_content.html
|
|
|
EP-140/2002
|
Planning and Engineering Feasibility Study for Development
at Anderson Road
|
Quarterly EM&A
Report (Sep 2016 to Nov 2016)(CV/2007/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep1402002_content.html
|
|
|
- Sham Shui Po District
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report(DC/2009/10)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Quarterly
EM&A Report(DC/2007/23)(Sep 2016 to Nov 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report
(DC/2007/23)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2009/23)(Jan 2017)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2009/23)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2009/20)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report
(DC/2009/18)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report(DC/2009/10,DC/2009/17,DC/2009/18)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2009/24)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report (DC/2009/17)(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
- Wong Tai Sin District
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Monthly EM&A
Report (Dec 2016)(KL/2015/02)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Monthly EM&A Report (Dec
2016)(KL/2014/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
EP-339/2009/A
|
Decommissioning of the Remaining Parts (EX_GFSBuilding, Radar Station
and Hong Kong Aviation Club) of the Former Kai Tak Airport
|
Monthly EM&A Report (Dec
2016)(KL/2014/03)
|
http://www.epd.gov.hk/eia/english/register/index8/vep2882009_content.html
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Quarterly EM&A Report (Oct
2016 to Dec 2016)(KL/2014/01)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Monthly EM&A Report (Dec
2016)(KL/2014/01)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Quarterly EM&A
Report (Sep 2016 to Nov 2016)(KL/2014/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
EP-339/2009/A
|
Decommissioning of the Remaining Parts (EX_GFSBuilding, Radar Station and
Hong Kong Aviation Club) of the Former Kai Tak Airport
|
Quarterly
EM&A Report (Sep 2016 to Nov
2016)(KL/2014/03)
|
http://www.epd.gov.hk/eia/english/register/index8/vep2882009_content.html
|
|
|
EP-344/2009
|
New Sewage Pumping Stations Serving Kai TakDevelopment
|
Monthly EM&A
Report (Dec 2016)(KL/2012/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3442009.html
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Monthly EM&A
Report (Dec 2016)(KL/2012/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
EP-438/2012/K
|
Shatin to
Central Link - Tai Wai to Hung HomSection
|
Monthly EM&A Report
(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep5062016_content.html
|
|
|
- Yau Tsim Mong District
|
|
|
EP-440/2012
|
MTR Tsim Sha Tsui Station Carnarvon Subway and Entrances
Modification Works
|
Monthly EM&AReport (Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/aep/ep4402012_content.html
|
|
|
EP-455/2013
|
Proposed Road Improvement Works in West Kowloon
Reclamation Development Phase 1
|
Monthly EM&A Report (Dec
2016)(HY/2013/17)
|
http://www.epd.gov.hk/eia/english/register/aep/ep4552013_content.html
|
|
|
EP-453/2013/B
|
Underpass Road and Austin Road Flyover Serving
the West Kowloon Cultural District
|
Monthly EM&A
Report (Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep5032016_content.html
|
|
|
EP-436/2012/E
|
Shatin to Central Link - Hung Hom
to Admiralty Section
|
Monthly EM&A
Report (Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep5102016_content.html
|
|
|
EP-366/2009/A
|
Road Works at West Kowloon
|
Monthly EM&AReport (Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep3682012_content.html
|
|
|
EP-399/2010/D
|
Kwun Tong
Line Extension
|
Monthly EM&A Report (Dec
2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4922016_content.html
|
|
|
EP-437/2012
|
Shatin to
Central Link - Mong Kok East to Hung HomSection
|
Monthly EM&A Report
(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/aep/ep4372012_content.html
|
|
|
EP-414/2011
|
Reprovision of
Bridges D1 and T in West Kowloon
|
Monthly EM&A Report
(Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/aep/ep4142011_content.html
|
|
|
EP-438/2012/K
|
Shatin to
Central Link - Tai Wai to Hung HomSection
|
Monthly EM&AReport (Dec 2016)
|
http://www.epd.gov.hk/eia/english/register/index8/vep5062016_content.html
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|