Application for EIA Study Brief

 

 

 

ESB-250/2012

Expansion of Hong Kong International Airport into a Three-Runway System

Project Profile

http://www.epd.gov.hk/eia/register/profile/latest/esb250/esb250.pdf

 

 

 

 

 

ESB-249/2012

Planning and Engineering Study for Tuen Mun Areas 40 and 46

Project Profile

http://www.epd.gov.hk/eia/register/profile/latest/esb249/esb249.pdf

 

 

 

 

 

ESB-245/2012

Reprovisioning of FEHD Sai Yee Street Vehicle Depot at Yen Ming Road, West Kowloon Reclamation Area

EIA Study Brief

http://www.epd.gov.hk/eia/register/study/latest/esb-245.pdf

 

 

 

 

 

Application for Permission to Apply Directly for Environmental Permit

 

 

 

DIR-220/2012

Enhanced Ash Utilisation and Water Management Facilities at the Castle Peak Power Station (CPPS)

 Project Profile

http://www.epd.gov.hk/eia/register/profile/latest/dir220/dir220.pdf

 

 

 

 

Application for Approval of EIA Report

 

 

 

Nil

 

 

 

Application for Environmental Permit

 

 

 

 Nil

 

 

 

Application for Variation of an Environmental Permit

 

 

 

VEP-364/2012

Drainage Diversion Works For the Comprehensive Residential Development At Various Lots In DD227 & DD229, Tai Po Tsai, Sai Kung

Environmental Permit issued (EP-428/2011/A)

http://www.epd.gov.hk/eia/register/permit/latest/vep3642012.htm

 

 

 

VEP-363/2012

Kwun Tong Line Extension

Environmental Permit issued (EP-399/2010/B)

http://www.epd.gov.hk/eia/register/permit/latest/vep3632012.htm

 

 

 

VEP-362/2012

West Rail

Environmental Permit issued (FEP-23/004/1998/I)

http://www.epd.gov.hk/eia/register/permit/latest/vep3622012.htm

 

 

 

VEP-361/2012

West Rail

Environmental Permit issued (EP-004/1998/I)

http://www.epd.gov.hk/eia/register/permit/latest/vep3612012.htm

 

 

 

VEP-360/2012

Hong Kong Section of Guangzhou - Shenzhen - Hong Kong Express Rail Link

Environmental Permit issued (EP-349/2009/G)

http://www.epd.gov.hk/eia/register/permit/latest/vep3602012.htm

 

 

 

Application for Further Environmental Permit

 

 

 

FEP-132/2012

East Rail Extensions Tai Wai to Ma On Shan

Environmental Permit issued (FEP-05/039/2000/F)

http://www.epd.gov.hk/eia/register/permit/latest/fep1322012.htm

 

 

 

 

Submission as required by Environmental Permit Condition - Design / Environmental Submissions

 

 

 

EP-313/2008

West Island Line

Baseline Monitoring Report (Part 2)

http://www.epd.gov.hk/eia/english/register/aep/ep3132008_content.html

 

 

 

 

EP-313/2008/D

West Island Line

Baseline Monitoring Report Part1

http://www.epd.gov.hk/eia/english/register/index8/vep3332011.html

 

 

 

 

EP-408/2011

Central Police Station Conservation and Revitalisation Project

Method Statement for Vibration Monitoring for Demolition Works

http://www.epd.gov.hk/eia/english/register/aep/ep4082011_content.html

 

 

 

 

EP-408/2011

Central Police Station Conservation and Revitalisation Project

Baseline Monitoring Report

 http://www.epd.gov.hk/eia/english/register/aep/ep4082011_content.html

 

 

 

 

EP-408/2011

Central Police Station Conservation and Revitalisation Project

Baseline Condition Survey Report

 http://www.epd.gov.hk/eia/english/register/aep/ep4082011_content.html

 

 

 

 

EP-408/2011/A

Central Police Station Conservation and Revitalisation Project

Baseline Vibration Impact Monitoring Report

 http://www.epd.gov.hk/eia/english/register/index8/vep3502011_content.html

 

 

 

 

Submission as required by Environmental Permit Condition - EM&A Reports

 

 

 

 

Island District

Central & Western District

 

 

 

 

 

North District

Wan Chai District

 

 

 

 

 

Sai Kung District

Eastern District

 

 

 

 

 

Sha Tin District

Southern District

 

 

 

 

 

Tai Po District

Kowloon City District

 

 

 

 

 

Tsuen Wan District

Kwun Tong District

 

 

 

 

 

Tuen Mun District

Sham Shui Po District

 

 

 

 

 

Yuen Long District

Wong Tai Sin District

 

 

 

 

 

Kwai Tsing District

Yau Tsim Mong District

 

 

 

 

- Island District

 

 

 

EP-071/2000/C

1,800MW Gas-Fired Power Station at Lamma Extension

Monthly Environmental Monitoring and Audit Report (Feb 2012)

http://www.epd.gov.hk/eia/english/register/index8/vep1742005_content.html

 

 

 

EP-071/2000/C

1,800MW Gas-Fired Power Station at Lamma Extension

Monthly Environmental Monitoring and Audit Report (Jan 2012)

http://www.epd.gov.hk/eia/english/register/index8/vep1742005_content.html

 

 

 

EP-083/2000 

Conversion of Two Existing Gas Turbines (GT5 & GT7) into a Combined Cycle Unit

Monthly Environmental Monitoring And Audit Report (Feb 2012)

http://www.epd.gov.hk/eia/english/register/aep/ep0832000_content.html

 

 

 

EP-237/2005/B

 Drainage Improvements in Southern Lantau

Monthly Environmental Monitoring & Audit Report (Dec 2011)

http://www.epd.gov.hk/eia/english/register/index8/vep2832007_content.html

 

 

 

EP-248/2006 

 Lamma Power Station Units L4 & L5 Flue Gas Desulphurization Plant Retrofit Project

Quarterly EM&A Report (Oct 2011 to Dec 2011)

http://www.epd.gov.hk/eia/english/register/aep/ep2482006_content.html

 

 

 

EP-281/2007/A

Outlying Islands Sewerage Stage 1 Phase 2 - Sok Kwu Wan Sewage Collection, Treatment and Disposal Facilities

Monthly EM&A Report (No. 19) (Feb 2012) (DC/2009/13)

http://www.epd.gov.hk/eia/english/register/index8/vep2992009_content.html

 

 

 

EP-282/2007 

 Outlying Islands Sewerage Stage 1 Phase 1 Part 2 – Yung Shue Wan Sewerage, Sewage Treatment Works and Outfall

Monthly EM&A Report (Feb 2012)

http://www.epd.gov.hk/eia/english/register/aep/ep2822007_content.html

 

 

 

EP-287/2007

 Lamma Power Station - Unit L2 Flue Gas Desulphurization Plant Retrofit Project

Quarterly EM&A Report (Oct 2011 to Dec 2011)

http://www.epd.gov.hk/eia/english/register/aep/ep2872007_content.html

 

 

 

EP-394/2010

Development of a 100MW Offshore Wind Farm in Hong Kong

Monthly EM&A Report (Feb 2012)

http://www.epd.gov.hk/eia/english/register/aep/ep3942010_content.html

 

 

 

EP-083/2000

 Conversion of Two Existing Gas Turbines (GT5 & GT7) into a Combined Cycle Unit

Monthly Environmental Monitoring And Audit Report (Jan 2012)

http://www.epd.gov.hk/eia/english/register/aep/ep0832000_content.html

 

 

 

EP-281/2007

Outlying Islands Sewerage Stage 1 Phase 2 - Sok Kwu Wan Sewage Collection, Treatment and Disposal Facilities

Monthly EM&A Report (Jan 2012)

http://www.epd.gov.hk/eia/english/register/aep/ep2812007_content.html

 

 

 

EP-282/2007

Outlying Islands Sewerage Stage 1 Phase 1 Part 2 – Yung Shue Wan Sewerage, Sewage Treatment Works and Outfall

Monthly EM&A Report (Jan 2012)

http://www.epd.gov.hk/eia/english/register/aep/ep2822007_content.html

 

 

 

FEP- 01/097/2001/C

 Water Recreation Centre at Penny's Bay (part & remaining part)

Monthly Environmental Monitoring and Audit Report (No. 78)

http://www.epd.gov.hk/eia/english/register/index8/vep1992005_content.html

 

 

 

- North District

 

 

 

EP-324/2008/A

Widening of Tolo Highway/Fanling Highway between Island House Interchange and Fanling

Quarterly EM&A Report (Nov 2011 to Jan 2012)

http://www.epd.gov.hk/eia/english/register/index8/vep3512012_content.html

 

 

 

 

EP-324/2008/A

Widening of Tolo Highway/Fanling Highway between Island House Interchange and Fanling

Monthly EM&A Report (Feb 2012) Stage1

http://www.epd.gov.hk/eia/english/register/index8/vep3512012_content.html

 

 

 

 

EP-324/2008

Widening of Tolo Highway/Fanling Highway between Island House Interchange and Fanling

Monthly EM&A Report (Jan 2012) (Stage 1)

http://www.epd.gov.hk/eia/english/register/aep/ep3242008_content.html

 

 

 

 

EP-329/2009

  Provision of Cremators at Wo Hop Shek Crematorium

Monthly EM&A Report (Jan 2012)

http://www.epd.gov.hk/eia/english/register/aep/ep3292009_content.html

 

 

 

 

EP-347/2009/A 

Construction of a Secondary Boundary Fence and new sections of Primary Boundary Fence and Boundary Patrol Road

Monthly EM&A Report (Feb 2012 )

http://www.epd.gov.hk/eia/english/register/index8/vep3142010_content.html

 

 

 

 

EP-347/2009/A

Construction of a Secondary Boundary Fence and new sections of Primary Boundary Fence and Boundary Patrol Road

Monthly EM&A Report (Jan 2012 )

http://www.epd.gov.hk/eia/english/register/index8/vep3142010_content.html

 

 

 

 

FEP-02/347/2009/A

  Construction of a Secondary Boundary Fence and new sections of Primary Boundary Fence and Boundary Patrol Road (Section 2 Lok Ma Chau Control Point to Ng Tung River)

Monthly EM&A Report (Jan 2012)

http://www.epd.gov.hk/eia/english/register/index8/vep3162010_content.html

 

 

 

 

FEP-03/347/2009

Construction of a Secondary Boundary Fence at Sha Tau Kok

Monthly EM&A Report (Jan 2012 )

http://www.epd.gov.hk/eia/english/register/index7/fep1042010_content.html

 

 

 

 

FEP-04/347/2009/A

Construction of a Secondary Boundary Fence at Sha Tau Kok (Remaining Section)

Monthly EM&A Report (Jan 2012 )

http://www.epd.gov.hk/eia/english/register/index7/fep1122010_content.html

 

 

 

 

- Sai Kung District

 

 

 

EP-134/2002/J

Fill Bank at Tseung Kwan O Area 137

Monthly EM&A Report (Feb 2012)

http://www.epd.gov.hk/eia/english/register/index8/vep3382011_content.html

 

 

 

EP-319/2009/A

Development of a Biodiesel Plant at Tseung Kwan O Industrial Estate

Monthly Environmental Monitoring & Audit Report (Feb 2012) (Version 1.0)

http://www.epd.gov.hk/eia/english/register/index8/vep2812009.html

 

 

 

EP-319/2009/A 

Development of a Biodiesel Plant at Tseung Kwan O Industrial Estate

Monthly Environmental Monitoring & Audit Report (Jan 2012)

http://www.epd.gov.hk/eia/english/register/index8/vep2812009.html

 

 

 

EP-319/2009/A

Development of a Biodiesel Plant at Tseung Kwan O Industrial Estate

Quarterly Environmental Monitoring & Audit Summary Report (Dec 2011 to Feb 2012) (Version 1.0)

http://www.epd.gov.hk/eia/english/register/index8/vep2812009.html

 

 

 

EP-397/2010 

Renewable Energy Supply on Town Island (also known as Dawn Island)

Monthly EM&A Report (Feb 2012)

http://www.epd.gov.hk/eia/english/register/aep/ep3972010_content.html

 

 

 

EP-397/2010 

Renewable Energy Supply on Town Island (also known as Dawn Island)

Monthly EM&A Report (Nov 2011)

http://www.epd.gov.hk/eia/english/register/aep/ep3972010_content.html

 

 

 

EP-410/2010

Phase III Redevelopment of The Hong Kong Federation of Youth Groups Jockey Club Sai Kung Outdoor Training Camp

Monthly EM&A Report (Feb 2012)

http://www.epd.gov.hk/eia/english/register/aep/ep4102010_content.html

 

 

 

EP-410/2010 

Phase III Redevelopment of The Hong Kong Federation of Youth Groups Jockey Club Sai Kung Outdoor Training Camp

Quarterly EM&A Report (Jun to Sep 2011)

http://www.epd.gov.hk/eia/english/register/aep/ep4102010_content.html

 

 

 

- Sha Tin District

 

 

 

EP-303/2008

Drainage Improvement in Sha Tin and Tai Po

Monthly EM&A Report (Jan 2012)

http://www.epd.gov.hk/eia/english/register/aep/ep3032008_content.html

 

 

 

EP-303/2008

Drainage Improvement in Sha Tin and Tai Po

Monthly EM&A Report (Feb 2012)

http://www.epd.gov.hk/eia/english/register/aep/ep3032008_content.html

 

 

 

EP-332/2009

Road D1(N), Road D1(W) and Box Culvert of Whitehead & Lok Wo Sha Phase One Project

Quarterly EM&A Report (Jul to Sep 2011)

http://www.epd.gov.hk/eia/english/register/aep/ep3322009_content.html

 

 

 

EP-332/2009

Road D1(N), Road D1(W) and Box Culvert of Whitehead & Lok Wo Sha Phase One Project

Monthly EM&A Report (Jan 2012)

http://www.epd.gov.hk/eia/english/register/aep/ep3322009_content.html

 

 

 

- Tai Po District

 

 

 

EP-223/2005/A

Drainage Improvement Works in Upper Tai Po River

Monthly EM&A Report (Jan 2012)

http://www.epd.gov.hk/eia/english/register/index8/vep2732009.html

 

 

 

EP-303/2008

Drainage Improvement in Sha Tin and Tai Po

Monthly EM&A Report (Jan 2012)

http://www.epd.gov.hk/eia/english/register/aep/ep3032008_content.html

 

 

 

EP-303/2008

Drainage Improvement in Sha Tin and Tai Po

Monthly EM&A Report (Feb 2012)

http://www.epd.gov.hk/eia/english/register/aep/ep3032008_content.html

 

 

 

EP-324/2008/A

Widening of Tolo Highway/Fanling Highway between Island House Interchange and Fanling

Quarterly EM&A Report (Nov 2011 to Jan 2012)

http://www.epd.gov.hk/eia/english/register/index8/vep3512012_content.html

 

 

 

EP-324/2008/A

Widening of Tolo Highway/Fanling Highway between Island House Interchange and Fanling

Monthly EM&A Report (Feb 2012) Stage1

http://www.epd.gov.hk/eia/english/register/index8/vep3512012_content.html

 

 

 

EP-265/2007

 Tai Po Sewage Treatment Works, Stage V

Monthly Environmental and Audit Report (Jan 2012) (DC/2009/09)

http://www.epd.gov.hk/eia/english/register/aep/ep2652007_content.html

 

 

 

EP-265/2007

 Tai Po Sewage Treatment Works, Stage V

Monthly Environmental and Audit Report (Jan 2012) (DE/2009/09)

http://www.epd.gov.hk/eia/english/register/aep/ep2652007_content.html

 

 

 

EP-324/2008

Widening of Tolo Highway/Fanling Highway between Island House Interchange and Fanling

Monthly EM&A Report (Jan 2012) (Stage 1)

http://www.epd.gov.hk/eia/english/register/aep/ep3242008_content.html

 

 

 

- Tsuen Wan District

 

 

 

EP-275/2007 

Drainage Improvement in Tsuen Wan and Kwai Chung - Tsuen Wan Drainage Tunnel

Monthly EM&A Report(Feb 2012)

http://www.epd.gov.hk/eia/english/register/aep/ep2752007_content.html

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Consolidated Monthly EM&A Report (Jan 2012) (DC/2007/23) (Ver 1.1)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Quarterly EM&A Report (Aug to Oct 2011) (Ver 1.1) (DC/2009/23)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report No.27 (DC/2007/24)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E

 Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report (Feb 2012) (DC/2009/23)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E 

Harbour Area Treatment Scheme (HATS) Stage 2A

Quarterly EM&A Report (Sep to Nov 2011) (DC/2007/23)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E 

Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report (Jan 2012) (DC/2008/09)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-349/2009/E

Hong Kong Section of Guangzhou - Shenzhen - Hong Kong Express Rail Link

Monthly EM&A Report (Jan 2012)

http://www.epd.gov.hk/eia/english/register/index8/vep3522012_content.html

 

 

 

EP-349/2009/E

Hong Kong Section of Guangzhou - Shenzhen - Hong Kong Express Rail Link

Monthly EM&A Report (Feb 2012)

http://www.epd.gov.hk/eia/english/register/index8/vep3522012_content.html

 

 

 

EP-322/2008

Harbour Area Treatment Scheme (HATS) Stage 2A

EM&A Consolidated Monthly report (Jan 2012) (ver1.1)

http://www.epd.gov.hk/eia/english/register/aep/ep3222008_content.html

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report (Jan 2012) (DC/2007/23)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E

 Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report (Jan 2012) (Ver 1.1) (DC/2009/24)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Quarterly Environmental Monitoring and Audit Report No.8 Covering the Period from 1 (Oct to Dec 2011) (DC/2008/09)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report No.25 (DC/2007/24)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

FEP- 01/097/2001/C

 Water Recreation Centre at Penny's Bay (part & remaining part)

Monthly Environmental Monitoring and Audit Report (No. 78)

http://www.epd.gov.hk/eia/english/register/index8/vep1992005_content.html

 

 

 

- Tuen Mun District

 

 

 

EP-210/2005/A

Expansion and Extension of Fill Bank at Tuen Mun Area 38

Monthly Environmental Monitoring and Audit Report (CV/2009/02) (Feb 2012)

http://www.epd.gov.hk/eia/english/register/index8/vep2772008.html

 

 

 

EP-226/2005

Development of an EcoPark in Tuen Mun Area 38

Quarterly EM&A Compliance Report (Aug to Oct 2011)

http://www.epd.gov.hk/eia/english/register/aep/ep2262005_content.html

 

 

 

EP-296/2007

Proposed Joint User Complex and Wholesale Fish Market at Area 44 Tuen Mun

Final Environmental Monitoring & Audit Report for operational phase

http://www.epd.gov.hk/eia/english/register/aep/ep2962007_content.html

 

 

 

EP-321/2008

 Upgrading of Pillar Point Sewage Treatment Works

Monthly EM&A Report (Feb 2012)

http://www.epd.gov.hk/eia/english/register/aep/ep3212008_content.html

 

 

 

EP-331/2009 

Widening of Tsing Lun Road, Tuen Mun

Monthly EM&A Report (Feb 2012)

http://www.epd.gov.hk/eia/english/register/aep/ep3312009_content.html

 

 

 

EP-342/2009/B

Traffic Improvements to Tuen Mun Road Town Centre Section

Quarterly EM&A Report (Nov 2011 to Jan 2012) (Final)

http://www.epd.gov.hk/eia/english/register/index8/vep3352011_content.html

 

 

 

FEP-01/334/2009/A

Sludge Treatment Facilities

Monthly EM&A Report (Feb 2012)

http://www.epd.gov.hk/eia/english/register/index8/vep3452011_content.html

 

 

 

EP-321/2008

 Upgrading of Pillar Point Sewage Treatment Works

Monthly EM&A Report (Jan 2012)

http://www.epd.gov.hk/eia/english/register/aep/ep3212008_content.html

 

 

 

EP-331/2009

Widening of Tsing Lun Road, Tuen Mun

Monthly EM&A Report (Jan 2012)

http://www.epd.gov.hk/eia/english/register/aep/ep3312009_content.html

 

 

 

EP-342/2009/B 

Traffic Improvements to Tuen Mun Road Town Centre Section

Monthly EM&A Report (Jan 2012) (Final)

http://www.epd.gov.hk/eia/english/register/index8/vep3352011_content.html

 

 

 

- Yuen Long District

 

 

 

EP-347/2009/A 

Construction of a Secondary Boundary Fence and new sections of Primary Boundary Fence and Boundary Patrol Road

Monthly EM&A Report (Feb 2012 )

http://www.epd.gov.hk/eia/english/register/index8/vep3142010_content.html

 

 

 

EP-349/2009/E

Hong Kong Section of Guangzhou - Shenzhen - Hong Kong Express Rail Link

Monthly EM&A Report (Jan 2012)

http://www.epd.gov.hk/eia/english/register/index8/vep3522012_content.html

 

 

 

EP-349/2009/E

Hong Kong Section of Guangzhou - Shenzhen - Hong Kong Express Rail Link

Monthly EM&A Report (Feb 2012)

http://www.epd.gov.hk/eia/english/register/index8/vep3522012_content.html

 

 

 

FEP-03/347/2009

Construction of a Secondary Boundary Fence at Sha Tau Kok

Monthly EM&A Report (Feb 2012 )

http://www.epd.gov.hk/eia/english/register/index7/fep1042010_content.html

 

 

 

FEP-04/347/2009/A 

 Construction of a Secondary Boundary Fence at Sha Tau Kok (Remaining Section)

Monthly EM&A Report (Feb 2012 )

http://www.epd.gov.hk/eia/english/register/index7/fep1122010_content.html

 

 

 

EP-327/2009/A

Expansion of Ha Tsuen Sewage Pumping Station

Impact monitoring Report (No.24) (Jan 2012)

http://www.epd.gov.hk/eia/english/register/index8/vep3132011_content.html

 

 

 

EP-347/2009/A

Construction of a Secondary Boundary Fence and new sections of Primary Boundary Fence and Boundary Patrol Road

Monthly EM&A Report (Jan 2012 )

http://www.epd.gov.hk/eia/english/register/index8/vep3142010_content.html

 

 

 

FEP-02/347/2009/A

 Construction of a Secondary Boundary Fence and new sections of Primary Boundary Fence and Boundary Patrol Road (Section 2 Lok Ma Chau Control Point to Ng Tung River)

Monthly EM&A Report (Jan 2012)

http://www.epd.gov.hk/eia/english/register/index8/vep3162010_content.html

 

 

 

FEP-03/347/2009

Construction of a Secondary Boundary Fence at Sha Tau Kok

Monthly EM&A Report (Jan 2012 )

http://www.epd.gov.hk/eia/english/register/index7/fep1042010_content.html

 

 

 

FEP-04/347/2009/A

Construction of a Secondary Boundary Fence at Sha Tau Kok (Remaining Section)

Monthly EM&A Report (Jan 2012 )

http://www.epd.gov.hk/eia/english/register/index7/fep1122010_content.html

 

 

 

- Kwai Tsing District

 

 

 

EP-121/2002/A

Demolition of Kwai Chung Incineration Plant

Monthly EM&A Report (Feb 2012)

http://www.epd.gov.hk/eia/english/register/index8/vep2842009_content.html

 

 

 

EP-275/2007 

Drainage Improvement in Tsuen Wan and Kwai Chung - Tsuen Wan Drainage Tunnel

Monthly EM&A Report(Feb 2012)

http://www.epd.gov.hk/eia/english/register/aep/ep2752007_content.html

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Consolidated Monthly EM&A Report (Jan 2012) (DC/2007/23) (Ver 1.1)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Quarterly EM&A Report (Aug to Oct 2011) (Ver 1.1) (DC/2009/23)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report No.27 (DC/2007/24)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E

 Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report (Feb 2012) (DC/2009/23)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E 

Harbour Area Treatment Scheme (HATS) Stage 2A

Quarterly EM&A Report (Sep to Nov 2011) (DC/2007/23)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E 

Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report (Jan 2012) (DC/2008/09)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-349/2009/E

Hong Kong Section of Guangzhou - Shenzhen - Hong Kong Express Rail Link

Monthly EM&A Report (Jan 2012)

http://www.epd.gov.hk/eia/english/register/index8/vep3522012_content.html

 

 

 

EP-349/2009/E

Hong Kong Section of Guangzhou - Shenzhen - Hong Kong Express Rail Link

Monthly EM&A Report (Feb 2012)

http://www.epd.gov.hk/eia/english/register/index8/vep3522012_content.html

 

 

 

EP-121/2002/A

Demolition of Kwai Chung Incineration Plant

Monthly EM&A Report (Jan 2012)

http://www.epd.gov.hk/eia/english/register/index8/vep2842009_content.html

 

 

 

EP-322/2008

Harbour Area Treatment Scheme (HATS) Stage 2A

EM&A Consolidated Monthly report (Jan 2012) (ver1.1)

http://www.epd.gov.hk/eia/english/register/aep/ep3222008_content.html

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report (Jan 2012) (DC/2007/23)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E

 Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report (Jan 2012) (Ver 1.1) (DC/2009/24)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Quarterly Environmental Monitoring and Audit Report No.8 Covering the Period from 1 (Oct to Dec 2011) (DC/2008/09)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report No.25 (DC/2007/24)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

- Central & Western District

 

 

 

EP-273/2007

Laying of Western Cross Harbour Main and Associated Land Mains from West Kowloon to Sai Ying Pun

Monthly EM&A Report (Feb 2012) No.22

http://www.epd.gov.hk/eia/english/register/aep/ep2732007_content.html

 

 

 

EP-273/2007 

Laying of Western Cross Harbour Main and Associated Land Mains from West Kowloon to Sai Ying Pun

Quarterly EM&A Report No.7 (Nov 2011 to Jan 2012)

http://www.epd.gov.hk/eia/english/register/aep/ep2732007_content.html

 

 

 

EP-313/2008/C

West Island Line

Environmental Monitoring & Audit Report (Feb 2012)

http://www.epd.gov.hk/eia/english/register/index8/vep2982009.html

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Consolidated Monthly EM&A Report (Jan 2012) (DC/2007/23) (Ver 1.1)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Quarterly EM&A Report (Aug to Oct 2011) (Ver 1.1) (DC/2009/23)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report No.27 (DC/2007/24)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E

 Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report (Feb 2012) (DC/2009/23)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E 

Harbour Area Treatment Scheme (HATS) Stage 2A

Quarterly EM&A Report (Sep to Nov 2011) (DC/2007/23)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E 

Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report (Jan 2012) (DC/2008/09)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-364/2009/A

Central-Wanchai Bypass (CWB) including its road tunnel and slip roads

Monthly EM&A Report (Feb 2012)

http://www.epd.gov.hk/eia/english/register/index8/vep3212010_content.html

 

 

 

EP-408/2011/A

Central Police Station Conservation and Revitalisation Project

Monthly EM&A Report (No.3)

http://www.epd.gov.hk/eia/english/register/index8/vep3502011_content.html

 

 

 

EP-408/2011/A

Central Police Station Conservation and Revitalisation Project

First Quarterly EM&A Report

http://www.epd.gov.hk/eia/english/register/index8/vep3502011_content.html

 

 

 

EP-408/2011/A

Central Police Station Conservation and Revitalisation Project

Monthly EM&A Report (No.4)

http://www.epd.gov.hk/eia/english/register/index8/vep3502011_content.html

 

 

 

EP-313/2008/D 

 West Island Line

Final EM&A Report for Works Area MA

http://www.epd.gov.hk/eia/english/register/index8/vep3332011.html

 

 

 

EP-322/2008

Harbour Area Treatment Scheme (HATS) Stage 2A

EM&A Consolidated Monthly report (Jan 2012) (ver1.1)

http://www.epd.gov.hk/eia/english/register/aep/ep3222008_content.html

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report (Jan 2012) (DC/2007/23)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E

 Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report (Jan 2012) (Ver 1.1) (DC/2009/24)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Quarterly Environmental Monitoring and Audit Report No.8 Covering the Period from 1 (Oct to Dec 2011) (DC/2008/09)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report No.25 (DC/2007/24)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

FEP-01/272/2007/B 

Drainage Improvement in Northern Hong Kong Island - Hong Kong West Drainage Tunnel

Monthly EM&A Report (DC/2007/10) (Jan 2012)

http://www.epd.gov.hk/eia/english/register/index8/vep2902009_content.html

 

 

 

- Wan Chai District

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Consolidated Monthly EM&A Report (Jan 2012) (DC/2007/23) (Ver 1.1)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Quarterly EM&A Report (Aug to Oct 2011) (Ver 1.1) (DC/2009/23)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report No.27 (DC/2007/24)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E

 Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report (Feb 2012) (DC/2009/23)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E 

Harbour Area Treatment Scheme (HATS) Stage 2A

Quarterly EM&A Report (Sep to Nov 2011) (DC/2007/23)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E 

Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report (Jan 2012) (DC/2008/09)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-364/2009/A

Central-Wanchai Bypass (CWB) including its road tunnel and slip roads

Monthly EM&A Report (Feb 2012)

http://www.epd.gov.hk/eia/english/register/index8/vep3212010_content.html

 

 

 

EP-407/2010/A

South Island Line (East)

Monthly EM&A Report (No.8)

http://www.epd.gov.hk/eia/english/register/index8/vep3442011_content.html

 

 

 

EP-416/2011 

 ShaTin to Central Link Protection Works at Causeway Bay Typhoon Shelter

Monthly EM&A Report No.3

http://www.epd.gov.hk/eia/english/register/aep/ep4162011_content.html

 

 

 

EP-322/2008

Harbour Area Treatment Scheme (HATS) Stage 2A

EM&A Consolidated Monthly report (Jan 2012) (ver1.1)

http://www.epd.gov.hk/eia/english/register/aep/ep3222008_content.html

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report (Jan 2012) (DC/2007/23)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E

 Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report (Jan 2012) (Ver 1.1) (DC/2009/24)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Quarterly Environmental Monitoring and Audit Report No.8 Covering the Period from 1 (Oct to Dec 2011) (DC/2008/09)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report No.25 (DC/2007/24)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-356/2009

Wan Chai Development Phase II and Central-Wan Chai Bypass

Monthly EM&A Report (Jan 2012)

http://www.epd.gov.hk/eia/english/register/aep/ep3562009_content.html

 

 

 

EP-364/2009/A

Central-Wanchai Bypass (CWB) including its road tunnel and slip roads

Monthly EM&A Report (Jan 2012)

http://www.epd.gov.hk/eia/english/register/index8/vep3212010_content.html

 

 

 

FEP-01/272/2007/B 

Drainage Improvement in Northern Hong Kong Island - Hong Kong West Drainage Tunnel

Monthly EM&A Report (DC/2007/10) (Jan 2012)

http://www.epd.gov.hk/eia/english/register/index8/vep2902009_content.html

 

 

 

- Eastern District

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Consolidated Monthly EM&A Report (Jan 2012) (DC/2007/23) (Ver 1.1)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Quarterly EM&A Report (Aug to Oct 2011) (Ver 1.1) (DC/2009/23)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report No.27 (DC/2007/24)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

 

 

EP-322/2008/E

 Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report (Feb 2012) (DC/2009/23)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

 

 

EP-322/2008/E 

Harbour Area Treatment Scheme (HATS) Stage 2A

Quarterly EM&A Report (Sep to Nov 2011) (DC/2007/23)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

 

 

EP-322/2008/E 

Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report (Jan 2012) (DC/2008/09)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

 

 

EP-322/2008

Harbour Area Treatment Scheme (HATS) Stage 2A

EM&A Consolidated Monthly report (Jan 2012) (ver1.1)

http://www.epd.gov.hk/eia/english/register/aep/ep3222008_content.html

 

 

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report (Jan 2012) (DC/2007/23)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

 

 

EP-322/2008/E

 Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report (Jan 2012) (Ver 1.1) (DC/2009/24)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Quarterly Environmental Monitoring and Audit Report No.8 Covering the Period from 1 (Oct to Dec 2011) (DC/2008/09)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report No.25 (DC/2007/24)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

 

 

FEP-01/335/2009

Phased Reprovisioning of Cape Collinson Crematorium

Monthly EM&A Report (Dec 2012)

http://www.epd.gov.hk/eia/english/register/index7/fep1092010_content.html

 

 

 

 

 

- Southern District

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Consolidated Monthly EM&A Report (Jan 2012) (DC/2007/23) (Ver 1.1)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Quarterly EM&A Report (Aug to Oct 2011) (Ver 1.1) (DC/2009/23)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report No.27 (DC/2007/24)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E

 Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report (Feb 2012) (DC/2009/23)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E 

Harbour Area Treatment Scheme (HATS) Stage 2A

Quarterly EM&A Report (Sep to Nov 2011) (DC/2007/23)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E 

Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report (Jan 2012) (DC/2008/09)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-407/2010/A

South Island Line (East)

Monthly EM&A Report (No.8)

http://www.epd.gov.hk/eia/english/register/index8/vep3442011_content.html

 

 

 

 

EP-249/2006

Repositioning and Long Term Operation Plan of Ocean Park

Quarterly EM&A Report (Oct to Dec 2011)

http://www.epd.gov.hk/eia/english/register/aep/ep2492006_content.html

 

 

 

EP-249/2006/A 

Repositioning and Long Term Operation Plan of Ocean Park

Monthly Environmental Monitoring and Audit Report (Jan 2012)

http://www.epd.gov.hk/eia/english/register/index8/vep2232006_content.html

 

 

 

EP-322/2008

Harbour Area Treatment Scheme (HATS) Stage 2A

EM&A Consolidated Monthly report (Jan 2012) (ver1.1)

http://www.epd.gov.hk/eia/english/register/aep/ep3222008_content.html

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report (Jan 2012) (DC/2007/23)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E

 Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report (Jan 2012) (Ver 1.1) (DC/2009/24)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Quarterly Environmental Monitoring and Audit Report No.8 Covering the Period from 1 (Oct to Dec 2011) (DC/2008/09)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report No.25 (DC/2007/24)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

FEP-01/272/2007/B 

Drainage Improvement in Northern Hong Kong Island - Hong Kong West Drainage Tunnel

Monthly EM&A Report (DC/2007/10) (Jan 2012)

http://www.epd.gov.hk/eia/english/register/index8/vep2902009_content.html

 

 

 

- Kowloon City District

 

 

 

EP-328/2009/A

Dredging Works for Proposed Cruise Terminal at Kai Tak

Monthly EM&A Report (Feb 2012)

http://www.epd.gov.hk/eia/english/register/index8/vep2892009_content.html

 

 

 

EP-337/2009

 New Distributor Roads Serving the Planned Kai Tak Development

Monthly EM&A Report(Jan 2012

http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html

 

 

 

EP-344/2009

New Sewage Pumping Stations Serving Kai Tak Development

Monthly EM&A Report(Jan 2012

http://www.epd.gov.hk/eia/english/register/aep/ep3442009.html

 

 

 

EP-399/2010/A 

Kwun Tong Line Extension

Monthly EM&A Report (Feb 2012)

http://www.epd.gov.hk/eia/english/register/index8/vep3292011_content.html

 

 

 

EP-399/2010/A

Kwun Tong Line Extension

Monthly EM&A Report (Jan 2012)

http://www.epd.gov.hk/eia/english/register/index8/vep3292011_content.html

 

 

 

- Kwun Tong District

 

 

 

 Nil

 

 

 

- Sham Shui Po District

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Consolidated Monthly EM&A Report (Jan 2012) (DC/2007/23) (Ver 1.1)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Quarterly EM&A Report (Aug to Oct 2011) (Ver 1.1) (DC/2009/23)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report No.27 (DC/2007/24)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E

 Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report (Feb 2012) (DC/2009/23)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E 

Harbour Area Treatment Scheme (HATS) Stage 2A

Quarterly EM&A Report (Sep to Nov 2011) (DC/2007/23)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E 

Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report (Jan 2012) (DC/2008/09)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-349/2009/E

Hong Kong Section of Guangzhou - Shenzhen - Hong Kong Express Rail Link

Monthly EM&A Report (Jan 2012)

http://www.epd.gov.hk/eia/english/register/index8/vep3522012_content.html

 

 

 

EP-349/2009/E

Hong Kong Section of Guangzhou - Shenzhen - Hong Kong Express Rail Link

Monthly EM&A Report (Feb 2012)

http://www.epd.gov.hk/eia/english/register/index8/vep3522012_content.html

 

 

 

EP-322/2008

Harbour Area Treatment Scheme (HATS) Stage 2A

EM&A Consolidated Monthly report (Jan 2012) (ver1.1)

http://www.epd.gov.hk/eia/english/register/aep/ep3222008_content.html

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report (Jan 2012) (DC/2007/23)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E

 Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report (Jan 2012) (Ver 1.1) (DC/2009/24)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Quarterly Environmental Monitoring and Audit Report No.8 Covering the Period from 1 (Oct to Dec 2011) (DC/2008/09)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

EP-322/2008/E

Harbour Area Treatment Scheme (HATS) Stage 2A

Monthly EM&A Report No.25 (DC/2007/24)

http://www.epd.gov.hk/eia/english/register/index8/vep3302010_content.html

 

 

 

- Wong Tai Sin District

 

 

 

Nil

 

 

 

- Yau Tsim Mong District

 

 

 

EP-273/2007

Laying of Western Cross Harbour Main and Associated Land Mains from West Kowloon to Sai Ying Pun

Monthly EM&A Report (Feb 2012) No.22

http://www.epd.gov.hk/eia/english/register/aep/ep2732007_content.html

 

 

 

EP-273/2007 

Laying of Western Cross Harbour Main and Associated Land Mains from West Kowloon to Sai Ying Pun

Quarterly EM&A Report No.7 (Nov 2011 to Jan 2012)

http://www.epd.gov.hk/eia/english/register/aep/ep2732007_content.html

 

 

 

EP-349/2009/E

Hong Kong Section of Guangzhou - Shenzhen - Hong Kong Express Rail Link

Monthly EM&A Report (Jan 2012)

http://www.epd.gov.hk/eia/english/register/index8/vep3522012_content.html

 

 

 

EP-349/2009/E

Hong Kong Section of Guangzhou - Shenzhen - Hong Kong Express Rail Link

Monthly EM&A Report (Feb 2012)

http://www.epd.gov.hk/eia/english/register/index8/vep3522012_content.html

 

 

 

EP-366/2009

Road Works at West Kowloon

Monthly EM&A Report (Feb 2012)

http://www.epd.gov.hk/eia/english/register/aep/ep3662009_content.html

 

 

 

EP-366/2009

Road Works at West Kowloon

Monthly EM&A Report (Jan 2012)

http://www.epd.gov.hk/eia/english/register/aep/ep3662009_content.html

 

 

 

EP-399/2010/A 

Kwun Tong Line Extension

Monthly EM&A Report (Feb 2012)

http://www.epd.gov.hk/eia/english/register/index8/vep3292011_content.html

 

 

 

EP-414/2011

 Reprovision of Bridges D1 and T in West Kowloon

Monthly EM&A Report (Feb 2012)

http://www.epd.gov.hk/eia/english/register/aep/ep4142011_content.html