Monthly Update of Documents Uploaded
Documents Uploaded to the EIAO
Website
|
|
(for the period between 16 April 2020
to 15 May 2020)
|
|
|
|
Application
No. / Permit No.
|
Project
Title
|
Document
Name
|
Hyperlink
|
|
|
|
Application
for EIA Study Brief
|
|
|
|
ESB-329/2020
|
Tung
Chung Line Extension
|
Project Profile
|
https://www.epd.gov.hk/eia/register/profile/latest/esb329/esb329.pdf
|
|
|
|
ESB-330/2020
|
Development
of Tai Sheung Tok Transfer Station
|
Project Profile
|
https://www.epd.gov.hk/eia/register/profile/latest/esb330/esb330.pdf
|
|
|
|
Application
for Permission to Apply Directly for Environmental Permit
|
|
|
|
DIR-272/2020
|
Bay to Bay Express Cable System - Hong Kong
Segment (BtoBE-HK) – Chung Hom Kok
|
Decisions on Applications for (DIR)
|
https://www.epd.gov.hk/eia/register/permission/conditions/dir2722020.pdf
|
|
|
|
DIR-273/2020
|
H2H Express Submarine Cable
|
Decisions on Applications for (DIR)
|
https://www.epd.gov.hk/eia/register/permission/conditions/dir2732020.pdf
|
|
|
|
Application
for Approval of EIA Report
|
|
|
|
EIA-262/2020
|
Improvement of Yuen Long Town Nullah (Town
Centre Section)
|
EIA Report
|
https://www.epd.gov.hk/eia/register/report/eiareport/eia_2622020/Webpage/Website_First_Page.htm
|
|
|
|
Application
for Environmental Permit
|
|
|
|
AEP-573/2020
|
Bay to Bay Express Cable System - Hong Kong
Segment (BtoBE-HK) – Chung Hom Kok
|
Environmental Permit issued (EP-573/2020)
|
https://www.epd.gov.hk/eia/register/permit/latest/ep5732020.htm
|
|
|
|
AEP-574/2020
|
Reuse of Treated Sewage Effluent from a
Treatment Plant at Mount Pavilia, Sai Kung
|
Environmental Permit issued (EP-574/2020)
|
https://www.epd.gov.hk/eia/register/permit/latest/ep5742020.htm
|
|
|
|
Application
for Variation of an Environmental Permit
|
|
|
|
VEP-572/2020
|
Central-Wanchai Bypass (CWB) including its road
tunnel and slip roads
|
Environmental Permit issued (EP-364/2009/H)
|
https://www.epd.gov.hk/eia/register/permit/latest/vep5722020.htm
|
|
|
VEP-573/2020
|
Central-Wanchai Bypass (CWB) including its road
tunnel and slip roads
|
Environmental Permit issued (EP-482/2013/C)
|
https://www.epd.gov.hk/eia/register/permit/latest/vep5732020.htm
|
VEP-574/2020
|
Central-Wanchai Bypass (CWB) including its road
tunnel and slip roads
|
Environmental Permit issued (FEP-07/364/2009/H)
|
https://www.epd.gov.hk/eia/register/permit/latest/vep5742020.htm
|
VEP-575/2020
|
Installation of One Additional Gas-fired Generation
Unit (CCGT Unit No.2) at the Black Point Power Station
|
Environmental Permit issued (EP-507/2016/C)
|
https://www.epd.gov.hk/eia/register/permit/latest/vep5752020.htm
|
|
Application
for Further Environmental Permit
|
|
|
|
Nil
|
|
|
|
Submission
as required by Environmental Permit Condition - Design / Environmental
Submissions
|
|
|
|
EP-312/2008/A
|
Disposal of Contaminated
Sediment - Dredging, Management and Capping of sediment Disposal Facility
at Sha Chau
|
Monthly
Progress Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/index8/vep2742009_content.html
|
|
|
|
EP-414/2011
|
Reprovision of Bridges D1 and T in West Kowloon
|
Landscape
Plan
|
https://www.epd.gov.hk/eia/english/register/aep/ep4142011_content.html
|
|
|
|
EP-438/2012/K
|
Shatin to Central Link - Tai Wai to Hung Hom
Section
|
Monthly
Operational Airborne Rail Noise Monitoring Report (Festival City)No.2
|
https://www.epd.gov.hk/eia/english/register/index8/vep5062016_content.html
|
|
|
|
FEP-04/356/2009
|
Central - Wan Chai Bypass - Tunnel (Causeway Bay
Typhoon shelter section) Contract No. HY/2009/15 - Marine Works
|
Silt
Screen Deployment Plan (HY/2009/15)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1172010_content.html
|
|
|
|
EP-560/2018
|
Intermodal Transfer Terminal – Bonded Vehicular
Bridge and Associated Roads
|
Baseline
Monitoring Report
|
https://www.epd.gov.hk/eia/english/register/aep/ep5602018_content.html
|
|
|
|
EP-429/2012/A
FEP-01/429/2012/A
|
Development of the Integrated Waste Management Facilities
Phase 1
|
Supportine
Document for reviewing dredging rate and filling rate (Rev. E)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1772017_content.html
|
|
|
|
EP-454/2013
|
Reprovisioning of FEHD Sai Yee Street Vehicle
Depot at Yen Ming Road, West Kowloon Reclamation Area
|
Submission
of Environmental Impact Monitoring Report(Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/aep/ep4542013_content.html
|
|
|
|
EP-510/2016
|
Police Facilities in Kong Nga Po
|
Baseline
Survey Report for Golden-Headed Cisticola
|
https://www.epd.gov.hk/eia/english/register/aep/ep5102016_content.html
|
|
|
|
EP-510/2016
|
Police Facilities in Kong Nga Po
|
Explanatory
Statement for Revised Road Layout Plan
|
https://www.epd.gov.hk/eia/english/register/aep/ep5102016_content.html
|
|
|
|
EP-559/2018
|
Natural Terrain Hazard
Mitigation Works at Study Area 11NE-B/SA3,Razor Hill, Clear Water Bay Road
|
Baseline
Vegetation Survey Report (Aug 2019)
|
https://www.epd.gov.hk/eia/english/register/aep/ep5592018_content.html
|
|
|
|
Submission
as required by Environmental Permit Condition - EM&A Report
|
|
|
|
|
Island District
|
Central & Western District
|
|
|
|
|
|
North District
|
Wan Chai District
|
|
|
|
|
|
Sai Kung District
|
Eastern District
|
|
|
|
|
|
Sha Tin District
|
Southern District
|
|
|
|
|
|
Tai Po District
|
Kowloon City District
|
|
|
|
|
|
Tsuen Wan District
|
Kwun Tong District
|
|
|
|
|
|
Tuen Mun District
|
Sham Shui Po District
|
|
|
|
|
|
Yuen Long District
|
Wong Tai Sin District
|
|
|
|
|
|
Kwai Tsing District
|
Yau Tsim Mong District
|
|
|
|
|
- Island District
|
|
|
|
EP-01/059/2000/C
|
The Theme Park at Penny's Bay, Lantau
|
175th Monthly EM&A Report (12 Mar 2020
to 11 Apr 2020)
|
http://www.epd.gov.hk/eia/english/register/index8/vep3782012_content.html
|
|
|
|
EP-353/2009/K
|
Hong Kong - Zhuhai - Macao Bridge Hong Kong Boundary
Crossing Facilities
|
Quarterly Environmental Monitoring and
Audit Report (Dec 2018 to Jan 2019)(HY/2013/02)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4982016_content.html
|
|
|
|
EP-353/2009/K
|
Hong Kong - Zhuhai - Macao Bridge Hong Kong Boundary Crossing
Facilities
|
Monthly Environmental Monitoring and Audit
Report (Dec 2018)(HY/2013/02)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4982016_content.html
|
|
|
|
EP-353/2009/K
|
Hong Kong - Zhuhai - Macao Bridge Hong Kong Boundary
Crossing Facilities
|
Quarterly Environmental Monitoring and Audit
Report (Sep 2018 to Nov 2018)(HY/2013/03)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4982016_content.html
|
|
|
|
EP-353/2009/K
|
Hong Kong - Zhuhai - Macao Bridge Hong Kong Boundary Crossing
Facilities
|
Monthly Environmental Monitoring and Audit
Report (Nov 2018)(HY/2013/03)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4982016_content.html
|
|
|
|
EP-353/2009/K
|
Hong Kong - Zhuhai - Macao Bridge Hong Kong Boundary
Crossing Facilities
|
Monthly Environmental Monitoring and Audit
Report (Jan 2019)(HY/2013/03)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4982016_content.html
|
|
|
|
EP-353/2009/K
|
Hong Kong - Zhuhai - Macao Bridge Hong Kong Boundary Crossing
Facilities
|
Quarterly Environmental Monitoring and Audit
Report (Dec 2018 to Jan 2019)(HY/2013/03)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4982016_content.html
|
|
|
|
EP-353/2009/K
|
Hong Kong - Zhuhai - Macao Bridge Hong Kong Boundary
Crossing Facilities
|
Quarterly Environmental Monitoring and Audit
Report (Sep 2019 to Nov 2019)(HY/2013/04)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4982016_content.html
|
|
|
|
EP-353/2009/K
|
Hong Kong - Zhuhai - Macao Bridge Hong Kong Boundary
Crossing Facilities
|
Quarterly Environmental Monitoring and Audit
Report (Jun 2019 to Aug 2019)(HY/2013/04)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4982016_content.html
|
|
|
|
EP-353/2009/K
|
Hong Kong - Zhuhai - Macao Bridge Hong Kong Boundary
Crossing Facilities
|
Final Environmental Monitoring and Audit Report
(Sep 2014 to Jan 2019) (HY/2013/01)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4982016_content.html
|
|
|
|
EP-353/2009/K
|
Hong Kong - Zhuhai - Macao Bridge Hong Kong Boundary Crossing
Facilities
|
Monthly EM&A Report(Mar 2020) (HY/2011/03)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4982016_content.html
|
|
|
|
EP-353/2009/K
|
Hong Kong - Zhuhai - Macao Bridge Hong Kong Boundary
Crossing Facilities
|
Monthly Environmental Monitoring and Audit
Report (Mar 2019)(HY/2013/04)(Rev 1)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4982016_content.html
|
|
|
|
EP-352/2009/D
|
Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road
|
Monthly EM&A Report(Mar 2020)
(HY/2011/03)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4592014_content.html
|
|
|
|
EP-071/2000/C
|
1,800MW Gas-Fired Power Station at Lamma Extension
|
Monthly Environmental Monitoring and Audit Report Unit
L10& L11 (Mar 2020)
|
http://www.epd.gov.hk/eia/english/register/index8/vep1742005_content.html
|
|
|
|
EP-071/2000/C
|
1,800MW Gas-Fired Power Station at Lamma Extension
|
Monthly EM&A Report (Mar 2020)
|
http://www.epd.gov.hk/eia/english/register/index8/vep1742005_content.html
|
|
|
|
EP-01/097/2001/C
|
Water Recreation Centre at Penny's Bay (part &
remaining part)
|
Monthly Environmental Monitoring and Audit Report (No.
176)
|
http://www.epd.gov.hk/eia/english/register/index8/vep1992005_content.html
|
|
|
|
FEP-01/395/2010/C
|
Organic Waste Treatment Facilities, Phase I
|
Fifty-eighth
Monthly EM&A Report(Mar 2020)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4872015_content.html
|
|
|
|
EP-429/2012/A
FEP-01/429/2012/A
|
Development of the Integrated Waste Management Facilities
Phase 1
|
Monthly EM&A Report No.21
|
https://www.epd.gov.hk/eia/english/register/index7/fep1772017_content.html
|
|
|
|
EP-083/2000
|
Conversion of Two Existing Gas Turbines (GT5 & GT7)
into a Combined Cycle Unit
|
Monthly Environmental Monitoring And Audit Report (Mar
2020)
|
https://www.epd.gov.hk/eia/english/register/aep/ep0832000_content.html
|
|
|
|
EP-354/2009/D
|
Tuen Mun - Chek Lap Kok Link
|
Quarterly Environmental Monitoring and
Audit Report (Nov 2019 to Jan 2020) (HY/2013/12)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4692015_content.html
|
|
|
|
EP-354/2009/D
|
Tuen Mun - Chek Lap Kok Link
|
77th Monthly Environmental Monitoring and
Audit Report (Mar 2020)(HY/2012/07)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4692015_content.html
|
|
|
|
EP-354/2009/D
|
Tuen Mun - Chek Lap Kok Link
|
Monthly Environmental Monitoring and Audit
Report (Mar 2020)(HY/2017/10)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4692015_content.html
|
|
|
|
EP-354/2009/D
|
Tuen Mun - Chek Lap Kok Link
|
Monthly Environmental Monitoring and Audit
Report (Mar 2020)(HY/2012/08)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4692015_content.html
|
|
|
|
EP-354/2009/D
|
Tuen Mun - Chek Lap Kok Link
|
Monthly Environmental Monitoring and Audit
Report (Mar 2020)(HY/2013/12)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4692015_content.html
|
|
|
|
EP-354/2009/D
|
Tuen Mun - Chek Lap Kok Link
|
24th Quarterly Environmental Monitoring and
Audit Report (Sep to Nov 2019) (HY/2012/07)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4692015_content.html
|
|
|
|
EP-489/2014
|
Expansion of
Hong Kong International Airport into a Three-Runway System
|
Construction
Phase Monthly EM&A Report No.51
|
https://www.epd.gov.hk/eia/english/register/aep/ep4892014_content.html
|
|
|
|
EP-519/2016
|
Tung Chung New
Town Extension
|
Monthly EM&A
Report(Feb 2020)
|
https://www.epd.gov.hk/eia/english/register/aep/ep5192016_content.html
|
|
|
|
EP-519/2016
|
Tung Chung New
Town Extension
|
Monthly EM&A
Report(Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/aep/ep5192016_content.html
|
|
|
|
EP-532/2017/A
|
Mui Wo Lai Chi
Yuen Cemetery Extension
|
Landscape
Mitigation & Tree Preservation Plan
|
https://www.epd.gov.hk/eia/english/register/index8/vep5582019_content.html
|
|
|
|
EP-532/2017/A
|
Mui Wo Lai Chi
Yuen Cemetery Extension
|
Monthly EM&A
Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5582019_content.html
|
|
|
|
EP-535/2017
|
Improvement Dredging
for Lamma Power Station Navigation Channel
|
Monthly EM&A
Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/aep/ep5352017_content.html
|
|
|
|
EP-248/2006
|
Lamma Power
Station Units L4 & L5 Flue Gas Desulphurization Plant Retrofit Project
|
Quarterly
EM&A Report (Oct 2019 to Dec 2019)
|
https://www.epd.gov.hk/eia/english/register/aep/ep2482006_content.html
|
|
|
|
EP-287/2007
|
Lamma Power
Station - Unit L2 Flue Gas Desulphurization Plant Retrofit Project
|
Quarterly
EM&A Report (Oct 2019 to Dec 2019)
|
https://www.epd.gov.hk/eia/english/register/aep/ep2872007_content.html
|
|
|
|
EP-262/2007/B
|
Permanent Aviation
Fuel Facility for Hong Kong International Airport
|
Environmental
Permit Annual Audit Report for 2019
|
https://www.epd.gov.hk/eia/english/register/index8/vep2512008_content.html
|
|
|
|
- North District
|
|
|
|
FEP-02/474/2013
|
Shek Wu Hui Effluent Polishing Plant
|
Monthly EM&A Report(Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1792018_content.html
|
|
|
|
FEP-02/474/2013
|
Shek Wu Hui Effluent Polishing Plant
|
Monthly EM&A Report(Dec 2019)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1792018_content.html
|
|
|
|
EP-534/2017
|
Site Formation and Associated Infrastructural Works for
Development of Columbarium, Crematorium and Related Facilities at Sandy
Ridge Cemetery
|
Monthly EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/aep/ep5342017_content.html
|
|
|
|
EP-534/2017/A
|
Site Formation and Associated Infrastructural Works for
Development of Columbarium, Crematorium and Related Facilities at Sandy
Ridge Cemetery
|
Monthly EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5542018_content.html
|
|
|
|
FEP-01/534/2017
|
Site Formation and Associated Infrastructural Works for
Development of Columbarium, Crematorium and Related Facilities at Sandy
Ridge Cemetery
|
Monthly EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1802018_content.html
|
|
|
|
FEP-01/534/2017/A
|
Site Formation and Associated Infrastructural Works for
Development of Columbarium, Crematorium and Related Facilities at Sandy Ridge
Cemetery
|
Monthly EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5552018_content.html
|
|
|
|
FEP-01/460/2013
|
Development of Organic Waste Treatment Facilities, Phase
2
|
Monthly EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1912019_content.html
|
|
|
|
EP-477/2013
|
Development of Lok Ma Chau Loop
|
Monthly EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/aep/ep4772013_content.html
|
|
|
|
EP-404/2011/D
|
Liantang / Heung Yuen Wai Boundary Control Point and
Associated Works
|
Monthly EM&A Report (Mar 2020)
|
http://www.epd.gov.hk/eia/english/register/index8/vep5192016_content.html
|
|
|
|
EP-517/2017/A
|
Expansion of Sha Tau Kok Sewage Treatment Works
|
Monthly EM&A Report(Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5672019_content.html
|
|
|
|
EP-324/2008/E
|
Widening of Tolo Highway/Fanling Highway between Island
House Interchange and Fanling
|
Monthly EM&A Report (Mar 2020)(CV/2012/09)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5222016_content.html
|
|
|
|
EP-324/2008/E
|
Widening of Tolo Highway/Fanling Highway between Island
House Interchange and Fanling
|
Quarterly EM&A Report (Nov 2019 - Jan 2020)
(CV/2012/06)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5222016_content.html
|
|
|
|
EP-324/2008/E
|
Widening of Tolo Highway/Fanling Highway between Island
House Interchange and Fanling
|
Quarterly EM&A Report (Nov 2019 - Jan 2020)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5222016_content.html
|
|
|
|
EP-324/2008/E
|
Widening of Tolo Highway/Fanling Highway between Island
House Interchange and Fanling
|
Monthly EM&A Report (Mar 2020)(CV/2012/06)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5222016_content.html
|
|
|
|
EP-470/2013
|
NENT - Utilization of Treated Sewage Effluent (TSE) from
Shek Wu Hui Sewage Treatment Works
|
Monthly EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/aep/ep4702013_content.html
|
|
|
|
EP-475/2013/A
|
Reprovision of temporary Wholesale Market in Fanling
North New Development Area
|
Monthly EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5162016_content.html
|
|
|
|
EP-450/2013/A
|
Construction of Cycle Tracks and the associated Supporting
Facilities from Sha Po Tsuen to Shek Sheung River
|
Monthly EM&A Report (Mar 2020)(Version 1.0)
|
https://www.epd.gov.hk/eia/english/register/index8/vep4782015_content.html
|
|
|
|
EP-501/2015
|
Construction of Cycle Tracks and the associated
Supporting Facilities from Sha Po Tsuen to Shek Sheung River
|
Monthly EM&A Report (Mar
2020)(Version 1.0)
|
https://www.epd.gov.hk/eia/english/register/aep/ep5012015_content.html
|
|
|
|
EP-502/2015/A
|
Operation of the Existing Tai Lam Explosives Magazine at
Tai Shu Ha, Yuen Long for Liantang / Heung Yuen Wai Boundary Control Point
Project
|
Monthly EM&A Report
(Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5052016_content.html
|
|
|
|
- Sai Kung District
|
|
|
|
EP-458/2013/C
|
Tseung Kwan O – Lam Tin Tunnel and Associated Works
|
Monthly EM&A Report (Mar 2020)(version
1.0)
|
http://www.epd.gov.hk/eia/english/register/index8/vep5272016_content.html
|
|
|
|
EP-458/2013/C
|
Tseung Kwan O – Lam Tin Tunnel and Associated Works
|
Quarterly EM&A Report (Nov 2019 to Jan
2020)(version 1.0)
|
http://www.epd.gov.hk/eia/english/register/index8/vep5272016_content.html
|
|
|
|
FEP-01/503/2015/A
|
Desalination Plant at Tseung Kwan O
|
Monthly EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1922019_content.html
|
|
|
|
EP-319/2009/D
|
Development of a Biodiesel Plant at Tseung Kwan O
Industrial Estate
|
Monthly EM&A Report (Mar 2020) (V.1)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4242014_content.html
|
|
|
|
EP-438/2012/K
|
Shatin to Central Link - Tai Wai to Hung Hom Section
|
Monthly EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5062016_content.html
|
|
|
|
EP-503/2015/A
|
Desalination Plant at Tseung Kwan O
|
6th Quarterly EM&A Report(Nov 2019 to Jan 2020)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5402018_content.html
|
|
|
|
EP-503/2015/A
|
Desalination Plant at Tseung Kwan O
|
Annually Report 1st (Aug 2018 - Aug 2019)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5402018_content.html
|
|
|
|
EP-503/2015/A
|
Desalination Plant at Tseung Kwan O
|
20th Monthly EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5402018_content.html
|
|
|
|
EP-513/2016
|
Development of Anderson Road Quarry site - Road
Improvement Works
|
Monthly EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/aep/ep5132016_content.html
|
|
|
|
EP-459/2013
|
Cross Bay Link, Tseung Kwan O
|
Monthly EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/aep/ep4592013_content.html
|
|
|
|
FEP-01/308/2008/B
|
South-East New Territories Landfill Extension
|
Monthly EM&A Report No.15 (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1872018_content.html
|
|
|
|
- Sha Tin District
|
|
|
|
EP-494/2015
|
In-situ Reprovisioning of Sha Tin Water Treatment Works -
South Works
|
Monthly EM&A Report No.49
|
http://www.epd.gov.hk/eia/english/register/aep/ep4942014_content.html
|
|
|
|
EP-463/2013/B
|
Widening and Reconstruction of Tai Po Road (Sha Tin
Section)
|
Monthly EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5142016_content.html
|
|
|
|
EP-533/2017
|
Sha Tin Cavern Sewage Treatment Works
|
Monthly EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/aep/ep5332017_content.html
|
|
|
|
EP-345/2009
|
Inter-reservoirs Transfer Scheme (IRTS) - Water
Tunnel between Kowloon Byewash Reservoir and Lower Shing Mun Reservoir
|
9th Monthly EM&A Report(Rev.2)
|
https://www.epd.gov.hk/eia/english/register/aep/ep3452009_content.html
|
|
|
|
EP-438/2012/K
|
Shatin to Central Link - Tai Wai to Hung Hom Section
|
Monthly EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5062016_content.html
|
|
|
|
- Tai Po District
|
|
|
|
EP-388/2010
|
Development of a Bathing Beach at Lung Mei, Tai Po
|
Monthly EM&A Report(Jan 2020) (CV/2012/05)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3882010_content.html
|
|
|
|
EP-388/2010
|
Development of a Bathing Beach at Lung Mei, Tai Po
|
Monthly EM&A Report(Mar 2020)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3882010_content.html
|
|
|
|
EP-324/2008/E
|
Widening of Tolo Highway/Fanling Highway between Island
House Interchange and Fanling
|
Monthly EM&A Report (Mar 2020)(CV/2012/09)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5222016_content.html
|
|
|
|
EP-324/2008/E
|
Widening of Tolo Highway/Fanling Highway between Island House
Interchange and Fanling
|
Quarterly EM&A Report (Nov 2019 - Jan 2020)
(CV/2012/06)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5222016_content.html
|
|
|
|
EP-324/2008/E
|
Widening of Tolo Highway/Fanling Highway between Island
House Interchange and Fanling
|
Quarterly EM&A Report (Nov 2019 - Jan 2020)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5222016_content.html
|
|
|
|
EP-324/2008/E
|
Widening of Tolo Highway/Fanling Highway between Island
House Interchange and Fanling
|
Monthly EM&A Report (Mar 2020)(CV/2012/06)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5222016_content.html
|
|
|
|
EP-470/2013
|
NENT - Utilization of Treated Sewage Effluent (TSE) from
Shek Wu Hui Sewage Treatment Works
|
Monthly EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/aep/ep4702013_content.html
|
|
|
|
EP-475/2013/A
|
Reprovision of temporary Wholesale Market in Fanling
North New Development Area
|
Monthly EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5162016_content.html
|
|
|
|
- Tsuen Wan District
|
|
|
|
EP-076/2000
|
Upgrading of Siu Ho Wan Sewage Treatment
Plant
|
Monthly Environmental Monitoring And Audit
Report (Mar 2020)
|
http://www.epd.gov.hk/eia/english/register/aep/ep0762000_content.html
|
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report (DC/2009/10)(Mar
2020)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report (DE/2018/17)(Mar 2020)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report (DC/2009/24)(Mar 2020)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Quarterly EM&A Report (DE/2018/17)(Dec
2019 to Feb 2020)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
|
EP-489/2014
|
Expansion of
Hong Kong International Airport into a Three-Runway System
|
Construction Phase Monthly EM&A Report
No.51
|
http://www.epd.gov.hk/eia/english/register/aep/ep4892014_content.html
|
|
|
|
FEP-01/395/2010/C
|
Organic Waste
Treatment Facilities, Phase I
|
Fifty-eighth Monthly EM&A Report(Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/index8/vep4872015_content.html
|
|
|
|
- Tuen Mun
District
|
|
|
|
EP-354/2009/D
|
Tuen Mun - Chek Lap Kok Link
|
Quarterly Environmental Monitoring and Audit
Report (Nov 2019 to Jan 2020) (HY/2013/12)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4692015_content.html
|
|
|
|
EP-354/2009/D
|
Tuen Mun - Chek Lap Kok Link
|
77th Monthly Environmental Monitoring and
Audit Report (Mar 2020)(HY/2012/07)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4692015_content.html
|
|
|
|
EP-354/2009/D
|
Tuen Mun - Chek Lap Kok Link
|
Monthly Environmental Monitoring and Audit
Report (Mar 2020)(HY/2012/08)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4692015_content.html
|
|
|
|
EP-354/2009/D
|
Tuen Mun - Chek Lap Kok Link
|
Monthly Environmental Monitoring and Audit
Report (Mar 2020)(HY/2017/10)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4692015_content.html
|
|
|
|
EP-354/2009/D
|
Tuen Mun - Chek Lap Kok Link
|
Monthly Environmental Monitoring and Audit
Report (Mar 2020)(HY/2013/12)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4692015_content.html
|
|
|
|
EP-354/2009/D
|
Tuen Mun - Chek Lap Kok Link
|
24th Quarterly Environmental Monitoring and
Audit Report (Sep to Nov 2019) (HY/2012/07)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4692015_content.html
|
|
|
|
EP-429/2012/A
FEP-01/429/2012/A
|
Development of the Integrated Waste Management Facilities
Phase 1
|
Monthly EM&A Report No.21
|
https://www.epd.gov.hk/eia/english/register/index7/fep1772017_content.html
|
|
|
|
FEP-02/507/2016/B
|
Additional Gas-fired Generation units Project -
Installation of one additional gas-fired generation unit (CCGT Unit No. 1) at
the Black Point Power Station
|
Monthly EM&A Report no.40
|
https://www.epd.gov.hk/eia/english/register/index8/vep5522018_content.html
|
|
|
|
FEP-02/507/2016/B
|
Additional Gas-fired Generation units Project -
Installation of one additional gas-fired generation unit (CCGT Unit No. 1)
at the Black Point Power Station
|
Annual EM&A Report No.3
|
https://www.epd.gov.hk/eia/english/register/index8/vep5512018_content.html
|
|
|
|
EP-507/2016/B
|
Installation of One additional gas-fired generation unit
(CCGT Unit No. 1) at the Black Point Power Station
|
Monthly EM&A Report no.40
|
https://www.epd.gov.hk/eia/english/register/index8/vep5512018_content.html
|
|
|
|
EP-507/2016/B
|
Installation of One additional gas-fired generation unit
(CCGT Unit No. 1) at the Black Point Power Station
|
Annual EM&A Report No.3
|
https://www.epd.gov.hk/eia/english/register/index8/vep5512018_content.html
|
|
|
|
EP-534/2017
|
Site Formation and Associated Infrastructural Works for
Development of Columbarium, Crematorium and Related Facilities at Sandy
Ridge Cemetery
|
Monthly EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/aep/ep5342017_content.html
|
|
|
|
EP-534/2017/A
|
Site Formation and Associated Infrastructural Works
for Development of Columbarium, Crematorium and Related Facilities at Sandy
Ridge Cemetery
|
Monthly EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5542018_content.html
|
|
|
|
FEP-01/534/2017
|
Site Formation and Associated Infrastructural Works for
Development of Columbarium, Crematorium and Related Facilities at Sandy
Ridge Cemetery
|
Monthly EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1802018_content.html
|
|
|
|
FEP-01/534/2017/A
|
Site Formation and Associated Infrastructural Works
for Development of Columbarium, Crematorium and Related Facilities at Sandy
Ridge Cemetery
|
Monthly EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5552018_content.html
|
|
|
|
EP-441/2012/A
|
Enhanced Ash Utilisation and Water Management Facilities
at the Castle Peak Power Station (CPPS)
|
Monthly EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5432018_content.html
|
|
|
|
EP-489/2014
|
Expansion of Hong Kong International
Airport into a Three-Runway System
|
Construction Phase Monthly EM&A Report
No.51
|
http://www.epd.gov.hk/eia/english/register/aep/ep4892014_content.html
|
|
|
|
EP-226/2006/F
|
Development of an EcoPark in Tuen Mun Area
38
|
Quarterly Environmental Monitoring and
Audit Report (Jan to Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5482018_content.html
|
|
|
|
- Yuen Long District
|
|
|
|
EP-477/2013
|
Development of Lok Ma Chau Loop
|
Monthly EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/aep/ep4772013_content.html
|
|
|
|
EP-464/2013
|
Expansion of Ha Tsuen Sewage Pumping Station
|
Monthly EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/aep/ep4642013_content.html
|
|
|
|
EP-450/2013/A
|
Construction of Cycle Tracks and the associated
Supporting Facilities from Sha Po Tsuen to Shek Sheung River
|
Monthly EM&A Report (Mar 2020)(Version 1.0)
|
https://www.epd.gov.hk/eia/english/register/index8/vep4782015_content.html
|
|
|
|
EP-501/2015
|
Construction of Cycle Tracks and the associated
Supporting Facilities from Sha Po Tsuen to Shek Sheung River
|
Monthly EM&A Report (Mar 2020)(Version 1.0)
|
https://www.epd.gov.hk/eia/english/register/aep/ep5012015_content.html
|
|
|
|
EP-502/2015/A
|
Operation of the Existing Tai Lam Explosives Magazine at
Tai Shu Ha, Yuen Long for Liantang / Heung Yuen Wai Boundary Control Point
Project
|
Monthly EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5052016_content.html
|
|
|
|
- Kwai Tsing District
|
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report (DC/2009/10)(Mar
2020)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report (DE/2018/17)(Mar 2020)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report (DC/2009/24)(Mar 2020)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Quarterly EM&A Report(DE/2018/17)(Dec 2019 to Feb
2020)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
|
EP-426/2011/A
|
Providing Sufficient Water Depth for Kwai Tsing Container
Basin and its Approach Channel
|
Monthly Environmental Monitoring & Audit Report (Mar
2020)
|
https://www.epd.gov.hk/eia/english/register/index8/vep3692012_content.html
|
|
|
|
- Central & Western District
|
|
|
|
EP-122/2002/E
|
Central Reclamation Phase III
|
Monthly EM&A Report (Mar 2020) (HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4832015_content.html
|
|
|
|
EP-122/2002/E
|
Central Reclamation Phase III
|
Quarterly EM&A Report (Nov 2019 to Jan 2020)
(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4832015_content.html
|
|
|
|
EP-364/2009/G
|
Central-Wanchai Bypass (CWB) including its road tunnel
and slip roads
|
Monthly EM&A Report (Mar 2020)(HK/2015/01)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5652019_content.html
|
|
|
|
FEP-01/364/2009
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Wan Chai East(CWB Tunnel)
|
Monthly EM&A Report (Mar 2020)(HK/2015/01)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1062010_content.html
|
|
|
|
FEP-05/364/2009/A
|
Central - Wan Chai Bypass - Central Interchange (Contract
No. HY/2009/18)
|
Monthly EM&A Report (Mar 2020)(HK/2015/01)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1162010_content.html
|
|
|
|
FEP-06/364/2009/A
|
Central - Wan Chai Bypass - Central Interchange (Contract
No. HY/2009/18)
|
Monthly EM&A Report (Mar 2020)(HK/2015/01)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1182010_content.html
|
|
|
|
FEP-07/364/2009/G
|
Central-Wanchai Bypass (CWB) including
its road tunnel and slip roads
|
Monthly EM&A Report (Mar 2020)(HK/2015/01)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5662019_content.html
|
|
|
|
FEP-09/364/2009/B
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Wan Chai West (Contract No. HK/2012/08) - Tunnel Work
|
Monthly EM&A Report (Mar 2020)(HK/2015/01)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1442013_content.html
|
|
|
|
FEP-10/364/2009/B
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Wan Chai West (Contract No. HK/2012/08) - Tunnel Work
|
Monthly EM&A Report (Mar 2020)(HK/2015/01)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1482013_content.html
|
|
|
|
FEP-11/364/2009/E
|
Central - Wan Chai Bypass - Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning (Contract No.
HY/2011/08)
|
Monthly EM&A Report (Mar 2020)(HK/2015/01)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5132016_content.html
|
|
|
|
FEP-12/364/2009/D
|
Central-Wanchai Bypass (CWB) including its road tunnel
and slip roads
|
Monthly EM&A Report (Mar 2020)(HK/2015/01)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1712016_content.html
|
|
|
|
EP-376/2009
|
DP2-Road P2 and other roads which are classified as
primary/district distributor roads
|
Monthly EM&A Report (Mar
2020)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3762009_content.html
|
|
|
|
EP-376/2009
|
DP2-Road P2 and other roads which are classified as primary/district
distributor roads
|
Quarterly EM&A Report (Nov 2019 to Jan
2020)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3762009_content.html
|
|
|
|
FEP-01/376/2009
|
DP2-Road P2 and other roads which are classified as
primary/district distributor roads
|
Monthly EM&A Report (Mar
2020)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1612015_content.html
|
|
|
|
FEP-01/376/2009
|
DP2-Road P2 and other roads which are classified as
primary/district distributor roads
|
Quarterly EM&A Report (Nov 2019 to Jan
2020)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1612015_content.html
|
|
|
|
FEP-02/376/2009
|
DP2-Road P2 and other roads which are classified as primary/district
distributor roads
|
Monthly EM&A Report (Mar
2020)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1702016_content.html
|
|
|
|
FEP-02/376/2009
|
DP2-Road P2 and other roads which are classified as
primary/district distributor roads
|
Quarterly EM&A Report (Nov 2019 to Jan
2020)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1702016_content.html
|
|
|
|
EP-356/2009
|
Wan Chai Development Phase II and Central-Wan Chai Bypass
|
Monthly
EM&A Report (Mar 2020)(HY/2019/18)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3562009_content.html
|
|
|
|
FEP-03/356/2009
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Wan Chai East
|
Monthly
EM&A Report (Mar 2020)(HY/2019/18)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1052010_content.html
|
|
|
|
FEP-04/356/2009
|
Central - Wan Chai Bypass - Tunnel (Causeway Bay Typhoon
shelter section) Contract No. HY/2009/15
- Marine Works
|
Monthly
EM&A Report (Mar 2020)(HY/2019/18)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1172010_content.html
|
|
|
|
FEP-07/356/2009
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Wan Chai West (Contract No. HK/2012/08) - Marine Work
|
Monthly
EM&A Report (Mar 2020)(HY/2019/18)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1492013_content.html
|
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report (DC/2009/10)(Mar
2020)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report (DE/2018/17)(Mar 2020)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report (DC/2009/24)(Mar 2020)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Quarterly EM&A Report(DE/2018/17)(Dec 2019 to Feb
2020)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
|
EP-518/2016
|
Conversion of the Former French Mission Building for
Accommodation Use by Law-related Organisation(s) and Related Purposes
|
IEC Monthly Audit Report For (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/aep/ep5182016_content.html
|
|
|
|
EP-518/2016
|
Conversion of the Former French Mission Building for Accommodation
Use by Law-related Organisation(s) and Related Purposes
|
IEC Monthly Audit Report For (Feb 2020)
|
https://www.epd.gov.hk/eia/english/register/aep/ep5182016_content.html
|
|
|
|
EP-518/2016
|
Conversion of the Former French Mission Building for
Accommodation Use by Law-related Organisation(s) and Related Purposes
|
IEC Monthly Audit Report For (Jan 2020)
|
https://www.epd.gov.hk/eia/english/register/aep/ep5182016_content.html
|
|
|
|
- Wan Chai District
|
|
|
|
EP-122/2002/E
|
Central Reclamation Phase III
|
Monthly EM&A Report (Mar 2020) (HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4832015_content.html
|
|
|
|
EP-122/2002/E
|
Central Reclamation Phase III
|
Quarterly EM&A Report (Nov 2019 to Jan 2020)
(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4832015_content.html
|
|
|
|
EP-364/2009/G
|
Central-Wanchai Bypass (CWB) including its road tunnel
and slip roads
|
Monthly EM&A Report (Mar 2020)(HK/2015/01)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5652019_content.html
|
|
|
|
FEP-01/364/2009
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Wan Chai East(CWB Tunnel)
|
Monthly EM&A Report (Mar 2020)(HK/2015/01)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1062010_content.html
|
|
|
|
FEP-05/364/2009/A
|
Central - Wan Chai Bypass - Central Interchange (Contract
No. HY/2009/18)
|
Monthly EM&A Report (Mar 2020)(HK/2015/01)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1162010_content.html
|
|
|
|
FEP-06/364/2009/A
|
Central - Wan Chai Bypass - Central Interchange (Contract
No. HY/2009/18)
|
Monthly EM&A Report (Mar 2020)(HK/2015/01)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1182010_content.html
|
|
|
|
FEP-07/364/2009/G
|
Central-Wanchai Bypass (CWB) including
its road tunnel and slip roads
|
Monthly EM&A Report (Mar 2020)(HK/2015/01)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5662019_content.html
|
|
|
|
FEP-09/364/2009/B
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Wan Chai West (Contract No. HK/2012/08) - Tunnel Work
|
Monthly EM&A Report (Mar 2020)(HK/2015/01)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1442013_content.html
|
|
|
|
FEP-10/364/2009/B
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Wan Chai West (Contract No. HK/2012/08) - Tunnel Work
|
Monthly EM&A Report (Mar 2020)(HK/2015/01)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1482013_content.html
|
|
|
|
FEP-11/364/2009/E
|
Central - Wan Chai Bypass - Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning (Contract No.
HY/2011/08)
|
Monthly EM&A Report (Mar 2020)(HK/2015/01)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5132016_content.html
|
|
|
|
FEP-12/364/2009/D
|
Central-Wanchai Bypass (CWB) including its road tunnel
and slip roads
|
Monthly EM&A Report (Mar 2020)(HK/2015/01)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1712016_content.html
|
|
|
|
EP-356/2009
|
Wan Chai Development Phase II and Central-Wan Chai Bypass
|
Monthly
EM&A Report (Mar 2020)(HY/2019/18)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3562009_content.html
|
|
|
|
FEP-03/356/2009
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Wan Chai East
|
Monthly
EM&A Report (Mar 2020)(HY/2019/18)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1052010_content.html
|
|
|
|
FEP-04/356/2009
|
Central - Wan Chai Bypass - Tunnel (Causeway Bay Typhoon
shelter section) Contract No. HY/2009/15
- Marine Works
|
Monthly
EM&A Report (Mar 2020)(HY/2019/18)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1172010_content.html
|
|
|
|
FEP-07/356/2009
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Wan Chai West (Contract No. HK/2012/08) - Marine Work
|
Monthly
EM&A Report (Mar 2020)(HY/2019/18)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1492013_content.html
|
|
|
|
EP-376/2009
|
DP2-Road P2 and other roads which are classified as primary/district
distributor roads
|
Monthly EM&A Report (Mar 2020)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3762009_content.html
|
|
|
|
EP-376/2009
|
DP2-Road P2 and other roads which are classified as
primary/district distributor roads
|
Quarterly EM&A Report (Nov 2019 to Jan
2020)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3762009_content.html
|
|
|
|
FEP-01/376/2009
|
DP2-Road P2 and other roads which are classified as
primary/district distributor roads
|
Monthly EM&A Report (Mar 2020)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1612015_content.html
|
|
|
|
FEP-01/376/2009
|
DP2-Road P2 and other roads which are classified as primary/district
distributor roads
|
Quarterly EM&A Report (Nov 2019 to Jan
2020)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1612015_content.html
|
|
|
|
FEP-02/376/2009
|
DP2-Road P2 and other roads which are classified as
primary/district distributor roads
|
Monthly EM&A Report (Mar 2020)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1702016_content.html
|
|
|
|
FEP-02/376/2009
|
DP2-Road P2 and other roads which are classified as
primary/district distributor roads
|
Quarterly EM&A Report (Nov 2019 to Jan
2020)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1702016_content.html
|
|
|
|
EP-436/2012/F
|
Shatin to Central Link - Hung Hom to Admiralty Section
|
Monthly EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5562018_content.html
|
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report (DC/2009/10)(Mar
2020)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report (DE/2018/17)(Mar 2020)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report (DC/2009/24)(Mar 2020)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Quarterly EM&A Report(DE/2018/17)(Dec 2019 to Feb
2020)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
|
- Eastern District
|
|
|
|
EP-122/2002/E
|
Central Reclamation Phase III
|
Monthly EM&A Report (Mar 2020) (HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4832015_content.html
|
|
|
|
EP-122/2002/E
|
Central Reclamation Phase III
|
Quarterly EM&A Report (Nov 2019 to Jan 2020)
(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4832015_content.html
|
|
|
|
EP-364/2009/G
|
Central-Wanchai Bypass (CWB) including its road tunnel
and slip roads
|
Monthly EM&A Report (Mar 2020)(HK/2015/01)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5652019_content.html
|
|
|
|
FEP-01/364/2009
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Wan Chai East(CWB Tunnel)
|
Monthly EM&A Report (Mar 2020)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1062010_content.html
|
|
|
|
FEP-05/364/2009/A
|
Central - Wan Chai Bypass - Central Interchange (Contract
No. HY/2009/18)
|
Monthly EM&A Report (Mar 2020)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1162010_content.html
|
|
|
|
FEP-06/364/2009/A
|
Central - Wan Chai Bypass - Central Interchange (Contract
No. HY/2009/18)
|
Monthly EM&A Report (Mar 2020)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1182010_content.html
|
|
|
|
FEP-07/364/2009/G
|
Central-Wanchai Bypass (CWB)
including its road tunnel and slip roads
|
Monthly EM&A Report (Mar 2020)(HK/2015/01)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5662019_content.html
|
|
|
|
FEP-09/364/2009/B
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Wan Chai West (Contract No. HK/2012/08) - Tunnel Work
|
Monthly EM&A Report (Mar 2020)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1442013_content.html
|
|
|
|
FEP-10/364/2009/B
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Wan Chai West (Contract No. HK/2012/08) - Tunnel Work
|
Monthly EM&A Report (Mar 2020)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1482013_content.html
|
|
|
|
FEP-11/364/2009/E
|
Central - Wan Chai Bypass - Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning (Contract No.
HY/2011/08)
|
Monthly EM&A Report (Mar 2020)(HK/2015/01)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5132016_content.html
|
|
|
|
FEP-12/364/2009/D
|
Central-Wanchai Bypass (CWB) including its road tunnel
and slip roads
|
Monthly EM&A Report (Mar 2020)(HK/2015/01)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1712016_content.html
|
|
|
|
EP-356/2009
|
Wan Chai Development Phase II and Central-Wan Chai Bypass
|
Monthly
EM&A Report (Mar 2020)(HY/2019/18)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3562009_content.html
|
|
|
|
FEP-03/356/2009
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Wan Chai East
|
Monthly
EM&A Report (Mar 2020)(HY/2019/18)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1052010_content.html
|
|
|
|
FEP-04/356/2009
|
Central - Wan Chai Bypass - Tunnel (Causeway Bay Typhoon
shelter section) Contract No. HY/2009/15
- Marine Works
|
Monthly
EM&A Report (Mar 2020)(HY/2019/18)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1172010_content.html
|
|
|
|
FEP-07/356/2009
|
Wan Chai Development Phase II - Central - Wan Chai Bypass
at Wan Chai West (Contract No. HK/2012/08) - Marine Work
|
Monthly
EM&A Report (Mar 2020)(HY/2019/18)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1492013_content.html
|
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report (DC/2009/10)(Mar
2020)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report (DE/2018/17)(Mar 2020)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report (DC/2009/24)(Mar 2020)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Quarterly EM&A Report(DE/2018/17)(Dec 2019 to Feb
2020)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
|
EP-458/2013/C
|
Tseung Kwan O – Lam Tin Tunnel and Associated Works
|
Monthly EM&A Report (Mar 2020)(version 1.0)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5272016_content.html
|
|
|
|
EP-458/2013/C
|
Tseung Kwan O – Lam Tin Tunnel and Associated Works
|
Quarterly EM&A Report (Nov 2019 to Jan 2020)(version
1.0)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5272016_content.html
|
|
|
|
EP-459/2013
|
Cross Bay Link, Tseung Kwan O
|
Monthly EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/aep/ep4592013_content.html
|
|
|
|
FEP-01/376/2009
|
DP2-Road P2 and other roads which are classified as
primary/district distributor roads
|
Monthly EM&A Report (Mar 2020)(HK/2015/01)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1612015_content.html
|
|
|
|
FEP-01/376/2009
|
DP2-Road P2 and other roads which are classified as
primary/district distributor roads
|
Quarterly EM&A Report (Nov 2019 to Jan
2020)(HK/2015/01)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1612015_content.html
|
|
|
|
FEP-02/376/2009
|
DP2-Road P2 and other roads which are classified as primary/district
distributor roads
|
Monthly EM&A Report (Mar 2020)(HK/2015/01)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1702016_content.html
|
|
|
|
FEP-02/376/2009
|
DP2-Road P2 and other roads which are classified as
primary/district distributor roads
|
Quarterly EM&A Report (Nov 2019 to Jan
2020)(HK/2015/01)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1702016_content.html
|
|
|
|
- Southern District
|
|
|
|
EP-487/2014/A
|
Tai Shue Wan Development at Ocean Park
|
Monthly EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5392017_content.html
|
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report (DC/2009/10)(Mar
2020)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report (DE/2018/17)(Mar 2020)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report (DC/2009/24)(Mar 2020)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Quarterly EM&A Report(DE/2018/17)(Dec 2019 to Feb
2020)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
|
EP-537/2017
|
Proposed Extension of Academic Block, The Swire Institute
of Marine Science, Faculty of Science, The University of Hong Kong, Cape
D’Aguilar Road, Shek O
|
Monthly EM&A Report No.30
|
http://www.epd.gov.hk/eia/8english/register/aep/ep5372017_content.html
|
|
|
|
- Kowloon City District
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Monthly EM&A Report (Mar
2020)(KL/2016/05)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Monthly EM&A Report (Mar 2020)(KL/2012/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Quarterly EM&A Report (Dec 2019 to Feb
2020)(KL/2014/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Monthly EM&A Report (Mar
2020)(ED/2018/01)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Monthly EM&A Report (Mar
2020)(KL/2014/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Submission of Baseline Monitoring Report
(Version 1.7)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Monthly EM&A Report (Mar
2020)(KL/2014/01)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Quarterly EM&A Report (Jan 2020 to Mar
2020)(KL/2014/01)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Quarterly EM&A Report (Jan 2020 to Mar
2020)(KL/2016/05)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
EP-344/2009
|
New Sewage Pumping Stations Serving Kai Tak Development
|
Monthly EM&A Report (Mar
2020)(KL/2012/03)
|
https://www.epd.gov.hk/eia/english/register/aep/ep3442009.html
|
|
|
|
EP-339/2009/A
|
Decommissioning of the Remaining Parts (EX_GFS Building,
Radar Station and Hong Kong Aviation Club) of the Former Kai Tak Airport
|
Quarterly EM&A Report (Dec 2019 to Feb
2020)(KL/2014/03)
|
https://www.epd.gov.hk/eia/english/register/index8/vep2882009_content.html
|
|
|
|
EP-339/2009/A
|
Decommissioning of the Remaining Parts (EX_GFS Building,
Radar Station and Hong Kong Aviation Club) of the Former Kai Tak Airport
|
Monthly EM&A Report (Mar
2020)(KL/2014/03)
|
https://www.epd.gov.hk/eia/english/register/index8/vep2882009_content.html
|
|
|
|
EP-437/2012/A
|
Shatin to Central Link - Mong Kok East to Hung Hom
Section
|
Monthly EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5352017_content.html
|
|
|
|
EP-438/2012/K
|
Shatin to Central Link - Tai Wai to Hung Hom Section
|
Monthly EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5062016_content.html
|
|
|
|
EP-451/2013
|
Trunk Road T2
|
Proposal for Relocation of Monitoring
Location KTD2b (KL/2014/03)
|
https://www.epd.gov.hk/eia/english/register/aep/ep4512013_content.html
|
|
|
|
EP-451/2013
|
Trunk Road T2
|
Monthly EM&A Report (Mar
2020)(KL/2014/03)
|
https://www.epd.gov.hk/eia/english/register/aep/ep4512013_content.html
|
|
|
|
EP-451/2013
|
Trunk Road T2
|
Quarterly EM&A Report (Dec 2019 to Feb
2020)(KL/2014/03)
|
https://www.epd.gov.hk/eia/english/register/aep/ep4512013_content.html
|
|
|
|
EP-451/2013
|
Trunk Road T2
|
Monthly EM&A Report (Mar 2020)(KL/2014/03)
|
https://www.epd.gov.hk/eia/english/register/aep/ep4512013_content.html
|
|
|
|
EP-445/2013
|
Kai Tak Development – Roads D3A & D4A
|
Monthly EM&A Report (Mar 2020)(ED/2018/01)
|
https://www.epd.gov.hk/eia/english/register/aep/ep4452012_content.html
|
|
|
|
EP-445/2013/A
|
Kai Tak Development – Roads D3A & D4A
|
Monthly EM&A Report (Mar 2020)(ED/2018/01)
|
https://www.epd.gov.hk/eia/english/register/index8/vep4492014_content.html
|
|
|
|
EP-445/2013/A
|
Kai Tak Development – Roads D3A & D4A
|
Monthly EM&A Report (Mar 2020)(KL/2014/01)
|
https://www.epd.gov.hk/eia/english/register/index8/vep4492014_content.html
|
|
|
|
EP-445/2013/A
|
Kai Tak Development – Roads D3A & D4A
|
Quarterly EM&A Report (Jan 2020 to Mar
2020)(KL/2014/01)
|
https://www.epd.gov.hk/eia/english/register/index8/vep4492014_content.html
|
|
|
|
EP-544/2017
|
Kai Tak Sports Park
|
EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/aep/ep5442017_content.html
|
|
|
|
EP-457/2013/C
|
Central Kowloon Route
|
Monthly EM&A Report (Mar 2020) (HY/2014/08)
|
http://www.epd.gov.hk/eia/english/register/index8/vep5172016_content.html
|
|
|
|
EP-457/2013/C
|
Central Kowloon Route
|
Monthly EM&A Report (Mar 2020) (HY/2014/07)
|
http://www.epd.gov.hk/eia/english/register/index8/vep5172016_content.html
|
|
|
|
EP-457/2013/C
|
Central Kowloon Route
|
Monthly EM&A Report (Mar 2020) (HY/2014/20)
|
http://www.epd.gov.hk/eia/english/register/index8/vep5172016_content.html
|
|
|
|
EP-457/2013/C
|
Central Kowloon Route
|
Monthly EM&A Report (Mar 2020) (HY/2018/02)
|
http://www.epd.gov.hk/eia/english/register/index8/vep5172016_content.html
|
|
|
|
EP-457/2013/C
|
Central Kowloon Route
|
Monthly EM&A Report (Mar 2020) (HY/2018/08)
|
http://www.epd.gov.hk/eia/english/register/index8/vep5172016_content.html
|
|
|
|
FEP-01/457/2013/C
|
Central Kowloon Route - Kai Tak West
|
Monthly EM&A Report (Mar 2020) (HY/2014/08)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1822018_content.html
|
|
|
|
FEP-01/457/2013/C
|
Central Kowloon Route - Kai Tak West
|
Monthly EM&A Report (Mar 2020) (HY/2014/07)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1822018_content.html
|
|
|
|
FEP-01/457/2013/C
|
Central Kowloon Route - Kai Tak West
|
Monthly EM&A Report (Mar 2020) (HY/2014/20)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1822018_content.html
|
|
|
|
FEP-01/457/2013/C
|
Central Kowloon Route - Kai Tak West
|
Monthly EM&A Report (Mar 2020) (HY/2018/02)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1822018_content.html
|
|
|
|
FEP-02/457/2013/C
|
Central Kowloon Route - Yau Ma Tei East
|
Monthly EM&A Report (Mar 2020) (HY/2014/08)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1832018_content.html
|
|
|
|
FEP-02/457/2013/C
|
Central Kowloon Route - Yau Ma Tei East
|
Monthly EM&A Report (Mar 2020) (HY/2014/07)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1832018_content.html
|
|
|
|
FEP-02/457/2013/C
|
Central Kowloon Route - Yau Ma Tei East
|
Monthly EM&A Report (Mar 2020) (HY/2014/20)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1832018_content.html
|
|
|
|
FEP-02/457/2013/C
|
Central Kowloon Route - Yau Ma Tei East
|
Monthly EM&A Report (Mar 2020) (HY/2018/02)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1832018_content.html
|
|
|
|
- Kwun Tong District
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Monthly EM&A Report (Mar
2020)(KL/2016/05)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Monthly EM&A Report (Mar
2020)(KL/2012/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Quarterly EM&A Report (Dec 2019 to Feb
2020)(KL/2014/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Monthly EM&A Report (Mar
2020)(ED/2018/01)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Monthly EM&A Report (Mar
2020)(KL/2014/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Submission of Baseline Monitoring Report
(Version 1.7)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Monthly EM&A Report (Mar
2020)(KL/2014/01)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Quarterly EM&A Report (Jan 2020 to Mar
2020)(KL/2014/01)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Quarterly EM&A Report (Jan 2020 to Mar
2020)(KL/2016/05)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
EP-344/2009
|
New Sewage Pumping Stations Serving Kai Tak Development
|
Monthly EM&A Report (Mar
2020)(KL/2012/03)
|
https://www.epd.gov.hk/eia/english/register/aep/ep3442009.html
|
|
|
|
EP-339/2009/A
|
Decommissioning of the Remaining Parts (EX_GFS Building,
Radar Station and Hong Kong Aviation Club) of the Former Kai Tak Airport
|
Quarterly EM&A Report (Dec 2019 to Feb
2020)(KL/2014/03)
|
https://www.epd.gov.hk/eia/english/register/index8/vep2882009_content.html
|
|
|
|
EP-339/2009/A
|
Decommissioning of the Remaining Parts (EX_GFS Building,
Radar Station and Hong Kong Aviation Club) of the Former Kai Tak Airport
|
Monthly EM&A Report (Mar
2020)(KL/2014/03)
|
https://www.epd.gov.hk/eia/english/register/index8/vep2882009_content.html
|
|
|
|
EP-458/2013/C
|
Tseung Kwan O – Lam Tin Tunnel and Associated Works
|
Monthly EM&A Report (Mar 2020)(version
1.0)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5272016_content.html
|
|
|
|
EP-458/2013/C
|
Tseung Kwan O – Lam Tin Tunnel and Associated Works
|
Quarterly EM&A Report (Nov 2019 to Jan
2020)(version 1.0)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5272016_content.html
|
|
|
|
EP-513/2016
|
Development of Anderson Road Quarry site - Road
Improvement Works
|
Monthly EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/aep/ep5132016_content.html
|
|
|
|
EP-544/2017
|
Kai Tak Sports Park
|
EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/aep/ep5442017_content.html
|
|
|
|
EP-457/2013/C
|
Central Kowloon Route
|
Monthly EM&A Report (Mar 2020) (HY/2014/08)
|
http://www.epd.gov.hk/eia/english/register/index8/vep5172016_content.html
|
|
|
|
EP-457/2013/C
|
Central Kowloon Route
|
Monthly EM&A Report (Mar 2020) (HY/2014/07)
|
http://www.epd.gov.hk/eia/english/register/index8/vep5172016_content.html
|
|
|
|
EP-457/2013/C
|
Central Kowloon Route
|
Monthly EM&A Report (Mar 2020) (HY/2014/20)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5172016_content.html
|
|
|
|
EP-457/2013/C
|
Central Kowloon Route
|
Monthly EM&A Report (Mar 2020) (HY/2018/02)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5172016_content.html
|
|
|
|
EP-457/2013/C
|
Central Kowloon Route
|
Monthly EM&A Report (Mar 2020) (HY/2018/08)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5172016_content.html
|
|
|
|
FEP-01/457/2013/C
|
Central Kowloon Route - Kai Tak West
|
Monthly EM&A Report (Mar 2020) (HY/2014/08)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1822018_content.html
|
|
|
|
FEP-01/457/2013/C
|
Central Kowloon Route - Kai Tak West
|
Monthly EM&A Report (Mar 2020) (HY/2014/07)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1822018_content.html
|
|
|
|
FEP-01/457/2013/C
|
Central Kowloon Route - Kai Tak West
|
Monthly EM&A Report (Mar 2020) (HY/2014/20)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1822018_content.html
|
|
|
|
FEP-01/457/2013/C
|
Central Kowloon Route - Kai Tak West
|
Monthly EM&A Report (Mar 2020) (HY/2018/02)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1822018_content.html
|
|
|
|
FEP-02/457/2013/C
|
Central Kowloon Route - Yau Ma Tei East
|
Monthly EM&A Report (Mar 2020) (HY/2014/08)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1832018_content.html
|
|
|
|
FEP-02/457/2013/C
|
Central Kowloon Route - Yau Ma Tei East
|
Monthly EM&A Report (Mar 2020) (HY/2014/07)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1832018_content.html
|
|
|
|
FEP-02/457/2013/C
|
Central Kowloon Route - Yau Ma Tei East
|
Monthly EM&A Report (Mar 2020) (HY/2014/20)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1832018_content.html
|
|
|
|
FEP-02/457/2013/C
|
Central Kowloon Route - Yau Ma Tei East
|
Monthly EM&A Report (Mar 2020) (HY/2018/02)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1832018_content.html
|
|
|
|
- Sham Shui Po District
|
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report (DC/2009/10)(Mar
2020)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report (DE/2018/17)(Mar 2020)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report (DC/2009/24)(Mar 2020)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Quarterly EM&A Report(DE/2018/17)(Dec 2019 to Feb
2020)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
|
|
- Wong Tai Sin District
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Monthly EM&A Report (Mar
2020)(KL/2016/05)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Monthly EM&A Report (Mar
2020)(KL/2012/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Quarterly EM&A Report (Dec 2019 to Feb
2020)(KL/2014/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Monthly EM&A Report (Mar 2020)(ED/2018/01)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Monthly EM&A Report (Mar
2020)(KL/2014/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Submission of Baseline Monitoring Report
(Version 1.7)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Monthly EM&A Report (Mar
2020)(KL/2014/01)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Quarterly EM&A Report (Jan 2020 to Mar
2020)(KL/2014/01)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai Tak Development
|
Quarterly EM&A Report (Jan 2020 to Mar
2020)(KL/2016/05)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
|
|
EP-344/2009
|
New Sewage Pumping Stations Serving Kai Tak Development
|
Monthly EM&A Report (Mar
2020)(KL/2012/03)
|
https://www.epd.gov.hk/eia/english/register/aep/ep3442009.html
|
|
|
|
EP-339/2009/A
|
Decommissioning of the Remaining Parts (EX_GFS Building,
Radar Station and Hong Kong Aviation Club) of the Former Kai Tak Airport
|
Quarterly EM&A Report (Dec 2019 to Feb
2020)(KL/2014/03)
|
https://www.epd.gov.hk/eia/english/register/index8/vep2882009_content.html
|
|
|
|
EP-339/2009/A
|
Decommissioning of the Remaining Parts (EX_GFS Building, Radar
Station and Hong Kong Aviation Club) of the Former Kai Tak Airport
|
Monthly EM&A Report (Mar
2020)(KL/2014/03)
|
https://www.epd.gov.hk/eia/english/register/index8/vep2882009_content.html
|
|
|
|
EP-438/2012/K
|
Shatin to Central Link - Tai Wai to Hung Hom Section
|
Monthly EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5062016_content.html
|
|
|
|
EP-544/2017
|
Kai Tak Sports Park
|
EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/aep/ep5442017_content.html
|
|
|
|
- Yau Tsim Mong District
|
|
|
|
EP-436/2012/F
|
Shatin to Central Link - Hung Hom to Admiralty Section
|
Monthly EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5562018_content.html
|
|
|
|
EP-437/2012/A
|
Shatin to Central Link - Mong Kok East to Hung Hom
Section
|
Monthly EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5352017_content.html
|
|
|
|
EP-438/2012/K
|
Shatin to Central Link - Tai Wai to Hung Hom Section
|
Monthly EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5062016_content.html
|
|
|
|
EP-453/2013/B
|
Underpass Road and Austin Road Flyover Serving the West
Kowloon Cultural District
|
Monthly EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5032016_content.html
|
|
|
|
EP-455/2013
|
Proposed Road Improvement Works in West Kowloon
Reclamation Development Phase 1
|
Monthly EM&A Report (Mar 2020)
|
https://www.epd.gov.hk/eia/english/register/aep/ep4552013_content.html
|
|
|
|
EP-457/2013/C
|
Central Kowloon Route
|
Monthly EM&A Report (Mar 2020) (HY/2014/08)
|
http://www.epd.gov.hk/eia/english/register/index8/vep5172016_content.html
|
|
|
|
EP-457/2013/C
|
Central Kowloon Route
|
Monthly EM&A Report (Mar 2020) (HY/2014/07)
|
http://www.epd.gov.hk/eia/english/register/index8/vep5172016_content.html
|
|
|
|
EP-457/2013/C
|
Central Kowloon Route
|
Monthly EM&A Report (Mar 2020) (HY/2014/20)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5172016_content.html
|
|
|
|
EP-457/2013/C
|
Central Kowloon Route
|
Monthly EM&A Report (Mar 2020) (HY/2018/02)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5172016_content.html
|
|
|
|
EP-457/2013/C
|
Central Kowloon Route
|
Monthly EM&A Report (Mar 2020) (HY/2018/08)
|
https://www.epd.gov.hk/eia/english/register/index8/vep5172016_content.html
|
|
|
|
FEP-01/457/2013/C
|
Central Kowloon Route - Kai Tak West
|
Monthly EM&A Report (Mar 2020) (HY/2014/08)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1822018_content.html
|
|
|
|
FEP-01/457/2013/C
|
Central Kowloon Route - Kai Tak West
|
Monthly EM&A Report (Mar 2020) (HY/2014/07)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1822018_content.html
|
|
|
|
FEP-01/457/2013/C
|
Central Kowloon Route - Kai Tak West
|
Monthly EM&A Report (Mar 2020) (HY/2014/20)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1822018_content.html
|
|
|
|
FEP-01/457/2013/C
|
Central Kowloon Route - Kai Tak West
|
Monthly EM&A Report (Mar 2020) (HY/2018/02)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1822018_content.html
|
|
|
|
FEP-02/457/2013/C
|
Central Kowloon Route - Yau Ma Tei East
|
Monthly EM&A Report (Mar 2020) (HY/2014/08)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1832018_content.html
|
|
|
|
FEP-02/457/2013/C
|
Central Kowloon Route - Yau Ma Tei East
|
Monthly EM&A Report (Mar 2020) (HY/2014/07)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1832018_content.html
|
|
|
|
FEP-02/457/2013/C
|
Central Kowloon Route - Yau Ma Tei East
|
Monthly EM&A Report (Mar 2020) (HY/2014/20)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1832018_content.html
|
|
|
|
FEP-02/457/2013/C
|
Central Kowloon Route - Yau Ma Tei East
|
Monthly EM&A Report (Mar 2020) (HY/2018/02)
|
https://www.epd.gov.hk/eia/english/register/index7/fep1832018_content.html
|
|
|
|
EP-523/2016
|
Proposed Sewage Pumping Station and Dry Weather Flow
Interceptor at Cherry Street Box Culvert
|
Submission of Monthly EM&A Report No.27
|
https://www.epd.gov.hk/eia/english/register/aep/ep5232016_content.html
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|