Monthly Update of Documents Uploaded
Documents Uploaded to the EIAO
Website
|
(for the period between 16 Oct 2015 to 15 Nov 2015)
|
|
Application
No. / Permit No.
|
Project
Title
|
Document
Name
|
Hyperlink
|
|
Application
for EIA Study Brief
|
|
ESB-289/2015
|
Proposed Interim Sewage Treatment Plant and
Effluent Reuse Facility at Wo Shang Wai, Yuen Long
|
EIA Study Brief
|
http://www.epd.gov.hk/eia/register/study/latest/esb-289.pdf
|
|
ESB-290/2015
|
Planning, Engineering and Architectural Study
for Topside Development at Hong Kong Boundary Crossing Facilities Island of
Hong Kong-Zhuhai- Macao Bridge – Feasibility Study
|
Project Profile
|
http://www.epd.gov.hk/eia/register/profile/latest/esb290/esb290.pdf
|
|
Application
for Permission to Apply Directly for Environmental Permit
|
|
NIL
|
|
Application
for Approval of EIA Report
|
|
EIA-229/2015
|
Desalination Plant at Tseung
Kwan O
|
Approval
Conditions
|
http://www.epd.gov.hk/eia/register/report/conditions/aeiar2292015.pdf
|
|
Application
for Environmental Permit
|
|
NIL
|
|
Application
for Variation of an Environmental Permit
|
|
VEP-484/2015
|
Shatin to Central Link - Tai Wai to Hung
Hom Section
|
Environmental
Permit issued (EP-438/2012/I)
|
http://www.epd.gov.hk/eia/register/permit/latest/vep4842015.htm
|
|
Application
for Further Environmental Permit
|
|
NIL
|
|
Submission
as required by Environmental Permit Condition - Design / Environmental
Submissions
|
|
EP-427/2011/A
|
Dredging, Management and Capping of
Contaminated Sediment Disposal Facility to the South of The Brothers
|
Monthly Progress Report (Aug 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep3492011_content.html
|
|
EP-427/2011/A
|
Dredging, Management and Capping of
Contaminated Sediment Disposal Facility to the South of The Brothers
|
Monthly Progress Report (Sep 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep3492011_content.html
|
|
FEP-01/474/2013
|
NENT - Shek Wu Hui Sewage Treatment Works - Further Expansion at Fanling North New Development Area
|
Baseline Monitoring Report
|
http://www.epd.gov.hk/eia/english/register/index7/fep1522014_content.html
|
|
EP-312/2008/A
|
Disposal of Contaminated Sediment - Dredging,
Management and Capping of sediment Disposal Facility at Sha
Chau
|
Monthly Progress Report(Jul 2011)
|
http://www.epd.gov.hk/eia/english/register/index8/vep2742009_content.html
|
|
Submission
as required by Environmental Permit Condition - EM&A Reports
|
|
|
Island District
|
Central & Western District
|
|
|
|
North District
|
Wan Chai District
|
|
|
|
Sai Kung District
|
Eastern District
|
|
|
|
Sha Tin District
|
Southern District
|
|
|
|
Tai Po District
|
Kowloon City District
|
|
|
|
Tsuen Wan District
|
Kwun Tong District
|
|
|
|
Tuen Mun District
|
Sham Shui Po District
|
|
|
|
Yuen Long District
|
Wong Tai Sin District
|
|
|
|
Kwai Tsing District
|
Yau Tsim Mong District
|
|
|
- Island District
|
|
EP-354/2009/D
|
Tuen Mun - Chek Lap Kok Link
|
Quarterly Environmental Monitoring and Audit Report (May to Jul
2015)(HY/2013/12)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4692015_content.html
|
|
EP-354/2009/D
|
Tuen Mun - Chek Lap Kok Link
|
Monthly Environmental Monitoring and Audit Report (Aug
2015)(HY/2013/12)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4692015_content.html
|
|
EP-354/2009/D
|
Tuen Mun - Chek Lap Kok Link
|
Monthly Environmental Monitoring and Audit
Report (Sep 2015)(HY/2012/08)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4692015_content.html
|
|
EP-354/2009/D
|
Tuen Mun - Chek Lap Kok Link
|
Monthly Environmental Monitoring and Audit
Report (Sep 2015)(HY/2012/07)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4692015_content.html
|
|
EP-354/2009/D
|
Tuen Mun - Chek Lap Kok Link
|
Monthly Environmental Monitoring and Audit
Report (Aug 2015)(HY/2010/02)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4692015_content.html
|
|
EP-083/2000
|
Conversion of Two Existing Gas Turbines
(GT5 & GT7) into a Combined Cycle Unit
|
Monthly Environmental Monitoring And Audit
Report (Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/aep/ep0832000_content.html
|
|
EP-071/2000/C
|
1,800MW Gas-Fired Power Station at Lamma Extension
|
Monthly Environmental Monitoring and Audit
Report (Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep1742005_content.html
|
|
EP-392/2010
|
Improvement of Fresh Water Supply to Cheung
Chau
|
Monthly EM&A Report (Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3922010_content.html
|
|
EP-452/2013
|
Temporary Sewage Pumping Station Ancillary to
Tung Chung Area 56 Public Housing Development
|
Monthly EM&A Report (Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/aep/ep4522013_content.html
|
|
EP-452/2013
|
Temporary Sewage Pumping Station Ancillary
to Tung Chung Area 56 Public Housing Development
|
Monthly EM&A Report (Sep
2015)
|
http://www.epd.gov.hk/eia/english/register/aep/ep4522013_content.html
|
|
EP- 01/097/2001/C
|
Water Recreation Centre at Penny's Bay
(part & remaining part)
|
Monthly Environmental Monitoring and Audit
Report (No. 121)
|
http://www.epd.gov.hk/eia/english/register/index8/vep1992005_content.html
|
|
EP-01/059/2000/C
|
The Theme Park at Penny's Bay, Lantau
|
120th Monthly EM&A Report (12 Aug 2015
to 11 Sep 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep3782012_content.html
|
|
FEP-01/395/2010/B
|
Organic Waste Treatment Facilities, Phase I
|
Third
Monthly EM&A Report
|
http://www.epd.gov.hk/eia/english/register/index7/fep1602015_content.html
|
|
FEP-01/395/2010/B
|
Organic Waste Treatment Facilities, Phase I
|
Forth
Monthly EM&A Report
|
http://www.epd.gov.hk/eia/english/register/index7/fep1602015_content.html
|
|
EP-353/2009/I
|
Hong Kong - Zhuhai
- Macao Bridge Hong Kong Boundary Crossing Facilities
|
Monthly Environmental Monitoring and Audit
Report (Aug 2015)(HY/2011/03)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4772015_content.html
|
|
EP-353/2009/I
|
Hong Kong - Zhuhai
- Macao Bridge Hong Kong Boundary Crossing Facilities
|
Monthly Environmental Monitoring and Audit
Report (Aug 2015)(HY/2013/02)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4772015_content.html
|
|
EP-353/2009/I
|
Hong Kong - Zhuhai
- Macao Bridge Hong Kong Boundary Crossing Facilities
|
Quarterly Environmental Monitoring and
Audit Report (Mar 2015 to May 2015)(HY/2011/03)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4772015_content.html
|
|
EP-353/2009/I
|
Hong Kong - Zhuhai
- Macao Bridge Hong Kong Boundary Crossing Facilities
|
Monthly Environmental Monitoring and Audit
Report (Aug 2015)(HY/2013/04)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4772015_content.html
|
|
EP-353/2009/I
|
Hong Kong - Zhuhai
- Macao Bridge Hong Kong Boundary Crossing Facilities
|
Monthly Environmental Monitoring and Audit
Report (Aug 2015)(HY/2013/01)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4772015_content.html
|
|
EP-353/2009/I
|
Hong Kong - Zhuhai
- Macao Bridge Hong Kong Boundary Crossing Facilities
|
Monthly Environmental Monitoring and Audit
Report (Aug 2015)(HY/2010/02)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4772015_content.html
|
|
EP-352/2009/D
|
Hong Kong - Zhuhai
- Macao Bridge Hong Kong Link Road
|
Monthly Environmental Monitoring and Audit
Report (Aug 2015)(HY/2011/03)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4592014_content.html
|
|
EP-352/2009/D
|
Hong Kong - Zhuhai
- Macao Bridge Hong Kong Link Road
|
Quarterly Environmental Monitoring and
Audit Report (Mar 2015 to May 2015)(HY/2011/03)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4592014_content.html
|
|
EP-352/2009/D
|
Hong Kong - Zhuhai
- Macao Bridge Hong Kong Link Road
|
Monthly EM&A Report(Aug 2015)
(HY/2011/09)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4592014_content.html
|
|
EP-287/2007
|
Lamma Power Station - Unit L2 Flue Gas
Desulphurization Plant Retrofit Project
|
Quarterly EM&A Report (Apr 2015 to Jun
2015)
|
http://www.epd.gov.hk/eia/english/register/aep/ep2872007_content.html
|
|
- North District
|
|
EP-404/2011/C
|
Liantang / Heung Yuen Wai
Boundary Control Point and Associated Works
|
Monthly EM&A Report (Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4662015_content.html
|
|
EP-277/2007/A
|
Drainage Improvements in Northern New
Territories - Package C
|
Quarterly EM&A Report (Jun 2015 to Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep3052009_content.html
|
|
EP-430/2011
|
Regulation of Shenzhen River Stage IV
|
Monthly EM&A Report(Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/aep/ep4302011_content.html
|
|
EP-430/2011
|
Regulation of Shenzhen River Stage IV
|
Quarterly EM&A Report (Jun 2015 to Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/aep/ep4302011_content.html
|
|
EP-436/2012/B
|
Shatin to Central Link - Hung Hom
to Admiralty Section
|
Monthly EM&A Report (Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4672015_content.html
|
|
EP-324/2008/C
|
Widening of Tolo
Highway/Fanling Highway between Island House
Interchange and Fanling
|
Monthly EM&A Report (Aug 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4702015_content.html
|
|
EP-436/2012/C
|
Shatin to Central Link - Hung Hom
to Admiralty Section
|
Monthly EM&A Report(Sep 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4822015_content.html
|
|
- Sai Kung
District
|
|
EP-134/2002/K
|
Fill Bank at Tseung
Kwan O Area 137
|
Monthly EM&A Report (Aug 2015)(CV/2013/06)
|
http://www.epd.gov.hk/eia/english/register/index8/vep3892013_content.html
|
|
EP-438/2012/H
|
Shatin to Central Link - Tai Wai
to Hung Hom Section
|
Monthly EM&A Report (Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4532014_content.html
|
|
EP-448/2013
|
Natural Terrain Hazard Mitigation Works at
Study Area No. 12NW-C/SA1 above Leung Fai Tin along Clear Water Bay Road, Sai Kung
|
Monthly EM&A Report (Aug 2015)
|
http://www.epd.gov.hk/eia/english/register/aep/ep4482013_content.html
|
|
EP-435/2011/A
|
Sewerage Works at Pik
Shui Sun Tsuen
|
Monthly EM&A Report (Aug 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4482014_content.html
|
|
- Sha Tin
District
|
|
EP-135/2002/J
|
Sha Tin New Town - Stage II TrunkRoad T3 and Associated Roadworks
|
Monthly Environmental Monitoring and Audit
Report (Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4282014_content.html
|
|
EP-438/2012/H
|
Shatin to Central Link - Tai Wai
to Hung Hom Section
|
Monthly EM&A Report (Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4532014_content.html
|
|
- Tai Po District
|
|
EP-303/2008
|
Drainage Improvement in Sha
Tin and Tai Po
|
Monthly EM&A Report (Aug
2015) (DC/2009/22)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3032008_content.html
|
|
EP-324/2008/C
|
Widening of Tolo
Highway/Fanling Highway between Island House
Interchange and Fanling
|
Monthly EM&A Report (Aug 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4702015_content.html
|
|
- Tsuen Wan District
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report (DC/2007/23)(Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly
EM&A Report (DC/2009/24)(Aug 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report (DC/2009/23)(Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report(DC/2007/23,DC/2009/10,DC/2009/17, DC/2009/18)(Aug 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Quarterly EM&A
Report(DC/2007/23,DC/2009/10,DC/2009/17, DC/2009/18,DC/2009/19)(Mar 2015 to
May 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
EP-349/2009/L
|
Hong Kong Section of Guangzhou - Shenzhen -
Hong Kong Express Rail Link
|
Monthly EM&A Report (Aug 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4392014_content.html
|
|
- Tuen Mun District
|
|
EP-354/2009/D
|
Tuen Mun - Chek Lap Kok Link
|
Quarterly Environmental Monitoring and
Audit Report (May to Jul 2015)(HY/2013/12)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4692015_content.html
|
|
EP-354/2009/D
|
Tuen Mun - Chek Lap Kok Link
|
Monthly Environmental Monitoring and Audit
Report (Aug 2015)(HY/2013/12)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4692015_content.html
|
|
EP-354/2009/D
|
Tuen Mun - Chek Lap Kok Link
|
Monthly Environmental Monitoring and Audit
Report (Sep 2015)(HY/2012/08)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4692015_content.html
|
|
EP-354/2009/D
|
Tuen Mun - Chek Lap Kok Link
|
Monthly Environmental Monitoring and Audit
Report (Sep 2015)(HY/2012/07)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4692015_content.html
|
|
EP-354/2009/D
|
Tuen Mun - Chek Lap Kok Link
|
Monthly Environmental Monitoring and Audit
Report (Aug 2015)(HY/2010/02)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4692015_content.html
|
|
EP-331/2009
|
Widening of Tsing
Lun Road, Tuen Mun
|
Monthly EM&A Report (Aug 2015)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3312009_content.html
|
|
EP-331/2009
|
Widening of Tsing
Lun Road, Tuen Mun
|
Quarterly EM&A Report (Jun 2015 to Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3312009_content.html
|
|
EP-381/2009
|
Tuen Mun Area 54
Sewage Pumping Station
|
Monthly EM&A Report (Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3812009_content.html
|
|
EP-210/2005/B
|
Expansion and Extension of Fill Bank at Tuen Mun Area 38
|
Monthly EM&A Report (Aug 2015)
(CV/2013/06)
|
http://www.epd.gov.hk/eia/english/register/index8/vep3952013_content.html
|
|
FEP-01/334/2009/A
|
Sludge Treatment Facilities
|
Final EM&A Report (Dec 2010 to Jun
2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep3452011_content.html
|
|
EP-349/2009/L
|
Hong Kong Section of Guangzhou - Shenzhen -
Hong Kong Express Rail Link
|
Monthly EM&A Report (Aug 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4392014_content.html
|
|
- Yuen Long District
|
|
FEP-24/004/1998/I
|
West Rail, Phase 1
|
Monthly EM&A Report (Aug 2015)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1382012_content.html
|
|
FEP-24/004/1998/I
|
West Rail, Phase 1
|
Monthly EM&A Report (Sep
2015)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1382012_content.html
|
|
EP-411/2011
|
Improvement to Pok
Oi Interchange
|
Monthly EM&A Report (Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/aep/ep4112011_content.html
|
|
EP-411/2011
|
Improvement to Pok
Oi Interchange
|
Quarterly EM&A Report (Jun 2015 to Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/aep/ep4112011_content.html
|
|
EP-490/2014
|
Drainage Works at Mai Po
|
Monthly EM&A Report(Aug 2015)
|
http://www.epd.gov.hk/eia/english/register/aep/ep4902014_content.html
|
|
EP-490/2014
|
Drainage Works at Mai Po
|
Monthly EM&A Report(Sep
2015)
|
http://www.epd.gov.hk/eia/english/register/aep/ep4902014_content.html
|
|
EP-349/2009/L
|
Hong Kong Section of Guangzhou - Shenzhen -
Hong Kong Express Rail Link
|
Monthly EM&A Report (Aug 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4392014_content.html
|
|
- Kwai Tsing District
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report (DC/2007/23)(Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly
EM&A Report (DC/2009/24)(Aug 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report (DC/2009/23)(Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report(DC/2007/23,DC/2009/10,DC/2009/17,
DC/2009/18)(Aug 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Quarterly EM&A
Report(DC/2007/23,DC/2009/10,DC/2009/17, DC/2009/18,DC/2009/19)(Mar 2015 to
May 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
EP-426/2011/A
|
Providing Sufficient Water Depth for Kwai Tsing Container Basin
and its Approach Channel
|
Monthly Environmental Monitoring &
Audit Report (Aug 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep3692012_content.html
|
|
EP-426/2011/A
|
Providing Sufficient Water Depth for Kwai Tsing Container Basin and
its Approach Channel
|
Monthly Environmental Monitoring &
Audit Report (Sep 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep3692012_content.html
|
|
EP-349/2009/L
|
Hong Kong Section of Guangzhou - Shenzhen -
Hong Kong Express Rail Link
|
Monthly EM&A Report (Aug 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4392014_content.html
|
|
- Central & Western District
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report (DC/2007/23)(Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly
EM&A Report (DC/2009/24)(Aug 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report (DC/2009/23)(Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report(DC/2007/23,DC/2009/10,DC/2009/17, DC/2009/18)(Aug 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Quarterly EM&A
Report(DC/2007/23,DC/2009/10,DC/2009/17, DC/2009/18,DC/2009/19)(Mar 2015 to
May 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
EP-313/2008/J
|
West Island Line
|
Monthly EM&A Report(Sep
2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4522014_content.html
|
|
EP-122/2002/D
|
Central Reclamation Phase III
|
Monthly EM&A Report (Aug 2015) (HK/2011/07)
|
http://www.epd.gov.hk/eia/english/register/index8/vep2972012_content.html
|
|
EP-407/2010/E
|
South Island Line (East)
|
Monthly EM&A Report(Sep
2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4512014_content.html
|
|
EP-407/2010/E
|
South Island Line (East)
|
Monthly EM&A Report(Oct
2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4512014_content.html
|
|
EP-376/2009
|
DP2-Road P2 and other roads which are classified
as primary/district distributor roads
|
Monthly EM&A Report (Aug
2015)(HK/2011/07)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3762009_content.html
|
|
EP-364/2009/C
|
Central-Wanchai
Bypass (CWB) including its road tunnel and slip roads
|
Monthly EM&A Report (Aug 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4432014_content.html
|
|
EP-364/2009/C
|
Central-Wanchai
Bypass (CWB) including its road tunnel and slip roads
|
Quarterly EM&A Report (Jun 2015 to Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4432014_content.html
|
|
EP-356/2009
|
Wan Chai
Development Phase II and Central-Wan Chai Bypass
|
Monthly EM&A Report (Aug
2015)(HK/2011/07)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3562009_content.html
|
|
EP-356/2009
|
Wan Chai
Development Phase II and Central-Wan Chai Bypass
|
Quarterly EM&A Report (Jun 2015 to Aug
2015)(HK/2011/07)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3562009_content.html
|
|
EP-436/2012/B
|
Shatin to Central Link - Hung Hom
to Admiralty Section
|
Monthly EM&A Report (Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4672015_content.html
|
|
EP-408/2011/B
|
Central Police Station Conservation and Revitalisation Project
|
Monthly EM&A Report (No.46)
|
http://www.epd.gov.hk/eia/english/register/index8/vep3572012_content.html
|
|
EP-408/2011/B
|
Central Police Station Conservation and Revitalisation Project
|
Monthly EM&A Report (No.47)
|
http://www.epd.gov.hk/eia/english/register/index8/vep3572012_content.html
|
|
EP-436/2012/C
|
Shatin to Central Link - Hung Hom
to Admiralty Section
|
Monthly EM&A Report(Sep 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4822015_content.html
|
|
- Wan Chai District
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report (DC/2007/23)(Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly
EM&A Report (DC/2009/24)(Aug 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report (DC/2009/23)(Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report(DC/2007/23,DC/2009/10,DC/2009/17, DC/2009/18)(Aug 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Quarterly EM&A Report(DC/2007/23,DC/2009/10,DC/2009/17,
DC/2009/18,DC/2009/19)(Mar 2015 to May 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
EP-122/2002/D
|
Central Reclamation Phase III
|
Monthly EM&A Report (Aug
2015) (HK/2011/07)
|
http://www.epd.gov.hk/eia/english/register/index8/vep2972012_content.html
|
|
EP-407/2010/E
|
South Island Line (East)
|
Monthly EM&A Report(Sep
2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4512014_content.html
|
|
EP-407/2010/E
|
South Island Line (East)
|
Monthly EM&A Report(Oct
2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4512014_content.html
|
|
EP-376/2009
|
DP2-Road P2 and other roads which are
classified as primary/district distributor roads
|
Monthly EM&A Report (Aug
2015)(HK/2011/07)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3762009_content.html
|
|
EP-416/2011
|
ShaTin to Central Link Protection Works at
Causeway Bay Typhoon Shelter
|
Monthly EM&A Report (Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/aep/ep4162011_content.html
|
|
EP-416/2011
|
ShaTin to Central Link Protection Works at
Causeway Bay Typhoon Shelter
|
Quarterly EM&A Report (Jun 2015 to Sep
2015)
|
http://www.epd.gov.hk/eia/english/register/aep/ep4162011_content.html
|
|
EP-444/2012/A
|
MTR Wan Chai
Station Lee Tung Street Subway
|
Monthly EM&A Report (Augl 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4412014_content.html
|
|
EP-444/2012/A
|
MTR Wan Chai
Station Lee Tung Street Subway
|
Monthly EM&A Report (Sep
2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4412014_content.html
|
|
EP-364/2009/C
|
Central-Wanchai
Bypass (CWB) including its road tunnel and slip roads
|
Monthly EM&A Report (Aug 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4432014_content.html
|
|
EP-364/2009/C
|
Central-Wanchai
Bypass (CWB) including its road tunnel and slip roads
|
Quarterly EM&A Report (Jun 2015 to Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4432014_content.html
|
|
EP-356/2009
|
Wan Chai
Development Phase II and Central-Wan Chai Bypass
|
Monthly EM&A Report (Aug
2015)(HK/2011/07)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3562009_content.html
|
|
EP-356/2009
|
Wan Chai
Development Phase II and Central-Wan Chai Bypass
|
Quarterly EM&A Report (Jun 2015 to Aug
2015)(HK/2011/07)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3562009_content.html
|
|
EP-436/2012/B
|
Shatin to Central Link - Hung Hom
to Admiralty Section
|
Monthly EM&A Report (Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4672015_content.html
|
|
EP-436/2012/C
|
Shatin to Central Link - Hung Hom
to Admiralty Section
|
Monthly EM&A Report(Sep 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4822015_content.html
|
|
- Eastern District
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report (DC/2007/23)(Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly
EM&A Report (DC/2009/24)(Aug 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report (DC/2009/23)(Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report(DC/2007/23,DC/2009/10,DC/2009/17,
DC/2009/18)(Aug 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Quarterly EM&A
Report(DC/2007/23,DC/2009/10,DC/2009/17, DC/2009/18,DC/2009/19)(Mar 2015 to
May 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
EP-122/2002/D
|
Central Reclamation Phase III
|
Monthly EM&A Report (Aug
2015) (HK/2011/07)
|
http://www.epd.gov.hk/eia/english/register/index8/vep2972012_content.html
|
|
EP-416/2011
|
ShaTin to Central Link Protection Works at
Causeway Bay Typhoon Shelter
|
Monthly EM&A Report (Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/aep/ep4162011_content.html
|
|
EP-416/2011
|
ShaTin to Central Link Protection Works at
Causeway Bay Typhoon Shelter
|
Quarterly EM&A Report (Jun 2015 to Sep
2015)
|
http://www.epd.gov.hk/eia/english/register/aep/ep4162011_content.html
|
|
EP-364/2009/C
|
Central-Wanchai
Bypass (CWB) including its road tunnel and slip roads
|
Monthly EM&A Report (Aug 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4432014_content.html
|
|
EP-364/2009/C
|
Central-Wanchai
Bypass (CWB) including its road tunnel and slip roads
|
Quarterly EM&A Report (Jun 2015 to Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4432014_content.html
|
|
EP-356/2009
|
Wan Chai
Development Phase II and Central-Wan Chai Bypass
|
Monthly EM&A Report (Aug
2015)(HK/2011/07)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3562009_content.html
|
|
EP-356/2009
|
Wan Chai
Development Phase II and Central-Wan Chai Bypass
|
Quarterly EM&A Report (Jun 2015 to Aug
2015)(HK/2011/07)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3562009_content.html
|
|
EP-436/2012/B
|
Shatin to Central Link - Hung Hom
to Admiralty Section
|
Monthly EM&A Report (Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4672015_content.html
|
|
EP-335/2009
|
Phased Reprovisioning
of Cape Collinson Crematorium
|
Monthly EM&A Report(Aug 2015)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3352009_content.html
|
|
FEP-01/335/2009
|
Phased Reprovisioning
of Cape Collinson Crematorium
|
Monthly EM&A Report (Jul 2015)
|
http://www.epd.gov.hk/eia/english/register/index7/fep1092010_content.html
|
|
EP-436/2012/C
|
Shatin to Central Link - Hung Hom
to Admiralty Section
|
Monthly EM&A Report(Sep 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4822015_content.html
|
|
-
Southern District
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report (DC/2007/23)(Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly
EM&A Report (DC/2009/24)(Aug 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A Report (DC/2009/23)(Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Monthly EM&A
Report(DC/2007/23,DC/2009/10,DC/2009/17, DC/2009/18)(Aug 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
EP-322/2008/G
|
Harbour Area Treatment Scheme (HATS) Stage 2A
|
Quarterly EM&A
Report(DC/2007/23,DC/2009/10,DC/2009/17, DC/2009/18,DC/2009/19)(Mar 2015 to
May 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4362014_content.html
|
|
EP-407/2010/E
|
South Island Line (East)
|
Monthly EM&A Report(Sep
2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4512014_content.html
|
|
EP-407/2010/E
|
South Island Line (East)
|
Monthly EM&A Report(Oct
2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4512014_content.html
|
|
EP-436/2012/B
|
Shatin to Central Link - Hung Hom
to Admiralty Section
|
Monthly EM&A Report (Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4672015_content.html
|
|
EP-487/2014
|
Tai Shue Wan
Development at Ocean Park
|
Monthly EM&A Report (17 Aug 2015 - 16
Sep 2015)
|
http://www.epd.gov.hk/eia/english/register/aep/ep4872014_content.html
|
|
EP-287/2007
|
Lamma Power Station - Unit L2 Flue Gas
Desulphurization Plant Retrofit Project
|
Quarterly EM&A Report (Apr 2015 to Jun
2015)
|
http://www.epd.gov.hk/eia/english/register/aep/ep2872007_content.html
|
|
EP-436/2012/C
|
Shatin to Central Link - Hung Hom
to Admiralty Section
|
Monthly EM&A Report(Sep 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4822015_content.html
|
|
- Kowloon City District
|
|
EP-437/2012
|
Shatin to Central Link - Mong
Kok East to Hung Hom
Section
|
Monthly EM&A Report No.36 (Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/aep/ep4372012_content.html
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned
Kai Tak Development
|
Monthly EM&A Report (Aug
2015)(KL/2012/02)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned Kai
Tak Development
|
Monthly EM&A Report (Aug
2015)(KL/2012/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned
Kai Tak Development
|
Monthly EM&A Report (Aug
2015)(KL/2010/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
EP-344/2009
|
New Sewage Pumping Stations Serving Kai Tak Development
|
Monthly EM&A Report (Aug
2015)(KL/2012/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3442009.html
|
|
EP-344/2009
|
New Sewage Pumping Stations Serving Kai Tak Development
|
Monthly EM&A Report (Aug
2015)(KL/2010/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3442009.html
|
|
EP-328/2009/A
|
Dredging Works for Proposed Cruise Terminal
at Kai Tak
|
Quarterly EM&A Report (Jun 2015 to Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep2892009_content.html
|
|
EP-328/2009/A
|
Dredging Works for Proposed Cruise Terminal
at Kai Tak
|
Monthly EM&A Report (Aug 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep2892009_content.html
|
|
EP-438/2012/H
|
Shatin to Central Link - Tai Wai
to Hung Hom Section
|
Monthly EM&A Report (Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4532014_content.html
|
|
- Kwun Tong
District
|
|
EP-140/2002
|
Planning and Engineering Feasibility Study
for Development at Anderson Road
|
Monthly EM&A Report (Aug
2015)(CV/2012/07)
|
http://www.epd.gov.hk/eia/english/register/aep/ep1402002_content.html
|
|
EP-140/2002
|
Planning and Engineering Feasibility Study for
Development at Anderson Road
|
Quarterly EM&A Report (Jun to Aug
2015)(CV/2007/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep1402002_content.html
|
|
EP-140/2002
|
Planning and Engineering Feasibility Study
for Development at Anderson Road
|
Monthly EM&A Report (Aug
2015)(CV/2007/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep1402002_content.html
|
|
EP-399/2010/C
|
Kwun Tong Line Extension
|
Monthly EM&A Report (Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep4622015_content.html
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned
Kai Tak Development
|
Monthly EM&A Report (Aug
2015)(KL/2012/02)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned
Kai Tak Development
|
Monthly EM&A Report (Aug 2015)(KL/2012/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
EP-337/2009
|
New Distributor Roads Serving the Planned
Kai Tak Development
|
Monthly EM&A Report (Aug
2015)(KL/2010/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3372009.html
|
|
EP-344/2009
|
New Sewage Pumping Stations Serving Kai Tak Development
|
Monthly EM&A Report (Aug
2015)(KL/2012/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3442009.html
|
|
EP-344/2009
|
New Sewage Pumping Stations Serving Kai Tak Development
|
Monthly EM&A Report (Aug
2015)(KL/2010/03)
|
http://www.epd.gov.hk/eia/english/register/aep/ep3442009.html
|
|
EP-328/2009/A
|
Dredging Works for Proposed Cruise Terminal
at Kai Tak
|
Quarterly EM&A Report (Jun 2015 to Aug
2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep2892009_content.html
|
|
EP-328/2009/A
|
Dredging Works for Proposed Cruise Terminal
at Kai Tak
|
Monthly EM&A Report (Aug 2015)
|
http://www.epd.gov.hk/eia/english/register/index8/vep2892009_content.html
|
|
|
|
|
|
|
|
|
|