1. Air and Water Quality Monitoring for GT57 Operation in OCTOBER 2009
This is the October 2009 Environmental
Monitoring and Audit (EM&A) report for the Project “Operation of GT57
Combined Cycle Unit” prepared by the
Environmental Team (ET). GT57
was not operated in the reporting month.
The
reliability upgrading work for GT57 is in progress. In this regard, no air
quality and water quality monitoring pertinent to GT57 was carried out in the
reporting month.
2.
Implementation
Status on Thermal Plume Surveys
No
thermal plume survey was carried out in the reporting month. The survey would only be conducted under the
conditions stipulated in the proposal on the programme and methodologies for
thermal plume survey attached in the EM&A manual (Operational Phase).
3.1
Outage
Plan for the coming 3 months
The major
outage plan for the next 3 months is shown below:
Date |
Remark |
01/11/2009 to 31/12/2009 |
Overhaul and reliability upgrading work for GT57 |
3.2 Key issues for the coming month
Key issues to be considered in the coming month include:
Air Impact
· To monitor the water injection rate continuously while GT57 is operating.
· To monitor the sulphur content of the LGO if the combined cycle unit is run on LGO.
Water Impact
· To carry out water quality monitoring while GT57 is operating as required by the EM&A manual (Operational phase).
~ End ~