3.               MONITORING RESULTS

 

            Air Quality

 

3.1               Air quality monitoring, including 24-hr TSP and 1-hr TSP monitoring, was conducted at 5 monitoring stations in October 2006. The impact 1-hr and 24-hr TSP monitoring had been ceased from 1 November 2006 due to the completion of works.

 

3.2               In October 2006, all the air quality monitoring results complied with the AL levels except two 24-hr TSP action level exceedances recorded.  The 24-hr TSP action level exceedance recorded at MA1 in October were concluded mainly due to poor ambient air quality and not related to the Project. The trend of air quality over the past four months is given in Appendix G.

 

3.3               Table 3.1 and Table 3.2 present the baseline monitoring results and the averaged impact air quality monitoring results of 1-hr TSP and 24-hr TSP in October 2006.

 

Table 3.1         Comparison of Baseline and Averaged Impact Monitoring Results of 1-hr TSP Concentration

Location

Baseline (mg/m3)

Oct 06 (mg/m3)

MA1

269.6

104.2

MA2

249.2

91.8

MA3

268.3

104.2

MA4

269.4

94.4

MA5

274.4

104.7

 

Table 3.2         Comparison of Baseline and Averaged Impact Monitoring Results of 24-hr TSP Concentration

Location

Baseline (mg/m3)

Oct 06 (mg/m3)

MA1

55.8

187.8

MA2

40.6

79.6

MA3

36.8

88.6

MA4

28.5

60.6

MA5

32.1

121.6

 

3.4               The 1-hr TSP concentrations were below the baseline levels whereas the 24-hr TSP levels were generally higher than the baseline levels but were still well within the AL levels in October 2006.

 

            Noise

 

3.5               In October 2006, noise monitoring was conducted during 07:00 – 19:00. Due to the completion of works, the impact noise monitoring had been ceased from 1 November 2006. There was no operational noise monitoring conducted in the reporting quarter.

 

3.6               In October 2006, all the daytime noise monitoring results complied with the AL levels. The noise levels monitored in the past four months are plotted in Appendix H.

 

3.7               Table 3.3 presents the comparison of ranges of baseline monitoring results and the impact noise monitoring results for daytime monitoring during the reporting quarter.

 

 


Table 3.3         Comparison of Baseline and Impact Monitoring Results of Noise (Day-time) Monitoring

Location

Baseline

(Range, Leq(30 mins), dB(A))

Oct 06

(Range, Leq(30 mins), dB(A))

MN1

53.6 – 71.1

61.2 – 64.6

MN2

60.0 – 80.2

63.5 – 67.1

MN3

66.1 – 73.7

67.1 – 68.2

MN4

63.2 – 72.1

63.0 – 64.5

MN5

56.6 – 71.5

64.2 – 65.7

  MN6 *

56.0 – 72.5

-

  MN7 *

39.6 – 66.0

-

MN8

49.0 – 72.3

63.5 – 65.7

MN9

58.4 – 74.1

64.6 – 66.7

 MN10

55.9 – 78.9

65.2 – 67.8

                Remark: *Noise monitoring programme was not required at MN6 & MN7 in the reporting quarter

 

3.8               The major noise sources were road paving outside Ting Kau Village, Ting Kau Carpark, BPRW100, RW22, Slope 13 and Sham Tseng. All monitoring results were below the limit level at the nearest monitoring station in October 2006. Construction activities were properly scheduled and sited to prevent cumulative impacts.

 

Water Quality

3.9               In accordance with the EM&A Manual, impact water quality monitoring is required to be conducted during the course of the marine works and the post-monitoring period. As informed by the Contractor, there were only a few marine works remaining at the reclamation works area, which might be conducted shortly. Therefore, though there were no activities at the Sham Tseng Reclamation Area, marine water quality monitoring continued in the reporting quarter.

 

3.10           Impact water quality monitoring was conducted three days per week. Measurements were taken at both mid-ebb and mid-flood tides at three depths (i.e. 1m below surface, mid depth and 1m from seabed). The AL levels are included in Appendix E.

 

3.11           A total of 117 water quality exceedances were recorded in the reporting quarter, 31 in October, 57 in November and 29 in December 2006 respectively. As there was no marine works at the reclamation works area, the exceedances were considered not related to the Project and they might be due to poor ambient water quality, local impacts and natural fluctuation of water body. The total number of exceedances for dissolved oxygen, turbidity and suspended solids recorded in the quarter and percentage difference between the months in the quarter are presented in Table 3.4. The trend of water quality is depicted in Appendix J.

 


Table 3.4         Total Number of Water Quality Exceedances and Percentage Differences of Number of Water Quality Exceedances in the Quarter

Parameter

Exceedance Level

Oct 06

Nov 06

Dec 06

% Difference

Oct – Nov

% Difference

Nov – Dec

Number of monitoring days*

12

13

12

N/A

N/A

DO (S&M)

Action

4

17

5

-

-

Limit

1

5

4

Total

5

22

9

Total/Monitoring Day

0.42

1.69

0.75

302.38

-55.62

DO(B)

Action

0

2

3

-

-

Limit

0

0

0

Total

0

2

3

Total/Monitoring Day

0.00

0.15

0.25

150.00

66.67

Turbidity

Action

5

0

1

-

-

Limit

2

0

0

Total

7

0

1

Total/Monitoring Day

0.58

0.00

0.08

-580.00

8.00

SS

Action

14

12

5

-

-

Limit

5

21

11

Total

19

33

16

Total/Monitoring Day

1.58

2.54

1.33

60.56

-47.64

Total number of DO, Turbidity & SS exceedances

Action

23

31

14

-

-

Limit

8

26

15

Total

31

57

29

Total/Monitoring Day

2.58

4.38

2.42

69.77

-44.75

 *This refers to the total no. of days when monitoring was carried out at Sensitive Receiver Stations.

 

3.12           A comparison between the quarterly mean of SS and 1.3 times of the baseline mean was made for each monitoring station. Table 3.5 shows the quarterly mean and 130% of baseline mean during both mid-ebb and mid-flood tides. It was observed that the water quality in the reporting quarter was better than 1.3 times of the baseline mean during both tides in the reporting quarter. The statistical analysis results are given in Appendix L.

 

Table 3.5         Summary of Statistical Analysis of SS Results

Monitoring Station

Mid-ebb

Mid-flood

130%

Baseline

Quarterly

Mean

130% Baseline

Quarterly

Mean

Designated Control Stations

MC1

11.9

7.3

10.3

7.5

MC2

11.3

7.5

10.4

7.6

Designated Reference Stations

MR5

12.2

7.6

10.3

7.7

MR6

10.9

7.7

10.6

7.7

Designated Monitoring Stations

MW1

12.3

7.2

9.7

7.3

MW2

11.9

7.1

9.1

7.5

MW3

10.3

7.7

8.9

7.9

MW4

10.2

7.7

9.4

7.9

MW5

11.6

7.8

10.6

7.9

MW6

10.8

7.8

10.3

7.4

WFCZF1

11.6

7.5

11.1

7.4