4.               INSPECTION RESULTS

 

            Implementation Status of Environmental Mitigation Measures

4.1               There were some observations about dust issues, such as lack of cover for stockpiled fill materials and lack of dust suppression measures along haul road in October 2006. The Contractor was advised to properly implement sufficient dust mitigation measures.

 

4.2               There were no marine works undertaken at the reclamation area in the reporting quarter. For the land-based activities, the concern is the presence of soil debris, construction material and general refuse in Ting Kau Bridge, E03B, RW42, Outfall PA, RW90, FB06 and Slope 13. The Contractor timely clear the debris and construction material dropped into nullah / stream and drainage channel.

 

4.3               In October 2006, construction noise was observed from road paving outside Ting Kau Village, Ting Kau Carpark, BPRW100, RW22, Slope 13 and Sham Tseng. All the noise monitoring results complied with the AL levels in October 2006.

 

4.4               Trip ticket system was implemented for all kinds of waste disposal. For the excavated material, some of it was used for backfilling, some was delivered to other construction sites for reuse and the remaining was disposed of at public fill. Some chemical containers were not provided with drip trays and dripped oil was occasionally observed on ground. The Contractor should ensure proper storage of chemical containers and maintenance of plant and equipment. On the other hand, the Contractor was reminded to properly maintain the chemical waste storage area.

 

4.5               In October 2006, two landscape & visual impact monitoring were held. No retained trees were felled.  The Contractor protected most exposed slopes/surfaces by hydroseeding, shotcreting and tarpaulin sheeting. The Contractor was requested to apply hydrosseeding to areas not covered by hydroseed after slope work completes. 2 retained trees outside Rhine Terrace were suspected to be dead after demolition of rock fall fence.

 

4.6               One landscape and visual audit for establishment period was carried out on 15 December 2006. The landscape and visual audit report is presented in Appendix M. Recommendations were given by the Registered Landscape Architect (RLA):

 

Ÿ             The Contractor is recommended to replace all dead trees as soon as possible;

Ÿ             The Contractor is recommended to carry out the planting of woodland mix plants on all outstanding slope areas as soon as possible. Also, the Contractor should carry out regular weeding, clearing of litter, and watering of plants during the dry periods;

Ÿ             The Contractor is recommended to carry out mulching to outstanding area of planter beds as soon as possible;

Ÿ             The Contractor is recommended to carry out remedial measures to ensure the healthy establishment of the existing retained tree ST1 near RW40.

 

4.7               The updated implementation status of environmental mitigation measures (EMIS) is given in Appendix F.

 

Status of Environmental Licensing and Permitting

4.8               Environmental permit (EP-095/2001) was in place during the reporting quarter. The Contractor also obtained an effluent discharge licence and registered as chemical waste producer for the Project. The status of licences and permits is summarised in Appendix I.

 

Advice on Solid and Liquid Waste Management Status

4.9               A large amount of excavated soil was generated from the Project and it was either reused or disposed of at public fill. The trip ticket system was implemented for all the wastes disposed offsite. Table 4.1 summarises the waste disposal in the quarter. Toilets connecting to public sewer have been in use since September 2002. No significant quantity of liquid waste was generated for the site office operation in the reporting quarter.

 

Table 4.1         Waste Disposal in the Reporting Quarter

Waste Type

Status

Estimated Amount

Oct 06

Nov 06

Dec 06

C&D waste and general refuse

Vegetation, domestic waste (site) collected in garbage bins and general refuse on land

32 Trucks

14 Trucks

16 Trucks

C&D material:

Excavated soil, rocks, etc.

For reuse internally or in other Contracts

Nil

Nil

Nil

To public fills

76 Trucks

91 Trucks

43 Trucks

To sorting facilities

Nil

Nil

Nil

Chemical waste

Spent oil, paint, paint thinner, adhesive diesel

Nil

Nil

Nil