Introduction
This
is the eighteenth Quarterly
Environmental Monitoring and Audit (EM&A) Summary Report prepared by
Maunsell Environmental Management Consultants Limited (MEMCL) for the Project
“Castle Peak Road Improvement between Ting Kau and Sham Tseng, Tsuen Wan” (The
Project). This report summarises the EM&A work performed in the quarter
from October to December 2006.
Construction
activities in the reporting quarter were:
· Landscaping works;
· Road paving;
· Backfilling;
· E&M works; and
· Retaining wall construction.
The
construction works had commenced since
July 2002. The
Contractor implemented most of the environmental mitigation measures and
effectively minimise the impacts arising from the construction activities.
The
Contract has been substantially completed on 31 July 2006. The Contractor only
carried out landscape works, remaining road paving and utilities installation
in the reporting quarter.
Environmental Monitoring Works
Air Quality
All
the air quality monitoring results complied with the Action and Limit Levels
(AL Levels) except two 24-hr TSP exceedances in October 2006. One action level and one limit level 24-hr
TSP exceedances recorded at MA1 in October were concluded not due to
construction activities. The impact air quality monitoring had been ceased from
1 November 2006 due to the completion of works.
Construction Noise
All
the construction noise monitoring results complied with the
Water Quality
Water
quality monitoring programme continued in the reporting quarter and there were 117 marine water quality
exceedances. Since there were no marine works conducted in the reporting
quarter in Sham Tseng Reclamation Works Area, the exceedances were considered
not related to the Project.
Landscape and Visual
Two site inspections were held for landscape and visual impact
monitoring in October 2006. No retained trees were felled. The Contractor
protected most exposed slopes/surfaces by hydroseeding, shotcreting and
tarpaulin sheeting. 2 retained trees outside Rhine Terrace were suspected to be
dead after demolition of rock fall fence. The landscape and visual impact
monitoring had been ceased from 1 November 2006 due to the completion of works.
One landscape and visual audit for establishment period was carried out on 15
December 2006.
Complaints, Non-compliance and
Prosecutions
No environmental complaint, non-compliance or prosecution was received in the reporting quarter.