1.1
Based upon on-going developments along the
1.2
As a result of this, the Government has decided that, in order to
enhance the level of service for the increasing number of users, the road needs
to be improved to cope with traffic growth predicted by the year 2011.
Meinhardt Halcrow Joint Venture (MHJV) has been commissioned by Highways
Department (HyD) under Agreement CE 1/96 to, in broad terms, review the
findings, conclusions and recommendations of the Feasibility Study, complete
the detailed design of the project taking into account any modifications noted
during the review, prepare the pre-qualification and tender documents and
implement the project.
1.3
China State Construction Engineering (
1.4
Maunsell Environmental Management Consultants Limited (MEMCL) was
employed by CSHK as the Environmental Team (ET) to undertake EM&A works for
the Project. In accordance with the EM&A Manual, environmental monitoring
of air quality, noise, water quality, landscape and visual, and environmental
site inspections would be required for this Project.
1.5
Under the Environmental Impact
Assessment (EIA) on the Feasibility Study for the Castle Peak Road Improvements completed in 1996,
reclamation at Sham Tseng East was defined as designated works. An
Environmental Permit (EP No.: EP-095/2001) was issued under the EIAO on 29
March 2001.
1.6
A few minor comments were received from EPD on the Marine Water Quality
Baseline Monitoring Report (Rev.2) on 27 August 2003. The upstream control
stations of MW5 & MW6 had been revised to MR5 & MR6 while there would
not be any upstream control station for WFCZF1 during mid-flood tide. The
revised pages were submitted after the verification of the IC(E) to all the
relevant parties on 1 September 2003.
1.7
This is the fifty-third monthly Environmental Monitoring and Audit
(EM&A) Report under Contract HY/99/19 – Castle Peak Road Improvement
between Ting Kau and Sham Tseng. This report presented a summary of the
environmental monitoring and inspection works, list of activities, and
mitigation measures carried out by the ET for the Project for November 2006.
1.8
The project organization is shown in Appendix A. The responsibilities of
respective parties are detailed in Section 1.10 of EM&A Manual.
1.9
The key personnel contact names and numbers are summarised in Table 1.1
Table 1.1 Contact Information of Key Personnel
Party |
Position |
Name |
Telephone |
Fax |
HyD |
Engineer |
Mr. Simon Lau |
2762 3593 |
2714 5289 |
ER (MHJV) |
SRE |
Mr. M S Harfoot |
2417 9305 |
2492 6201 |
IC(E) (Hyder) |
IC(E) |
Mr. Coleman Ng |
2911 2719 |
2827 2891 |
Contractor |
Project Manager |
Mr. Dave Chan |
2492 8029 |
2404 9290 |
Environmental Officer |
Mr. Leo Chung |
|||
ET (MEMCL) |
ET Leader |
Mr. Y T Tang |
3105 8537 |
2891 0305 |
1.10
The construction works under Contract HY/99/19 – Middle Section
commenced in July 2002, the main scope of the proposed works as a whole are as
follows:
·
Improvement to Castle Peak Road between Area 2 and Ka Loon Tsuen, Tsuen
Wan to a dual two-lane carriageway;
·
Provision of pedestrian facilities in the form of footpaths, subways,
footbridges and crossings;
·
Road junction and signal design and re-provisioning of access roads and
connections to existing road networks;
·
Construction of associated drainage and landscaping works;
·
Environmental mitigation measures;
·
Design and construction of water mains; and
·
Construction of entrusted sewerage works.
1.11
The contract has been substantially completed on 31 July 2006.
Outstanding works being carried out in the reporting month included:
·
Landscaping works;
·
Remaining road paving; and
·
Remaining Utilities installation.
The remaining marine works has yet commenced
in the reporting month.
1.12
The general layout plan of the Project site showing the contract area is
shown in Figure 1.1.
Monitoring Locations
1.13
The description and detailed locations of monitoring stations for water
quality are shown in Figure 4.1 and relevant sections of this Report.
EM&A Programmes
1.14
Upon substantially completion of the Project, the EM&A programme
requires environmental monitoring for water quality and environmental site
inspection for water quality. The EM&A requirements for each parameter
described in the following sections include:
·
All monitoring parameters;
·
Monitoring schedules for the reporting month and forthcoming months
·
Action and Limit levels for all environmental parameters;
·
Event/Action Plans;
·
Environmental mitigation measures, as recommended in the Project EIA
study final report; and
·
Environmental requirements in contract documents.
1.15
The advice on the implementation status of environmental protection and pollution
control/mitigation measures is summarised in Section 6 of the Report.