5.1
The
construction phase landscape and visual audit had been ceased from 1 November
2006 due to the completion of works. No landscape and visual audit was
conducted in the reporting month. The approval letters from the engineers and
the IEC for the cessation of landscape and visual audit programme is provided
in Appendix M.
5.2
Landscape and visual audits during the
establishment period will be carried out bimonthly and the next audit was
scheduled to December 2006.