Construction Programme for the
Coming Months
7.1
The construction programme for the Project is shown in Appendix I.
7.2
Key issues to be considered in the coming month include:
·
Wastewater/runoff generated on site; and
·
Management of chemicals and avoidance of oil spillage.
7.3 The following mitigation measures are required:
Water Quality Impact
·
To carry out water quality testing in compliance with the Effluent
Discharge Licence.
·
To provide sufficient treatment for the
wastewater/runoff and groundwater prior to discharge.
·
To properly maintain the drainage systems on site.
Chemical and Waste Management
·
To remove waste from the site
regularly such that accumulation of waste materials or rubbish on site could be avoided.
· To avoid any improper storage and handling of chemical waste on site.
· To provide a sheltered and properly labelled chemical storage area; surround the area completely by concrete bunding; seal the gaps around the base of the storage area and properly lock the storage area.
· To provide drip trays with sufficient capacity for all diesel drums or chemical containers, if any, outside locked storage area.
· To consider reuse, recycle or return of Construction/ Demolition (C&D) material.
· To identify C&D material by packaging, labelling, storage, transportation and disposal in accordance with statutory regulations.
Monitoring Schedule for
the Coming Months
7.4
The tentative schedule for environmental monitoring and landscape and
visual audit from December 2006 to February 2007 is shown in Appendix J.