Leader – wai kee (C&T) Joint venture
Prepared
by: Linda
Law Environmental
Officer Checked
by: C.
L. Lau Environmental
Team Leader Approved
by: Tony
Wong Operations
Manager
Report
No.: ENA60542
CHECK CERTIFICATE
Verified: _______________________________ Independent Environmental
Checker Name: Ir Coleman Ng Senior Environmental
Consultant Hyder Consulting Limited
TABLE OF CONTENTS Page
Executive SUMMARY
1.0 |
INTRODUCTION |
1 |
2.0 |
PROJECT INFORMATION |
|
|
2.1 Background |
1 |
|
2.2 Site Description |
1 |
|
2.3 Construction Programme |
1 |
|
2.4 Project Organization and Management Structure |
1 |
|
2.5 Contact Details of Key Personnel |
1 – 2 |
3.0 |
Construction
progress in this reporting month |
2 |
4.0 |
Air Quality
Monitoring |
|
|
4.1 Monitoring Requirement |
3 |
|
4.2 Monitoring Equipment |
3 |
|
4.3 Monitoring Parameters, Frequency and duration |
3 |
|
4.4 Monitoring Locations and Period |
3 – 4 |
|
4.5 Monitoring Methodology |
5 – 6 |
|
4.6 Action and Limit levels |
6 |
|
4.7 Event-Action Plans |
6 |
|
4.8 Results |
6 |
5.0 |
Noise
Monitoring |
|
|
5.1 Monitoring Requirement |
7 |
|
5.2 Monitoring Equipment |
7 |
|
5.3 Monitoring Parameters, Frequency and duration |
7 |
|
5.4 Monitoring Locations and Period |
7 – 8 |
|
5.5 Monitoring Methodology |
8 – 9 |
|
5.6 Action and Limit levels |
9 |
|
5.7 Event-Action Plans |
9 |
|
5.8 Results |
9 |
6.0 |
Wastewater
monitoring |
9 |
7.0 |
Environmental
Non-conformance |
|
|
7.1 Summary of air quality, noise and wastewater monitoring |
9 – 10 |
|
7.2 Summary of environmental complaints |
10 |
|
7.3 Summary of notification of summons and prosecutions |
10 |
8.0 |
Site
Inspection |
|
|
8.1 Summary of site inspection findings and Action(s) taken by
LWKJV and ET |
10 |
|
8.2 Status of Environmental Licensing and Permitting |
10 – 12 |
|
8.3 Recommendation on Site Inspection findings |
12 |
9.0 |
Waste
Management |
|
|
9.1 Waste Management Audit |
12 |
|
9.2 Records of waste quantities |
12 |
10.0 |
Implementation Status |
|
|
10.1 Implementation Status of Environmental Mitigation Measures |
13 |
|
10.2 Implementation Status of Event and Action Plan |
13 |
|
10.3 Implementation Status of Environmental Complaint Handling |
13 |
11.0 |
Conclusion |
13 |
12.0 |
Future key
issue |
|
|
12.1 Upcoming EM&A Schedule in coming two months |
14 |
|
12.2 Upcoming Construction Works Schedule in coming month |
14 |
APPENDIX |
|
A |
Organization Chart and Lines of Communication |
B1 |
Calibration Certificates for Impact Air Quality Monitoring
Equipment |
B2 |
Impact Air Quality Monitoring Results |
B3 |
Graphical Plots of Impact Air Quality Monitoring Data |
C1 |
Calibration Certificates for Impact Noise Monitoring Equipment |
C2 |
Impact Noise Monitoring Results |
C3 |
Graphical Plots of Impact Noise Monitoring Data |
D |
Weather Condition |
E |
Event-Action Plans |
F |
Construction Programme |
G |
Construction Site Area |
H |
Implementation Status of Mitigation Measures and Follow-up
Actions during weekly site inspections |
I |
IEC and RE Comments on Monthly EM&A
Report – June 2006 |
Figure |
|
Figure 1 |
Location of Noise Monitoring Locations |
Figure 2 |
Location of Air Monitoring Locations |
Figure 3 |
Location of Air and Noise Monitoring
Stations at HKIB Staff Accommodation |
Figure 4 |
Location of Noise Monitoring Station at
CUHK Residence No. 10 |
Figure 5 |
Location of Air and Noise Monitoring
Stations at Cheung Shue Tan Village |
Tables |
|
2.1 |
Contact Details of Key Personnel |
3.1 |
Major Construction Activities in this
reporting month |
3.2 |
Implementation of Environmental
Mitigation Measures |
4.1 |
Air Quality Monitoring Equipment |
4.2 |
Monitoring parameters, duration and
frequency of air quality monitoring |
4.3 |
Air Quality Monitoring Locations |
4.4 |
Monitoring Schedule for air quality
monitoring stations |
4.5 |
Action and Limit levels for 24-hr TSP
and 1-hr TSP |
5.1 |
Noise Monitoring Equipment |
5.2 |
Duration, Frequency and Parameters of
noise monitoring |
5.3 |
Noise Monitoring Locations |
5.4 |
Monitoring Schedule for noise
monitoring stations |
5.5 |
Action and Limit levels for noise
monitoring |
7.1 |
A Cumulative Log of Notification of
Summons and Prosecution |
8.1 |
The summary of the IEC and ET site
inspection findings and Action(s) taken by LWKJV and ET |
8.2 |
Summary of environmental licensing and
permit status |
9.1 |
Summary of Quantities of waste for
disposal |
12.1 |
Upcoming EM&A Schedule in coming
two months |
12.2 |
Upcoming Construction Works Schedule in
coming month |
Executive
SUMMARY
This monthly
EM&A report (No.15) has been prepared to document the impact monitoring
works conducted for the Contract of the
Remaining Engineering Infrastructure Works for Pak Shek Kok Development Package
2A (Contract No: TP 37/03) during
the reporting period from 01 to 31 July 2006.
Construction
Progress
The major
construction works in this reporting month were as below:
§ Drainage
works (Excavation, pipe lying and
breaking) at Section 1 & 2; |
§ Construction
of column and wall at Voided Abutment, RE Wall and pile cap at North
Abutment, and Retaining wall No.1; |
§ Construction
of MLS Subway pump ramp and barrel; |
§ Construction
of foundation slab for Toilet No.2; |
§ Drainage
work, landscape softworks, finishing works and installation of precast
concrete planter units and concreting of insitu concrete planter at Section 7
and 8 (promonade) of the Works; |
§ Footpath
construction, desilting and CCTV inspection of the completed drainage works
at Section 5 (Road L4) of the Works; |
§ Installation
additional valves and connection for watermains at the cycle track, pavement
construction and fencing erection at Section 6 of the Works; |
§ Installation
of lighting footing and duct, finishing the landscape structure at the
proposed Landscape Node P1, P2 & P3; |
§ Construction
of in-situ mass concrete coping at the proposed LandscapeNode P1, P2 &
P3; |
§ Construction
of bus bays at Section 10 of the Works; |
§ Setting
back of existing stockpile mound adjacent to the proposed cycle track at
Housing Site 4; |
§ Filling
of soil mix at planter; and |
§ Further
in-situ concreting of section above +2.5mPD at the proposed Public Landing
Steps. |
Environmental
Monitoring Progress
The summary of
the monitoring activities in this monitoring month is listed below:
·
Noise Monitoring (Day-time): 4 Occasion
at 4 designated locations
·
24-hour TSP Monitoring: 5 Occasions at 3
designated locations
·
1-hour TSP Monitoring: 12 Occasions at 3
designated locations
·
Weekly-site inspection: 4 Occasions
Noise
Monitoring
No
exceedances of Action and Limit levels for noise monitoring were recorded in
the reporting month.
Air
Monitoring
No exceedances of
Action and Limit levels were recorded for 24-hr and 1-hr TSP monitoring in the
reporting month.
Wastewater
Monitoring
During this reporting month, wastewater monitoring
was carried out at Pak Shek Kok Workshop Area Adjacent to Site Office on 13
July 2006. One wastewater sample was collected from the discharge point during
the monitoring. The result of suspended solids content of the wastewater sample
was complied the discharge limit of the Discharge Licence. The next wastewater monitoring should be at October 2006.
Site
Inspection
Environmental
site inspections conducted in this reporting month are presented as follows:
Concerned Parties |
Dates of Audit /
Inspection |
Weekly site inspection
(ET) |
08, 13, 21, 29 |
Monthly site inspection
(IEC/LWKJV/RE) |
21 |
The
observations were raised during this reporting month. The site inspection
findings are presented as follows:
Item |
Aspects |
Findings |
Action(s) taken by LWKJV |
ET Verification |
1 |
Air |
Stockpiles at SA3 were found covered improperly during the
weekly site inspections on 08/07/06 and 13/07/06. |
LWKJV replied to hydro-seed the stockpiles as soon as possible. |
Since the stockpiles were found to be hydro-seeded during the
subsequent weekly site inspection (21/07/06), no further verification was
required to be taken by ET. |
2 |
Air |
Silt and sand track was observed on the public road between SA1
and SA3 during weekly site inspection on 21/07/06. |
LWKJV replied to clean up the road immediately. |
During the subsequent weekly site inspection, no silt and sand
track was observed and hence no further verification was required. |
3 |
Air |
Stockpiles at SA1 were found without cover during weekly site
inspections on 21/07/06 and 29/07/06. |
LWKJV replied to cover the stockpiles with tarpaulin sheets to
avoid dust generation. |
Since the finding was still noted during the last inspection of
this reporting month, it will be verified during the first weekly site
inspection of the coming month. |
4 |
Water |
Follow up action to the finding of previous month, damaged part
of silt curtain at Node 2 was found to have repaired during weekly site
inspection on 21/07/06. |
Since the finding was improved, no further action was required
to be taken by LWKJV. |
Since the finding was improved, no further ET verification was
required. |
5 |
Water |
Storm water was found to be accumulated at Node 1 and SA1 during
weekly site inspection on 08/07/06. |
LWKJV replied to provide temporary ditches to drain the
accumulated storm water out. |
During the subsequent weekly site inspection on 13/07/06, no
storm water was found at Node 1and SA1. Hence, no further verification was
required. |
6 |
Water |
Wastewater was found directly discharged to u-channel during
weekly site inspection on 29/07/06. |
LWKJV replied to divert the wastewater to sedimentation tank
before discharge. |
Since the finding was observed at the last inspection of this
reporting month, it will be verified during the first weekly site inspection
of the coming month. |
7 |
Water |
Manhole at SA3 was found full of silt and mud during weekly site
inspection on 13/07/06. |
LWKJV replied to clean up the silt and mud inside the manhole
immediately. |
During the subsequent weekly site inspection on 21/07/06, no
silt and mud was found inside the manhole. Since the finding was improved, no
further verification was required. |
8 |
Water |
Stagnant water was accumulated at Workshop during weekly site
inspection on 29/07/06. |
LWKJV replied to provide temporary ditches to drain the
accumulated storm water out. |
Since the finding was observed at the last inspection of this
reporting month, it will be verified during the first weekly site inspection
of the coming month. |
9 |
Water |
Muddy water was observed at cycle track near Ma Liu Shui site
entrance during weekly site inspection on 29/07/06. |
LWKJV replied to clean up the muddy water immediately. |
Since the finding was observed at the last inspection of this
reporting month, it will be verified during the first weekly site inspection
of the coming month. |
10 |
Chemical |
A 200L chemical container was found at SA3 without drip tray
during weekly site inspection on 21/07/06. |
LWKJV replied to relocate the chemical container to an
appropriate chemical storage area. |
During the subsequent weekly site inspection on 29/07/06, the
chemical container was removed. |
11 |
Chemical |
Follow up action to the finding of previous month, an appropriate
chemical storage area was provided at Workshop during weekly site inspection
on 27/07/06. |
Since the finding was improved, no further action was taken by
LWKJV. |
Since the finding was improved, no further verification was
required to be taken by ET. |
12 |
Site Practice |
Valid CNP was recommended to be post on the notice board of site
office during weekly site inspection on 21/07/06. |
LWKJV replied to post the valid CNP immediately. |
Since the valid CNP was found post during weekly site inspection
on 29/07/06, the finding was improved and no further verification was
required. |
Waste Management
According to weekly site inspection, ET
found that the Contractor followed the recommended procedures stipulated in the
Waste Management Plan (WMP) on handling and disposal of wastes. 3000m3
inert C&D materials, 50kg metals, 100kg paper/cardboard packaging, 10kg
plastic and 48370kg general refuse were generated in this reporting month. All
inert C&D materials were reused in the Contract and other wastes were
handling under the instruction and procedure stated in the WMP in this
reporting month.
Environmental
Complaints
No
environmental complaints were received in this monitoring month.
Notification
of summons and successful prosecutions
No
notification of summons and prosecutions with respect to environmental issues
were registered in this reporting month.
Future
Key Issues
Base
on the site inspections and forecast of engineering works in the coming month,
key issues to be considered are as follows:
·
Noise and air
quality impact due to construction works;
·
Maintain wheel washing
facilities properly;
·
Cleanup the access
road regularly;
·
Watering,
hydro-seeding or covering all stockpiles with tarpaulin to avoid wind and water
erosion;
·
Diverting the silty
runoff to sedimentation trap or sedimentation tanks;
·
Use and maintenance of silt
curtain properly during marine works;
·
Maintain good
site practice and waste management to minimize environmental impacts at the
site;
·
Follow-up improvements on
waste management issues.
1.0
INTRODUCTION
Leader – Wai Kee
(C&T) Joint Venture (LWKJV) appointed Environmental Team (ET) of
ETS-Testconsult Limited (ETL) to undertake the Environmental Monitoring and
Audit (EM&A) for Remaining Engineering Infrastructure Works for Pak Shek
Kok Development Package 2A (Contract No.: TP 37/03).
In accordance with
the Section 10 of Environmental Permit to Construct and Operate a Designate
Project (EP-108/2001/AEP-108/2001), EM&A programme as set out in the
EM&A Manual is required to be implemented. In accordance with the EM&A
manual, environmental monitoring of air quality and noise is required for the
Project. The EM&A requirement for each parameter are described in details
in subsequent sections, including:
·
All
monitoring parameters;
·
Action
and Limit levels for all environmental parameters;
·
Event-Action
Plans;
·
Environmental
mitigation measures, as recommended in the project EIA study report;
·
Environmental
requirements in contract documents.
This
monthly EM&A report summarizes the impact monitoring results and audit
findings of the EM&A program during the reporting period from 01 to 31 July
2006.
2.0
PROJECT INFORMATION
2.1
Background
Remaining
Engineering Infrastructure Works for Pak Shek Kok Development Package 2A
(Contract No.: TP 37/03) was planned and designed by the
Civil Engineering and Development Department (CEDD).
As the main
Contractor of the captioned project: contracted by, LWKJV will follow the
environmental monitoring recommendation stated at the EM&A Manual that was
prepared with reference to the EIA Study for Feasibility Study on the Pak Shek
Kok Development Area (PSKDA) Environmental Monitoring and Audit Manual under
Agreement No. CE 90/96.
2.2
Site Description
Generally, the construction site is located at Pak Shek Kok
development area. Surrounding the construction site, there are two air
sensitive receivers: HKIB
Staff Accommodation and Cheung Shue Tan Village and three noise sensitive
receivers: HKIB Staff Accommodation, CUHK Residence No.10 and Cheung Shue Tan
Village.
Figure 1and 2 show the noise and air monitoring locations of this project.
2.3
Construction Programme
Details of construction programme are shown in Appendix F.
2.4 Project
Organization and Management Structure
The organization chart and lines of
communication with respect to the on-site environmental management and
monitoring program are shown in Appendix A.
2.5 Contact
Details of Key Personnel
The key personnel contact names and telephone numbers, and
construction programme are shown in table 2.1.
Table 2.1 Contact
Details of Key Personnel
Organization |
Project Role |
Name of Key Staff |
Tel. No. |
Fax No. |
CEDD |
Mr. M. S. Lam |
Employer |
2158 5630 |
2693 2918 |
Hyder |
Mr. Herman Fong |
Engineer |
2603 6638 |
2603 7883 |
LWJV |
Mr. T. T. Wong |
Project Manager |
2442 1123 |
2442 9733 |
Hyder |
Ir. Coleman Ng |
Independent Environmental Checker |
2911 2233 |
2805 5028 |
ETL |
Mr. C.L. Lau |
Environmental Team Leader |
2946 7791 |
2695 3944 |
3.0 Construction
Progress in this reporting month
The
site area of this project is shown in Appendix G.
A
summary of the major construction activities undertaken in this monitoring
month is shown in Table 3.1. The implementation of corresponding mitigation
measures is summarized in Table 3.2.
Table 3.1 Major
Construction Activities in this reporting month
Major Construction Activity |
Location |
Drainage works (Excavation, pipe lying and breaking) |
Section 1 &
2 |
Construction of
column and wall |
Voided
Abutment, RE Wall and pile cap at North Abutment, and Retaining wall No.1 |
Construction of
MLS Subway pump ramp and barrel |
SA3 |
Construction of
foundation slab for Toilet No.2 |
Toilet No.2 at
Public Plaza |
Drainage work,
landscape softworks, finishing works and installation of
precast concrete planter units and concreting of insitu concrete planter |
Section 7 &
8 (Promenade) |
Footpath construction,
desilting and CCTV inspection of the completed drainage works |
Section 5 (Road
L4) |
Installation
additional valves for watermains |
Cycle track at
Section 6 |
Installation of
lighting footing and duct, finishing the landscape structure |
Proposed Landscape
Node P1, P2 & P3 |
Construction of
mass concrete coping |
Proposed
Landscape Node P1, P2 & P3 |
Construction of
bus bays |
Section 10 of
the Works |
Setting back of
existing stockpile mound adjacent to the proposed cycle track |
Housing Site 4 |
Filling of soil
mix at planter |
Node 1 |
Further in-situ
concreting of section above +2.5mPD |
Proposed Public
Landing Steps |
Table 3.2 Implementation
of Environmental Mitigation Measures
General construction works |
· Effective water sprays used on the site at potential dust
emission sources such as haul roads and unpaved areas; · The heights from which fill materials are dropped should be
controlled to a practical height to minimize the fugitive dust arising from
unloading; · Minimize of exposed soil areas to reduce the potential for
increased siltation and contamination of run-off; · Water, hydro-seed or cover the open stockpile and exposed loose
soil areas by using clean tarpaulin sheets; · Provide proper and efficient drainage facilities (e.g. wheel washing
facilities) and sedimentation system to ensure that site runoff should be
treated before discharged to drains; · Remove the sand/rubbish accumulated in the drain/channel
regularly; · Use
and maintenance of silt curtain properly during marine works; · Provide good site practice (e.g. selection of quieter plant and
working methods and reduction in number of plant operating in critical areas
close to NSRs) to limit noise emissions at source; · Remove the construction waste accumulated inside or outside the
site regularly. |
4.0
AIR QUALITY MONITORING
4.1 Monitoring
Requirement
1-hour and 24-hour TSP monitoring were required to conducted
to monitor the air quality, at designated monitoring locations:
-
HKIB
Staff Accommodation (on ground floor near the entrance facing south-east);
-
Cheung
Shue Tan Village (near the outer building, temple) for 1-hr TSP monitoring;
-
Cheung
Shue Tan Village (in front of Man Kee Store) for 24-hr TSP monitoring;
-
Near
Wen Chih Tang at the CUHK.
4.2 Monitoring
Equipment
Continuous
24-hour TSP air quality monitoring was performed using a GMWS2310
High Volume Air Sampler (HVS) located at each of the designated monitoring
station. One portable dust meter
was used to carry out the 1-hour TSP monitoring. Table 4.1 summarizes the equipment used
in the air quality monitoring programme. A copy of the calibration certificates
for the HVS and portable dust meter are attached in Appendix B1.
Table 4.1 Air Quality Monitoring Equipment
Equipment |
Model and Make |
HVS |
Greasby GMWS2310 |
Calibrator |
Tisch TE-5025A |
1-hour TSP Dust Meter |
TSI Model 8520 Dust TrakTM Aerosol Monitor |
4.3 Monitoring
Parameters, Frequency and Duration
Table
4.2 summarizes the monitoring parameters, monitoring duration and frequencies
of air quality monitoring.
Table
4.2 Monitoring
parameters, duration, frequencies of impact air quality monitoring
Parameter |
Duration |
Frequency |
24-hr
TSP |
24
hr (0000-2400) |
Once
every six days |
1-hr
TSP |
1
hr (0700-1900) |
Three
times every six days |
4.4 Monitoring
Locations and Schedule
Table
4.3 tabulates the air quality monitoring locations of this project.
Table 4.3 Air
quality monitoring locations
Monitoring
stations |
Locations
|
AM1 |
HKIB
Staff Accommodation (on ground floor near the entrance facing south-east) for
1-hr TSP monitoring |
AM3 |
Cheung
Shue Tan Village (near the outer building, temple) for 1-hr TSP monitoring |
AM3A |
Cheung
Shue Tan (in front of Man Kee Store) for 24-hr TSP monitoring |
AM5 |
Near Wen
Chih Tang at the CUHK |
The air quality monitoring schedule for 24-hr and
1-hr TSP monitoring at designated monitoring locations is summarized in table
4.4.
Table
4.4 Monitoring
Schedule for the air quality monitoring stations
Air quality monitoring stations |
Location |
Monitoring
Period |
||||||||
24-hr TSP |
1-hr TSP |
|||||||||
Start |
Finish |
Date |
Start |
Finish |
||||||
Date |
Time |
Date |
Time |
|||||||
AM1 |
HKIB
Staff Accommodation |
--- |
04/07/06 |
10:45 |
11:45 |
|||||
06/07/06 |
10:15 |
11:15 |
||||||||
08/06/06 |
10:00 |
11:00 |
||||||||
11/07/06 |
09:30 |
10:30 |
||||||||
13/07/06 |
08:30 |
09:30 |
||||||||
15/07/06 |
09:15 |
10:15 |
||||||||
18/07/06 |
09:00 |
10:00 |
||||||||
20/07/06 |
09:30 |
10:30 |
||||||||
22/07/06 |
11:00 |
12:00 |
||||||||
25/07/06 |
09:20 |
10:20 |
||||||||
27/07/06 |
08:40 |
09:40 |
||||||||
29/07/06 |
09:40 |
10:40 |
||||||||
AM3 |
Cheung Shue Tan Village (Near the outer building, temple) |
--- |
04/07/06 |
13:06 |
14:06 |
|||||
06/07/06 |
13:00 |
14:00 |
||||||||
08/06/06 |
13:00 |
14:00 |
||||||||
11/07/06 |
10:55 |
11:55 |
||||||||
13/07/06 |
14:15 |
15:15 |
||||||||
15/07/06 |
14:00 |
15:00 |
||||||||
18/07/06 |
10:20 |
11:20 |
||||||||
20/07/06 |
13:00 |
14:00 |
||||||||
22/07/06 |
13:00 |
14:00 |
||||||||
25/07/06 |
15:10 |
16:10 |
||||||||
27/07/06 |
13:30 |
14:30 |
||||||||
29/07/06 |
13:30 |
14:30 |
||||||||
AM5 |
Near Wen Chih Tang at the CUHK |
--- |
04/07/06 |
14:28 |
15:28 |
|||||
06/07/06 |
16:00 |
17:00 |
||||||||
08/06/06 |
14:20 |
15:20 |
||||||||
11/07/06 |
18:00 |
19:00 |
||||||||
13/07/06 |
13:00 |
14:00 |
||||||||
15/07/06 |
15:20 |
16:20 |
||||||||
18/07/06 |
15:00 |
16:00 |
||||||||
20/07/06 |
14:30 |
15:30 |
||||||||
22/07/06 |
14:20 |
15:20 |
||||||||
25/07/06 |
17:06 |
18:06 |
||||||||
27/07/06 |
14:50 |
15:50 |
||||||||
29/07/06 |
15:30 |
16:30 |
||||||||
AM1 |
HKIB
Staff Accommodation |
04/07/06 |
10:55 |
05/07/06 |
10:53 |
--- |
||||
10/07/06 |
14:30 |
11/07/06 |
14:30 |
|||||||
15/07/06 |
09:20 |
16/07/06 |
08:22 |
|||||||
21/07/06 |
14:00 |
22/07/06 |
13:09 |
|||||||
27/07/06 |
08:45 |
28/07/06 |
08:40 |
|||||||
AM3A |
Cheung Shue Tan (in front of Man Kee Store) |
04/07/06 |
13:15 |
05/07/06 |
13:52 |
--- |
||||
10/07/06 |
15:05 |
11/07/06 |
15:05 |
|||||||
15/07/06 |
14:06 |
16/07/06 |
14:19 |
|||||||
21/07/06 |
14:20 |
22/07/06 |
14:27 |
|||||||
27/07/06 |
13:36 |
28/07/06 |
14:01 |
|||||||
AM5 |
Near Wen
Chih Tang at the CUHK |
04/07/06 |
14:38 |
05/07/06 |
14:48 |
--- |
||||
10/07/06 |
14:45 |
11/07/06 |
14:45 |
|||||||
15/07/06 |
16:25 |
16/07/06 |
16:54 |
|||||||
21/07/06 |
14:40 |
22/07/06 |
14:56 |
|||||||
27/07/06 |
14:55 |
28/07/06 |
14:59 |
|||||||
4.5 Monitoring
Methodology
4.5.1 24-hour TSP Monitoring
Instrumentation
High volume sampler, as HVS, (Greasby GMWS2310) complete
with appropriate sampling inlets are employed for 24-hour TSP. The sampler is composed of a motor, a
filter holder, a flow controller and a sampling inlet and its performance
specification complies with that required by USEPA standard Title 40, Code of
Federation Regulations Chapter 1 (Part 50).
Installation
The installation of HVS refers to the requirement stated in
EM&A Manual.
Operation/Analytical Procedures
Operating/analytical procedures for the operation of HVS
are as below:
Prior to the commencement of the dust sampling, the flow
rate of the high volume sampler was properly set (between 0.6m3/min
and 1.7m3/min.) in accordance with the manufacturer’s instruction to
within the range recommended in USEPA Standard Title 40, CFR Part 50.
·
For TSP sampling, fiberglass filters
(GA-55) were used.
·
The power supply was checked to ensure
the sampler worked properly.
·
On sampling, the sampler was operated 5
minutes to establish thermal equilibrium before placing any filter media at
designated air monitoring station.
·
The filter holding frame was then
removed by loosening the four nuts and carefully a weighted and conditioned
filter was centered with the stamped number upwards, on a supporting screen.
·
The filter was aligned on the screen so
that the gasket formed an air-tight seal on the outer edges of the filter. Then the filter holder frame was
tightened to the filter holder with swing bolts. The applied pressure should be
sufficient to avoid air leakage at the edges.
·
The programmable timer will be set for a
sampling period of 24 hours.
Information was recorded on the record sheet, which included the
starting time, the weather condition and the filter number (the initial weight
of the filter paper can be found out by using the filter number.).
·
After sampling, the filter was
transferred from the filter holder of the HVS to a sealed plastic bag and sent
to the laboratory for weighting.
The elapsed time was also recoded.
·
Before weighting, all filters were
equilibrated in a desiccator for 24 hour with the temperature of 25oC
+ 3oC and the relative humidity (RH) <50% +5%.
Maintenance & Calibration
·
The HVS and their accessories should be
maintained in good working condition, such as replacing motor brushes routinely
and checking electrical wiring to ensure a continuous power supply.
·
HVS should be calibrated at bi-monthly
intervals.
4.5.2 1-hour
TSP Monitoring
Measuring Procedures
The measuring procedures of the 1-hr dust meter are in
accordance with the Manufacturer’s instruction Manual as follows:
·
Set POWER to ON, check the battery
indicator to ensure whether the power supply is enough to conduct the TSP
monitoring;
·
Calibrate the dust meter by zero check;
·
Set the time constant of the dust meter;
·
Press sample
to start the TSP monitoring;
·
Record the maximum, minimum and average
reading directly from the dust meter by press Statistics
when monitoring complete.
Maintenance & Calibration
·
1-hr
dust meter should be checked at 3-month intervals and calibrated at 1-year
intervals throughout all stages of impact air quality monitoring.
4.5.3
Wind Data Monitoring
Wind data (wind speed and wind direction) were directly
extracted from Sha Tin Station (located at Sha Tin Race Course) of Hong Kong
Observatory. All wind data during this reporting month are shown in Appendix D.
4.6 Action
and Limit Levels
Action and Limit levels for 24-hr TSP and 1-hr TSP derived as
illustrated in Table 4.5.
Table 4.5 Action
and Limit Levels for 24-hr TSP and 1-hr TSP
Monitoring Location |
24-hr TSP (mg/m3) |
1-hr TSP (mg/m3) |
||
Action Level |
Limit Level |
Action Level |
Limit Level |
|
AM1 |
164 * |
260 * |
325 * |
500 * |
AM3 |
--- |
--- |
306 ** |
500 ** |
AM3A |
183 ** |
260 ** |
--- |
--- |
AM5 |
174 |
260 |
329 |
500 |
* = Reference
to the information contained in the Baseline Monitoring Report submitted under
the “Advance Engineering Infrastructure Works for Pak Shek Kok Development –
Southern Access Road and Sewage Pumping Station No.3.
** = Reference to the information contained in the Baseline Monitoring Report
submitted under the “Remaining Engineering Infrastructure Works for Pak Shek
Kok Development Package 1 – Contract No. TP 35/02.
4.7 Event-Action Plans
Please
refer to Appendix E for details.
4.8 Results
4.8.1 24-hour TSP Monitoring
All monitoring data
of 24-hour TSP monitoring is provided in Appendix B2. Graphical presentation of
24-hour TSP monitoring results for the reporting month is shown in Appendix B3.
No exceedances of Action and Limit Level of 24-hour TSP
monitoring results were recorded during the reporting month.
4.8.2 1-hour TSP Monitoring
1-hour TSP monitoring was carried out at monitoring
stations, AM1 and AM3 in the reporting month. All monitoring data of 1-hour TSP
monitoring is provided in Appendix B2. Graphical presentation of 1-hour TSP
monitoring results for the reporting month is shown in Appendix B3.
No exceedances of Action and Limit Level of 1-hour TSP
monitoring results were recorded during the reporting month.
5.0 Noise
Monitoring
5.1 Monitoring
Requirements
As the requirement in EM&A Manual, noise monitoring was
conducted at designated monitoring locations:
-
HKIB
Staff Accommodation (on ground floor near the entrance facing south-east);
-
Cheung
Shue Tan Village (near the outer building, temple);
- CUHK Residence No.10;
- Near Wen Chih Tang at the CUHK.
5.2 Monitoring
Equipment
Integrating Sound Level Meters were used for noise
monitoring. They were Type 1 sound level meters capable of giving a continuous
readout of the noise level reading including equivalent continuous sound
pressure level (Leq) and percentile sound pressure level (Lx). They
comply with International Electro technical Commission Publications 651:1979
(Type1) and 804:1985 (Type1), and speed in m/s was used to monitor the wind
speed.
Table 5.1 summarized noise monitoring equipment model being
used. A copy of the calibration certificates for noise meters and calibrator
are attached in Appendix C1.
Table 5.1 Noise Monitoring Equipment
Equipment |
Model |
Integrating
Sound Level Meter |
Rion
NL-31 Sound Level Meter |
Calibrator |
Rion
NL-73 Sound Level Calibrator |
Portable
Wind Speed Indicator |
TSI
Model 8340-M Air Velocity Meter |
5.3 Monitoring
Parameters, duration and Frequency
Noise monitoring for the A-weighted levels Leq, L10 and L90
were recorded. The following guide
on the regular monitoring frequency for each monitoring station on a per week
basis when noise generating activities are underway:
· One
set of measurements between 0700-1900 hours on normal weekdays (6 consecutive Leq(5-min));
· One
set of measurements between 1900-2300 hours (3 consecutive Leq(5-min))*;
· One
set of measurements between 2300-0700 hours of next day (3 consecutive Leq(5-min))*;
· One
set of measurements between 0700-1900 hours on holidays (3 consecutive Leq(5-min))*.
(*): Noise
monitoring to be conducted only when there is construction work.
Duration,
frequencies and parameters of noise measurement are presented in Table 5.2.
Table
5.2 Duration,
Frequencies and Parameters of Noise Monitoring
Time
period |
Duration/min |
Parameters |
Frequency |
Day-time:
0700-1900 hrs on normal weekday |
30 |
Leq,
L10, L90 |
Once
per week |
Evening-time:
1900-2300 hrs |
15 |
Leq,
L10, L90 |
Once per week |
Night-time:
2300-0700 hrs of next day |
15 |
Leq,
L10, L90 |
Once per week |
Holiday: 0700-1900 hrs |
15 |
Leq,
L10, L90 |
Once per week |
5.4 Monitoring
Locations and Period
In this reporting
month, there were four noise monitoring locations: HKIB Staff Accommodation,
Cheung Shue Tan Village, CUHK Residence No.10 and Near Wen Chih Tang at the
CUHK. The location of the monitoring stations are described in Table 5.3 and
depicted in Figure 1.
Table
5.3 Noise
Monitoring Locations
Noise
Monitoring station |
Location |
NM1 |
HKIB
Staff Accommodation (on
ground floor near the entrance facing south-east) |
NM2 |
CUHK
Residence No.10 |
NM3 |
Cheung
Shue Tan Village (near the outer building, a temple) |
NM8 |
Near Wen
Chih Tang at the CUHK |
The noise-monitoring programme of monitoring
locations (Day-time, Evening-time, Holiday and Night-time) is summarized in
Table 5.4.
Table
5.4 Monitoring
Periods for noise monitoring stations
Monitoring stations |
Monitoring Period |
|||||||
Day-time |
Evening-time |
Holiday |
Night-time |
|||||
NM1 |
04/07/06 |
10:50 |
--- |
--- |
--- |
--- |
--- |
--- |
11/07/06 |
13:10 |
--- |
--- |
--- |
--- |
--- |
--- |
|
18/07/06 |
09:02 |
--- |
--- |
--- |
--- |
--- |
--- |
|
25/07/06 |
09:25 |
--- |
--- |
--- |
--- |
--- |
--- |
|
NM2 |
04/07/06 |
17:38 |
--- |
--- |
--- |
--- |
--- |
--- |
11/07/06 |
16:10 |
--- |
--- |
--- |
--- |
--- |
--- |
|
18/07/06 |
16:15 |
--- |
--- |
--- |
--- |
--- |
--- |
|
25/07/06 |
18:30 |
--- |
--- |
--- |
--- |
--- |
--- |
|
NM3 |
04/07/06 |
13:11 |
--- |
--- |
--- |
--- |
--- |
--- |
11/07/06 |
17:15 |
--- |
--- |
--- |
--- |
--- |
--- |
|
18/07/06 |
10:22 |
--- |
--- |
--- |
--- |
--- |
--- |
|
25/07/06 |
15:15 |
--- |
--- |
--- |
--- |
--- |
--- |
|
NM8 |
04/07/06 |
14:33 |
--- |
--- |
--- |
--- |
--- |
--- |
11/07/06 |
18:15 |
--- |
--- |
--- |
--- |
--- |
--- |
|
18/07/06 |
15:02 |
--- |
--- |
--- |
--- |
--- |
--- |
|
25/07/06 |
17:25 |
--- |
--- |
--- |
--- |
--- |
--- |
5.5 Monitoring
Procedures and Calibration Details
Operation/Analysis
Procedures
·
The Sound Level Meter was set on a
tripod at a height of 1.2m above the ground.
·
For free field measurement, the meter
was positioned away from any nearby reflective surfaces.
·
The battery condition was checked to
ensure the correct functioning of the meter.
·
Parameters such as frequency weighting,
the time weighting and the measurement time were set as follows:
-
Frequency weighting: A
-
Time weighting
: Fast
-
Time measurement :
5 mins
·
Prior to and after each noise
measurement, the meter was calibrated using a Calibrator for 94 dB at
1000HZ. If the difference in the
calibration level before and after measurement was more than 1dB(A), the measurement
would be considered invalid and repeat measurement would be required after
re-calibration or repair of the equipment.
·
The wind speed was frequently checked
with a portable wind meter.
·
During the monitoring period, the Leq,
L10 and L90 were recorded. In
addition, site conditions and noise sources were recorded on a standard record
sheet.
·
Free Field correction to the measurements should be
made. Correction factor of +3dB(A) should be made to the free Field
measurements.
·
Noise monitoring would be cancelled in
the presence of fog, rain, wind with a steady speed exceeding 5m/s, or wind
gusts exceeding 10m/s.
Maintenance and Calibration
·
The microphone head of the sound level
meter and calibrator is cleaned with soft cloth at quarterly intervals.
·
The meter is sent to be supplier or HOKLAS
laboratory to check and calibrated at yearly intervals.
5.6 Action
and Limit Levels
The Action and Limit levels for noise levels derived as illustrated in
Table 5.5.
Table 5.5 Action and Limit Levels
for noise monitoring
Time
Period |
Time
Period |
Action |
Limit |
Normal hours |
0700-1900
hrs on normal weekdays |
When
one documented complaint is received |
75
dB(A) * |
Holiday |
0700-1900
hrs on holidays |
70
dB(A) ** |
|
Evening-time |
1900-2300
hrs on all other days |
||
Night-time |
2300-0700
hrs of next day |
55
dB(A) ** |
* = Reduce to 70 dB(A) for
schools and 65 dB(A) during school examination periods.
** = Area
Sensitivity Rating (ASR) C is selected from the “Technical Memorandum on Noise
from Construction Work Other Than Percussive Piling”.
5.7 Event-Action Plans
Please
refer to the Appendix E for details.
5.8 Results
Only Day-time noise monitoring were carried out at
monitoring stations in this reporting month. No Evening-time, Night-time and
Holiday noise monitoring were required since no construction works were
processed during the night-time period. All noise levels are provided in
Appendix C2. Graphical presentation of the monitoring results for the reporting
month is shown in Appendix C3.
No Day-time noise monitoring results at all monitoring
stations exceeded the Action Level since no documented complaints on noise
issue were received in this reporting month. Besides, no exceedances in Limit
Level were recorded according to the results from Day-time noise monitoring.
6.0
Wastewater monitoring
Effluent Discharge
License of this Project is valid from 06 December 2004 (Discharge Licence No.:
3246-Part A and Part B).
During this reporting month, wastewater monitoring was carried out at Pak
Shek Kok Workshop Area Adjacent to Site Office on 13 July 2006. One wastewater
sample was collected from the discharge point during the monitoring. The result
of suspended solids content of the wastewater sample was complied the discharge
limit of the Discharge Licence. The test report was attached at Appendix I.
Since the Discharge Licence required carrying out wastewater
monitoring at effluent discharge point quarterly, the next wastewater
monitoring should be at October 2006.
7.0
Environmental Non-conformance
7.1
Summary of environmental monitoring
No exceedances of Action and Limit Level of 24-hour and
1-hour TSP monitoring results were recorded during the reporting month.
No
day-time noise level measured at all monitoring stations exceeded the Action
and Limit Level in the reporting month. No evening-time, night-time and holiday
noise monitoring were required since no construction works were processed
during these periods.
During this reporting month, wastewater monitoring was carried out at Pak
Shek Kok Workshop Area Adjacent to Site Office on 13 July 2006. One wastewater
sample was collected from the discharge point during the monitoring. The result
of suspended solids content of the wastewater sample was complied the discharge
limit of the Discharge Licence.
7.2
Summary of Environmental Complaints
No environmental complaints were received in this monitoring
month.
7.3 Summary
of Notification of Summons and Prosecution
There
was no notification of summons respect to environmental issues registered in
this month.
8.0 SITE INSPECTION
Weekly
site inspections were carried out by the ET in this reporting month (08, 13, 21
and 29 July 2006). Monthly joint site inspection at 21 July 2006 was carried
out by Engineer’s Representative, IEC and LWKJV. The implementation status of
the mitigation measures on site inspections in this reporting month is
presented in Appendix H.
8.1
Summary of the site inspection findings and Action(s) taken by
LWKJV and ET
Summaries of the site
inspection findings in this reporting month are shown in Table 8.1.
Table
8.1 The summary of
the site inspection findings and Action(s) taken by LWKJV and ET
Item |
Aspects |
Findings |
Action(s) taken by
LWKJV |
ET Verification |
1 |
Air |
Stockpiles at SA3 were found covered improperly during the
weekly site inspections on 08/07/06 and 13/07/06. |
LWKJV replied to hydro-seed the stockpiles as soon as possible. |
Since the stockpiles were found to be hydro-seeded during the
subsequent weekly site inspection (21/07/06), no further verification was
required to be taken by ET. |
2 |
Air |
Silt and sand track was observed on the public road between SA1
and SA3 during weekly site inspection on 21/07/06. |
LWKJV replied to clean up the road immediately. |
During the subsequent weekly site inspection, no silt and sand
track was observed and hence no further verification was required. |
3 |
Air |
Stockpiles at SA1 were found without cover during weekly site
inspections on 21/07/06 and 29/07/06. |
LWKJV replied to cover the stockpiles with tarpaulin sheets to
avoid dust generation. |
Since the finding was still noted during the last inspection of
this reporting month, it will be verified during the first weekly site
inspection of the coming month. |
4 |
Water |
Follow up action to the finding of previous month, damaged part
of silt curtain at Node 2 was found to have repaired during weekly site
inspection on 21/07/06. |
Since the finding was improved, no further action was required
to be taken by LWKJV. |
Since the finding was improved, no further ET verification was
required. |
5 |
Water |
Storm water was found to be accumulated at Node 1 and SA1 during
weekly site inspection on 08/07/06. |
LWKJV replied to provide temporary ditches to drain the
accumulated storm water out. |
During the subsequent weekly site inspection on 13/07/06, no
storm water was found at Node 1and SA1. Hence, no further verification was
required. |
6 |
Water |
Wastewater was found directly discharged to u-channel during
weekly site inspection on 29/07/06. |
LWKJV replied to divert the wastewater to sedimentation tank
before discharge. |
Since the finding was observed at the last inspection of this
reporting month, it will be verified during the first weekly site inspection
of the coming month. |
Item |
Aspects |
Findings |
Action(s) taken by
LWKJV |
ET Verification |
7 |
Water |
Manhole at SA3 was found full of silt and mud during weekly site
inspection on 13/07/06. |
LWKJV replied to clean up the silt and mud inside the manhole
immediately. |
During the subsequent weekly site inspection on 21/07/06, no
silt and mud was found inside the manhole. Since the finding was improved, no
further verification was required. |
8 |
Water |
Stagnant water was accumulated at Workshop during weekly site
inspection on 29/07/06. |
LWKJV replied to provide temporary ditches to drain the
accumulated storm water out. |
Since the finding was observed at the last inspection of this
reporting month, it will be verified during the first weekly site inspection
of the coming month. |
9 |
Water |
Muddy water was observed at cycle track near Ma Liu Shui site
entrance during weekly site inspection on 29/07/06. |
LWKJV replied to clean up the muddy water immediately. |
Since the finding was observed at the last inspection of this
reporting month, it will be verified during the first weekly site inspection
of the coming month. |
10 |
Chemical |
A 200L chemical container was found at SA3 without drip tray
during weekly site inspection on 21/07/06. |
LWKJV replied to relocate the chemical container to an
appropriate chemical storage area. |
During the subsequent weekly site inspection on 29/07/06, the
chemical container was removed. |
11 |
Chemical |
Follow up action to the finding of previous month, an
appropriate chemical storage area was provided at Workshop during weekly site
inspection on 27/07/06. |
Since the finding was improved, no further action was taken by
LWKJV. |
Since the finding was improved, no further verification was
required to be taken by ET. |
12 |
Site Practice |
Valid CNP was recommended to be post on the notice board of site
office during weekly site inspection on 21/07/06.. |
LWKJV replied to post the valid CNP immediately. |
Since the valid CNP was found post during weekly site inspection
on 29/07/06, the finding was improved and no further verification was
required. |
8.2
Status of Environmental Licensing and Permitting
All permits/licenses valid in this reporting month are
summarized in Table 8.2.
Table 8.2 Summary
of environmental licensing and permit status
Description |
Permit No. |
Valid Period |
Section |
|
From |
To |
|||
Construction Noise Permit for the Construction Works of the
Project at Pak Shek Kok Development Package 2A, Tai Po |
GW-RN0006-06 |
26/01/06 |
25/07/06 |
Group A Two Poker, vibratory, hand-held (CNP170) Two Concrete lorry mixer (CNP044) One Excavator, tracked (CNP081) Group B One Dump Truck (CNP067) One Excavator, tracked (CNP081) Group C One Asphalt Paver (CNP004) One Roller, Vibratory (CNP186) One Road Roller (CNP185) One Dump Truck (CNP067) Group D One Dump Truck (CNP067) One Excavator, tracked (CNP081) One Crane, mobile (diesel) (CNP048) One Lorry with crane |
Construction Noise Permit for Reclamation area of Science Park
Phase 2 & 3, Pak Shek Kok, N.T. |
GW-RN0305-06 |
17/06/06 |
16/12/06 |
Group A Two Derrick Barge (CNP061) One Tug Boat (CNP221) One Generator, standard (CNP101) Group B Two Excavator, tracked (CNP081) Two Dump truck (CNP067) One Generator, standard (CNP101) |
Description |
Permit No. |
Valid Period |
Section |
|
From |
To |
|||
Construction Noise Permit for the use of Powered Mechanical
Equipment for the Purpose of carrying out Construction Work other than
Percussive Piling and/or the carrying out of prescribed Construction Work |
GW-RN0240-06 |
30/05/06 |
29/12/06 |
Group A Two Poker, vibrator, hand-held (CNP170) Two Concrete pump, lorry mounted (CNP047) Two Concrete lorry mixer (CNP044) Group B One Dump Truck (CNP067) One Excavator, tracked (CNP081) One Roller, vibratory Group C One Asphalt Paver (CNP004) One Roller, Vibratory (CNP186) One Road Roller (CNP185) One Dump Truck (CNP067) Group D One Dump Truck (CNP067) One Excavator, tracked (CNP081) One Crane, mobile (diesel) (CNP048) One Lorry with crane |
Construction Noise Permit for the Construction Works of the
Project at Pak Shek Kok Development Package 2A, Tai Po |
GW-RN0388-06 |
27/07/06 |
26/01/07 |
Group A Two Poker, vibratory, hand-held (CNP170) Two Concrete lorry mixer (CNP044) One Excavator, tracked (CNP081) Group B One Dump Truck (CNP067) One Excavator, tracked (CNP081) Group C One Asphalt Paver (CNP004) One Roller, Vibratory (CNP186) One Road Roller (CNP185) One Dump Truck (CNP067) Group D One Dump Truck (CNP067) One Excavator, tracked (CNP081) One Crane, mobile (diesel) (CNP048) One Lorry with crane |
Construction Noise Permit for the use of Powered Mechanical
Equipment for the Purpose of carrying out Construction Work other than
Percussive Piling and/or the carrying out of prescribed Construction Work |
GW-RN0307-06 |
21/06/06 |
20/12/06 |
Group A One Derrick Barge (CNP061) Four Dump truck, 5.5 tonne < gross vehicle weight < 38
tonne One Excavator, tracked (CNP081) One Generator, standard (CNP101) Group B One Derrick Barge (CNP061) One Tug Boat (CNP221) One Generator, standard (CNP101) |
Construction Noise Permit for Ma Liu Shui Bridge at Sui Cheung
Street adjacent to Ma Liu Shui |
GW-RN0347-06 |
26/06/06 |
08/07/06 |
One Crane, mobile (diesel) (CNP048) Two Lorry with crane Two welding set |
Wastewater Discharge License |
3246 – Part A |
06/12/04 |
05/12/09 |
Discharge of trade Effluent, surface run-off and all other
wastewater arising from the construction site and sedimentation tank to
Coastal water or communal drain for the carriage of surface drainage water. |
Wastewater Discharge License |
3246 – Part B |
06/12/04 |
05/12/09 |
Discharge of trade Effluent, surface run-off and all other
wastewater arising from the construction site and on-site aerobic waste water
treatment system to soak-away pit. |
Chemical Waste Producer |
5113-729-LL1113-01 |
24/09/04 |
--- |
Spent lubricating oil, spent battery parts containing heavy
metals |
8.3
Recommendations on site inspection findings in Site Inspections of
this month
Based on the site inspection findings, the recommendations
are as below:
· All stockpiles should be covered with clean tarpaulin sheets,
spraying with water or hydro-seeding to avoid wind and water erosion;
· The heights from which fill materials are dropped should be
controlled to a practical height to minimize the fugitive dust arising from
unloading;
· Minimize of exposed soil areas to reduce the potential for increased
siltation and contamination of run-off;
· Checking and maintaining
all the site machines to prevent dust emission;
· Providing briefing to the
concerned site staff on remedial actions, such as handling method of chemicals
and chemical waste;
·
Use and maintenance of silt curtain properly during
marine works;
· Provide good site practice (e.g. selection of quieter plant and
working methods and reduction in number of plant operating in critical areas
close to NSRs) to limit noise emissions at source;
· Maintain good waste management at the site.
9.0
Waste Management
9.1 Waste
Management Audit
Waste
management audit was carried out by the ET on a weekly basis. The
implementation status of the mitigation measures on waste management in this
reporting month is presented in Appendix H.
9.2
Records of Waste Quantities
All
type of wastes arising from the construction work are classified into the
following:
· General refuses;
· Chemical waste;
· Construction & demolition
(C&D) material.
The
quantities of waste for disposal in this month are summarized in Table 9.1.
Table 9.1 Summary
of Quantities of Waste for Disposal in this reporting month
Type of Waste |
Quantity |
Disposal Location |
Cumulative Quantity |
|
Inert C&D Materials |
Total Quantity Generated (m3) |
3000 |
Reused in the Contract |
113365 |
Broken Concrete (m3) |
0 |
N/A |
865 |
|
Reused in the Contract (m3) |
3000 |
N/A |
112500 |
|
Reused in other Projects (m3) |
0 |
N/A |
0 |
|
Disposal as Public Fill (m3) |
0 |
N/A |
0 |
|
C&D Waste |
Metals (1000kg) |
0.050 |
N/A |
37.565 |
Paper/Cardboard Packaging (1000kg) |
0.100 |
N/A |
1.136 |
|
Plastics (1000kg) |
0.010 |
N/A |
0.043 |
|
Chemical Waste (1000kg) |
0.000 |
N/A |
3.000 |
|
Other, e.g. General Refuse (1000kg) |
48.37 |
SENT |
246.98 |
10.0 Implementation
Status
10.1 Implementation
Status of Environmental Mitigation Measures
LWKJV has been implementing the required
environmental mitigation measures according to the Mitigation Protection
Measures stated in Implementation Schedule of the EM&A Manual. The
implementation status of the environmental mitigation measures in this
reporting month is presented in Appendix H.
Air Quality
The Contractor was reminded to water or cover all the stockpiles
by using clean tarpaulin sheets. The Contractor was also reminded to cleanup
the access road regularly to avoid dust emission and provide effective wheel washing
facilities.
Noise
All mitigation measures stated in Appendix H were implemented
properly in this reporting month.
Water Quality
The Contractor was reminded to provide more effort to implement
mitigation measures, such as diverting site runoff to suitable treatment
processes before discharge, sedimentation system and drainage facilities.
Waste Management
LWKJV
has been implementing most mitigation measures on waste management.
10.2
Implementation Status of Event and Action Plan
There were no exceedances in air quality and noise monitoring
parameters recorded in this monitoring month. No further mitigation measures
were required.
10.3 Implementation
Status of Environmental Complaint Handling
No
complaints had been received during this monitoring month.
11.0 Conclusion
Impact monitoring of air quality and noise were carried out at
designated locations in accordance with the EM&A Manual in this reporting
month.
According to the summary of air and noise monitoring results, no exceedances of Action and Limit Level of
24-hour and 1-hour TSP monitoring results were recorded during the reporting
month. Besides, No Day-time noise level measured at all monitoring stations
exceeded the Action and Limit Level in the reporting month. No Evening-time,
Night-time and Holiday noise monitoring were required since no construction
works were processed during these periods.
During this reporting month, wastewater monitoring was carried out at Pak
Shek Kok Workshop Area Adjacent to Site Office on 13 July 2006. One wastewater
sample was collected from the discharge point during the monitoring. The result
of suspended solids content of the wastewater sample was complied the discharge
limit of the Discharge Licence.
According to the ET weekly site inspection and IEC monthly
site audit carried out this month, it indicated that site practices of the
LWKJV were generally undertaken in an environmentally acceptable manner and the
overall site environmental performance was satisfactory.
12.0
Future Key Issues
12.1
Upcoming
EM&A Schedule in coming two months
The Proposed EM&A program in coming two months are presented as
following table:
Table 12.1 Upcoming
EM&A Schedule in coming two months
Type of Monitoring |
August 2006 |
September 2006 |
Noise Monitoring (Day-time) |
01, 08, 15, 22, 29 |
05, 12, 19, 26 |
1-hour TSP |
01, 03, 05, 08, 10, 12, 15, 17, 19, 22,24,26, 29, 31 |
02, 05, 07, 09, 12, 14, 16, 19, 21, 23, 26, 28, 30 |
24-hour TSP |
02, 08, 14, 19, 25, 31 |
06, 12, 18, 23, 29 |
Site Inspection |
03, 10, 17, 24, 31 |
07, 14, 21, 28 |
12.2
Upcoming
construction works schedule in the coming months
The major
construction works planned to be carried out in next two months and their
possible impact is tabulated (Table 12.2) for reference.
Table 12.2 Construction Plan in
the coming months
Month |
Works Planned to be Carried Out |
Between August and September 2006 |
§ Drainage
Works (excavation, pipe lying and breaking) at Section 1 and 2 (Ma Liu Shui),
7 and 8 (Promenade) of the Works; § Installation
of watermains at Section 1 of the Works; § Steel
fixing and concreting of beam and wall at Voided Abutment, construction of RE
wall and pile cap at North Abutment, and erection of formwork and falsework
for deck costruction for the Alternative Design of the proposed Ma Liu Shui
Bridge; § Construction
of Retaining Wall No.1; § Construction
of pedestrian ramps and barrel of the proposed Ma Liu Shui Subway
(Alternative Design); § Construction
of wall and columns, and installation of sewerage and drainage system for
Toilet No.2; § Paving
of footpath at the proposed Road L4 under Section 5 of the Works; § Installation
of additional valves and connection for watermains at the cycle track,
pavement construction and fencing erection at Section 6 of the Works; § Installation
of public light footing and duct along the proposed Promenade, construction
of hard landscape structures, and CCTV inspection of the completed drainage
pipes; § Hard
landscaping works at Section 7 of the Works; § Constructon
of mass concrete coping at the proposed Landscape Node P1, P2 & P3; § Installation
of precast concrete planter and parapet wall units along the proposed
Promenade at Section 8 of the Works; § Construction
of in-situ concreting of section above +2.5mPD and shelter foundation at the
proposed Public Landing Steps; § Setting
back of surcharge mound at Housing Site 4 as per VO/146; § Filling
of soil mix at planter wall. |
Appendix
A
Organization Chart and Lines of Communication
Engineer/Engineer’s
Representative Hyder
Consulting Ltd |
Independent
Environmental Checker Hyder
Consulting Ltd. |
CEDD |
Contractor Leader – Wai
Kee (C&T) Joint Venture. |
Environmental
Team (Environmental Team Leader ETS-Testconsult
Ltd. |
Appendix B1
Calibration Certificates for
Air Quality Monitoring Equipments
Appendix B2
Air Quality Monitoring Results
Summary
of 24-hr TSP Monitoring Results
Monitoring Station : AM1
Location : HKIB Staff Accommodation
Start |
Finish |
Elapse
Time |
Sampling
Time (hrs) |
Flow
Rate (m3/min.) |
Average (m3/min.) |
Filter
Weight (g) |
Conc.
(mg/m3) |
Weather
Condition |
|||||
Date |
Time |
Date |
Time |
Initial |
Final |
Initial |
Final |
Initial |
Final |
||||
04/07/06 |
10:55 |
05/07/06 |
10:53 |
10245.99 |
10269.96 |
23.97 |
1.34 |
1.34 |
1.34 |
2.8955 |
2.9730 |
40 |
Cloudy |
10/07/06 |
14:30 |
11/07/06 |
14:30 |
10269.96 |
10293.96 |
24.00 |
1.16 |
1.16 |
1.16 |
2.8933 |
2.9582 |
39 |
Cloudy |
15/07/06 |
09:20 |
16/07/06 |
08:22 |
10293.96 |
10316.99 |
23.03 |
1.17 |
1.17 |
1.17 |
2.8119 |
2.8740 |
38 |
Rainy |
21/07/06 |
14:00 |
22/07/06 |
13:09 |
10316.99 |
10340.14 |
23.15 |
1.17 |
1.17 |
1.17 |
2.9135 |
2.9649 |
32 |
Sunny |
27/07/06 |
08:45 |
28/07/06 |
08:40 |
10340.14 |
10364.05 |
23.91 |
0.96 |
0.96 |
0.96 |
2.9068 |
2.9652 |
42 |
Rainy |
Monitoring Station :
AM3A
Location :
Cheung Shue Tan (in front of
Man Kee Store)
Start |
Finish |
Elapse
Time |
Sampling
Time (hrs) |
Flow
Rate (m3/min.) |
Average (m3/min.) |
Filter
Weight (g) |
Conc.
(mg/m3) |
Weather
Condition |
|||||
Date |
Time |
Date |
Time |
Initial |
Final |
Initial |
Final |
Initial |
Final |
||||
04/07/06 |
13:15 |
05/07/06 |
13:52 |
15611.99 |
15636.61 |
24.62 |
1.20 |
1.20 |
1.20 |
2.8978 |
2.9266 |
16 |
Cloudy |
10/07/06 |
15:05 |
11/07/06 |
15:05 |
15636.61 |
15660.61 |
24.00 |
1.35 |
1.35 |
1.35 |
2.8657 |
2.9179 |
27 |
Cloudy |
15/07/06 |
14:06 |
16/07/06 |
14:19 |
15660.61 |
15684.82 |
24.21 |
1.34 |
1.34 |
1.34 |
2.8967 |
2.9567 |
31 |
Rainy |
21/07/06 |
14:20 |
22/07/06 |
14:27 |
15684.82 |
15708.94 |
24.12 |
1.34 |
1.34 |
1.34 |
2.9020 |
2.9400 |
20 |
Sunny |
27/07/06 |
13:36 |
28/07/06 |
14:01 |
15708.94 |
15733.36 |
24.42 |
1.34 |
1.34 |
1.34 |
2.8993 |
2.9789 |
41 |
Rainy |
Monitoring Station :
AM5
Location :
Near Wen Chin Tung at the
CUHK
Start |
Finish |
Elapse
Time |
Sampling
Time (hrs) |
Flow
Rate (m3/min.) |
Average (m3/min.) |
Filter
Weight (g) |
Conc.
(mg/m3) |
Weather
Condition |
|||||
Date |
Time |
Date |
Time |
Initial |
Final |
Initial |
Final |
Initial |
Final |
||||
04/07/06 |
14:38 |
05/07/06 |
14:48 |
5638.22 |
5662.38 |
24.16 |
1.23 |
1.23 |
1.23 |
2.8934 |
2.9412 |
27 |
Cloudy |
10/07/06 |
14:45 |
11/07/06 |
14:45 |
5662.38 |
5686.38 |
24.00 |
1.04 |
1.04 |
1.04 |
2.8809 |
2.9407 |
40 |
Cloudy |
15/07/06 |
16:25 |
16/07/06 |
16:54 |
5686.38 |
5710.86 |
24.48 |
1.08 |
1.08 |
1.08 |
2.8842 |
2.9159 |
20 |
Rainy |
21/07/06 |
14:40 |
22/07/06 |
14:56 |
5710.86 |
5735.13 |
24.27 |
1.08 |
1.08 |
1.08 |
2.9020 |
2.9474 |
29 |
Sunny |
27/07/06 |
14:55 |
28/07/06 |
14:59 |
5735.13 |
5759.19 |
24.06 |
1.00 |
1.00 |
1.00 |
2.8949 |
2.9458 |
35 |
Rainy |
Summary of 1-hr TSP Monitoring Results
Monitoring Station :
AM1 (HKIB Staff
Accommodation)
Date |
Monitoring Period |
1-hr TSP (mg/m3) |
Weather |
|||
Start |
Finish |
Minimum |
Maximum |
Average |
||
04/07/06 |
10:45 |
11:45 |
82 |
344 |
153 |
Cloudy |
06/07/06 |
10:15 |
11:15 |
90 |
387 |
155 |
Sunny |
08/06/06 |
10:00 |
11:00 |
87 |
362 |
143 |
Cloudy |
11/07/06 |
09:30 |
10:30 |
92 |
324 |
141 |
Rainy |
13/07/06 |
08:30 |
09:30 |
97 |
453 |
217 |
Sunny |
15/07/06 |
09:15 |
10:15 |
73 |
392 |
118 |
Rainy |
18/07/06 |
09:00 |
10:00 |
105 |
403 |
230 |
Cloudy |
20/07/06 |
09:30 |
10:30 |
82 |
377 |
153 |
Sunny |
22/07/06 |
11:00 |
12:00 |
92 |
389 |
160 |
Sunny |
25/07/06 |
09:20 |
10:20 |
106 |
417 |
168 |
Cloudy |
27/07/06 |
08:40 |
09:40 |
85 |
347 |
119 |
Rainy |
29/07/06 |
09:40 |
10:40 |
68 |
306 |
128 |
Rainy |
Monitoring Station :
AM3 – Cheung
Shue Tan Village (near the outer building, a temple)
Date |
Monitoring Period |
1-hr TSP (mg/m3) |
Weather |
|||
Start |
Finish |
Minimum |
Maximum |
Average |
||
04/07/06 |
13:06 |
14:06 |
75 |
316 |
117 |
Cloudy |
06/07/06 |
13:00 |
14:00 |
71 |
356 |
120 |
Sunny |
08/06/06 |
13:00 |
14:00 |
62 |
312 |
104 |
Cloudy |
11/07/06 |
10:55 |
11:55 |
78 |
305 |
116 |
Rainy |
13/07/06 |
14:15 |
15:15 |
65 |
492 |
169 |
Sunny |
15/07/06 |
14:00 |
15:00 |
62 |
317 |
100 |
Rainy |
18/07/06 |
10:20 |
11:20 |
64 |
327 |
113 |
Cloudy |
20/07/06 |
13:00 |
14:00 |
76 |
396 |
111 |
Sunny |
22/07/06 |
13:00 |
14:00 |
60 |
310 |
99 |
Sunny |
25/07/06 |
15:10 |
16:10 |
91 |
364 |
135 |
Cloudy |
27/07/06 |
13:30 |
14:30 |
63 |
306 |
99 |
Rainy |
29/07/06 |
13:30 |
14:30 |
57 |
286 |
109 |
Rainy |
Summary of 1-hr TSP Monitoring Results
Monitoring Station :
AM5 – Near
Wen Chih Tang at the CUHK
Date |
Monitoring Period |
1-hr TSP (mg/m3) |
Weather |
|||
Start |
Finish |
Minimum |
Maximum |
Average |
||
04/07/06 |
14:28 |
15:28 |
88 |
358 |
157 |
Cloudy |
06/07/06 |
16:00 |
17:00 |
86 |
396 |
150 |
Sunny |
08/06/06 |
14:20 |
15:20 |
79 |
330 |
116 |
Cloudy |
11/07/06 |
18:00 |
19:00 |
85 |
336 |
122 |
Rainy |
13/07/06 |
13:00 |
14:00 |
82 |
388 |
193 |
Sunny |
15/07/06 |
15:20 |
16:20 |
58 |
276 |
85 |
Rainy |
18/07/06 |
15:00 |
16:00 |
70 |
359 |
122 |
Cloudy |
20/07/06 |
14:30 |
15:30 |
79 |
381 |
133 |
Sunny |
22/07/06 |
14:20 |
15:20 |
76 |
345 |
112 |
Sunny |
25/07/06 |
17:06 |
18:06 |
99 |
399 |
154 |
Cloudy |
27/07/06 |
14:50 |
15:50 |
70 |
327 |
106 |
Rainy |
29/07/06 |
15:30 |
16:30 |
60 |
312 |
114 |
Rainy |
Appendix B3
Graphical Plots of Air Quality Monitoring Data
Appendix C1
Calibration Certificates for
Noise Monitoring Equipments
Appendix C2
Noise Monitoring Results
Day-time Noise Monitoring
Monitoring
Location: NM1 (HKIB Staff Accommodation)
Date |
Start
Sampling Time (hh:mm) |
Noise Level
dB (A) |
Wind Speed (m/s) |
Weather Condition |
||
Leq(30min) |
L10 |
L90 |
||||
04/07/06 |
10:50 |
59.2 |
62.4 |
56.7 |
1.3 |
Cloudy |
11/07/06 |
13:10 |
58.1 |
60.7 |
52.7 |
1.1 |
Cloudy |
18/07/06 |
09:02 |
58.1 |
60.1 |
57.0 |
0.8 |
Cloudy |
25/07/06 |
09:25 |
60.3 |
61.7 |
57.5 |
1.2 |
Cloudy |
Monitoring
Location: NM2 (CUHK Residence No.10)
Date |
Start
Sampling Time (hh:mm) |
Noise Level
dB (A) |
Wind Speed (m/s) |
Weather Condition |
||
Leq(30min) |
L10 |
L90 |
||||
04/07/06 |
17:38 |
57.8 |
61.2 |
55.3 |
1.0 |
Cloudy |
11/07/06 |
16:10 |
57.9 |
60.1 |
52.7 |
0.9 |
Cloudy |
18/07/06 |
16:15 |
56.2 |
58.5 |
55.2 |
1.0 |
Cloudy |
25/07/06 |
18:30 |
57.9 |
59.7 |
53.8 |
1.4 |
Cloudy |
Mon
Monitoring Location: NM3 (Cheung Shue Tan Village)
Date |
Start
Sampling Time (hh:mm) |
Noise Level
dB (A) |
Wind Speed (m/s) |
Weather Condition |
||
Leq(30min) |
L10 |
L90 |
||||
04/07/06 |
13:11 |
57.1 |
59.8 |
54.8 |
0.9 |
Cloudy |
11/07/06 |
17:15 |
53.3 |
56.3 |
51.6 |
1.0 |
Cloudy |
18/07/06 |
10:22 |
52.3 |
54.2 |
48.9 |
0.8 |
Cloudy |
25/07/06 |
15:15 |
55.3 |
57.2 |
49.2 |
1.0 |
Cloudy |
Monitoring
Location: NM8 (Near Wen Chih Tang at the CUHK)
Date |
Start
Sampling Time (hh:mm) |
Noise Level
dB (A) |
Wind Speed (m/s) |
Weather Condition |
||
Leq(30min) |
L10 |
L90 |
||||
04/07/06 |
14:33 |
61.3 |
63.9 |
59.0 |
1.2 |
Cloudy |
11/07/06 |
18:15 |
61.3 |
63.0 |
56.0 |
1.3 |
Cloudy |
18/07/06 |
15:02 |
56.4 |
58.8 |
55.5 |
1.1 |
Cloudy |
25/07/06 |
17:25 |
60.4 |
61.8 |
55.3 |
1.6 |
Cloudy |
Appendix C3
Graphical Plots of Noise Monitoring Data
Appendix D
Weather Condition
Weather Condition
Date |
Rainfall (mm) |
Max. Temp (oC) |
Min. Temp. (oC) |
Relative Humidity (%) |
Wind Direction |
Wind Speed (m/s) |
01/07/06 |
2.9 |
31.1 |
27.1 |
87 |
E |
<5 |
02/07/06 |
5.3 |
31.4 |
27.5 |
87 |
E |
<5 |
03/07/06 |
6.3 |
31.4 |
27.7 |
86 |
SE |
<5 |
04/07/06 |
14.8 |
31.8 |
27.0 |
84 |
S |
<5 |
05/07/06 |
1.5 |
32.0 |
28.4 |
79 |
SW |
<5 |
06/07/06 |
2.0 |
32.3 |
27.6 |
77 |
SW |
<5 |
07/07/06 |
3.2 |
32.7 |
28.6 |
78 |
SW |
<5 |
08/07/06 |
19.5 |
31.9 |
27.0 |
81 |
SW |
<5 |
09/07/06 |
7.0 |
30.8 |
26.0 |
82 |
SW |
<5 |
10/07/06 |
6.8 |
30.6 |
27.9 |
84 |
SW |
<5 |
11/07/06 |
32.3 |
31.1 |
26.4 |
89 |
SW |
<5 |
12/07/06 |
- |
32.2 |
28.0 |
79 |
SW |
<5 |
13/07/06 |
Trace |
34.0 |
28.2 |
77 |
W |
<5 |
14/07/06 |
0.2 |
32.2 |
28.8 |
80 |
W |
<5 |
15/07/06 |
7.0 |
29.9 |
27.9 |
83 |
SW |
<5 |
16/07/06 |
195.6 |
29.0 |
24.1 |
86 |
S |
<5 |
17/07/06 |
5.3 |
31.4 |
27.6 |
82 |
S |
<5 |
18/07/06 |
Trace |
32.4 |
28.2 |
79 |
SE |
<5 |
19/07/06 |
Trace |
31.7 |
27.7 |
78 |
S |
<5 |
20/07/06 |
- |
31.9 |
27.4 |
76 |
SW |
<5 |
21/07/06 |
- |
32.6 |
27.7 |
74 |
SW |
<5 |
22/07/06 |
- |
31.7 |
28.1 |
81 |
SE |
<5 |
23/07/06 |
Trace |
32.2 |
28.2 |
81 |
E |
<5 |
24/07/06 |
10.1 |
33.9 |
26.3 |
80 |
W |
<5 |
25/07/06 |
- |
33.9 |
29.2 |
73 |
W |
<5 |
26/07/06 |
Trace |
30.0 |
26.1 |
78 |
SW |
<5 |
27/07/06 |
72.8 |
27.0 |
24.2 |
91 |
SW |
<5 |
28/07/06 |
85.6 |
28.3 |
23.9 |
95 |
SE |
<5 |
29/07/06 |
87.2 |
25.3 |
23.7 |
98 |
SE |
<5 |
30/07/06 |
3.8 |
28.4 |
24.8 |
91 |
NE |
<5 |
31/07/06 |
Trace |
30.9 |
26.2 |
80 |
NE |
<5 |
Remark: Data
of wind speed and wind direction were extracted from Hong Kong Observatory (Shatin Station).
Appendix E
Event-Action Plans
Event / Action Plan for Air Quality |
||||
EVENT |
ACTION |
|||
ET Leader |
IC(E) |
ER |
CNOTRACTOR |
|
Action Level |
|
|
|
|
1. Exceedance of
one sample |
1.
Identify source 2.
Inform IC(E) and ER 3.
Repeat measurement to confirm finding 4.
Increase monitoring frequency to daily |
1.
Check monitoring data submitted by ET 2.
Check Contractor’s working method. |
1. Notify Contractor |
1.
Rectify any unacceptable practice 2.
Amend working methods if possible |
2. Exceedance
for two more consecutive samples |
1.
Identify source 2.
Inform IC(E) and ER 3.
Repeat measurement to confirm findings 4.
Increase monitoring frequency to daily 5.
Discuss with IC(E) and Contractor on remedial
actions required 6.
If exceedance continuous, arrange meeting with
IC(E) and ER 7.
If exceedance stops, cease additional monitoring |
1.
Checking monitoring data submitted by ET 2.
Check Contactor’s working method 3.
Discuss with ET and Contractor on possible
remedial measures 4.
Advise the ER on the effectiveness of the proposed
remedial measures 5.
Supervisor implementation of remedial measures |
1.
Confirm receipt of notification of failure in
writing 2.
Notify Contractor 3.
Ensure remedial measures properly implemented |
1.
Submit proposals for remedial action to IC(E)
within 3 working days of notification 2.
Implement the agreed proposals 3.
Amend proposal if possible |
Limit Level |
|
|
|
|
1. Exceedance of
one sample |
1.
Identify source 2.
Inform ER and EPD 3.
Repeat measurement to confirm finding 4.
Increase monitoring frequency to daily 5.
Assess effectiveness of Contractor’s remedial
actions and keep IC(E), EPD and ER informed of the results |
1.
Check monitoring data submitted by ET 2.
Check Contractor’s working method. 3.
Discuss with ET and Contractor on possible
remedial measures 4.
Advise the ER on the effectiveness of the proposal
remedial measures 5.
Supervisor implementation of remedial measures |
1.
Confirm receipt of notification of failure in
writing 2.
Notify Contractor 3.
Ensure remedial measures properly implemented |
1.
Take immediate action to avoid further exceedance 2.
Submit proposal for remedial actions to IC(E)
within 3 working days of notification 3.
Implement the agreed proposals 4.
Amend proposal if appropriate |
2. Exceedance
for two or more consecutive samples |
1.
Notify IC(E), ER, Contractor and EPD 2.
Identify source 3.
Repeat measurement to confirm findings 4.
Increase monitoring frequency to daily 5.
Carry out analysis of Contractor’s working
procedures to determine possible mitigation to be implemented 6.
Arrange meeting with IC(E) and ER to discuss the
remedial actions to be taken 7.
Assess effectiveness of Contractor’s remedial
actions and keep IC(E), EPD and ER to discuss the remedial action to taken 8.
If exceedance stops, cease additional monitoring |
1.
Discuss amongst ER, ET, and Contractor on
potential remedial actions 2.
Review Contractor’s remedial actions whenever
necessary to assure their effectiveness and advise the ER accordingly 3.
Supervise the implementation of remedial measures |
1.
Confirm receipt of notification of failure in
writing 2.
Notify Contractor 3.
In consultation with the IC(E), agreed with the
Contractor on the remedial measures to be implemented 4.
Ensure remedial measures properly implemented 5.
If exceedance continues, consider what portion of
this work is responsible and instruct the Contract to stop that portion of
work until the exceedance is abated. |
1.
Take immediate action to avoid further exceedance 2.
Submit proposals for remedial actions to IC(E)
within 3 working days of notification 3.
Implement the agreed proposals 4.
Resubmit proposals if possible still not under
control 5.
Stop the relevant portion of works as determined
by the ER until the exceedance if abated. |
Event / Action Plan for Construction Noise |
||||
EVENT |
ACTION |
|||
ET Leader |
IC(E) |
ER |
CNOTRACTOR |
|
|
||||
Action Level |
1.
Notify IC(E) and Contractor 2.
Carry out investigation 3.
Report the results of investigation to the IC(E)
and Contractor 4.
Discuss with the Contractor and formulate remedial
measures 5.
Increase monitoring frequency to check mitigation
effectiveness |
1.
Review the analyzed results submitted by the ET 2.
Review the proposed remedial measures by the
Contractor and advise the ER accordingly 3.
Supervise the implementation of remedial measures |
1.
Confirm receipt of notification of failure in
writing 2.
Notify Contractor 3.
Require Contractor to propose remedial measures
for the analyzed noise problem 4.
Ensure remedial measures are properly implemented |
1.
Submit noise mitigation proposal to IC(E) 2.
Implement noise mitigation proposals |
|
||||
Limit Level |
1.
Notify IC(E), ER, and Contractor 2.
Identify source 3.
Repeat measurement to confirm findings 4.
Increase monitoring frequency 5.
Carry out analysis of Contractor’s working
procedures to determine possible mitigation to be implemented 6.
Inform IC(E), ER and EPD the causes & action
taken for the exceedances 7.
Assess effectiveness of Contractor’s remedial
action and keep IC(E), EPD and ER informed to the results 8.
If exceedance stops, cease additional monitoring |
1.
Discuss amongst ER, ET and Contractor on the
potential remedial actions 2.
Review Contractor’s remedial actions whenever
necessary to assure their effectiveness and advice the ER accordingly 3.
Supervise the implementation of remedial measures |
1.
Confirm receipt of notification of failure in
writing 2.
Notify Contractor 3.
Require Contractor to propose remedial measures
for the analysed noise problem 4.
Ensure remedial measures are properly implemented 5.
If exceedance continues, consider what protion of
the work is responsible and instruct the Contractor to stop that portion of
work until the exceedance is abated |
1.
Take immediate action to avoid further exceedance 2.
Submit proposals for remedial actions to IC(E)
within 3 working days of notification 3.
Implement the agreed proposals 4.
Resubmit proposals if problem still not under
control 5.
Stop the relevant portion of works as determined
by the ER until the exceedance is abated |
Appendix F
Construction Programme
Appendix G
Construction Site Area
Appendix H
The Implementation Status
of
Mitigation Measures and Follow-up Actions during Weekly Site
Inspections
Appendix I
IEC and RE Comments on Monthly EM&A Report
–
June 2006
IEC and RE Comments on Monthly
Environmental Monitoring and Audit Report – June 2006
Item No. |
Document Reference |
Comment |
ET Response |
--- |
--- |
No RE and IEC comments were noticed. |
No responses were required since no
comments were noticed. |
Appendix
J
Wastewater
Monitoring
–
Test
Reports of Wastewater Samples from Discharge Points
Figures