Civil
Engineering and Development Department
Land Works Division
2/F, Civil
Engineering and
Homantin,
Demolition of Kwai Chung Incineration Plant
Environmental
Permit No.
EP-121/2002
Monthly EM&A Report
for Oct 2008 Rev A
Report No.: 203204/KCIP/EM&A/11/A
November 08
Mott MacDonald Hong Kong Limited
7/F,
Tsim Sha Tsui,
Tel: 2828 5757
Fax: 2827 1823
This document has been prepared for the titled project
or named part thereof and should not be relied upon or used for any other
project without an independent check being carried out as to its suitability
and prior written authority of Mott MacDonald being obtained. Mott MacDonald accepts no responsibility or
liability for the consequence of this document being used for a purpose other
than the purposes for which it was commissioned. Any person using or relying on the document
for such other purpose agrees, and will by such use or reliance be taken to
confirm his agreement to indemnify Mott MacDonald Hong Kong for all loss or damage
resulting therefrom.
Mott MacDonald accepts no responsibility or liability for this document
to any party other than the person by whom it was commissioned.
To the extent that this report is based on information
supplied by other parties, Mott MacDonald accepts no liability for any loss or
damage suffered by the client, whether contractual or tortious,
stemming from any conclusions based on data supplied by parties other than Mott
MacDonald and used by Mott MacDonald in preparing this report.
Pursuant to
Condition 2.3 and 3.5 of the Environmental Permit
EP-121/2002
This
Monthly EM&A Report (Oct
2008) has been reviewed, certified and verified by the following EM&A
members as Conforming to the Information and Recommendations contained in the
EIA Report
Certified by:
Joseph Chan
Environmental
Team (ET) Leader
Mott
MacDonald Hong Kong Ltd.
Date 14 November
2008
Verified by:
Independent
Environmental Checker (IEC)
Hyder Consulting Limited
Date 14 November
2008
List of Contents Page
EXECUTIVE
SUMMARY iii
1. INTRODUCTION 1-1
1.1 Background to the Project............................................................................... 1-1
1.2 Coverage of this EM&A
Report...................................................................... 1-1
1.3 Project Management Organisation................................................................... 1-1
1.4 Project Program............................................................................................. 1-1
1.5 Works Undertaken in the
Reporting Month....................................................... 1-2
2. EM&A Requirements 2-1
2.1 Summary of EM&A
Requirements.................................................................. 2-1
2.2 Environmental Quality
Performance Limits....................................................... 2-1
2.3 Event and Action Plans................................................................................... 2-1
2.4 Implementation of Environmental
Mitigation Measures...................................... 2-1
3. Monitoring Results 3-1
3.1 Impact Monitoring Schedule............................................................................ 3-1
3.2 Monitoring Methodology.................................................................................. 3-1
3.3 Monitoring Equipment..................................................................................... 3-3
3.4 Equipment Calibration..................................................................................... 3-3
3.5 Results of Impact Monitoring........................................................................... 3-3
4. Project Environmental Status 4-1
4.1 Environmental Meetings.................................................................................. 4-1
4.2 Status of Environmental
Submissions, Permits and Licenses.............................. 4-1
4.3 Waste Management Status.............................................................................. 4-2
4.4 Review of Environmental
Monitoring Procedures.............................................. 4-3
4.5 Implementation Status of
Environmental Mitigation Measures............................ 4-3
5. AUDIT FINDINGS 5-1
5.1 Site Environmental Audit................................................................................. 5-1
5.2 Site Effluent Discharge/WPCO Effluent Discharge.......................................... 5-1
6. Environmental COMPLAINTS AND
NON-COMPLIANCE 6-1
6.1 Summary of Environmental
Complaints, Notifications of Summons and Successful Prosecutions 6-1
6.2 Environmental Enquires................................................................................... 6-1
6.3 Environmental Events..................................................................................... 6-1
6.4 Environmental Exceedance/ Non-compliance................................................... 6-1
7. future key issues 7-1
7.1 Key Issues and Recommendations
for Coming Month....................................... 7-1
8. conclusion and recommendation 8-1
8.1 Conclusions.................................................................................................... 8-1
8.2 Recommendations.......................................................................................... 8-1
List of Appendices
Appendix
A.......... Environmental Quality
Performance Limits
Appendix B.......... Event
and Action Plans
Appendix D.......... EM&A
Schedule
Appendix E.......... Air
Quality Monitoring Results and Graphical Presentation
Appendix F.......... Calibration
Certificates
Appendix G.......... Works
Programme
List of Tables
Table 2‑1............. Summary of Impact EM&A Requirements....................................................... 2-1
Table 3‑1............. TSP Monitoring Equipment.............................................................................. 3-3
Table
3‑2............. Equipment Calibration
Frequencies.................................................................. 3-3
Table
3‑3............. Results of 1-Hour TSP
Impact Monitoring........................................................ 3-3
Table
3‑4............. Results of 24-Hour TSP
Impact Monitoring...................................................... 3-4
Table
4‑1............. Status of Environmental
Submissions, Permits and Licenses.............................. 4-1
Table
4‑2............. Monthly Summary Waste Flow Table for 2008................................................. 4-2
Table
5‑1............. Summary of Environmental
Site Inspections..................................................... 5-1
Table 6‑1............. Summary of Environmental Complaints and Prosecutions.................................. 6-1
Table
6‑2............. Summary of Exceedances............................................................................... 6-1
Table B‑1............. Event and Action Plan for Air Quality.............................................................. B1
Table C‑2............. Implementation Schedule of Recommended Mitigation Measures From the EIA.. C1
Table C‑3............. Event Contingency Plan for Environmental Complaints...................................... C5
List of Figures
Figure 1.1 Layout Plan of Work Site and the Environs
Figure 1.2 Project Organisation Chart
Figure 2.1 Location of Air Quality (Dust) Monitoring Station
The EM&A programme for this Project commenced on 1 Dec 2007. This report presents a summary of the environmental monitoring and audit works, list of activities, and mitigation measures implemented during the reporting month of October 2008.
This is the 11th Monthly EM&A Report for the works carried out during the reporting month.
The following construction activities have taken place during the reporting month: -
· Erection of bamboo scaffolding for ACM (cladding) removal;
· Erection of full containment for removal of asbestos flexible joints and gaskets from vent ducts in the base of chimney;
· Disposal of ACM through Portion B barging point to SENT;
· Diversion of ponding water from ash bunker to refuse reception bunker; and
· Demolition of EMSD site office.
Impact monitoring for air quality (dust) due to the demolition work continued during the reporting month. No exceedance of the Action and Limit Levels for dust was recorded.
No environmental complaint, notification of summons and prosecution was received or made against the Project in the reporting month.
Site inspection was carried out on a weekly basis to monitor proper implementation of environmental pollution control and mitigation measures for the Project. In this reporting month, site inspections were carried out on 2, 9, 16, 23 & 30 Oct 2008.
No non-compliances with regard to site environmental audits were recorded in this reporting month.
As
per the EM&A Manual, baseline 1-hour and 24-hour Total Suspended
Particulates (TSP) monitoring was conducted during the period of 31 October
2007 to 13 November 2007. Results were reported in the Baseline Monitoring
Report submitted in November 2007.
Future key issues to be considered in the forthcoming month include: -
·
Removal of asbestos wall cladding at Zones 1.8, 1.9
& 2.0 of IP;
·
Excavation of and treatment to the sediment at the
bottom of the Ash Bunker;
· Removal of asbestos flexible joints of the air ducts in the Chimney base.
1.1.1 This Project – “Demolition of Kwai Chung Incineration Plant” is a Designated Project defined under the EIA Ordinance. An Environmental Permit (“EP”) was issued on 1 March 2002 [Permit No. EP-121/2002].
1.1.2 This Contract [No.: CV/2007/06] for the Project was awarded to the Contractor – China International Water & Electric Corporation and contractually commenced on 31 October 2007. The main Contract will last for 45 months excluding 12 months for landscape establishment works. In accordance with Condition 1.11 of the Environmental Permit EP-121/2002, the Director of Environmental Protection (DEP) was notified that the commencement date for the Project was on 24 Jan 2008.
1.1.3 The scope of the Project includes demolition and clearance of the existing chimney, buildings and ancillary structures above the existing concrete ground slab where the former Kwai Chung Incineration Plant (“KCIP”) is located. It also includes the removal of asbestos containing materials (“ACM”) and dioxin/ furan contaminated materials (“DCM”) prior to demolition of structures and subsequent site remediation.
1.1.4 A layout plan of the Project site and the environs are presented in Figure 1.1.
1.1.5 Mott MacDonald Hong Kong Limited (MMHK) has been commissioned by the Project Proponent – Civil Engineering and Development Department (“CEDD”) as the Environmental Team (“ET”) to undertake the Environmental Monitoring and Audit (EM&A) programme described in the approved EM&A Manual of the Project.
1.2 Coverage of this EM&A Report
1.2.1 The EM&A programme for this Project commenced on 1 Dec 2007. This report presents a summary of the environmental monitoring and audit works, list of activities, and mitigation measures implemented during the reporting month in October 2008.
1.2.2 This is the 11th Monthly EM&A Report for the works carried out during the reporting month.
1.3 Project Management Organisation
1.3.1 The project organisation chart is presented in Figure 1.2.
1.5 Works Undertaken in the Reporting Month
1.5.1 The following construction activities have taken place during the reporting month: -
· Erection of bamboo scaffolding for ACM (cladding) removal;
· Erection of full containment for removal of asbestos flexible joints and gaskets from vent ducts in the base of chimney;
· Disposal of ACM through Portion B barging point to SENT;
· Diversion of ponding water from ash bunker to refuse reception bunker; and
· Demolition of EMSD site office.
2.1 Summary of EM&A Requirements
2.1.1 The EM&A programme requires environmental monitoring of air quality and waste management as specified in the approved EM&A Manual dated Sep 2001.
2.1.2 1-hour TSP and 24-hour TSP levels at 1 dust monitoring station are to be taken during the course of dusty work in every reporting month. This air quality monitoring stations for 24-hour TSP and 1-hour TSP measurements is shown in Figure 2.1 Location of Air Quality (Dust) Monitoring Station.
2.1.3 A summary of impact EM&A requirements is presented in Table 2‑1 below.
Table 2‑1 Summary
of Impact EM&A Requirements
Descriptions |
Locations |
Frequencies |
Duration |
|
Air Quality |
24-Hour TSP |
1 Location - A1 |
Once every 6 days |
During dust generating construction works |
1-Hour TSP |
1 Location - A1 |
3 times every 6 days |
During dust generating construction works |
|
Waste |
On-Site Waste Audit |
Active Work Sites |
Weekly |
During Construction |
On-Site Waste Inspection |
||||
Wastewater |
On-Site Wastewater Audit |
Active Work Sites |
Weekly |
During Construction |
General Site Conditions |
Environmental Site Inspection |
Works areas and areas affected by works |
Weekly |
During Construction |
N.B.
A1 – Boundary
of the site adjacent to the Kwai Chung Primary
Treatment Plant
2.2 Environmental Quality Performance Limits
2.2.1 Environmental Quality Performance Limits for air quality are shown in Appendix A.
2.3.1 The Event and Action Plans for air quality are shown in Appendix B.
2.4 Implementation of Environmental Mitigation Measures
2.4.1 The Contractor is required to implement mitigation measures listed in the latest EP, EIA Report and EM&A Manual. During routine site inspections, the Contractor's implementation of mitigation measures, if any, are to be inspected and reviewed. A schedule of the implementation of mitigation measures identified at the EIA stage is given in Appendix C.
Figure 2.1 Location of Air Quality (Dust) Monitoring Station
3.1 Impact Monitoring Schedule
3.1.1 Regular site inspections were carried out on 2, 9, 16, 23, & 30 Oct 2008 in the reporting month to assess the compliance with environmental requirements. The EM&A schedule is given in Appendix D.
3.1.2 Impact monitoring for air quality (dust) due to the demolition work continued during the reporting month.
24-hour TSP Monitoring
Installation
3.2.1 The HVS has been installed close to representative air sensitive receivers. The following criteria have been considered in the installation of the HVS.
· A horizontal platform with appropriate support to secure the sampler against gusty wind was provided.
· The distance between the HVS and any obstacles, such as buildings, was at least twice the height that the obstacle protrudes above the HVS.
· A minimum of 2m separation from walls, parapets and penthouse was required for rooftop sampler.
· No furnace or incinerator flues were nearby.
· Airflow around the sampler was unrestricted.
· Permission was obtained to set up the samplers and to obtain access to the monitoring stations.
· A secured supply of electricity is needed to operate the samplers.
Preparation of Filter Papers
· Glass fibre filters, G810 are to be labelled with sufficient filters that are clean and without pinholes.
· All filters are to be equilibrated in the conditioning environment for 24 hours before weighing. The conditioning environment temperature is to be around 25 °C and not variable by more than ±3°C, the relative humidity (RH) is to be < 50% and not variable by more than ±5 %. A convenient working RH is 40%.
Field Monitoring
· The power supply is to be secured to ensure the HVS works properly.
· The filter holder and the area surrounding the filter are to be cleaned.
· The filter holder is to be removed by loosening the 4 bolts and a new filter, with stamped number upward, on a supporting screen to be aligned carefully.
· The filter is to be properly aligned on the screen so that the gasket forms an airtight seal on the outer edges of the filter.
· The swing bolts are to be fastened to hold the filter holder down to the frame. The pressure applied is to sufficient to avoid air leakage at the edges.
· The shelter lid is then closed and is secured with the aluminium strip.
· The HVS shall be warmed-up for about 5 minutes to establish run-temperature conditions.
· A new flow rate record sheet is to be set into the flow recorder.
· The flow rate of the HVS is to be checked and adjusted at around 1.1 m3/min. The range specified in the updated EM&A Manual is between 0.6-1.7 m3/min.
· The programmable timer is set for a sampling period of 24 hrs + 1 hr, and the starting time, weather condition and the filter number are to be recorded.
· The initial elapsed time is to be recorded.
· At the end of sampling, the sampled filter is to be removed carefully and folded in half length so that only surfaces with collected particulate matter are in contact.
· It was then placed in a clean plastic envelope and sealed.
· All monitoring information is to be recorded on a standard data sheet.
· Filters are to be sent to a HOKLAS accredited laboratory for analysis.
Maintenance and Calibration
· The HVS and its accessories are to be maintained in good working condition, such as replacing motor brushes routinely and checking electrical wiring to ensure a continuous power supply.
· HVSs are to be calibrated at a bi-monthly intervals using GMW-25 Calibration Kit throughout all stages of the air quality monitoring.
1-hour TSP Monitoring
Field Monitoring
3.2.2 The measuring procedures of the 1-hour dust meter are to be in accordance with the Manufacturer’s Instruction Manual as follows:
·
Set POWER to “ON”, push
· Push the knob at MEASURE position.
· Push “O-ADJ” button. (Then meter’s indication is 0).
· Push the knob at SENSI ADJ position and set the meter’s indication to S value described on the Test Report using the trimmer for SENSI ADJ.
· Pull out the knob and return it to MEASURE position.
· Push “START” button.
Maintenance and Calibration
· The 1-hour TSP meter would be checked at 3-month intervals and calibrated at 1-year intervals throughout all stages of the air quality baseline monitoring.
3.2.3 As per the approved EM&A Manual, dust monitoring stations are located as shown in Figure 2.1 Location of Air Quality (Dust) Monitoring Station.
3.3.1 The equipment used for air quality (dust) monitoring is listed in Table 3‑1.
Table 3‑1 TSP Monitoring Equipment
Equipment |
Model |
HVS Sampler |
Greasby GMWS 2310 Accu-vol system |
Calibrator |
Tisch TE-5025A |
1-hour TSP Dust Meter |
TSI Model 8520 Dust
Trak Aerosol Monitor |
3.4.1 The calibration frequencies of the monitoring equipment are provided in Table 3‑2.
Table 3‑2 Equipment Calibration Frequencies
Equipment |
Calibration Frequency |
Latest Calibration Date |
High Volume Sampler Greasby GMWS 2310 Accu-vol system |
Every two months |
5 Sep 2008 |
1-hour TSP Dust Meter TSI Model 8520 Dust Trak Aerosol Monitor |
Every six months |
14 Jul 2008 |
3.4.2 The calibration certificates are included in Appendix F.
3.5 Results of Impact Monitoring
3.5.1 Results of 1-hour TSP level are summarised in Table 3‑3. Detailed results, including weather conditions, and graphical presentations are included in Appendix E.
Table 3‑3 Results of 1-Hour TSP Impact Monitoring
Monitoring Station |
1-hour |
Action Level (µg/m3) |
Limit Level (µg/m3) |
A1 |
153-257 |
345 |
500 |
3.5.2 No exceedance of Action / Limit Levels for 1-hr TSP was recorded in the reporting month.
Air Quality (24-hr TSP)
3.5.3 Results of 24-hour TSP level are summarised in Table 3‑4. Detailed results, including weather conditions, and graphical presentations are included in Appendix E.
Table 3‑4 Results of 24-Hour TSP Impact Monitoring
Monitoring Station |
24-hour
|
Action Level (µg/m3) |
Limit Level (µg/m3) |
A1 |
32-108 |
179 |
260 |
3.5.4 No exceedance of Action / Limit Levels for 24-hr TSP was recorded in the reporting month.
4.1.1 One environmental meeting was held on the day of the monthly site inspection on 16 Oct 2008.
4.2 Status of Environmental Submissions, Permits and Licenses
4.2.1 A summary of status of all environmental submissions, permits, licenses, and/or notifications to EPD for this Project during the reporting period is presented in Table 4‑1 below.
Table 4‑1 Status of Environmental Submissions, Permits and Licenses
Item |
Description |
Date of Application/ Submission |
Status |
1. |
Environmental Permit (EP No. EP-121/2002) |
4 Feb 2002 |
Valid |
2. |
Billing Account under Waste Disposal (Charges for Disposal of Construction Waste) Regulation (Ref. No.: 7006285) |
Approved on 16 Nov 2007 |
Valid |
3. |
Waste Management Plan |
v2.3 approved on 25 Jul 2008 v3.1
submitted to EPD on 15 Oct 2008 |
v2.3: valid v3.1: pending approval |
4. |
Registration as a Chemical Waste Producer under Waste Disposal (Chemical Waste) (General) Regulation (Ref. No.: WPN-5292-320-C3459-01) |
2 Nov 2007 |
Approved by EPD on 26 Nov 2007 |
5. |
Effluent Discharge Licence (Ref. No.: EP760/320/0128821) |
Variation of License submitted on 25 March 2008 (Approved on 8 July 2008) |
Valid |
6. |
Notification pursuant to Section 3(1) of the Air Pollution Control (Construction Dust) Regulation (Form NA) |
EPD notified on 15 Jan 2008 |
Valid |
7. |
Notification of commencement of asbestos abatement work pursuant to Section 73 of the Air Pollution Control Ordinance |
EPD notified on 4 Feb 2008 |
Valid. Approved by EPD on 5 Mar 2008. |
New submissions |
|||
|
No new submissions |
|
|
4.3.1 No C&D material, except general refuse, was generated by the Project in the reporting month, as shown in Table 4‑2. A trip ticket system has been implemented for all off-site waste disposals. (It was recorded that 111.5667 m3 of ACM and 2.78 m3 have been generated from the site while 85.9934 m3 of ACM were disposed of in Oct 2008. No DCM waste has been disposed off-site.)
Table 4‑2 Monthly Summary Waste Flow Table for 2008
Month |
Actual Quantities of Inert C&D Materials Generated Monthly |
Actual Quantities of C&D Wastes Generated Monthly |
||||||||||||||||||
Total Quantity Generated |
Broken Concrete |
Reused in the Contract |
Reused in other Projects |
Disposed of at Public Fill |
Metals |
Paper/ Cardboard |
Plastics |
Chemical waste |
Others (e.g. refuse) |
|||||||||||
(In tons) |
(In tons) |
(In tons) |
(In tons) |
(In tons) |
(In ‘000 kg) |
(In ‘000 kg) |
(In ‘000 kg) |
(In ‘000 kg) |
(In ‘000 m3) |
|||||||||||
Est. |
Act. |
Est. |
Act. |
Est. |
Act. |
Est. |
Act. |
Est. |
Act. |
Est. |
Act. |
Est. |
Act. |
Est. |
Act. |
Est. |
Act. |
Est. |
Act. |
|
Jan |
0 |
0 |
- |
0 |
- |
0 |
- |
0 |
0 |
0 |
0 |
0 |
0.1 |
0 |
0.1 |
0 |
0 |
0 |
0.250 |
0.0585 |
Feb |
0 |
0 |
- |
0 |
- |
0 |
- |
0 |
0 |
0 |
0 |
0 |
0.1 |
0 |
0.1 |
0 |
0 |
0 |
0.250 |
0.063 |
Mar |
0 |
0 |
- |
0 |
- |
0 |
- |
0 |
0 |
0 |
0 |
0 |
0.1 |
0 |
0.1 |
0 |
0 |
0 |
0.125 |
0.018 |
Apr |
0 |
0 |
- |
0 |
- |
0 |
- |
0 |
0 |
0 |
0 |
0 |
0.1 |
0 |
0.1 |
0 |
0 |
0 |
0.125 |
0.0045 |
May |
0 |
0 |
- |
0 |
- |
0 |
- |
0 |
0 |
0 |
0 |
3.2 |
0.1 |
0 |
0.1 |
0 |
0 |
0 |
0.125 |
0 |
June |
0 |
0 |
- |
0 |
- |
0 |
- |
0 |
0 |
0.0225 |
0 |
8.1 |
0.1 |
0 |
0.1 |
0 |
0 |
0 |
0.125 |
0.0135 |
Jul |
0 |
0 |
- |
0 |
- |
0 |
- |
0 |
0 |
0 |
0 |
0 |
0.1 |
0 |
0.1 |
0 |
0 |
0 |
0.125 |
0.009 |
Aug |
0 |
0 |
- |
0 |
- |
0 |
- |
0 |
0 |
0.018 |
0 |
0 |
0.1 |
0 |
0.1 |
0 |
120 |
0 |
0.125 |
0.009 |
Sep |
0 |
0 |
- |
0 |
- |
0 |
- |
0 |
0 |
0 |
0 |
9 |
0.1 |
0.018 |
0.1 |
0.005 |
120 |
15.5020 |
0.125 |
0.018 |
Oct |
0 |
0 |
- |
0 |
- |
0 |
- |
0 |
0 |
0 |
0 |
16.12 |
0.1 |
0 |
0.1 |
0 |
120 |
20.2940 |
0.125 |
0.018 |
Nov |
0 |
|
- |
|
- |
|
- |
|
0 |
|
0 |
|
0.1 |
|
0.1 |
|
120 |
|
0.125 |
|
Dec |
0 |
|
- |
|
- |
|
- |
|
0 |
|
0 |
|
0.1 |
|
0.1 |
|
120 |
|
0.125 |
|
Total |
0 |
0 |
- |
0 |
- |
0 |
- |
0 |
0 |
0.0405 |
0 |
36.42 |
1.2 |
0.018 |
1.2 |
0.005 |
600 |
35.7960 |
1.750 |
0.2655 |
4.4 Review of Environmental Monitoring Procedures
4.4.1 The monitoring works conducted by the Environmental Team have been reviewed regularly. No changes in the environmental monitoring procedures are considered necessary at this stage.
4.5 Implementation Status of Environmental Mitigation Measures
4.5.1 An Implementation Schedule of Mitigation Measures from the EIA/ EM&A Manual has been given in Appendix C.
5.1.1 Site inspection is to be carried out on a weekly basis to monitor proper implementation of environmental pollution control and mitigation measures for the Project. In this reporting month, one monthly site inspection was carried out jointly by the ER, Contractor, ETL and IEC on 16 October 2008 and additional weekly site inspections were carried out by the ER, Contractor and ET on 2, 9, 23 & 30 Oct 2008.
5.1.2 Major findings provided by ET and those jointly provided by the ET and IEC on 16 October 2008 from the site inspection are summarised in Table 5‑1 below.
Table 5‑1 Summary of Environmental Site Inspections
Date of Inspection |
Major Observations |
Action(s) |
2 Oct 2008 |
Ground (paved) was broken during demolition of small buildings near
the ramp and is exposed to air. The potential dust impact due to exposed soil
should be properly mitigated. |
The broken pavement has been reinstated by the contractor. |
9 Oct 2008 |
No new observation. |
- |
16 Oct 2008 |
The contractor is reminded to keep clear of dusty materials at the
haul road to reduce dust impact by means of water spraying regularly or
sweeping up the materials. |
The dusty materials at the haul road observed have been swept up. |
23 Oct 2008 |
Loose sand and stone was left on the ground after demolition of the
minor structures. This is a source of dust, especially when the winter time
is coming. It is recommended that the sand and stone be swept away to prevent
dust impact. |
Some of the sand and stone have been cleared while the remaining will
be cleared at a later stage. The contractor is reminded to water the haul
road to avoid dust emission. |
30 Oct 2008 |
Sand from the broken sand bags is a potential source of pollutant to
runoff. Therefore, those sand bags observed at several places in the site
should be removed and the sand should be swept away. |
Sand bags and loose sand have been cleared. |
5.2
Site
Effluent Discharge/WPCO Effluent Discharge
5.2.1 A WPCO effluent discharge licence was granted by EPD on 10 March 2008 and subsequently the Contractor has applied for variation of licence conditions on 15 March 2008. EPD has granted the new discharge licence on 8 July 2008. The foul water from toilets of Contractor’s & Engineer’s site offices in Portion B would be temporarily stored in storage tank and then collected and disposed by a sewage collector.
6.1 Summary of Environmental Complaints, Notifications of Summons and Successful Prosecutions
6.1.1 No environmental complaints have been received during the reporting month. Appendix C presents the environmental complaint event contingency plan of the Project and Table 6‑1 below presents a statistics of complaints, notification of summons and successful prosecution since the commencement of the Project.
Table
6‑1 Summary of Environmental Complaints
and Prosecutions
Complaints
Logged |
Summons
Served |
Successful
Prosecutions |
|||
Oct 2008 |
Cumulative |
Oct 2008 |
Cumulative |
Oct 2008 |
Cumulative |
0 |
0 |
0 |
0 |
0 |
0 |
6.1.2 No environmental complaint, notification of summons and prosecution has been received or made against the Project in this reporting month.
6.2.1 No environmental enquiries were received during the reporting month.
6.3.1 No unusual events were recorded during the reporting month.
6.4 Environmental Exceedance/ Non-compliance
6.4.1 The Event and Action Plan for air quality (dust) is presented in Appendix B.
Air Quality - Dust
6.4.2 No exceedance of the Action and Limit Levels for 1-hour and 24-hour TSP was recorded.
Waste Management
6.4.3 Not applicable.
Summary of Exceedances
6.4.4 Table 6‑2 summarises the total number of exceedances for air quality recorded during the reporting period.
Table 6‑2 Summary of Exceedances
Parameters |
Total no. of
Measurements |
Action Level Exceedance |
% of Action Level Exceedance |
Limit Level Exceedance |
% of Limit Level Exceedance |
Air Quality |
22 |
0 |
0% |
0 |
0% |
6.4.5 No exceedance was recorded in the reporting period.
7.1 Key Issues and Recommendations for Coming Month
7.1.1 Key issues to be considered in the coming month include: -
· Removal of
asbestos wall cladding at Zones 1.8, 1.9 & 2.0 of IP;
· Excavation of
and treatment to the sediment at the bottom of the Ash Bunker;
· Removal of asbestos flexible joints of the air ducts in the Chimney base.
7.1.2 Based on the above key issues, the recommended mitigation measures to be implemented include the following: -
Air
· Covers for dusty stockpiles and control of dust emissions from construction (demolition) works;
· Haul road watering and vehicle wheel wash prior to exit;
· All plant to be maintained to prevent any undue air emissions;
· Dust suppression by water spraying during demolition of minor structures.
Noise
· All plant shall be maintained to prevent any undue noise nuisance.
· Use quiet plants during demolition whenever possible.
· Noisy activities should be avoided during holidays.
Water
· All wheel wash water shall be diverted to a sediment pit before discharge;
· Stagnant water shall be cleared quickly after rain;
· All fuel cans, generators shall be placed within a bunded area; and any fuel spills shall be mopped up or excavated and disposed of as necessary;
· All washout from concrete mixer shall be collected properly to avoid direct discharge.
Waste
· Different types of waste should be segregated, stored, transported and disposed of in accordance with the relevant legislative requirements and guidelines;
· Records of quantities of wastes generated, recycled and disposal (with locations) shall be kept.
Asbestos
· Removal, handling, transportation and disposal of the ACM in line with relevant regulations.
Dioxin
· Removal, handling, transportation and disposal of the DCM in line with relevant regulations.
8.1.1 EM&A was performed in October 2008 during which some site works have continued. All monitoring and audit results in the reporting month were checked and reviewed.
8.1.2 Airborne dust monitoring continued due to the demolition work during the reporting month. Also, ACM removal was carried out. In general, the Contractor is preparing to implement all required mitigation measures and has been reasonably responsive to the ET’s recommendations on any discrepancies observed during the weekly environmental site inspection of this reporting month.
8.1.3 No environmental complaints, notification summons or successful prosecutions have been received or made against this Project in this reporting month.
8.2.1 No further recommendations made at this stage pending more site progress achieved.
Action and Limit Levels for 24-hour TSP
Monitoring Station |
Action Level (mg/m3) |
Limit Level (mg/m3) |
A1 |
179 |
260 |
Action and Limit Levels for 1-hour TSP
Monitoring Station |
Action Level (mg/m3) |
Limit Level (mg/m3) |
A1 |
345 |
500 |
Appendix B Event and
Action Plans
Table B‑1 Event and Action Plan for Air Quality
EVENT |
ACTION |
|||
ET |
IEC |
ER |
CONTRACTOR |
|
ACTION LEVEL |
||||
1. Exceedance for one sample |
1. Identify
source 2. Inform IEC
and ER 3. Repeat
measurement to confirm finding 4. Increase
monitoring frequency to daily |
1. Check
monitoring data submitted by ET 2. Check
Contractor’s working method |
1. Notify Contractor 2. Check monitoring data and Contractor's
working methods |
1. Rectify any
unacceptable practice 2. Amend working
methods if appropriate |
2. Exceedance for two
or more consecutive samples |
1. Identify
source 2. Inform IEC
and ER 3. Repeat
measurements to confirm findings 4. Increase
monitoring frequency to daily 5. Discuss with
Contractor , IEC and ER for remedial actions required 6. If exceedance continues, arrange meeting with IEC and ER 7. If exceedance stops, cease additional monitoring |
1. Checking
monitoring data submitted by ET 2. Check
Contractor’s working method 3. Discuss with
ET and Contractor on possible remedial measures 4. Advise the ER
on the effectiveness of the proposed remedial measures 5. Supervise
implementation of remedial measures |
1. Confirm receipt of notification of failure in
writing 2. Notify Contractor 3. Check monitoring data and Contractor's
working methods 4. Discuss with IEC and Contractor on potential
remedial actions 5. Ensure remedial actions properly implemented |
1. Submit
proposals for remedial actions to ER within 3 working days of notification 2. Implement the
agreed proposals 3. Amend
proposal if appropriate |
LIMIT LEVEL |
||||
1. Exceedance for one sample |
1. Identify source 2. Inform ER and EPD 3. Repeat measurement to confirm finding 4. Increase monitoring frequency to daily 5. Assess effectiveness of Contractor's remedial
actions and keep IEC, EPD and ER informed of the results |
1. Checking monitoring data submitted by ET 2. Check Contractor’s working method 3. Discuss with ET and Contractor on possible
remedial measures 4. Advise the ER on the effectiveness of the
proposed remedial measures 5. Supervise implementation of remedial measures |
1. Confirm receipt of notification of failure in
writing 2. Notify Contractor 3. Check monitoring data and Contractor's
working methods 4. Discuss with ET Leader and Contractor
potential remedial actions 5. Ensure remedial actions properly implemented |
1. Take immediate action to avoid further exceedance 2. Submit proposals for remedial actions to ER
within 3 working days of notification 3. Implement the agreed proposals 4. Amend proposal if appropriate |
2. Exceedance for two
or more consecutive samples |
1. Identify source 2. Inform IEC, ER and EPD the causes &
actions taken for the exceedances 3. Repeat measurement to confirm findings 4. Increase monitoring frequency to daily 5. Investigate the causes of exceedance,
Contractor’s working procedures to identify possible mitigation 6. Arrange meeting with IEC and ER to discuss
the remedial actions to be taken 7. Assess effectiveness of Contractor's remedial
actions and keep IEC, EPD and ER informed of the results 8. If exceedance
stops, cease additional monitoring |
1. Discuss amongst ER, ET and Contractor as the
potential remedial actions 2. Review Contractor’s remedial actions whenever
necessary to ensure their effectiveness and advise the ER accordingly 3 Supervise the implementation of remedial
measures |
1. Confirm receipt of notification of failure in
writing 2. Notify Contractor 3. Carry out analysis of Contractor's working
procedures with IEC to determine possible mitigation to be implemented 4. Discuss amongst Environmental Team Leader and
the Contractor potential remedial actions 5. Review Contractor's remedial actions whenever
necessary to assure their effectiveness 6. If exceedance
continues, consider what portion of the work is responsible and instruct the
Contractor to stop that portion of work until the exceedance
is abated |
1. Take immediate action to avoid further exceedance 2. Submit proposals for remedial actions to ER
within 3 working days of notification 3. Implement the agreed proposals 4. Resubmit proposals if problem still not under
control 5. Stop the relevant portion of works as
determined by the ER until the exceedance is abated |
Appendix C Schedule of
Mitigation Measures from the EIA/ EM&A Manual and Event Contingency Plan
for Environmental Compliant
Table C‑2 Implementation Schedule of Recommended
Mitigation Measures From the EIA
No. |
Activity |
Mitigation/EIA
Recommendations |
Responsibility for
Implementation |
Location/Duration
completion of measures |
Implementation Stage |
Relevant Guidelines
Legislation |
Implementation Status ^ |
1 |
Ash Disposal |
|
|
|
|
|
|
I |
Treatment |
Reconfirm extent of
contaminated ash deposits by sampling for dioxins and furans. Handling, transportation and disposal of
the ash waste in line with relevant regulations. Collection, immobilisation and testing of
waste for disposal to landfill shall be carried out according to the relevant
regulations and recommendations of the EIA including immobilisation by
collection and mixing the ash material with cement. Pilot mixing and TCLP tests should
establish the ratio of cement to ash to the satisfaction of EPD. Ash waste to be treated and placed into steel
drums lined with plastic sheeting. The
drums should be adequately sealed and in new or good condition. Prior agreement of the disposal criteria
from EPD and agreement to disposal from the landfill operator must be
obtained. |
CEDD’s Contractor |
KCIP work areas. Duration of the ash removal |
A@ |
1, 10, EIA |
P |
II |
Disposal |
To monitor the disposal of
waste at landfills, a “trip-ticket” system (WBTC No. 5/99) for all solid
waste transfer/disposal operations should be implemented. The system should be included as a
contractual requirement, and monitored by the Environmental Team and audited
by the Independent Checker (Environment). |
CEDD’s Contractor |
As above |
A |
1, 5, 9 |
ü |
III |
Asbestos Removal |
An asbestos abatement
programme should be submitted to EPD for approval prior to the commencement
of the asbestos abatement work. |
CEDD and Contractor |
As above |
A |
4 |
ü |
2 |
Demolition |
|
|
|
|
|
|
A1 |
Non-blasting Methodology |
Demolition by Non-Blasting
Methodology Only. All structures and
buildings should be demolished and removed prior to demolition of chimneys |
CEDD |
KCIP work areas. Duration of the demolition |
C# |
8 |
ü |
A2 |
Waste Management Plan. |
A Waste Management Plan
shall be submitted to EPD for approval.
The Waste Management Plan shall include, but not be limited to, the
findings of the Waste Management Paper of the EIA, the types, quantities,
disposal methods, timing, and locations of final disposition,
responsibilities for implementation and the possible recycling and reuse of
wastes generated. |
CEDD and Contractor |
Prior to commencement of the demolition
works |
Prior to C# |
1 |
ü |
B |
Material Storage |
Covers for dusty stockpiles
and control of dust emissions from construction (demolition) works requires
appropriate dust control measures to be implemented in accordance with the
requirements in the Air Pollution Control (Construction Dust) Regulation. |
CEDD’s Contractor |
KCIP work areas. Duration of the demolition |
C |
4 |
ü |
C |
Vehicle movement |
Haul road watering, vehicle
wheel wash prior to exit. Where practical, access roads should be protected
with crushed gravel. |
CEDD’s Contractor |
As above |
C |
4 |
P |
D |
Plant maintenance |
All plant shall be
maintained to prevent any undue air emissions. |
CEDD’s Contractor |
As above |
Prior to start of works |
4 |
ü |
E |
Demolition Techniques |
Selection of non-blasting
demolition techniques to minimise noise and vibration. |
CEDD’s Contractor |
As above |
C |
8 |
ü |
F |
Plant maintenance |
All plant shall be
maintained to prevent any undue noise nuisance. |
CEDD’s Contractor |
As above |
C |
2, 3 |
ü |
G |
Wheel wash |
All wheel wash water shall
be diverted to a sediment pit. |
CEDD’s Contractor |
As above |
C |
5 |
P |
H |
Sediment control |
Sediment removal facilities
shall provided and be maintained and excavated as necessary to prevent
sedimentation of channels. Perimeter
channels should be provided. Works should be programmed for the dry season
where feasible. Environmental
guidelines for the handling and disposal of discharges from construction
sites, as stipulated in the Practice Note for Professional Persons,
Construction Site Drainage (ProPECC PN 1/94) to be
followed. |
CEDD’s Contractor |
As above |
C |
5, 12 |
N/A |
I |
Surface water diversion |
All clean surface water
shall be diverted around the site. |
CEDD’s Contractor |
As above |
C |
5, 12 |
X |
J |
Fuel can storage |
All fuel cans shall be
placed within a bunded area. Any fuel spills shall
be mopped up as necessary. |
CEDD’s Contractor |
As above |
C |
5,6 |
ü |
K |
Material, plant movement
& fuel can filling. |
Any fuel or oil spills
shall be excavated and disposed of. |
CEDD’s Contractor |
As above |
C |
6,7 |
ü |
L |
Generators |
All generators shall be
placed within a bunded area. Any fuel spills shall
be mopped up as necessary. |
CEDD’s Contractor |
As above |
C |
5,6,7 |
ü |
M |
Material containers |
All empty bags and
containers shall be collected for disposal. |
CEDD’s Contractor |
As above |
C |
6,7 |
ü |
N |
Worker generated litter and
Waste |
Litter receptacles shall be
placed around the site. Litter shall be taken regularly to the refuse
collection points. Chemical toilets (or suitable equivalent) should be
provided for workers. Any canteens should have grease traps. |
CEDD’s Contractor |
As above |
C |
6 |
ü |
O |
Neighbourhood nuisance |
All complaints regarding
construction works shall be relayed to the environmental team. |
CEDD’s Contractor |
As above |
C |
1, 6 |
ü |
P |
Legal requirements |
Different types of waste
should be segregated, stored, transported and disposed of in accordance with
the relevant legislative requirements and guidelines |
CEDD’s Contractor |
As above |
C |
1,6 |
ü |
Q |
On-site separation |
On-site separation of
municipal solid waste and construction/demolition wastes shall be conducted
in order to minimise the amount of solid waste to be disposed to landfill. |
CEDD’s Contractor |
As above |
C |
1, 11 |
ü |
R |
Temporary storage area |
Separated wastes should be
stored in different containers, skips, or stockpiles to enhance reuse or
recycling of materials and encourage their proper disposal. |
CEDD’s Contractor |
As above |
C |
1, 11 |
ü |
S |
Record of wastes |
Records of quantities of
wastes generated, recycled and disposed (with locations) shall be kept. |
CEDD’s Contractor |
As above |
C |
1, 9 |
ü |
T |
Trip-ticket system |
To monitor the disposal of
waste at landfills and control fly-tipping, a “trip-ticket” system under WBTC
N0.5/99 for all solid waste transfer/disposal operations should be
implemented. The system should be
included as a contractual requirement, and monitored by the Environmental
Team and audited by the Independent Checker (Environment). |
CEDD’s Contractor |
As above |
C |
1, 9 |
ü |
3 |
Soil Remediation Phase |
|
|
|
|
|
|
U |
B, C, D, F, G, I, J, K, L,
M, N, O, P, Q, R, S and T as above |
As above (see W for soil
remediation). |
As above |
As above |
R |
As above |
N/A |
V |
De-watering |
Collect and recycle
extracted groundwater and leachate by mixing with
cement for soil remediation.
Environmental guidelines for the handling and disposal of discharges
from construction sites, as stipulated in the Practice Note for Professional
Persons, Construction Site Drainage (ProPECC PN
1/94) to be followed. Any surplus
groundwater and leachate requiring disposal to be
disposed of under the relevant legislation or treated to meet the standards
given in Table 9a of the WPCO TM. |
CEDD’s Contractor |
KCIP work areas. Duration of the soil
remediation |
R |
5 |
N/A |
W |
Immobilisation |
Immobilisation and testing
of waste soil shall be carried out according to the relevant regulations and
recommendations of the EIA including immobilisation by collection and mixing
the contaminated soil material with cement.
Pilot mixing and TCLP tests should verify the effectiveness and
establish the ratio of cement to soil to the satisfaction of EPD. Reassurance confirmatory sampling shall be
carried out to confirm the extent of contamination. Soil waste to be cast in blocks and
replaced in the ground. Extracted
soils and materials and stabilisation/solidification to be conducted in bunded area to prevent surface run-off. See also item 2(H) above. Final soil decontamination report to be
submitted to EPD. |
CEDD’s Contractor |
As above |
R |
1, 10 |
N/A |
4 |
Monitoring and Audit |
To be carried out in
accordance with the Schedule in the EM&A Manual. |
CEDD*/ Contractor/ RSS |
KCIP works areas During demolition and at end of demolition
throughout execution of Remediation Action Plan |
C |
1 |
ü |
* Normally undertaken by a specialist monitoring team employed directly by the proponent and audited by the Independent Checker (Environment)
@ A = during ash
removal (before demolition)
# C = during
construction (i.e. demolition phase).
* R = during soil
remediation phase (after demolition)
^ Implementation Status:
ü implemented
Ï not implemented
P partially
implemented
X rectified by Contractor
N/A not applicable
1.
Environmental Impact Assessment Ordinance Technical Memorandum (EIAO)
2.
Noise Control Ordinance
3.
The ProPECC Note PN2/93 (Construction Noise
daytime limits)
4.
Air Pollution Control Ordinance (APCO)
5.
Water Pollution Control Ordinance (WPCO)(Cap. 358)
6.
Waste Disposal Ordinance (Cap 354)
7.
Waste Disposal (Chemical Waste)(General) Regulation (Cap 354)
8.
Draft Code of Practice on Demolition of Buildings (BD, 1998)
9.
Works Bureau Technical Circular No. 5/99, Trip-ticket System for
Disposal of Construction and Demolition Material
10.
Guidance Notes for Investigation and Remediation of Contaminated Sites
11.
Works Bureau Technical Circular No. 5/98, On Site Sorting of
Construction Waste on Demolition Sites
12. ProPECC Note PN 1/94Construction Site Drainage
Table
C‑3 Event Contingency Plan for
Environmental Complaints
Step |
Day |
Action |
Contractor |
ER |
ET |
IEC |
1 |
1 |
Party receiving complaint shall create a new
complaint record. If the Contractor receives a complaint, he shall pass the
information to the ER. |
¨ |
¨ |
¨ |
|
2 |
1 |
ER to ensure details of complaint provided
to Contractor (if complaint not originally received by the Contractor), ET
and IEC |
|
¨ |
|
|
3 |
2 |
Within 1 working day after the receipt of
the Notification of Complaint, provide ER relevant works site information,
e.g. types and locations of construction works. |
¨ |
|
|
à |
4 |
2 |
Investigate the complaint to determine its
validity, and to assess whether the source of the problem is due to the works
activities. Report the validity of the
complaint to ER. |
|
|
|
¨à |
5 |
2 |
If complaint is valid and due to works, ER
shall notify the Contractor. If
complaint is invalid or not due to works, Go to Step 12. |
|
¨ |
|
|
6 |
2 |
Propose mitigation measures to ER within 1
working day of the receipt of the Notification. |
¨ |
|
|
à |
7 |
2 |
Review and agree with the proposed
mitigation measures and make recommendations where necessary. |
|
¨à |
|
¨à |
8 |
2 |
Implement the mitigation measures once they
have been agreed. |
¨ |
|
|
|
9 |
4 |
Audit the implementation of the proposed
mitigation measures on site within 2 working days after measures have been
agreed. |
|
¨à |
|
¨à |
10 |
- |
Undertake additional monitoring to verify
the situation where necessary. |
|
|
¨ |
|
11 |
4 |
Report the investigation results and
subsequent actions taken to ER within 2 working days after the implementation
of mitigation measures. |
¨ |
|
¨ |
|
12 |
5 |
Respond to the complainant within 1 working
day after receiving the investigation report. |
|
¨ |
|
|
13 |
25 |
If no further comments or complaints are
received from the complainant within 20 working days after responding to the
complainant, close the complaint record.
If the complainant has further comments or complaints on the same
issue, notify other parties on the same day and go to step 2. |
|
¨ |
|
¨à |
¨ Action Party
à Enter comments/
proposals into appropriate complaint record where applicable
Appendix D EM&A
Schedule
Appendix E Air
Quality Monitoring Results and Graphical Presentation