Waste Management Policy
We are committed to reduce/minimise the generation of construction and demolition (C&D) material and to undertake construction activities in an environmental friendly manner.
We are committed to:
· Ensure construction works complied with specified standards and statutory requirements.
· Achieve the objectives we have established in this Waste Management Plan (WMP).
· Provide adequate resources and facilities to facilitate the implementation of this WMP.
· Ensure that all staff members in relevant departments perform their duties according to this WMP.
· Conduct regular review and audit to monitor the implementation of this WMP.
Project Director
China International Water & Electric Corporation
March 2008
List of Contents
Chapters Page
1.2 Scope
of Demolition Works of the Project
1.5 Environmental
Legislation and Guidelines
1.6 Application
for Licenses, Permit and Approvals
2.2 Hierarchy
of Waste Management
3 ORGANIZATIONAL STRUCTURE FOR
WASTE MANAGEMENT
3.2 Roles
and Responsibilities of Key Waste Management Personnel for KCIP
4 WASTE GENERATION AND DISPOSAL
4.2 General
Refuse & Non-Inert C&D Material
4.3 Inert
C&D Materials & Recyclables
4.4 Asbestos
Containing Materials (ACM)
4.5 Dioxin
/ Furan Contaminated Wastes
5 IMPLEMENTATION OF WASTE
MANAGEMENT
5.4 Inspection
Programme and Performance Monitoring
5.5 Record Keeping and Reporting
6.1 Objective
of the Emergency Response Procedure
6.6 Communications with the Public
6.9 The
Contractor and Employees
6.10 Sub-Contractors
and Others
6.11 Emergency
Response Procedures
6.12 Post-Emergency
Procedures
List of Tables
Table
1‑1.... Structures
to be Demolished at KCIP
Table 2‑1.... Hierarchy of Waste Management
Table 4‑1.... Summary of Waste Disposal
Table 4‑2.... Estimated Quantity of ACM
Table 4‑3.... PCDDs/ PCDFs Analysis Results for Samples
Collected at the Ash Bunker
List of Appendices
Appendix A1 Figure 1-1 Location
Plan of the Project Site
Appendix A2 Figure 4-1 Location of Temporary Storage Area
Appendix A3 Figure 4-2 Transportation Route for Different Type of Waste
Appendix A4 Figure 4-3 Dioxin Sampling Locations at Ash Bunker
Appendix B1 Master Works Programme
Appendix B2 General Demolition Procedure
Appendix C Project Organization Chart
Appendix D Generic Method Statement and Work Sequence of ACM Removal
Appendix E Memo from Mines Division of CEDD for the use of TKO Area 137 Pier
Appendix
F1 Flow Diagram of Cement
Solidification
Appendix F2 Methodology of TCLP Test
Appendix G1 Waste Disposal Delivery Schedule to Landfill Site
Appendix G2 Yearly Summary Waste Flow Table
Appendix G3 Monthly Summary Waste Flow Table
Appendix H Site Management Plan for Trip-ticket System
1.1.1
This
Waste Management Plan (WMP) has been prepared to fulfil Condition 2.8 of the
Environmental Permit (EP No. EP-121/2002) with respect to the demolition works
of the Project – “Demolition of Kwai Chung Incineration Plant”. The major scope
of the demolition works of the Project is to remove all ACM/DCM in chimney and
superstructures before commencement of the demolition works. The decontamination works of the Project will
be carried out after completion of the demolition works of the Project.
1.1.2
This
WMP does not cover the decontamination works to be carried out for the Kwai
Chung Incineration Plant (KCIP). The corresponding WMP for the decontamination
works will be submitted under a separate cover for ground decontamination
works.
1.1.3
As
there have been ongoing discussions between EPD and CEDD on proposals for
treatment and disposal of dioxin containing materials (“DCM”) within the KCIP
Chimney, these parts of the WMP have been put on hold until an agreement is
reached between the two departments.
Subject to agreement with EPD, the treatment method and disposal of DCM
for the KCIP Chimney will be finalized.
1.1.4
This
WMP has therefore focused on and finalized the rest of waste management aspects
with respect to waste generation, treatment and disposal for this Project other
than DCM (and ACM to avoid
cross-contamination) within the KCIP Chimney in order to facilitate early
approval by part so that other parts of the Project can proceed independently.
1.1.5
WMP
versions 1.1 and 2.2 were certified by ET and verified by IEC and submitted to
EPD on
1.2 Scope of Demolition Works of the Project
1.2.1
The
demolition works of the Project with boundary as shown in Figure 1-1 is
summarised in Table 1.1.
Table 1‑1 Structures to be Demolished at KCIP
Building |
Brief Description |
KCIP
Chimney |
Reinforced
concrete construction of diameter 6m – 12m and 150m high. Internal metal
flues and platforms |
KCIP
Buildings |
High,
single storey steel frame, with weather cladding, pre-cast concrete slab,
reinforced concrete partitions, corrugated metal sheet external wall and
roof. The overall size is
approximately 83m x 92m on plan. |
|
Single
Storey. Approximately 4m x 13m on plan. |
Site
Office/ |
Two
storey high prefabricated building. Approximately 40m x 7.5m on plan. |
1.2.2 The demolition works of the Project also includes the removal of asbestos containing materials (“ACM”) and dioxin/ furan contaminated materials (“DCM”) prior to demolition of the relevant structures.
1.3.1
The
Contract for the Project was awarded on
1.3.2
The
removal of ACM can be independent from DCM because ACM were found at locations
different from those of DCM. Therefore, removal of ACM can commence prior to
DCM removal works.
1.4.1
Condition
2.8 of the Environmental Permit EP-121/2002 requires that a WMP shall be
submitted to the DEP 8 weeks before the commencement of the decommissioning of
the Project. WMP versions 1.1 and 2.2 were certified by ET and verified by IEC
and submitted to EPD on
1.4.2
This
WMP includes details on the types, quantities, disposal methods, timings and
locations for treatment and disposal of wastes, responsibilities for
implementation and possible recycling and reuse of materials and is written
with reference to the requirements set out in the ETWB TCW No. 19/2005.
1.4.3
This
WMP has taken into account in devising any findings and recommendations in the
waste management section of the EIA Report (Register No. AEIAR-049/2002), and
relevant findings of the Reassurance and Confirmatory Testing Report
(“RCT”). Before submission to the
Director, the WMP will have to be certified by the ET Leader and verified by
the IEC as conforming to the information and recommendations contained in the
EIA Report, and any relevant findings of the RCT.
1.4.4
This
WMP has included, but not limited to, the following information for each type
of the wastes relevant to the specific Project part that it is intended to
cover. The types of wastes covered
include general refuse, asbestos containing materials (“ACM”) (other than those
within Chimney), DCM in Ash Bunker and construction and demolition (“C&D”)
materials.
·
summary of the locational sources, quantity, level of contamination (if
applicable), remediation required prior to disposal (if applicable), and
on-site and off-site disposal methods for different type of wastes;
·
timings for generation, remediation (if applicable), temporary on-site
stockpiling or storage, and final on-site or off-site disposal of different
type of wastes;
·
method statements on the remediation works to be carried out on ACM and
DCM (ash bunker only), and the confirmatory and parallel independent testing to
be conducted;
·
on-site waste management measures to control nuisances during the
generation, handling, remediation (if applicable), and temporary stockpiling of
the different types of wastes, in particular for ACM/ DCM,;
·
possible recycling and reuse of materials;
·
location of the disposal site(s) for various types of wastes;
·
confirmation on whether or not barges would be used for removal of
wastes;
·
transportation routing(s) of the removal of various types of wastes from
the project site to the disposal site(s);
·
measures to control nuisances due to transportation of different type of
wastes, in particular to avoid loss of asbestos containing materials; to remove
possible soil left on the first several hundred meters of roads by vehicles
leaving the site, such as the option of using specially design road cleansing
vehicle; and to reduce dust nuisance from trucks carrying wastes, such as the
option of installing mechanical covers to trucks;
·
trip-ticket system for waste transfer/disposal operations, including a
certification system to confirm to the disposal site’s operator that the
contaminated wastes have been remediated to meet the specific disposal
criteria; and
·
responsibilities for implementation.
1.5 Environmental Legislation and Guidelines
Regulatory Requirements
1.5.1
During
the Contract, the Contractor will comply with the following Ordinances and
Regulations, which cover, or have some bearing upon, the handling, treatment
and disposal of wastes in the Hong Kong SAR.
Waste Disposal Ordinance (Cap 354)
1.5.2
The
Waste Disposal Ordinance (WDO) prohibits any person from using any land or
premises for the disposal of wastes unless one has been authorised by or has
obtained a license from the Waste Disposal Authority, the Environmental
Protection Department (EPD).
Waste Disposal (Chemical Waste) (General) Regulation
(CWR), Enacted under the WDO
1.5.3
The
Regulation has provisions to require any person who produces chemical waste to
register with the EPD as well as to control the processing, storage,
collection, transport and disposal of chemical waste. In additional, the CWR
also provides for the licensing of waste collection, transport and disposal
activities.
1.5.4 For chemical waste registration, Contractor is required to provide particulars on the location of waste generating activities, the nature of operation and waste types to be generated. A registration form shall be prepared and submitted to the EPD for approval prior to the waste generating activities. Upon successful completion of the registration procedure, the EPD will then issue a confirmation note and assign a waste producer number. Any disposal of chemical waste registered shall give prior notification to EPD and the disposal has to follow directions of the EPD. If certain types of chemical wastes are classifiable as Dangerous Goods under the Dangerous Goods Ordinance (Cap. 295) (DGO), handling of these wastes shall also comply with the requirements of the DGO and its regulations.
Waste Disposal (Charges for Disposal of Construction
Waste) Regulation
1.5.5
The
Charging Scheme has come into operation on
1.5.6
Starting
from
1.5.7
For
construction work under a contract with value less than $1 million, such as
minor construction or renovation work, any person such as the owner of the
premises where the construction work takes place or his/her contractor can open
a billing account; the account can also be used for contracts each with value
less than $1 million. The premises owner concerned may also engage a contractor
with a valid billing account to make arrangement for disposal of construction
waste.
1.5.8
Charging
for disposal of construction waste has started on
Land (Miscellaneous Provisions) Ordinance (Cap 28)
1.5.9
Public
fill construction wastes may be taken to public dumps. The Land (Miscellaneous
Provisions) Ordinance (LO) requires that dumping licences be obtained by
individuals or companies who deliver suitable construction wastes to public
dumps. The licences are issued by the CEDD. In the case that public dumping of
public fill construction waste is desired, the contractor shall apply for the
licence prior to disposal of the construction wastes.
Public Health and Municipal Services Ordinance (Cap
132) - Public Cleansing and Prevention of Nuisances Regulation
1.5.10
The
Public Health and Municipal Services Ordinance (PHMSO), Water Pollution Control
Ordinance Cap. 358, and Waste Disposal Ordinance Cap. 354 have provisions on
the control of the discharge of hazardous materials to sewers and for the
control of littering. The ordinances prohibit placing or throwing any solid matter,
mud or waste into public sewers or drains and also placing these substances in
a location where they may fall into these public sewers/drains.
1.5.11
It
also has provisions to require the owner or occupier of the land adjoining any
street or place in which is situated near a public sewer to exercise measures
to prevent obstruction of sewers and drains caused by soil and waste.
Additional Guidelines
1.5.12
This
WMP has been prepared with reference to the following 'guideline' documents:
·
Waste Disposal Plan for
·
Chapter 9 Environment of
·
Works Branch Technical Circular
No. 2/93, Public Dumps, Works Branch,
·
Works Branch Technical Circular
No. 2/93B, Public Filling Facilities; Works Branch,
·
Works Branch Technical Circular
No. 16/96, Wet Soil in Public Dumps; Works Branch,
·
Works Bureau Technical Circular
No. 4/98 & 4/98A, Use of Public Fill in Reclamation and Earth Filling
Projects; Works Bureau,
·
Waste Reduction Framework Plan,
1998 to 2007, Planning, Environment and Lands Bureau, Government Secretariat,
·
Works Bureau Technical Circular
No 19/2001, Metallic Site Hoardings and Signboards; Works Bureau,
·
Works Bureau Technical Circular
No. 12/2000, Fill Management; Works Bureau,
·
Works Bureau Technical Circular
No 12/2002, Specifications Facilitating the Use of Recycled Aggregates. Works
Bureau,
· Environment, Transport and Works Bureau Technical Circular (Works) No 33/2002, Management of Construction and Demolition Material Including Rock, Environment, Transport and Works Bureau, Hong Kong SAR;
· Works Bureau Technical Circular No 31/2004, Trip-ticket System for Disposal of Construction and Demolition Material; Works Bureau, Hong Kong SAR Government;
· A Guide to Chemical Waste Control Scheme and A Guide to the Registration of Chemical Waste Producer, Environmental Protection Department, Hong Kong SAR; and
· Code of Practice on the Packaging, Labelling and Storage of Chemical
1.5.13
Practices
for asbestos handling and disposal are in accordance with the followings:
· Air Pollution Control (asbestos) Administration Regulation
· ProPECC PN2/97 Handling of Asbestos Containing Materials in Buildings.
· Code of Practice on the Handling , Transportation and Disposal of Asbestos Waste,
· Code of Practice on Asbestos Control, Preparation Work Using Full Containment or Mini Containment Method,
· Code of Practices on Asbestos Control; Asbestos Work Using Glove Bag Method,
· Code of Practice on Asbestos Control; Safe Handling of Low Risk Asbestos Containing Material, and
· Code of Practice on Asbestos Control; Preparation management Plan and Asbestos Abatement Plan.
1.6 Application for Licenses, Permit and Approvals
1.6.1
The
Contractor will apply for, where appropriate, and maintain all the following
permits and licenses required under the legislation for the handling and
disposal of waste arising from the Contract.
· Public Dumping Licence under the Land (Miscellaneous Provisions) Ordinance (Cap 28);
· Chemical Waste Producer Licence under the Waste Disposal (Chemical Waste) (General) Regulation (Cap 354);
· Chemical Waste Collection Licence under the Waste Disposal (Chemical Waste) (General) Regulation (Cap 354);
· Land (Miscellaneous Provisions) Ordinance
Ø Dumping licences are issued free of charge by the Port Works Division, Civil Engineering Department to lorry owners for delivering public fill to public filling facilities. The licences are valid to the end of each calendar year and the licensee need to apply for a new licence for the new calendar year. Dumping labels are also issued together with the licences for display on the wind-screen of the lorry.
·
Waste Disposal (Chemical Waste)
(General) Regulation
Ø Chemical waste, as defined under the Waste Disposal (Chemical Waste) (General) Regulation, includes any substance or thing being scrap material, effluent, or an unwanted substances or by-product arising from the application of or in the course of any process or trade activity, and which is or contains any substance or chemical specified in the prescribed schedule (i.e. Schedule 1 of the Waste Disposal Regulations) if such substance or chemical occurs in such form, quantity or concentration so as to cause pollution, constitute a danger to health or risk of pollution to the environment.
2.1.1
The
principles of waste management to be adopted in this Project will be in line
with the latest Government policy on environmental management.
2.2 Hierarchy of Waste Management
2.2.1
The
various waste management options will be categorised in terms of preference
from an environmental viewpoint. The
options considered to be more preferable have the least impacts and are more
sustainable in the longer term. Hence,
the hierarchy of waste management is as follows in descending order:
Table 2‑1 Hierarchy of Waste Management
Avoidance and Minimization |
Avoid
and minimize generation of C&D materials through careful planning and
design of works |
Reuse |
Reuse
inert portion of the C&D materials generated. |
Recovery
and Recycle |
Undertake
on-site and off-site waste recycling |
Treatment
and Disposal |
Properly
treat and dispose of waste in accordance with legislative requirements,
guidelines and good practices. |
2.2.2
This
hierarchy will be used to evaluate waste management options, thus allowing
maximum waste reduction. Waste reduction
measures will be introduced at the planning and detailed design stage and
carried through the construction activities, whenever possible, by careful
purchasing control, reuse of formworks and good site management.
3.1.1
The
organisation of the waste management team is described under this section, the
personnel responsible for waste management shall:
· Work within the scope of the demolition contract;
· Participate in the waste management site inspections undertaken by the Environmental Team (ET) and the Independent Environmental Checker (IEC) as required and undertake any corrective actions instructed by the ER; and
· Take responsibility and strictly adhere to the provisions of the WMP and the contract specifications.
3.2 Roles and Responsibilities of Key Waste Management Personnel for KCIP
3.2.1
The
major scope of the demolition works is to remove all ACM/DCM in structures and
demolish all structures above ground level within the KCIP site. All underground structural components shall
remain undisturbed before the land decontamination works.
3.2.2
A
Project Organization Chart is shown in Appendix C. The roles and
responsibilities of the key waste management personnel shall include, but not
be limited to the following:-
The Employer and EP Holder
3.2.3
The
Project Proponent shall be responsible for providing full support on the
implementation of the approved WMP.
The Engineer’s
Representative (ER)
3.2.4
The
ER shall:
· Ensuring that the WMP is fully implemented throughout the Project;
· Review the waste monitoring and audit report submitted by the ET;
· Follow up and ensure the proposed corrective actions to be in accordance with the WMP;
· Investigate and audit the equipment and work methodologies with respect to waste management; and
· Monitor and report any exceedance or non-compliance under the environmental permit and pollution control ordinances.
The Contractor’s
Representative
3.2.5
The
CR is responsible for overall planning, site operations, appointment of
committee members for waste management, staff supervision control,
co-ordination and external liaison. The CR shall:
· Oversee the waste management within the Project, which they achieve by implementation of the WMP;
· Participate and provide necessary support to the ET for the preparation and review of WMP;
· Ensure that staff attends environmental training with regard to waste management organized by the Waste Manager;
· Implement environmental controls and mitigation as set out in this WMP as well as any additional measures necessary for compliance with environmental control measures;
· Ensure the recommendations and instructions of the ER or ET are implemented to improve the waste management practice and carry out immediate action to rectify the non-compliance of waste management and environmental protection requirements;
· Providing leadership in the efficient management of the Project and in meeting the Work’s waste management objectives; and
· Anticipate waste generation impacts that may require mitigation before the problem arises.
Site Agent
3.2.6
The
Site Agent shall:
· Arrange routine joint site inspection with ET and review environmental inspection report submitted by the ET;
· Ensure works are undertaken in accordance with the recommendations made and instructions given by the ER and ET;
· Monitor and control the works including those of subcontractors to ensure compliance with specified requirements;
· Ensure appropriate waste management mitigation measures are properly implemented;
· Ensure follow up actions are properly undertaken in the event of non-compliance of the WMP;
· Review method statement to ensure appropriate mitigation measures are implemented prior to execution of work;
· Liaise with ER, and ET on waste management and environmental protection issues;
· Monitor records of all trained personnel in the site offices;
· Monitor the following documents:
Ø Any statutory required waste management permits/licenses including dumping license, chemical waste producer, admission ticket and etc.;
Ø C&D material disposal delivery record; and
Ø Waste reuse / recycle / disposal summary.
· Keep abreast of the statutory requirements and regulations about waste management; and
· Supervise and arrange the maintenance of waste management facilities.
Waste Manager
3.2.7
The
Waste Manager shall:
· Ensure all relevant legislation and the Contractor’s duty of care is complied with throughout the duration of the Project;
· Initiate waste reduction scheme on site;
· Ensure that all the Contractor’s employees and nominated subcontractors’ employees are aware of their responsibilities regarding the content of the WMP; and
· Co-ordinate waste management on site, gather data on waste and keep accurate records on waste movement both on and off site.
Registered Asbestos
Consultant
3.2.8
The
Registered Asbestos Consultant shall:
· Verify the extent of the ACM identified prior to commencement of the asbestos abatement works;
· Supervise ACM removal works of the Registered Asbestos Contractor;
· Certification and acceptance of the site preparation or completion of asbestos abatement works by the Registered Asbestos Contractor for each work zone; and
· Prepare Asbestos Investigation Report (AIR) and Asbestos Abatement Plan (AAP) and submit to the EPD of any ACM that was previously not found or reported.
Registered Asbestos
Contractor
3.2.9
The
Registered Asbestos Contractor shall:
· Be responsible for the asbestos abatement works including the removal of all ACM identified in the Asbestos Study Report (ASR) including the AIR and AAP, and any unsurveyed ACM found during the demolition works;
· Establish containment and associated ventilation and filtration equipment as required for asbestos abatement works;
· Provide three-chamber decontamination unit for each of the containment for asbestos abatement works;
· Carry out air monitoring requirements for the containments for asbestos abatement works;
· Be responsible for the appropriate removal, packaging and storage for different types of ACM;
· Transport properly packaged ACM to designated facilities for disposal;
· Comply with emergency procedures under various emergency cases; and
· Provide experienced full-time Registered Asbestos Supervisor(s) on site every day during the course of the asbestos abatement works.
Registered Asbestos
Supervisor
3.2.10
The
Registered Asbestos Supervisor shall:
· Oversee all safety procedures and monitor the Controlled Works Area(s) for asbestos abatement works and ensure that the Contaminated Works Area(s) for asbestos abatement works is continuously cleaned of asbestos fibres;
· Verify that all workers for asbestos abatement works wear suitable close fitting respirators every day, and shall maintain a register to verify correct procedures and movement of all persons who enter the Contaminated Works Area(s); and
· Undertake all duties as required by the Factories and Industrial Undertakings (Safety Officers and Safety Supervisor) Regulations as necessary for asbestos abatement works.
Site Engineer (Demolition)
3.2.11
The
Site Engineer shall:
· Assist the Site Agent in the implementation of WMP;
· Monitor and control works including those of subcontractors to ensure compliance of WMP;
· Report to the Site Agent regarding non-compliance of waste management issues; and
· Ensure the remedial actions or mitigation measures are carried out as planned.
General Foremen
3.2.12
General
Foremen shall:
· Assist the Site Engineer in the implementation of WMP;
· Control works, including those of subcontractors, to fulfil the requirement of waste management issues;
· Report to the Site Engineer any non-compliance of waste management issues;
· Maintain the on-site waste management facilities including sorting area, temporary storage area, general refuse bins and recycling bins etc;
· Carry out remedial actions or mitigation measures to rectify non-compliance;
· Carry out routine maintenance of waste management facilities and proper maintenance records shall be kept in site office; and
· Report non-compliance of environmental protection issues.
Subcontractor and other
employees
3.2.13
Every
employee and subcontractor has the duty to carry out the waste management
practices instructed by the Site Engineers and General Foreman. Copies of WMP
are to be issued to all subcontractors.
3.2.14
Every
employee and subcontractor shall report promptly to foreman any non-compliance
of waste management and environmental protection issues.
The Environmental Team (ET)
and ET Leader
3.2.15
The
ET, including the ETL, shall:
· Be responsible for the duties defined in the EM&A Manual of the EIA Report;
· Conduct site inspections and investigate and inspect the Contractor’s equipment and work methodologies with respect to waste management and environmental mitigation measures. They shall review the works for anticipating potential waste management and environmental pollution implications;
· Review the programme of works to anticipate potential waste management implications;
· Report the implementation status of waste management mitigation measures from site inspections; and
· Follow the procedures stipulated in the agreed Event and Action Plans in the event of non-compliance or complaint.
· Be responsible for the implementation of the EM&A programme in accordance with the EM&A requirements as contained in the EM&A Manual; and
· Keep a contemporaneous log-book of each and every instance or circumstance or change of circumstances which may affect the environmental impact assessment and for each and every non-compliance of the EIA Report or the EP.
The IEC
3.2.16
The
IEC shall:
· Be responsible for the duties defined in the EM&A Manual of the EIA Report, and shall audit the overall EM&A programme described in the EIA Report, including the implementation of all environmental mitigation measures, submissions required in the EM&A Manual, and any other submissions required under the EP;
· Be responsible for verifying the environmental acceptability of permanent and temporary works, relevant design plans and submissions under the EP;
· Verify the log-book(s) kept by the ETL;
· Notify EPD of each and every occurrence, change of circumstances or non-compliance with the EIA Report or the EP, which might affect the monitoring or control of adverse environmental impact;
· Conduct monthly site audit to ensure the Environmental Management System (EMS) is in place and recommend any changes as appropriate;
· Review and audit all aspects of the EM&A programme, including the WMP;
· Assist the ET on complaint investigation and recommend and/or instruct mitigation measures as appropriate; and
· Liaise with the ET on all environmental performance matters.
4.1.1
The
following types of waste would be generated from the demolition activities
under this contract:
·
General refuse
·
Inert Construction and Demolition (C&D) Material
·
Non-inert C&D Material
·
Recyclables
·
Asbestos Containing Materials (ACM)
·
Dioxin/Furan Contaminated Materials (DCM)
·
Chemical waste
4.1.2
The
estimated quantity of waste arising from different activity & work areas,
and the disposal sites for the wastes generated from the project are provides
in the following sections. The estimated period of waste generation to landfill
site is from December 2007 to August 2009 excluded the period of land
decontamination works. The waste disposal schedule to landfill site is shown in
Appendix G1.
Table 4‑1 Summary of Waste Disposal
Waste Type |
Examples / Classification |
Disposal Site |
General Refuse |
•
Packaging waste •
Office waste •
Putrescible wastes •
Vegetation |
•
SENT Landfill by vehicles |
Inert C&D material |
•
Broken concrete •
Brick •
Aggregate |
•
Public Fill at Tuen Mun Area 38 Fill Bank |
Non-inert C&D material |
•
Wood •
Bamboo |
•
SENT Landfill |
Recyclables |
•
Metal •
Paper •
Plastic |
•
Recycling collectors |
Asbestos Containing Material (ACM) |
•
Type 1 •
Type 2 •
Type 3 •
|
•
Disposal of at SENT Landfill by licensed collector •
Abatement and disposal ACM
within Chimney not covered in this WMP and will be submitted in next version. |
Dioxin/Furan Contaminated Material (DCM) |
•
Ash bunker •
Chimney flues |
•
Disposal of at SENT / WENT Landfill by licensed collector
(disposal to CWTC will only be a fallback solution as per EP No. 121/2002) •
Treatment and disposal of DCM
within Chimney not covered in this WMP and will be submitted in next version. |
•
Spent lubricant oil •
Surplus paint •
Spent diesel |
•
To be collected by licensed waste collector |
4.2 General Refuse & Non-Inert C&D Material
4.2.1
General
refuse will be generated largely by food service activities for on‑site
staff, from office work and certain aspects of the construction works, and will
include food wastes, unrecyclable waste etc.
Estimated
Quantities and Timing for Generation
4.2.2
It
is estimated that the general refuse and non-inert C&D material arising
will be about 50m3 per month exclude the period of land
decontamination works. Although the size of the site office establishment will
vary at different stages of the demolition works, thus be observed that the
relative contribution to the general wastes from site staff, which will be
generated throughout the whole contract period, will be small in terms of the
overall wastes arising. The tentative programme of the non-inert C&D
material generation would be from December 2007 to August 2009 exclude the
period of land decontamination works.
4.2.3
Office
waste will be reduced through reduce use of paper and minimize the waste
generation.
4.2.4
General
refuse including food wastes, such as lunch boxes, and domestic wastes
generated on-site will be stored in enclosed bins or compaction units separated
from construction and chemical wastes.
On-Site Handling or Storage
4.2.5
Putrescible
wastes, such as lunch box, and domestic wastes generated on-site will be stored
in enclosed bins or compaction units separate from C&D and chemical
wastes. Location of temporary storage of
general refuse is indication in Figure 4-1.
4.2.6
A
reputable waste collector will be employed by the Contractor to remove general
refuse and to be disposed of at landfill site, separately from C&D material
and chemical wastes, preferably daily to minimise odour, pest and litter
impacts. The burning of refuse on
construction sites is prohibited by law.
4.2.7
Waste
disposal records will be obtained from the appropriate authorities and
collection of general refuse and general site housekeeping will be carried out
in accordance with the Waste Disposal Ordinance (Cap. 354), Waste Disposal
(Chemical Waste) (General) Regulation (Cap. 354) and the Government Land
(Miscellaneous Provisions) Ordinance (Cap. 28).
4.3 Inert C&D Materials & Recyclables
4.3.1
Due
to the nature of the works, C&D materials, other than material mentioned at
paragraph 4.2, will also be generated under the contract. The types of C&D materials include the
following:
·
Inert C&D materials (including rock, broken concrete, etc); and
·
Recyclables non-inert materials such as metal components, plastic &
paper.
4.3.2
C&D
material comprises materials broken up during demolition, including concrete
and structural steel. Alternatively
there are materials which are surplus to requirements for the demolition
process and materials which have been used and discarded. The bulk of the C&D material will come
from the buildings and other related structures (e.g. chimney) which are to be
demolished. C&D material may
comprise different types of materials.
4.3.3
C&D
materials are typically generated simultaneously in mixed form and the
individual waste materials may be altered (e.g. painted). The final actual volume and composition of
C&D waste requiring disposal to public filling area following the
demolition at KCIP will be dependent on the demolition procedure and material
recovery practices employed.
Estimated Quantities and
Timing for Generation
4.3.4
It
is estimated that the total C&D material arising will be about 9,000m3
which mainly consist of broken concrete. Meanwhile, a small portion of
recyclables (approx. 180m3) which would be collected by the
recycling collectors would also be generated from the demolition works. The
estimated quantities of recyclables would be:
·
Steel bars: total 1,900 tonne;
·
Plastic: 100kg per month; and
·
Paper: 100kg per month.
4.3.5
The
tentative programme of C&D materials generation would be from the 12th
month to the 24th month covering the period from the commencement of
the contract works to the completion of the demolition works.
4.3.6
To
reduce / minimize the generation of C&D materials, materials resulted from
the demolition works will be sorted properly to recover the inert portions for
reuse on site or disposal to designated outlets.
4.3.7
Sorting
of inert and non-inert portions of demolition materials will be carried out at
the source site to avoid double handling and loss of materials due to
transportation. In case the site condition is inapplicable for sorting, it will
be carried out at the designated storage area. Reusable / recycling materials
of both the inert and non-inert portion will be further recovered for on-site
reuse or collection by the recycling contractors.
4.3.8
Demolition
materials will be segregated from other wastes to avoid contamination thereby
ensuring acceptability at public filling areas and avoiding the need for
disposal at landfill.
On-Site Handling or Storage
4.3.9
Due
to the large volumes of (non-contaminated) C&D material generated from the
demolition works, it is important that selective demolition and on-site sorting
as described below will be incorporated into the tender documents for
implementation by the Contractor.
Selective
Demolition
4.3.10
“Selective
Demolition” involves demolition and removal of wastes of the same category one
at a time. In general, domestic wastes
such as furniture, household appliances; metal components such as window
frames, pipes; timber components such as doors, wooden floors; and other wastes
such as tiles, asphalt materials, ceramic products will be removed first. The building demolition will begin after all
the above non-structural materials have been stripped and removed. To avoid mixing the non-recyclable bricks
with the broken concrete, the demolition sequence will be planned in such a way
that brick walls are demolished first and stockpiled separately before the
demolition of structural members.
On-site
Sorting
4.3.12
All
inert C&D materials from demolition such as the rock and broken concrete
will be disposed off site to the designated Public fill reception Facilities
(PFRF) whilst the non-inert portion excluding all reusable / recyclables
material, is classified as C&D waste which will require to be disposed of
at the WENT/ SENT Landfill Site or other areas as designated by EPD. For inert
C&D materials to be disposed of at designated PFRF, the Contractor will
ensure that the C&D materials be broken down on site to less than 250mm so
as to facilitate its reuse in reclamation or earth filling projects.
4.3.13
C&D
material will be transported by barge. The C&D material generated from the
demolition works will be loaded on barge immediately and be transported offsite
as soon as it fills the capacity. Location of temporary storage of C&D
material is indicated in Figure 4-1.
4.3.14
Designated
areas for segregation and temporary storage of reusable and recyclable
materials are identified. The Contractor
will recycle as much of the C&D material as possible on‑site. Different areas of the work site will be
designated for such segregation and storage wherever site conditions permit.
Recyclables
4.3.15
To
encourage environmental awareness and to reduce waste by reducing the number of
photocopies to a minimum and by copying on both sides of paper for internal
documents and external documents where appropriate. Recycling bins for paper
and plastic bottle will be provided in site office to facilitate the recycling.
Waste paper and plastic bottle will be stored in containers clearly marked as
recyclable or waste. Location of temporary storage of recyclable is indicated
in Figure 4-1 of Appendix A.
Disposal Arrangement
4.3.16
Environment, Transport and Works Bureau Technical Circular (Works) No.
31/2004 – Trip-ticket System for Disposal of Construction and Demolition
Materials
promulgates the policy to implement a trip-ticket system in Public Works
Programme (PWP) contracts for the proper disposal of C&D material at public
filling facilities or landfills. A trip-ticket system should be implemented for
this Project in accordance with ETWB TC(W) No. 31/2004 as per the
recommendation of the approved EIA Report and the conditions of the
Environmental Permit therefore overrule the exemption quantity of 50,000 m3
specified in ETWB TC(W) No. 31/2004.
4.3.17
All
inert C&D material for disposal shall be transported by barge to the public
fill area or other areas as designated by EPD. Vessel chits forms should be
used for C&D material disposal of at public fill area by barge.
4.3.18
The
transportation route for disposal of C&D material is indication in Figure
4-2 of Appendix A.
4.4 Asbestos Containing Materials (ACM)
4.4.1
ACM
is classified as Part A waste under the Waste Disposal (Chemical Waste)
(General) Regulation. An Asbestos Investigation Report (AIR) and Asbestos
Abatement Plan (AAP) have been prepared by Registered Asbestos Consultants (EPD
register 1014 and 1019) based on thorough site investigations under the Air
Pollution Control Ordinance (APCO).
Estimated Quantities and
Timing for Generation
4.4.2
There
will be up to 1,500m3 of asbestos waste mainly in the form of
“Galbestos” (galvanised metal sheeting which forms the outer cladding on the
main building). The galvanised metal cladding is coated with asbestos
containing material paint and will be disposed of in line with the requirements
of the APCO. Three types of ACM were identified at the EIA stage. The
quantities of each type of ACM identified are summarized in Table 4-2.
Table 4‑2 Estimated Quantity of ACM
ACM
Type |
Location
of ACM |
Estimated
Quantity in EIA |
Estimated
Volume, m3 |
Type 1 |
Flue guide plates (flue guides on platforms 1 to 7,
chimney)* (< 3m3) |
3m3 |
3 |
Floor tile
(Thickness = 2mm) - Conference
Room, Office Block (6m x 6m) - Plant Manager
Offices, Office Block (18m x 6m) - Kitchen
Office, - Laboratory, - Corridor, - Workshop
Office, - Day Supervisors Office, |
36m2 108m2 18m2 110m2 40m2 20m2 72m2 |
|
|
Sub-total |
404m2 |
0.8 |
|
Weather cladding
( (Package method#:
Dimension of
cladding sheet: 3m x 0.7m = 2.1m2, 10 sheets per
pack per meter depth. Each pack volume
= 3m x 0.7m x >1m (thickness) = 2.1m3 No. of packs =
13,000m2/2.1m2/10 sheets = 619 packs Volume of
cladding: 619 packs x 2.1m3 = 1,300m3) |
13,000 m2 # |
1,300 |
|
ACM waste (from
cleaning, containment materials, wastewater, etc.) (Type 1) |
<100m3 |
100 |
|
Type 1 Total |
1,403.8 |
||
Type 2 |
Flexible joints (joint between remains of gas ducts
on flues at ground level, base of chimney)* |
Total < 20m3 |
20 |
Gasket (gas door seal on flues at ground level, base
of chimney)* |
Total < 2m3 |
2 |
|
Gasket (duct
seal on ventilation above ground level, outside Kitchen) |
Total < 0.2m3 |
0.2 |
|
Ribbon (Fuse box
at the office block) |
Total <0.1m3 |
0.1 |
|
ACM waste (from
cleaning, containment materials, wastewater, etc.) (Type 2) |
<30m3 |
30 |
|
Type 2 Total |
52.3 |
||
Type 3 |
Gaskets (flues on platforms 1 and 2, chimney)* |
Total < 3m3 |
3 |
Water pipe (fire
water supply, ash bunker) |
Total < 20m3 |
20 |
|
ACM waste (from
cleaning, containment materials, wastewater, etc.) (Type 3) |
<20m3 |
20 |
|
Type 3 Total |
43 |
||
|
Total Volume = Type 1 + Type 2 + Type 3 |
Grand Total |
1,499.1 |
*The abatement, treatment and disposal of
any ACM within the KCIP Chimney shall be subject to later agreement with EPD
and to be covered in a separate WMP for Chimney.
# There are
the same estimation between onsite survey and estimated in the EIA stage and
approved AAP. The proposed packing method is following the approved AAP section
5.1.3. The actual bulk volume of weather cladding depends on the shape and the
Contractor will try the best to reduce the waste volume if applicable.
4.4.3
The
tentative programme of the ACM generation would be from June 2008 to December
2008.
4.4.4
All
ACM will be removed prior to commencement of demolition works. Other than ACM
located in chimney, ACM are located separately from DCM. Thus asbestos removal
works will not be disturbed and cross contamination with DCM Details on the
method statements, work sequence and procedure with regard to removal of ACM
are included in Appendix D.
Package
of Asbestos Wastes:
·
Type 1
asbestos wastes (approximately 3m3 of bulk material plus 13,404m2
of floor tile and claddings. It is estimated that the thickness of floor tiles
is 2mm and removal of weather cladding will follow the approved AAP section
5.1.3, i.e. a total of 1,403.8m3 of type 1 asbestos waste including
ACM waste generated during decontamination. Refers to
Table 4-2 for details) (bonded asbestos wastes, other than blue or
brown asbestos in good condition) will be packed with 2 individual layers of
strong transparent plastic sheets of not less than 0.15 mm thickness and
completely sealed with adhesive tapes. Type 1 waste will be packed in suitable sizes for easy handling. The height of each package will be around 1m.
·
Type 2 asbestos wastes
(approximately 52.3m3 of bulk material
including ACM waste generated during decontamination, refers to Table
4-2 for details) (any waste containing loose
asbestos fibres (other than blue or brown asbestos)) must be contained, as soon
as it is produced, in strong bags made from plastic or other containers
approved by EPD. The bags should be goose-neck sealed by means of adhesive
tapes. A bag filled with asbestos waste should be placed inside another plastic
bag to provide additional protection. The colour of the inner bag should be
white while the outer bag should be transparent to facilitate visual
inspection.
·
The handling of Type 3
asbestos wastes (approximately 43m3 of bulk material including ACM waste generated during decontamination,
refers to Table 4-2 for details) (all blue asbestos
(crocidolite) and brown asbestos (amosite), whether in good condition or not,
or any articles contaminated by blue or brown asbestos) should be similar to
that of Type 2 except that the colour of the inner bags should be orange.
Storage of Asbestos Wastes
4.4.5
All
asbestos waste will be stored properly in a secure place isolated from other
substances so as to prevent any possible release of asbestos fibres into the
atmosphere and contamination of other substances. Type 1 asbestos waste will not be stored
together with Types 2 and 3 asbestos wastes so as to avoid damage to the
plastic bags of Type 2 or 3 asbestos waste, unless the bags are packed in boxes
or drums for additional protection. Bagged asbestos waste will not be stacked
more than 3 bags high in order to avoid damage to the bottom bag. The storage
area will be isolated from other working areas and bear warning panels to alert
people of the presence of asbestos waste.
4.4.6
Location
of temporary storage area of asbestos wastes is indicated in Figure 4-1.
4.4.7
Disposal
of asbestos wastes will not commence before a designated notification has been
given to EPD and confirmed. Before being transported for disposal, all the
asbestos waste produced will be stored in a temporary storage area which
complies with the requirements of Section 7 of the Code of Practice on the
Handling, Transportation and Disposal of Asbestos Waste.
4.4.8
All
asbestos wastes for disposal shall be transported by an asbestos waste
collector - General Central Engineering Limited, licensed by EPD and in a
designated barge equipped as stated in the Code of Practice and to be disposed
of at the SENT Landfill Site or other areas as designated by EPD. For waste
transportation arrangement for the delivery to and deposition at SENT Landfill
Site, the Contractor will use CEDD’s pier at TKO Area 137 for unloading the
materials to truck and then deliver to EPD’s landfill site. The
self-explanatory letter of CEDD is shown in Appendix E. The asbestos wastes
would be temporarily stored in 39 containers to be transported to the barge. It
is estimated that each barge could accommodate 8 nos. containers and therefore
totally 5 barge trips for the disposal of the waste to the landfill from June 2008
to December 2008 would be required.
4.4.9
Pursuant
to S74(3) of the APCO, the proposed amendment to use marine vessel for
transportation of asbestos waste was approved by EPD [Ref.: (10) in
EPAC/A/15/000/918 Pt.VI dated 29 August 2007] on the condition that the marine
vessels will be the approved ones listed in the list of licensed chemical waste
collectors issued by EPD. Transportation route for disposal of ACM waste is
indicated in Figure 4-2 and the generic method statement of ACM removal is
attached in Appendix D.
4.5 Dioxin / Furan Contaminated Wastes
Source of Wastes
4.5.1
According
to Section 4.7.26 of the approved EIA Report (AEIAR-049/2002), ash waste
containing a considerable amount of dioxin and in its untreated state would be
classified as a chemical waste under the Waste Disposal (Chemical Waste)
(General) Regulation.
4.5.2
Dioxin
contaminated ash on the walls and floor near the ash bunker will be collected
and stabilized with cement to meet landfill disposal criteria of EPD, e.g. TCLP
tests as per Section 4.7.32 of the approved EIA Report (AEIAR-049/2002). The
stabilized ash/ sediment will then be sealed in polythene-lined steel drums for
landfill disposal.
4.5.3
Treatment
and disposal of ash from the chimney of the KCIP shall be subject to later
agreement with EPD and be documented in a separate WMP for approval.
4.5.4
Regarding
the quantities and level of contamination of DCM in ash bunker and the KCIP
chimney, please refer to the following section.
Estimated Quantities and
Timing for Generation
Ø Ash and sediment in the area of the Ash bunker: 20m3 [Cement-stabilisation on-site, followed by disposal to landfill (disposal to CWTC will only be a fallback solution as per EP No. 121/2002)]
Ø
Ash in the chimney flue: 7m3 (to be agreed with EPD in a
separate WMP)
Ø
Chimney flue sections: 1,100m3 (to be agreed with EPD in
separate WMP)
Level of Contamination
Ash Bunker
4.5.6
The
laboratory analysis results presented Table 4-3 below has verified the findings
of the EIA Report with respect to dioxin contamination around the ash
bunker. Amongst the 12 samples collected
around the ash bunker, PCDDs/PCDFs were detected in 11 samples, and 4 samples
were found to have TEQ exceeding the USEPA criterion and EP no. EP-121/2002
Clause 2.13 requirements of 1ppb TEQ. The sampling location is given Figure 4-3
of Appendix A.
Table 4‑3 PCDDs/ PCDFs Analysis Results for Samples Collected at the Ash Bunker
Sample ID |
Type of Sample |
Location |
Total TEQ (ppb)* |
D1 |
Ash |
Surface sample from wall of ash bunker at
5m above ground level |
4.6184 |
D2 |
Ash |
Surface sample from wall of ash bunker at
7m above ground level |
0.32281 |
D3 |
Ash |
Surface sample from wall of ash bunker at
5m above ground level |
3.06332 |
D4 |
Ash |
Surface sample from wall of ash bunker at
7m above ground level |
2.77459 |
D5 |
Ash |
Surface sample from floor at 5m away from
the ash bunker |
0.02491 |
D6 |
Ash |
Surface sample from floor at 5m away from
the ash bunker |
0.00301 |
D7 |
Sediment |
Sediment sample from bottom of ash bunker |
0.20995 |
D8 |
Sediment |
Sediment sample from bottom of ash bunker |
0.41922 |
D9 |
Water |
Water sample taken from ash bunker |
0 |
D10 |
Water |
Water sample taken from ash bunker |
0.00017 |
D11 |
Ash |
Surface sample from floor at 5m away from
the ash bunker |
2.73043 |
D12 |
Ash |
Surface sample from floor at 5m away from
the ash bunker |
0.01233 |
* Limited level
= 1 part per billion (ppb)
4.5.7
Dioxin
was found in ash deposits in the ash/sediment of the Ash Bunkers, the Main Hall
Ash Bunker and wall above Ash Bunker of the KCIP site. As indicated in the
approved EIA Report, remedial action is required to clean up these materials
prior to demolition. The decontaminated structures, including the ash bunker,
wall and floor would be dismantled as part of the overall demolition programme. The dismantled structures should be disposed
of as Construction and Demolition (C&D) Material.
4.5.8
Based
on the laboratory testing results, it is considered that the ash material
retained on the surface of the wall (D1, D3 & D4) and north side of upper floor
beside the ash bunker (D11) are dioxin-contaminated (i.e. >1ppb TEQ with the
range of 2.7 – 4.6 ppb TEQ). Furthermore,
the surface of the wall (D2), the ground floor nearby the ash bunker (D5, D6
& D12), accumulated water (D9 & D10) and sediment (D7 & D8) inside
the ash bunker were found below 1ppb TEQ. The total quantity of ash and
sediment material to be handled is estimated to be in the order of 20m3
(i.e., 13m3 of sediment at the bottom of the ash bunker and 7m3
of ash on surface of wall and floor around the bunker).
Timing for generation
4.5.9
The
tentative programme for DCM generation around the ash bunker would be
tentatively from August 2008 to December 2008.
On-Site Remediation Works
Ash
Bunker (20 m3 of ash and sediment in the area of the ash bunker)
4.5.10
To
prevent cross-contamination with the low concentration DCM, the treatment
sequence is firstly for accumulated water in ash bunker; secondly for sediment
and wall ash to be treated at the last.
4.5.11
There
is about 2,000m3 water accumulated inside the ash bunker. From the laboratory
results of the water samples (D9 & D10), it was found that the dioxin
concentration is much lower than the criteria. To prevent extract the sediment
prior to discharge, water will be pumped into the sediment tank with 5mm water filter, reassurance test
will be carried out prior to discharge.
4.5.12
As
the dioxin level of sediment (D7 & D8) and ground floor (D5, D6 & D12) were
below 1ppb TEQ, sediment will be excavated and ground floor will be HEPA
vacuumed cleaned. The collected sediment and ash will be mixed with 10% cement
for solidification within the full containment. The treated sediment floor ash shall
meet the TCLP test before be sealed into steel drums lined with plastic
sheeting prior to disposal at designated area in landfill. In case of failure
in the reassurance TCLP test, the mixing percentage will be increased to ensure
passing the TCLP requirement. It is estimated that 13m3 ash and
sediment to be collected and 14.3m3 treated ash and sediment to be
disposed of.
4.5.13
The
remediation strategies for contaminated material will be adopted where the
level of dioxin contaminants exceeded the USEPA criterion of 1ppb. D2 is
located on the wall of the ash bunker which closed to D1, as prudent approach
to prevent cross-contamination during decontamination works, D2 will be treated
together with D1, D3, D4 and D11. For the sampling locations vicinity to D1, D2,
D3, D4 and D11, ash/rubble will be HEPA vacuumed and
scrabbled. Cement stabilization/solidification will be carried out for the ash/rubble
to meet landfill disposal criteria (TCLP test) of EPD, 1ppb TEQ and specified in Condition 2.13, Part C of the
EP. Pilot test will be carried out first
to obtain the reasonable cement ratio for the ash/rubble. The confirmation test will be carried
out. The flow diagram of cement solidification is given Appendix F1. It is
estimated that 7m3 ash will be collected and estimated that 14m3
treated wall ash will be disposed of subjected to cement ratio obtained from
pilot test.
Pilot Test for Dioxin/Furan Contaminated Soil/Ash
Solidification
4.5.14
The
ratio of contaminants / cement mixture must be predetermined as the
effectiveness of the solidification process depends upon a number of factors
including the concentration of contaminants, contaminants quality, moisture
content, and quality of cement.
4.5.15
Given
the time factor and as a conservative approach, the pilot test for the dioxin
contaminated ash/rubble (i.e. ash collected near D1, D2, D3, D4 and D11) will commence with
cement ratio of 50% to ensure passing the TCLP requirement of 1ppb TEQ. The
ratio of cement will be increased in case of failed in the test to achieve the landfill disposal criteria (TCLP test) of 1ppb TEQ. The flow diagram of cement
solidification is given Appendix F1. In accordance with the EP Condition 2.14,
disposal at the Chemical Waste Treatment Centre, Tsing Yi, will be considered
as a fall back option if the pilot test criteria cannot be met.
4.5.16
It
is estimated that the cement mixing ratio of 300% could be achieved the
disposal criteria, otherwise fall back option as stated in EP Condition 2.14
will be considered. All collected ash near D1, D2, D3, D4 and D11 will be
sealed into steel drums lined with plastic sheeting prior to disposal at the
Tsing Yi Chemical Waste Treatment Centre. Designated barge will deliver to the
Chemical Waste Treatment Centre.
4.5.17
After
granted the disposal license from EPD, the Contractor will carry out the
reassurance test to satisfy the disposal licence requirements, if any. The
ratio of cement to soil/ash will then be selected based on the results of the
TCLP tests. The methodology of TCLP is given in Appendix F2.
On-site Handling and
Storage
4.5.18
DCM
decontamination works will be conducted within a full containment. Ash
contaminated with dioxin will be treated by solidification / stabilisation with
cement, and the treated ash shall meet the TCLP test before it is sealed into
steel drums lined with plastic sheeting prior to disposal at designated areas
in landfill. According to “A Guide to the Registration of Chemical Waste
Producers” issued by the EPD, ash generated from incineration of wastes is
classified as chemical waste.
4.5.19
As
a prudent approach, all wastes generated from the decontamination and removal
works will be considered as contaminated waste and will be properly handled and
disposed of. Other waste such as polythene wrapping sheets, waste generated
from the dismantlement of the containment and decontamination units, and cloth
used in wet wrapping, etc. will also be classified as contaminated waste. It is
estimated that 3m3 used materials will be generated and disposed of.
4.5.20
The
storage, handling, transport and disposal of chemical waste will be in
accordance with the Code of Practice on the Packaging, Labelling and Storage
of Chemical Wastes issued by EPD.
4.5.21
A
total of 31.3m3 of treated DCM and contaminated materials, subjected
to cement ratio obtained from pilot test, will be generated from the decontamination
works of ash bunker and will be either directly sealed in drums or be
remediated followed by sealing in drums. These drums will be temporarily stored within the
enclosed material storage building, prior to landfill disposal. Location of the
temporary storage area is indicated in Figure 4-1.
Disposal Arrangement
4.5.22
All
contaminated residual ash removed from the ash bunker will be solidified with
cement and sent to designated landfill site for disposal after passing the TCLP
test.
4.5.23
This
waste stream will be disposed of at a designated landfill site under the
surveillance of trip ticket system. A permit will be obtained from EPD prior to
disposal.
4.5.24
All
DCM wastes for disposal will be transported by licensed chemical waste
collector approved by EPD and in a designated barge equipped as stated in the
Code of Practice and to be disposed of. Barge will berth at the barging facilities
of CEDD Mines Division at Tsuen Kwan O Area 137 and waste will be delivered to
designated landfill by trucks or other disposal outlets as directed by the EPD
/ Engineer’s Representative.
Transportation route for disposal of DCM waste is indication in Figure
4-2.
Source of Wastes
4.6.1
The
chemical wastes generated from the demolition works will primarily arise from
the maintenance of plant and equipment. These wastes include spent lubricant
oil, surplus paint and spent diesel.
4.6.2
For
chemical waste produced from a process, as defined by Schedule 1 of the Waste
Disposal (Chemical Waste) (General) Regulation, registration will be made with
EPD as a Waste Producer.
Estimated Quantity and Timing for generation
4.6.3
The
generation of chemical wastes from the maintenance of plant and equipment is
anticipated throughout the demolition project based on the utilisation of plant
and equipment. The maintenance of plants and equipments will be minimized
conducted on site except emergency maintenance. It is estimated that the
generation of chemical waste is 75L per month (approx. 64kg/month).
Control Measures
4.6.4
Preventive
measures will be implemented for leakage and spillage of fuel and lubricating
oil to avoid contamination of the construction site.
4.6.5
All
plant and equipment will require regular maintenance. Their maintenance records
will be kept in site office for future reference.
4.6.6
Good
housekeeping practices will be adopted to deal with chemical waste include:
(i) Generating less chemical waste through:
·
Delivering appropriate quantity of chemicals to the construction site.
·
Avoiding unnecessary wastage of chemicals by using the chemicals more
sensible and in accordance with the manufacturer’s instructions.
·
Finishing one bottle/container of chemicals before opening the next one
for use.
·
Collecting the remaining chemicals in suitable containers.
·
Removing the unused chemicals out of the construction site after
completion of the project.
(ii) Preventing illegal discharge of chemicals or chemical wastes through staff of the project.
(iii) Minimising the volume of unused chemicals to be disposed of through:
·
Using the chemicals before the expiry date.
·
Ordering appropriate quantity of chemicals and avoiding unnecessary
storage of excess chemicals.
On-site Handling and Storage
4.6.7
Chemical
waste will be handled in accordance with the Code of Practice on
the Packaging, Handling and Storage of Chemical Waste. The details are described as follows and the location of temporary
storage area of chemical waste is indicated in Figure 4-1.
(i) Containers used for the storage of chemical waste will:
·
be suitable for the substance they are holding, resistant to corrosion,
maintained in a good condition, and securely closed;
·
have a capacity of less than 450 litres unless the specification have
been approved by EPD; and
·
display a label in English and Chinese in accordance with instruction
prescribed in Schedule 2 of the Regulations.
(ii) The storage area for chemical waste will:
·
be clearly labelled and used solely for the storage of chemical waste;
·
be enclosed on at least three sides;
·
have an impermeable floor and bund, 110% capacity of the largest
container or 20% of the storage capacity, whichever is the greatest;
·
have adequate ventilation;
·
be covered to prevent rainfall entering (water collected within the bund
must be tested and disposed as chemical waste if necessary); and
·
be arranged so that incompatible materials are adequately separated.
Disposal Arrangement
4.6.8
Chemical
waste will be disposed of:
·
via a licensed waste collector;
·
to a facility licensed to receive chemical waste, e.g. Chemical Waste
Treatment Facility in Tsing Yi; or others
· to a re-user of the waste, under the approval from the EPD.
5.1.1
Waste
Flow Tables will be used to record all waste removed off site each month.
5.1.2
The
estimated and actual quantities of wastes that will be generated each year from
the project will be reported, using the table “Yearly Summary Waste Flow
Table”, which is attached in Appendix G of this WMP.
5.1.3
The
actual quantities of wastes generated in each month will be recorded in a
monthly basis, using the table “Monthly Summary Waste Flow Table”, which is
attached in Appendix G of this WMP.
5.1.4
Site
Agent will be responsible to update the Yearly and Monthly Summary Waste Flow
Tables.
5.2.1
As
outline in Sections 4, the Contractor will segregate, as far as practical, the
recyclable materials (mainly metals), from the C&D waste stream and general
waste, so that the recycling contractors can collect the materials on a regular
basis for recycling or export. Waste sorting and segregation will be carried
out in accordance with the following categories for recycling:
·
Plastic (i.e. plastic bag, plastic bottle, plastic
packaging, etc.);
·
Rubber;
·
Paper;
·
Wood/ timber;
·
Glass;
·
Textile; and
·
Metal (i.e. aluminium can, steel metal, ferrous
metal, and non-ferrous)
5.3.1
The
disposal of C&D Material will be carried out in accordance with the ETWB
TC(W) No. 31/2004. The Contractor will
produce a Construction and Demolition Material Disposal Delivery Form (the
Form) for each and every vehicular trip transporting C&D material off
site. The Contractor will complete all
relevant details on the Form in quadruplicate except for the Time of Departure.
A sample of the Form is attached in Appendix H. All inert C&D material will
be disposed of by marine transport to the public fill area or other areas as
designated by EPD. Vessel chits forms should be used for C&D material
disposal of at public fill area by barge.
5.3.2
Prior
to the vehicle leaving the site, the Contractor will present to the ER the
completed Form. The ER will insert the
Time of Departure and stamp the Form.
The ER will retain a copy of the Form and return the original to the
Contractor. The Form will be carried on
board the vehicle at all times throughout the vehicular trip.
5.3.3
In
case marine transportation is employed for disposal of inert C&D material,
the Contractor follow the vessel trip-ticket system arrangement for all barges
to deliver to designated public fill area. For disposal of ACM, the Contractor
still needs to follow the aforesaid trip ticket arrangement for all trucks when
materials are transferred from the barges to the trucks at existing barging
point nearby the disposal site before the trucks are allowed to dispose of the
collected materials at the designated sites.
5.3.4
The
copies of the Form and the receipt will be maintained on site for future
references.
5.3.5
For
each trip of off-site disposal of chemical waste, trip tickets issued for every
chemical waste collection made by the licensed waste collector will be copied
to the ER with the original maintained on site for future references.
5.3.6
The
Site Management Plan for Trip-Ticket System is attached for reference in
Appendix H.
5.4 Inspection Programme and Performance Monitoring
5.4.1
Auditing
of each waste stream will be carried out periodically by the EM&A Team to
determine if wastes are being managed in accordance with approved procedures.
The audits will look at all aspects of waste management including waste
generation, storage, recycling, treatment, transport, and disposal. An
appropriate audit programme would be to undertake a first audit at the
commencement of the demolition works, and then to audit quarterly thereafter.
5.4.2
The
Waste Manager and the ET will be responsible for the monitoring and auditing of
the waste management practice during his weekly site inspection in order to
ensure that appropriate control measures are properly implemented.
5.4.3
If
deficiency of the waste control measures were identified during the site
inspection and audit, the Waste Manager of the Contractor will discuss with the
Site Agent for formulation of remedial measures and the Site Agent will
implement the remedial measures promptly to rectify the situation. If deficiency persists, alternative and/or
additional control measures will be proposed to the satisfaction of the ER.
5.5 Record Keeping and Reporting
5.5.1
The
Contractor will keep adequate and proper records such as trip tickets,
photographs and measurement records relating to the implementation of the WMP,
and submit such records of each calendar month to the ER within the first week
of the following calendar month for their onward submission to the Public Fill
Committee for information. The record
will include the amount of wastes generated, recycled and disposed of
(including the disposal sites). A sample of the Construction and Demolition
Material Disposal Delivery Form is included in Appendix H for reference.
5.5.2
After
the completion of the Contract, the Contractor will submit a report on the
implementation of the WMP in the content to be agreed by the ER. The report will include the following
information and any other information as the ER may consider appropriate:
·
The quantities of different types of C&D material as estimated at the
commencement of the Contract;
·
A statistics on the monthly quantities of different types of C&D
material generated and their disposal method; and
·
Reasons for any significant differences between the estimated quantities
at (a) and the actual quantities at (b).
6.1 Objective of the Emergency Response Procedure
6.1.1
The
plan addresses emergencies related to the demolition, treatment, storage and
transportation of contaminated materials. Such emergencies may include:
·
Fire in full containment for ACM / DCM decontamination;
·
Chemicals & chemical wastes spillages on land and sea;
·
Typhoon attack on chimney decontamination containment;
·
Overflow of contaminated surface run-off due to heavy rain storm attack;
·
On-site traffic accident; and
·
Power failure during ACM / DCM decontamination
6.1.2
The
Project identifies three general groups of activities that have the potential
to affect the public or the environment in the event of an emergency:
·
Demolition and decontamination of ACM / DCM; and
·
Storage and transportation of ACM / DCM.
6.2.1
An
emergency is an existing or imminent event that presents a danger of major
proportions to human health or the environment. An emergency requires prompt
co-ordination of actions to protect the health, safety or welfare of people,
and/or to limit damage to the environment or property and equipment.
6.3.1
An
Emergency Response Team (ERT) has been formed and consists of the following
personnel:
·
Safety Officer;
·
Safety Supervisor;
·
Site Agent;
·
General Foreman;
·
Site Engineer;
·
First Aider;
·
Electrician; and
·
Public Relation Officer.
6.3.2
The
ERT members and the action of each stakeholder for tackling emergency
situations are included in Table 6-1.
Position |
Emergency Team |
Contact No. |
Action, Roles and Responsibilities in
Emergency Situations |
|
Mr.
Vincent LEUNG |
Safety
Officer |
ERT
Leader |
9475
3666 |
l Manage all resources on-site for the implementation of emergency. l Inform Project Manager / Site Agent l Responsible for all emergency arrangement on-site and develop appropriate handling procedures. l Advice on health and safety related issues. |
Mr.
Steven Ho |
Site
Agent |
Deputy
ERT Leader |
6281
8608 |
l Assist the ERT leader for carrying out his duties in case of emergency event. l Implement emergency procedures. l Oversee the emergency management and provide necessary support to ERT Leader. l Advise on clean-up procedure and co-ordination of resources. |
Mr.
Sai Ho CHAN |
Safety
Supervisor |
ERT
member |
6909
6344 |
l Assist the Safety Officer for carrying out his duties in case of emergency event. |
Mr.
Hon Wing WONG |
General
Foreman |
ERT
member |
9076
1422 |
l Assist in implementing emergency procedures. |
Mr.
Shao Chen NING |
Site
Engineer |
ERT
member |
6692
2413 |
l Notify relevant Government Department and Parties, where necessary. |
Mr.
Sai Ho CHAN |
First
Aider |
ERT
member |
6909
6344 |
l Provide necessary on-site first aid recovery as instructed by ERT Leader under safe environmental condition. |
Mr.
Kwan Yuen WU |
Electrician |
ERT
member |
9109
6231 |
l Ensure electrical safety as instructed by ERT Leader under safe environmental condition. |
Mr.
Ivan KONG |
Public
Relation Officer |
ERT
member |
8102
2699 |
l Answer 24-hr Hotline. l Provide communication support and service. l Manage public communications in the event of issues, crisis and complaints. |
24-hr Hotline |
8102
2699 |
6.4.1
A
person within the ERT will be appointed to be the ERT leader - a primary
decision-maker in the event of an emergency. In the case that the ERT leader
cannot be contacted, an alternative person will be available to conduct the
duties of the ERT leader. The responsibilities of the ERT leader are as
follows:
·
To understand the project emergency plan and rescue procedures.
·
To immediately notify the ERT members in the event of an emergency.
·
To arrange the whole operation of the emergency rescue and fire
fighting.
·
To determine the seriousness of the cases and take appropriate actions
to handle the emergency / fire;
·
To assign personnel in the ERT to assist the ERT leader to carry out the
rescue procedures in case of fire / emergency.
·
Immediately notify the Site Engineer and Project Manager of the detail
of any accident and rescue procedures in case of a serious accident.
·
Review and recommend changes if necessary, the emergency procedures
periodically with other safety personnel and monitor the system and its
implementation.
·
To arrange necessary fire fighting / rescue equipment in accordance with
legislation requirements.
·
To re-organise the ERT members from time to time to ensure the effectiveness
of the system and competency of the members.
·
To arrange practice drills for assessing the efficiency and
effectiveness of the rescue team regularly.
6.4.2
In
general, anyone that has discovered chemical leakage and spillage shall
immediately report to the ERT leader, ET/ ET Leader, and the Waste Manager. ERT
leader shall take into account the safety and environmental advises from
Environmental Officer and Safety Officer once the chemical leakage and spillage
incident is observed/ reported.
6.5.1
Telephones
and direct face-to-face communication will form the basis of communications
within the site. The site office will be equipped with telephones. Cellular
phones will allow for communication among field personnel, truck drivers and
the site office.
6.6
Communications with the Public
6.6.1
All
community enquiries or complaints in relation to activities described in this
emergency section should be directed to the project 24-hr Hotline and the
project representatives identified in the ERT member list. A separate Public
Relation (PR) Plan has been prepared by the Public Relation Officer detailing
the communication channel with the public. (Contract Clause PSA 2.4)
6.6.2
Communication
between the public and project personnel will only be required in the event of
issues, crisis and complaints where the situation is to be handled within the
project site. However, depending on the nature of an emergency, in the event
where the situation has been handed to the Police or FSD, Police or FSD will be
the overall commander and communication with government agencies, medical
service providers, external experts and the public. The ERT leader will
maintain close liaison with the Police or FSD representative on site.
6.7.1
An
up-to-date emergency call-out list including major ERT members will be
displayed on a prominent position in the site office. This list shall be a
dynamic document and be continuously updated as necessary. This list is
currently based on normal working hours but will be updated if required by an
increase in operational hours.
6.7.2
In
addition to the above contacts, other organisations that may need to be
contacted in the event of an emergency include:
Kwai Chung Fire Station 2426-5694
Tsuen Wan Fire Station 2499-5044
Water Supplies Department 2824-5000
Police Emergency Call 999
HKPF – Duty Officer, Kwai
Tsing District 2410 2205
Drainage Services
Department 2300-1110
The
CLP Power Hong Kong Limited
2678 2678 Customer Service
(24-hour)
(Emergency Reporting) 2728 8333
(24-hour)
(Engineering) 2678 7900
6.8.1
An
emergency often creates unfamiliar circumstances and a hostile working
environment for people required to respond to the emergency. In addition, time
is usually a very important factor in determining the most appropriate response
to an emergency. Training and experience can significantly improve the
effectiveness of the responders and decision-makers. Training is therefore a
vital part of the implementation of an Emergency Response Procedure (ERP).
6.8.2
The
specialist personnel identified in this procedure will be trained and qualified
in their respective roles as identified in this procedure. For example, it will
be ensured that all First Aiders hold valid First Aid Certificates.
6.8.3
All
workers will be briefed of the emergency response process in the site
induction, and all workers identified in this section will be trained in its
content in the language that the worker understands.
6.9 The Contractor and Employees
6.9.1
All
employees of the Contractor shall be thoroughly familiar with company policies
and procedures for responding to emergencies. He/she will be knowledgeable in
the contents under this section of the plan, and be actively involved in the
training of other personnel identified under this section.
6.9.2
All
personnel at the site will be made familiar with the Chain of Command with
respect to reporting emergencies and subsequently taking directions from
identified personnel. Every person is a potential resource in the early
detection of problems, which if not reported and not addressed could lead to
emergency situations.
6.9.3
The
frequency of the training necessarily depends on the personnel and the
circumstances at the site. New personnel should be trained systematically.
Changes in the roles of individual personnel would warrant new training.
6.10 Sub-Contractors and Others
6.10.1
Sub-contractors
and all other personnel working at the site shall be made familiar with the
chain of command with respect to reporting emergencies and subsequently taking
directions from site personnel.
6.11 Emergency Response Procedures
Response to General Emergency
6.11.1
Where
the ERT leader deems an emergency situation, he will contact the necessary
personnel identified in the ERT. The Safety Officer will go to the site of the
incident and relay all details to the other ERT members who will gather at the
contractor site office. The Safety Office will advise the ERT of all necessary
equipment/PPE requirements/first aid treatment needed at the accident site. The
ERT and associated team members will then co-ordinate all items require by the
Safety Officer.
6.11.2
Upon
clearing the accident site, a post-mortem report will be completed which
details all occurrences prior to, during and following the incident. Applicable
workers will be briefed on the contents of the incident report following its
completion.
Fire in Full Containment for ACM / DCM Decontamination
6.11.3
In
the event of fire in full containment for ACM / DCM decontamination, the Fire
Services Department will be immediately notified and all personnel working
within the containment or in the vicinity of the work site area evacuated. All
personnel working within the containment shall:
·
Stop all work and if necessary remove worker(s) to a safe area;
·
If a worker has collapsed remove face mask (in all other cases the face
mask should be left in place), carry out normal emergency first aid procedures
and arrange to transfer the worker to hospital.
Personal decontamination should be carried out if possible;
·
Where it is impossible to carry out decontamination procedures on the
worker, inform the medical team to enable them to take the appropriate safety
measures;
·
Bag all loose ACM / DCM debris present in the ACM / DCM removal work
area and remove to a secure store. Wipe
clean and vacuum all surfaces and any adjoining area contaminated during the
emergency;
·
Spray all surfaces and debris within the ACM / DCM removal work area
with amended water in a fine mist spray, using airless spray equipment once the
fire has been extinguished and the Site is safe for re-entry;
·
Prepare the Site for inspection by the Registered Asbestos Consultant;
and
·
Carry out air testing prior to recommencing removal work.
Chemicals & Chemical Wastes Spillages on Land and Sea
6.11.4
Transportation
of chemical waste including ACM / DCM and other chemicals shall be carried out
by barge, loss of ACM / DCM and other chemical waste on roads are not
anticipated.
6.11.5
Transportation
of chemical waste including ACM / DCM and other chemicals shall be carried out
by licensed waste collector, and be contained either in steel drums lined with
plastic sheeting or by use of safety and suitable labelled containers.
6.11.6
Spillages
or dropping into the sea while marine transportation shall be recoverable.
Detail of the Works Execution Plan for transportation by vessels is included in
Appendix H for reference.
6.11.7
While
ACM / DCM are being loaded onto and off between barging point and the barge for
marine transport, net carrier shall be used to prevent damages and dropping on
land and sea.
Typhoon Attack on Decontamination Containment
6.11.8
In
order to prevent water retention on the site (in particular, during
decontamination of ACM), all storm and surface water drains, ditches and
out-falls will be regularly checked and if necessary cleared of debris, soil
and litter. Frequency of checking and clearing will increase during the
typically wet months (June to August). Additionally, the drains, ditches and
out-falls will be checked when heavy rainfall events are forecasted (including
when an Amber Rainstorm Warning is hoisted) to confirm that these surface water
management features are not obstructed.
6.11.9
After
intense rainfall events such as Red or Black Rainstorm Warning or Typhoons,
inspections and necessary actions (such as maintenance or repair of damaged
drainage items) will be carried out.
6.11.10
The
transportation of ACM / DCM will cease when warnings for a Black rainstorm
and/or Typhoon signal No. 8 are given.
6.11.11
When
warnings for a Black rainstorm and/or Typhoon signal No. 8 are given, the
Contractor shall:
·
Stop all processes which may result in the production of ACM / DCM dust;
·
Spray all surfaces and debris within the ACM / DCM removal work area
with amended water in a fine mist spray, using airless spray equipment;
·
Bag all loose ACM / DCM debris present in the ACM / DCM removal work
area and remove to a secure store. Wipe
clean and vacuum all surfaces;
·
Cut off all power and water supplies and secure all loose equipment
against typhoon damage;
·
Arrange a revised inspection by the Site Agent and Site Engineer before
the workers leave Site;
·
Recommence the ACM / DCM removal works once the No. 8 typhoon signal has
been lowered, the necessary cleaning up work and repairs to containment have
been completed and permission has been given by the Site Engineer.
6.11.12
If
during the course of abatement work, a worker collapses or some other accidents
occur, the victim should follow normal decontamination procedures with
assistance from fellow workers before exiting the work area. For
life-threatening situation, however, decontamination should take a lower
priority and every effort should be made to ensure the victim receives
immediate medical treatment. Any area contaminated during the emergency should
be thoroughly cleaned by wet wiping and HEPA vacuuming at the earliest
opportunity, and verified by the registered asbestos supervisor and approved by
the registered asbestos consultant before work is allowed to continue.
6.11.13
In
addition, the construction of containment is governed by the “Code of
Practice on Asbestos Control, Asbestos Work Using Full Containment or Mini
Containment Method”, Section 6 – Construction of Containment. Under which,
the registered asbestos consultant is also responsible for the structural
safety of the containment, and for the provision of safe means of access as
well as alternative escape route for emergency situations. Sections extracted
from the “Code of Practice on Asbestos Control, Asbestos Work Using Full
Containment or Mini Containment Method” with regard to the construction,
maintenance and emergency procedures for use of the containment approach are
included in Annex V of Appendix D for reference.
Overflow of Contaminated Surface Run-off Due to Heavy Rain Storm
Attack
6.11.14
As
mention in Section 6.9.5, in order to prevent water retention on the site, all
storm and surface water drains, ditches and out-falls will be regularly checked
and if necessary cleared of debris, soil and litter. Owing to the nature of the
Project, removal of ACM / DCM, solidification pilot test, and the actual cement
solidification process shall be carried out under “full containment” approach.
6.11.15
Treatment
and storage for the ACM / DCM removed shall strictly follow the Asbestos
Abatement Report (Appendix 25 to the PS). As such, none of the removed ACM /
DCM will be exposed to the surface run-off due to heavy rain storm in its
untreated stated, overflow of contaminated surfaces of the ACM / DCM is not
anticipated.
On-site Traffic Accident
6.11.16
On-site
traffic accident will be minimised by speed control limit for all vehicle to 5
km/hr. In additional, all storage area of ACM / DCM shall form within a fenced
/ protected area and/or are inside existing buildings of the project site.
6.11.17
All
vehicles shall only be driven by personnel who have been trained in the
Emergency Response Procedure and hold a valid
Power Failure during ACM / DCM Decontamination
6.11.18
In
the event of loss of power, back-up power will be available from portable
generators. These units are readily available in the event of a disruption to the
power supply.
6.11.19
Appropriate
back-up facilities will be supplied in order to ensure the effective operation
of the site and associated ACM / DCM decontamination containment when the
standard facilities are out of action due to power failure.
6.12 Post-Emergency Procedures
6.12.1
An
investigation will be carried out immediately after incident occurred. It aims
to find out the causes of such incident. Base on this information, adequate
preventive measures as well as toolbox training to relevant staffs will be
provided in order to minimize the probability of recurrence. A post-mortem
report of emergency incident including mitigation and preventive measures shall
be submitted to the authorities.
7.1.1
The
Contractor shall arrange and provide training on waste management in the
site-specific induction and its refresher training for all employee and
subcontractors involved in the works.
The content of the training will include the following:
·
Concepts of Site cleanliness.
·
The steps/requirements of the WMP stipulated in the Contract.
·
Classification of different waste types in accordance with the WMP.
·
Proper segregation, handling and storage of different types of waste in
accordance with the WMP.
·
Procedures and measures for waste minimisation, reuse and recycling.
·
Locations of designated storage areas for different waste types in
accordance with the WMP.
·
Handling of the ACM / DCM, including the appropriate PPE requirements.
·
Procedures for handling ACM / DCM; and
·
Emergency Response Procedure and mitigation measures.
7.1.2
An
auditable record will be maintained for all environmental training undertaken.
APPENDICES
List
of Appendices
Appendix A1 Figure 1-1 Location Plan of the Project Site
Appendix A2 Figure 4-1 Location of Temporary Storage Area
Appendix A3 Figure
Appendix A4 Figure 4-3 Dioxin Sampling Locations at Ash Bunker
Appendix B1 Master Works Programme
Appendix B2 General Demolition Procedure
Appendix C Project Organization Chart
Appendix D Generic Method Statement and Work Sequence of ACM Removal
Appendix E Memo from Mines Division of CEDD for the use of TKO Area 137 Pier
Appendix F Methodology of TCLP Test
Appendix G1 Waste Disposal Delivery Schedule to Landfill Site
Appendix G2 Yearly Summary Waste Flow Table
Appendix G3 Monthly Summary Waste Flow Table
Appendix H Site Management Plan for Trip-ticket System
Appendix A
Figure 1-1
Location Plan of the Project Site
Figure 4-1 Location of
Temporary Storage Area
Figure
Figure 4-3 Dioxin Sampling Locations at Ash Bunker
Appendix B
B1 – Master Construction Programme
B2 –
General Demolition Procedure
Appendix C
Project
Organization Chart
Appendix D
Generic Method Statement and
Work
Sequence of ACM Removal
Appendix E
Memo from Mines Division of CEDD for
the Use of
TKO Area 137 Pier
Appendix F
F1 – Flow Diagram of Cement Solidification
F2 – Methodology
of TCLP Test
Appendix G
G1 – Waste Disposal Delivery Scheulde to Landfill Site
G2 – Yearly Summary Waste Flow Table
G3 – Monthly Summary Waste Flow Table
Appendix H
Site Management Plan for Trip-ticket System
List of Appendices of Appendix H
Appendix 1 Management Structure for TTS
Appendix 2 Yearly Summary Waste Flow Table
Appendix 3 Monthly Summary Waste Flow Table
Appendix 4 Site procedure s to ensure each truckload of C&D material leaving the Site will bear a duly completed DDF
Appendix 5 Proposed Mechanism to ensure timely retrieval of DDF
Appendix 6 Register of the DDF issued
Appendix 7 Control Measures to track internal movement of materials
Appendix 8 Sample Format of the Construction and Demolition Material Disposal Delivery Form
Appendix 9 Works Execution Plan by Chun Ming Machinery Engineering Ltd. for Chun Ming Vessel No. 23, 33, 68, 78
Appendix 10 Written Instruction to Barge Operator & Truck Drivers
Appendix 11 Site Layout Plan Showing Outlets