Civil Engineering and Development Department

Fill Management Division

5/F, Civil Engineering and Development Building

101 Princess Margaret Road

Homantin, Kowloon

 

 

 

 

Demolition of Kwai Chung Incineration Plant

Environmental Permit No.

EP-121/2002

 

Waste Management Plan (WMP) for Demolition Works (C&D Materials, Asbestos, & Dioxin/ Furan containing materials in Ash Bunker)

June 2008

(Version 2.3)

 

 

 

 

 


Waste Management Policy

 

 

We are committed to reduce/minimise the generation of construction and demolition (C&D) material and to undertake construction activities in an environmental friendly manner.

 

We are committed to:

 

·         Ensure construction works complied with specified standards and statutory requirements.

·         Achieve the objectives we have established in this Waste Management Plan (WMP).

·         Provide adequate resources and facilities to facilitate the implementation of this WMP.

·         Ensure that all staff members in relevant departments perform their duties according to this WMP.

·         Conduct regular review and audit to monitor the implementation of this WMP.

 

 

 

 

 


YAO Fei Xiong

Project Director

China International Water & Electric Corporation

March 2008

 

 

 


List of Contents                                                                                           

Chapters                                                                                                                              Page

1        INTRODUCTION   1

1.1     Background  1

1.2     Scope of Demolition Works of the Project 1

1.3     Construction Programme  2

1.4     Obligations under the EP  2

1.5     Environmental Legislation and Guidelines  3

1.6     Application for Licenses, Permit and Approvals  6

2        WASTE MANAGEMENT POLICY   7

2.1     General Principles  7

2.2     Hierarchy of Waste Management 7

3        ORGANIZATIONAL STRUCTURE FOR WASTE MANAGEMENT   8

3.1     General 8

3.2     Roles and Responsibilities of Key Waste Management Personnel for KCIP  8

4        WASTE GENERATION AND DISPOSAL   13

4.1     Waste Overview   13

4.2     General Refuse & Non-Inert C&D Material 14

4.3     Inert C&D Materials & Recyclables  15

4.4     Asbestos Containing Materials (ACM) 17

4.5     Dioxin / Furan Contaminated Wastes  20

4.6     Chemical Wastes  24

5        IMPLEMENTATION OF WASTE MANAGEMENT   26

5.1     Waste Flow Table (WFT) 26

5.2     Recycling Proposal 26

5.3     Trip-ticket System   26

5.4     Inspection Programme and Performance Monitoring  27

5.5     Record Keeping and Reporting  27

6        EMERGENCY RESPONSE   29

6.1     Objective of the Emergency Response Procedure  29

6.2     Definition of Emergency  29

6.3     Emergency Response Team   29

6.4     Chain of Command  31

6.5     Internal Communications  31

6.6     Communications with the Public  31

6.7     Emergency Call List 32

6.8     Training  32

6.9     The Contractor and Employees  33

6.10   Sub-Contractors and Others  33

6.11   Emergency Response Procedures  33

6.12   Post-Emergency Procedures  36

7        Training  37

 

List of Tables

Table 1‑1.... Structures to be Demolished at KCIP. 1

Table 2‑1.... Hierarchy of Waste Management 7

Table 4‑1.... Summary of Waste Disposal 13

Table 4‑2.... Estimated Quantity of ACM.. 18

Table 4‑3.... PCDDs/ PCDFs Analysis Results for Samples Collected at the Ash Bunker 21

Table 6‑1.... ERT Member List 30

 

List of Appendices

Appendix A1     Figure 1-1         Location Plan of the Project Site

Appendix A2     Figure 4-1         Location of Temporary Storage Area

Appendix A3     Figure 4-2         Transportation Route for Different Type of Waste

Appendix A4     Figure 4-3         Dioxin Sampling Locations at Ash Bunker

Appendix B1     Master Works Programme

Appendix B2     General Demolition Procedure

Appendix C       Project Organization Chart

Appendix D      Generic Method Statement and Work Sequence of ACM Removal

Appendix E       Memo from Mines Division of CEDD for the use of TKO Area 137 Pier

Appendix F1     Flow Diagram of Cement Solidification

Appendix F2     Methodology of TCLP Test

Appendix G1     Waste Disposal Delivery Schedule to Landfill Site

Appendix G2     Yearly Summary Waste Flow Table

Appendix G3     Monthly Summary Waste Flow Table

Appendix H      Site Management Plan for Trip-ticket System

 

 

 


1                        INTRODUCTION

1.1                   Background

1.1.1              This Waste Management Plan (WMP) has been prepared to fulfil Condition 2.8 of the Environmental Permit (EP No. EP-121/2002) with respect to the demolition works of the Project – “Demolition of Kwai Chung Incineration Plant”. The major scope of the demolition works of the Project is to remove all ACM/DCM in chimney and superstructures before commencement of the demolition works.  The decontamination works of the Project will be carried out after completion of the demolition works of the Project.

1.1.2              This WMP does not cover the decontamination works to be carried out for the Kwai Chung Incineration Plant (KCIP). The corresponding WMP for the decontamination works will be submitted under a separate cover for ground decontamination works.

1.1.3              As there have been ongoing discussions between EPD and CEDD on proposals for treatment and disposal of dioxin containing materials (“DCM”) within the KCIP Chimney, these parts of the WMP have been put on hold until an agreement is reached between the two departments.  Subject to agreement with EPD, the treatment method and disposal of DCM for the KCIP Chimney will be finalized.

1.1.4              This WMP has therefore focused on and finalized the rest of waste management aspects with respect to waste generation, treatment and disposal for this Project other than DCM  (and ACM to avoid cross-contamination) within the KCIP Chimney in order to facilitate early approval by part so that other parts of the Project can proceed independently.

1.1.5              WMP versions 1.1 and 2.2 were certified by ET and verified by IEC and submitted to EPD on 29 November 2007 and 9 April 2008 respectively for approval.

1.2                   Scope of Demolition Works of the Project

1.2.1              The demolition works of the Project with boundary as shown in Figure 1-1 is summarised in Table 1.1.

Table 11     Structures to be Demolished at KCIP

Building

Brief Description

KCIP Chimney

Reinforced concrete construction of diameter 6m – 12m and 150m high. Internal metal flues and platforms

KCIP Buildings

High, single storey steel frame, with weather cladding, pre-cast concrete slab, reinforced concrete partitions, corrugated metal sheet external wall and roof.  The overall size is approximately 83m x 92m on plan.

Weigh Bridge Office No. 2

Single Storey. Approximately 4m x 13m on plan.

Site Office/ Storage Buildings

Two storey high prefabricated building. Approximately 40m x 7.5m on plan.

1.2.2              The demolition works of the Project also includes the removal of asbestos containing materials (“ACM”) and dioxin/ furan contaminated materials (“DCM”) prior to demolition of the relevant structures.

1.3                   Construction Programme

1.3.1              The Contract for the Project was awarded on 26 October 2007 and contractually commenced on 31 Oct 2007. The main contract will last for 45 months excluding 12 months for landscape establishment works. In accordance with Condition 1.11 of the Environmental Permit EP-121/2002, the Director of Environmental Protection (DEP) was notified that the commencement date for the decommissioning of the Project was 24 Jan 2008 within the context of the Environmental Permit. The master construction programme and demolition method is included in Appendix B.

1.3.2              The removal of ACM can be independent from DCM because ACM were found at locations different from those of DCM. Therefore, removal of ACM can commence prior to DCM removal works.

1.4                   Obligations under the EP

1.4.1              Condition 2.8 of the Environmental Permit EP-121/2002 requires that a WMP shall be submitted to the DEP 8 weeks before the commencement of the decommissioning of the Project. WMP versions 1.1 and 2.2 were certified by ET and verified by IEC and submitted to EPD on 29 November 2007 and 9 April 2008 respectively for approval.

1.4.2              This WMP includes details on the types, quantities, disposal methods, timings and locations for treatment and disposal of wastes, responsibilities for implementation and possible recycling and reuse of materials and is written with reference to the requirements set out in the ETWB TCW No. 19/2005.

1.4.3              This WMP has taken into account in devising any findings and recommendations in the waste management section of the EIA Report (Register No. AEIAR-049/2002), and relevant findings of the Reassurance and Confirmatory Testing Report (“RCT”).  Before submission to the Director, the WMP will have to be certified by the ET Leader and verified by the IEC as conforming to the information and recommendations contained in the EIA Report, and any relevant findings of the RCT.

1.4.4              This WMP has included, but not limited to, the following information for each type of the wastes relevant to the specific Project part that it is intended to cover.  The types of wastes covered include general refuse, asbestos containing materials (“ACM”) (other than those within Chimney), DCM in Ash Bunker and construction and demolition (“C&D”) materials.

·         summary of the locational sources, quantity, level of contamination (if applicable), remediation required prior to disposal (if applicable), and on-site and off-site disposal methods for different type of wastes;

·         timings for generation, remediation (if applicable), temporary on-site stockpiling or storage, and final on-site or off-site disposal of different type of wastes;

·         method statements on the remediation works to be carried out on ACM and DCM (ash bunker only), and the confirmatory and parallel independent testing to be conducted;

·         on-site waste management measures to control nuisances during the generation, handling, remediation (if applicable), and temporary stockpiling of the different types of wastes, in particular for ACM/ DCM,;

·         possible recycling and reuse of materials;

·         location of the disposal site(s) for various types of wastes;

·         confirmation on whether or not barges would be used for removal of wastes;

·         transportation routing(s) of the removal of various types of wastes from the project site to the disposal site(s);

·         measures to control nuisances due to transportation of different type of wastes, in particular to avoid loss of asbestos containing materials; to remove possible soil left on the first several hundred meters of roads by vehicles leaving the site, such as the option of using specially design road cleansing vehicle; and to reduce dust nuisance from trucks carrying wastes, such as the option of installing mechanical covers to trucks;

·         trip-ticket system for waste transfer/disposal operations, including a certification system to confirm to the disposal site’s operator that the contaminated wastes have been remediated to meet the specific disposal criteria; and

·         responsibilities for implementation.

1.5                   Environmental Legislation and Guidelines

Regulatory Requirements

1.5.1              During the Contract, the Contractor will comply with the following Ordinances and Regulations, which cover, or have some bearing upon, the handling, treatment and disposal of wastes in the Hong Kong SAR.

Waste Disposal Ordinance (Cap 354)

1.5.2              The Waste Disposal Ordinance (WDO) prohibits any person from using any land or premises for the disposal of wastes unless one has been authorised by or has obtained a license from the Waste Disposal Authority, the Environmental Protection Department (EPD).

Waste Disposal (Chemical Waste) (General) Regulation (CWR), Enacted under the WDO

1.5.3              The Regulation has provisions to require any person who produces chemical waste to register with the EPD as well as to control the processing, storage, collection, transport and disposal of chemical waste. In additional, the CWR also provides for the licensing of waste collection, transport and disposal activities.

1.5.4              For chemical waste registration, Contractor is required to provide particulars on the location of waste generating activities, the nature of operation and waste types to be generated. A registration form shall be prepared and submitted to the EPD for approval prior to the waste generating activities. Upon successful completion of the registration procedure, the EPD will then issue a confirmation note and assign a waste producer number. Any disposal of chemical waste registered shall give prior notification to EPD and the disposal has to follow directions of the EPD. If certain types of chemical wastes are classifiable as Dangerous Goods under the Dangerous Goods Ordinance (Cap. 295) (DGO), handling of these wastes shall also comply with the requirements of the DGO and its regulations.

Waste Disposal (Charges for Disposal of Construction Waste) Regulation

1.5.5              The Charging Scheme has come into operation on 1 December 2005. Processing of account applications by the Environmental Protection Department has started on the same day.

1.5.6              Starting from 1 December 2005, main contractor who undertakes construction work under a contract with value of $1 million or above is required to open a billing account solely for the contract. Application shall be made within 21 days after the contract is awarded. Failing this will be an offence under the law.

1.5.7              For construction work under a contract with value less than $1 million, such as minor construction or renovation work, any person such as the owner of the premises where the construction work takes place or his/her contractor can open a billing account; the account can also be used for contracts each with value less than $1 million. The premises owner concerned may also engage a contractor with a valid billing account to make arrangement for disposal of construction waste.

1.5.8              Charging for disposal of construction waste has started on 20 January 2006 and from this day, any person before using waste disposal facilities for disposal of construction waste needs to open an account.

Land (Miscellaneous Provisions) Ordinance (Cap 28)

1.5.9              Public fill construction wastes may be taken to public dumps. The Land (Miscellaneous Provisions) Ordinance (LO) requires that dumping licences be obtained by individuals or companies who deliver suitable construction wastes to public dumps. The licences are issued by the CEDD. In the case that public dumping of public fill construction waste is desired, the contractor shall apply for the licence prior to disposal of the construction wastes.

Public Health and Municipal Services Ordinance (Cap 132) - Public Cleansing and Prevention of Nuisances Regulation

1.5.10           The Public Health and Municipal Services Ordinance (PHMSO), Water Pollution Control Ordinance Cap. 358, and Waste Disposal Ordinance Cap. 354 have provisions on the control of the discharge of hazardous materials to sewers and for the control of littering. The ordinances prohibit placing or throwing any solid matter, mud or waste into public sewers or drains and also placing these substances in a location where they may fall into these public sewers/drains.

1.5.11           It also has provisions to require the owner or occupier of the land adjoining any street or place in which is situated near a public sewer to exercise measures to prevent obstruction of sewers and drains caused by soil and waste.

Additional Guidelines

1.5.12           This WMP has been prepared with reference to the following 'guideline' documents:

·         Waste Disposal Plan for Hong Kong (December 1989), Planning, Environment and Lands Branch Government Secretariat;

·         Chapter 9 Environment of Hong Kong Planning Standards and Guidelines, Hong Kong Government;

·         Works Branch Technical Circular No. 2/93, Public Dumps, Works Branch, Hong Kong Government;

·         Works Branch Technical Circular No. 2/93B, Public Filling Facilities; Works Branch, Hong Kong Government;

·         Works Branch Technical Circular No. 16/96, Wet Soil in Public Dumps; Works Branch, Hong Kong Government;

·         Works Bureau Technical Circular No. 4/98 & 4/98A, Use of Public Fill in Reclamation and Earth Filling Projects; Works Bureau, Hong Kong SAR Government;

·         Waste Reduction Framework Plan, 1998 to 2007, Planning, Environment and Lands Bureau, Government Secretariat, 5 November 1998;

·         Works Bureau Technical Circular No 19/2001, Metallic Site Hoardings and Signboards; Works Bureau, Hong Kong SAR Government;

·         Works Bureau Technical Circular No. 12/2000, Fill Management; Works Bureau, Hong Kong SAR Government;

·         Works Bureau Technical Circular No 12/2002, Specifications Facilitating the Use of Recycled Aggregates. Works Bureau, Hong Kong SAR Government;

·         Environment, Transport and Works Bureau Technical Circular (Works) No 33/2002, Management of Construction and Demolition Material Including Rock, Environment, Transport and Works Bureau, Hong Kong SAR;

·         Works Bureau Technical Circular No 31/2004, Trip-ticket System for Disposal of Construction and Demolition Material; Works Bureau, Hong Kong SAR Government;

·         A Guide to Chemical Waste Control Scheme and A Guide to the Registration of Chemical Waste Producer, Environmental Protection Department, Hong Kong SAR; and

·         Code of Practice on the Packaging, Labelling and Storage of Chemical

1.5.13           Practices for asbestos handling and disposal are in accordance with the followings:

·         Air Pollution Control (asbestos) Administration Regulation

·         ProPECC PN2/97 Handling of Asbestos Containing Materials in Buildings.

·         Code of Practice on the Handling , Transportation and Disposal of Asbestos Waste,

·         Code of Practice on Asbestos Control, Preparation Work Using Full Containment or Mini Containment Method,

·         Code of Practices on Asbestos Control; Asbestos Work Using Glove Bag Method,

·         Code of Practice on Asbestos Control; Safe Handling of Low Risk Asbestos Containing Material, and

·         Code of Practice on Asbestos Control; Preparation management Plan and Asbestos Abatement Plan.

1.6                   Application for Licenses, Permit and Approvals

1.6.1              The Contractor will apply for, where appropriate, and maintain all the following permits and licenses required under the legislation for the handling and disposal of waste arising from the Contract.

·         Public Dumping Licence under the Land (Miscellaneous Provisions) Ordinance (Cap 28);

·         Chemical Waste Producer Licence under the Waste Disposal (Chemical Waste) (General) Regulation (Cap 354);

·         Chemical Waste Collection Licence under the Waste Disposal (Chemical Waste) (General) Regulation (Cap 354);

·         Land (Miscellaneous Provisions) Ordinance

Ø          Dumping licences are issued free of charge by the Port Works Division, Civil Engineering Department to lorry owners for delivering public fill to public filling facilities. The licences are valid to the end of each calendar year and the licensee need to apply for a new licence for the new calendar year. Dumping labels are also issued together with the licences for display on the wind-screen of the lorry.

·         Waste Disposal (Chemical Waste) (General) Regulation

Ø          Chemical waste, as defined under the Waste Disposal (Chemical Waste) (General) Regulation, includes any substance or thing being scrap material, effluent, or an unwanted substances or by-product arising from the application of or in the course of any process or trade activity, and which is or contains any substance or chemical specified in the prescribed schedule (i.e. Schedule 1 of the Waste Disposal Regulations) if such substance or chemical occurs in such form, quantity or concentration so as to cause pollution, constitute a danger to health or risk of pollution to the environment.

 


2                        WASTE MANAGEMENT POLICY

2.1                   General Principles

2.1.1              The principles of waste management to be adopted in this Project will be in line with the latest Government policy on environmental management.

2.2                   Hierarchy of Waste Management

2.2.1              The various waste management options will be categorised in terms of preference from an environmental viewpoint.  The options considered to be more preferable have the least impacts and are more sustainable in the longer term.  Hence, the hierarchy of waste management is as follows in descending order:

Table 21     Hierarchy of Waste Management

Avoidance and Minimization

Avoid and minimize generation of C&D materials through careful planning and design of works

Reuse

Reuse inert portion of the C&D materials generated.

Recovery and Recycle

Undertake on-site and off-site waste recycling

Treatment and Disposal

Properly treat and dispose of waste in accordance with legislative requirements, guidelines and good practices.

 

2.2.2              This hierarchy will be used to evaluate waste management options, thus allowing maximum waste reduction.  Waste reduction measures will be introduced at the planning and detailed design stage and carried through the construction activities, whenever possible, by careful purchasing control, reuse of formworks and good site management. 

 

 


3                        ORGANIZATIONAL STRUCTURE FOR WASTE MANAGEMENT

3.1                   General

3.1.1              The organisation of the waste management team is described under this section, the personnel responsible for waste management shall:

·         Work within the scope of the demolition contract;

·         Participate in the waste management site inspections undertaken by the Environmental Team (ET) and the Independent Environmental Checker (IEC) as required and undertake any corrective actions instructed by the ER; and

·         Take responsibility and strictly adhere to the provisions of the WMP and the contract specifications.

3.2                   Roles and Responsibilities of Key Waste Management Personnel for KCIP

3.2.1              The major scope of the demolition works is to remove all ACM/DCM in structures and demolish all structures above ground level within the KCIP site.  All underground structural components shall remain undisturbed before the land decontamination works.

3.2.2              A Project Organization Chart is shown in Appendix C. The roles and responsibilities of the key waste management personnel shall include, but not be limited to the following:-

The Employer and EP Holder

3.2.3              The Project Proponent shall be responsible for providing full support on the implementation of the approved WMP.

The Engineer’s Representative (ER)

3.2.4              The ER shall:

·         Ensuring that the WMP is fully implemented throughout the Project;

·         Review the waste monitoring and audit report submitted by the ET;

·         Follow up and ensure the proposed corrective actions to be in accordance with the WMP;

·         Investigate and audit the equipment and work methodologies with respect to waste management; and

·         Monitor and report any exceedance or non-compliance under the environmental permit and pollution control ordinances.

The Contractor’s Representative

3.2.5              The CR is responsible for overall planning, site operations, appointment of committee members for waste management, staff supervision control, co-ordination and external liaison. The CR shall:

·         Oversee the waste management within the Project, which they achieve by implementation of the WMP;

·         Participate and provide necessary support to the ET for the preparation and review of WMP;

·         Ensure that staff attends environmental training with regard to waste management organized by the Waste Manager;

·         Implement environmental controls and mitigation as set out in this WMP as well as any additional measures necessary for compliance with environmental control measures;

·         Ensure the recommendations and instructions of the ER or ET are implemented to improve the waste management practice and carry out immediate action to rectify the non-compliance of waste management and environmental protection requirements;

·         Providing leadership in the efficient management of the Project and in meeting the Work’s waste management objectives; and

·         Anticipate waste generation impacts that may require mitigation before the problem arises.

Site Agent

3.2.6              The Site Agent shall:

·         Arrange routine joint site inspection with ET and review environmental inspection report submitted by the ET;

·         Ensure works are undertaken in accordance with the recommendations made and instructions given by the ER and ET;

·         Monitor and control the works including those of subcontractors to ensure compliance with specified requirements;

·         Ensure appropriate waste management mitigation measures are properly implemented;

·         Ensure follow up actions are properly undertaken in the event of non-compliance of the WMP;

·         Review method statement to ensure appropriate mitigation measures are implemented prior to execution of work;

·         Liaise with ER, and ET on waste management and environmental protection issues;

·         Monitor records of all trained personnel in the site offices;

·         Monitor the following documents:

Ø      Any statutory required waste management permits/licenses including dumping license, chemical waste producer, admission ticket and etc.;

Ø      C&D material disposal delivery record; and

Ø      Waste reuse / recycle / disposal summary.

·         Keep abreast of the statutory requirements and regulations about waste management; and

·         Supervise and arrange the maintenance of waste management facilities.

 

 

Waste Manager

3.2.7              The Waste Manager shall:

·         Ensure all relevant legislation and the Contractor’s duty of care is complied with throughout the duration of the Project;

·         Initiate waste reduction scheme on site;

·         Ensure that all the Contractor’s employees and nominated subcontractors’ employees are aware of their responsibilities regarding the content of the WMP; and

·         Co-ordinate waste management on site, gather data on waste and keep accurate records on waste movement both on and off site.

Registered Asbestos Consultant

3.2.8              The Registered Asbestos Consultant shall:

·         Verify the extent of the ACM identified prior to commencement of the asbestos abatement works;

·         Supervise ACM removal works of the Registered Asbestos Contractor;

·         Certification and acceptance of the site preparation or completion of asbestos abatement works by the Registered Asbestos Contractor for each work zone; and

·         Prepare Asbestos Investigation Report (AIR) and Asbestos Abatement Plan (AAP) and submit to the EPD of any ACM that was previously not found or reported.

Registered Asbestos Contractor

3.2.9              The Registered Asbestos Contractor shall:

·         Be responsible for the asbestos abatement works including the removal of all ACM identified in the Asbestos Study Report (ASR) including the AIR and AAP, and any unsurveyed ACM found during the demolition works;

·         Establish containment and associated ventilation and filtration equipment as required for asbestos abatement works;

·         Provide three-chamber decontamination unit for each of the containment for asbestos abatement works;

·         Carry out air monitoring requirements for the containments for asbestos abatement works;

·         Be responsible for the appropriate removal, packaging and storage for different types of ACM;

·         Transport properly packaged ACM to designated facilities for disposal;

·         Comply with emergency procedures under various emergency cases; and

·         Provide experienced full-time Registered Asbestos Supervisor(s) on site every day during the course of the asbestos abatement works.

 

Registered Asbestos Supervisor

3.2.10           The Registered Asbestos Supervisor shall:

·         Oversee all safety procedures and monitor the Controlled Works Area(s) for asbestos abatement works and ensure that the Contaminated Works Area(s) for asbestos abatement works is continuously cleaned of asbestos fibres;

·         Verify that all workers for asbestos abatement works wear suitable close fitting respirators every day, and shall maintain a register to verify correct procedures and movement of all persons who enter the Contaminated Works Area(s); and

·         Undertake all duties as required by the Factories and Industrial Undertakings (Safety Officers and Safety Supervisor) Regulations as necessary for asbestos abatement works.

Site Engineer (Demolition)

3.2.11           The Site Engineer shall:

·         Assist the Site Agent in the implementation of WMP;

·         Monitor and control works including those of subcontractors to ensure compliance of WMP;

·         Report to the Site Agent regarding non-compliance of waste management issues; and

·         Ensure the remedial actions or mitigation measures are carried out as planned.

General Foremen

3.2.12           General Foremen shall:

·         Assist the Site Engineer in the implementation of WMP;

·         Control works, including those of subcontractors, to fulfil the requirement of waste management issues;

·         Report to the Site Engineer any non-compliance of waste management issues;

·         Maintain the on-site waste management facilities including sorting area, temporary storage area, general refuse bins and recycling bins etc;

·         Carry out remedial actions or mitigation measures to rectify non-compliance;

·         Carry out routine maintenance of waste management facilities and proper maintenance records shall be kept in site office; and

·         Report non-compliance of environmental protection issues.

Subcontractor and other employees

3.2.13           Every employee and subcontractor has the duty to carry out the waste management practices instructed by the Site Engineers and General Foreman. Copies of WMP are to be issued to all subcontractors.

3.2.14           Every employee and subcontractor shall report promptly to foreman any non-compliance of waste management and environmental protection issues.

The Environmental Team (ET) and ET Leader

3.2.15           The ET, including the ETL, shall:

·         Be responsible for the duties defined in the EM&A Manual of the EIA Report;

·         Conduct site inspections and investigate and inspect the Contractor’s equipment and work methodologies with respect to waste management and environmental mitigation measures. They shall review the works for anticipating potential waste management and environmental pollution implications;

·         Review the programme of works to anticipate potential waste management implications;

·         Report the implementation status of waste management mitigation measures from site inspections; and

·         Follow the procedures stipulated in the agreed Event and Action Plans in the event of non-compliance or complaint.

·         Be responsible for the implementation of the EM&A programme in accordance with the EM&A requirements as contained in the EM&A Manual; and

·         Keep a contemporaneous log-book of each and every instance or circumstance or change of circumstances which may affect the environmental impact assessment and for each and every non-compliance of the EIA Report or the EP.

The IEC

3.2.16           The IEC shall:

·         Be responsible for the duties defined in the EM&A Manual of the EIA Report, and shall audit the overall EM&A programme described in the EIA Report, including the implementation of all environmental mitigation measures, submissions required in the EM&A Manual, and any other submissions required under the EP;

·         Be responsible for verifying the environmental acceptability of permanent and temporary works, relevant design plans and submissions under the EP;

·         Verify the log-book(s) kept by the ETL;

·         Notify EPD of each and every occurrence, change of circumstances or non-compliance with the EIA Report or the EP, which might affect the monitoring or control of adverse environmental impact;

·         Conduct monthly site audit to ensure the Environmental Management System (EMS) is in place and recommend any changes as appropriate;

·         Review and audit all aspects of the EM&A programme, including the WMP;

·         Assist the ET on complaint investigation and recommend and/or instruct mitigation measures as appropriate; and

·         Liaise with the ET on all environmental performance matters.

 


4                        WASTE GENERATION AND DISPOSAL

4.1                   Waste Overview

4.1.1              The following types of waste would be generated from the demolition activities under this contract:

·         General refuse

·         Inert Construction and Demolition (C&D) Material

·         Non-inert C&D Material

·         Recyclables

·         Asbestos Containing Materials (ACM)

·         Dioxin/Furan Contaminated Materials (DCM)

·         Chemical waste

4.1.2              The estimated quantity of waste arising from different activity & work areas, and the disposal sites for the wastes generated from the project are provides in the following sections. The estimated period of waste generation to landfill site is from December 2007 to August 2009 excluded the period of land decontamination works. The waste disposal schedule to landfill site is shown in Appendix G1.

Table 41     Summary of Waste Disposal

Waste Type

Examples / Classification

Disposal Site

General Refuse

          Packaging waste

          Office waste

          Putrescible wastes

          Vegetation

          SENT Landfill by vehicles

Inert C&D material

          Broken concrete

          Brick

          Aggregate

            Public Fill at Tuen Mun Area 38 Fill Bank

Non-inert C&D material

          Wood

          Bamboo

            SENT Landfill

Recyclables

          Metal

          Paper

          Plastic

          Recycling collectors

Asbestos Containing Material (ACM)

          Type 1

          Type 2

          Type 3

           

          Disposal of at SENT Landfill by licensed collector

          Abatement and disposal ACM within Chimney not covered in this WMP and will be submitted in next version.

Dioxin/Furan Contaminated Material (DCM)

          Ash bunker

          Chimney flues

          Disposal of at SENT / WENT Landfill by licensed collector (disposal to CWTC will only be a fallback solution as per EP No. 121/2002)

          Treatment and disposal of DCM within Chimney not covered in this WMP and will be submitted in next version.

Chemical Waste

          Spent lubricant oil

          Surplus paint

          Spent diesel

          To be collected by licensed waste collector


4.2                   General Refuse & Non-Inert C&D Material

Source of Wastes

4.2.1              General refuse will be generated largely by food service activities for on‑site staff, from office work and certain aspects of the construction works, and will include food wastes, unrecyclable waste etc.

Estimated Quantities and Timing for Generation

4.2.2              It is estimated that the general refuse and non-inert C&D material arising will be about 50m3 per month exclude the period of land decontamination works. Although the size of the site office establishment will vary at different stages of the demolition works, thus be observed that the relative contribution to the general wastes from site staff, which will be generated throughout the whole contract period, will be small in terms of the overall wastes arising. The tentative programme of the non-inert C&D material generation would be from December 2007 to August 2009 exclude the period of land decontamination works.

Control Measures

4.2.3              Office waste will be reduced through reduce use of paper and minimize the waste generation.

4.2.4              General refuse including food wastes, such as lunch boxes, and domestic wastes generated on-site will be stored in enclosed bins or compaction units separated from construction and chemical wastes.

On-Site Handling or Storage

4.2.5              Putrescible wastes, such as lunch box, and domestic wastes generated on-site will be stored in enclosed bins or compaction units separate from C&D and chemical wastes.  Location of temporary storage of general refuse is indication in Figure 4-1.

Disposal Arrangement

4.2.6              A reputable waste collector will be employed by the Contractor to remove general refuse and to be disposed of at landfill site, separately from C&D material and chemical wastes, preferably daily to minimise odour, pest and litter impacts.  The burning of refuse on construction sites is prohibited by law.

4.2.7              Waste disposal records will be obtained from the appropriate authorities and collection of general refuse and general site housekeeping will be carried out in accordance with the Waste Disposal Ordinance (Cap. 354), Waste Disposal (Chemical Waste) (General) Regulation (Cap. 354) and the Government Land (Miscellaneous Provisions) Ordinance (Cap. 28).

 

 

 

4.3                   Inert C&D Materials & Recyclables

Source of Wastes

4.3.1              Due to the nature of the works, C&D materials, other than material mentioned at paragraph 4.2, will also be generated under the contract.  The types of C&D materials include the following:

·         Inert C&D materials (including rock, broken concrete, etc); and

·         Recyclables non-inert materials such as metal components, plastic & paper.

4.3.2              C&D material comprises materials broken up during demolition, including concrete and structural steel.  Alternatively there are materials which are surplus to requirements for the demolition process and materials which have been used and discarded.  The bulk of the C&D material will come from the buildings and other related structures (e.g. chimney) which are to be demolished.  C&D material may comprise different types of materials.

4.3.3              C&D materials are typically generated simultaneously in mixed form and the individual waste materials may be altered (e.g. painted).  The final actual volume and composition of C&D waste requiring disposal to public filling area following the demolition at KCIP will be dependent on the demolition procedure and material recovery practices employed. 

Estimated Quantities and Timing for Generation

4.3.4              It is estimated that the total C&D material arising will be about 9,000m3 which mainly consist of broken concrete. Meanwhile, a small portion of recyclables (approx. 180m3) which would be collected by the recycling collectors would also be generated from the demolition works. The estimated quantities of recyclables would be:

·         Steel bars: total 1,900 tonne;

·         Plastic: 100kg per month; and

·         Paper: 100kg per month.

4.3.5              The tentative programme of C&D materials generation would be from the 12th month to the 24th month covering the period from the commencement of the contract works to the completion of the demolition works.

Control Measures

4.3.6              To reduce / minimize the generation of C&D materials, materials resulted from the demolition works will be sorted properly to recover the inert portions for reuse on site or disposal to designated outlets.

4.3.7              Sorting of inert and non-inert portions of demolition materials will be carried out at the source site to avoid double handling and loss of materials due to transportation. In case the site condition is inapplicable for sorting, it will be carried out at the designated storage area. Reusable / recycling materials of both the inert and non-inert portion will be further recovered for on-site reuse or collection by the recycling contractors.

4.3.8              Demolition materials will be segregated from other wastes to avoid contamination thereby ensuring acceptability at public filling areas and avoiding the need for disposal at landfill.

On-Site Handling or Storage

4.3.9              Due to the large volumes of (non-contaminated) C&D material generated from the demolition works, it is important that selective demolition and on-site sorting as described below will be incorporated into the tender documents for implementation by the Contractor.

Selective Demolition

4.3.10           “Selective Demolition” involves demolition and removal of wastes of the same category one at a time.  In general, domestic wastes such as furniture, household appliances; metal components such as window frames, pipes; timber components such as doors, wooden floors; and other wastes such as tiles, asphalt materials, ceramic products will be removed first.  The building demolition will begin after all the above non-structural materials have been stripped and removed.  To avoid mixing the non-recyclable bricks with the broken concrete, the demolition sequence will be planned in such a way that brick walls are demolished first and stockpiled separately before the demolition of structural members.

On-site Sorting

4.3.11           C&D material will be removed from site as soon as practicable to avoid adverse environmental impacts due to on-site storage of the material. It will be sorted/separated at the construction site as far as practicable into two main types: inert (including soil, rock, concrete, brick, aggregates and asphalt) and non-inert (wood, paper, general garbage and other inorganic). 

4.3.12           All inert C&D materials from demolition such as the rock and broken concrete will be disposed off site to the designated Public fill reception Facilities (PFRF) whilst the non-inert portion excluding all reusable / recyclables material, is classified as C&D waste which will require to be disposed of at the WENT/ SENT Landfill Site or other areas as designated by EPD. For inert C&D materials to be disposed of at designated PFRF, the Contractor will ensure that the C&D materials be broken down on site to less than 250mm so as to facilitate its reuse in reclamation or earth filling projects.

4.3.13           C&D material will be transported by barge. The C&D material generated from the demolition works will be loaded on barge immediately and be transported offsite as soon as it fills the capacity. Location of temporary storage of C&D material is indicated in Figure 4-1.

4.3.14           Designated areas for segregation and temporary storage of reusable and recyclable materials are identified.  The Contractor will recycle as much of the C&D material as possible on‑site.  Different areas of the work site will be designated for such segregation and storage wherever site conditions permit.

 

Recyclables

4.3.15           To encourage environmental awareness and to reduce waste by reducing the number of photocopies to a minimum and by copying on both sides of paper for internal documents and external documents where appropriate. Recycling bins for paper and plastic bottle will be provided in site office to facilitate the recycling. Waste paper and plastic bottle will be stored in containers clearly marked as recyclable or waste. Location of temporary storage of recyclable is indicated in Figure 4-1 of Appendix A.

Disposal Arrangement

4.3.16           Environment, Transport and Works Bureau Technical Circular (Works) No. 31/2004 – Trip-ticket System for Disposal of Construction and Demolition Materials promulgates the policy to implement a trip-ticket system in Public Works Programme (PWP) contracts for the proper disposal of C&D material at public filling facilities or landfills. A trip-ticket system should be implemented for this Project in accordance with ETWB TC(W) No. 31/2004 as per the recommendation of the approved EIA Report and the conditions of the Environmental Permit therefore overrule the exemption quantity of 50,000 m3 specified in ETWB TC(W) No. 31/2004.

4.3.17           All inert C&D material for disposal shall be transported by barge to the public fill area or other areas as designated by EPD. Vessel chits forms should be used for C&D material disposal of at public fill area by barge.

4.3.18           The transportation route for disposal of C&D material is indication in Figure 4-2 of Appendix A.

4.4                   Asbestos Containing Materials (ACM)

Source of Wastes

4.4.1              ACM is classified as Part A waste under the Waste Disposal (Chemical Waste) (General) Regulation. An Asbestos Investigation Report (AIR) and Asbestos Abatement Plan (AAP) have been prepared by Registered Asbestos Consultants (EPD register 1014 and 1019) based on thorough site investigations under the Air Pollution Control Ordinance (APCO).

Estimated Quantities and Timing for Generation

4.4.2              There will be up to 1,500m3 of asbestos waste mainly in the form of “Galbestos” (galvanised metal sheeting which forms the outer cladding on the main building). The galvanised metal cladding is coated with asbestos containing material paint and will be disposed of in line with the requirements of the APCO. Three types of ACM were identified at the EIA stage. The quantities of each type of ACM identified are summarized in Table 4-2. 

 

 

 

 

Table 42     Estimated Quantity of ACM

ACM Type

Location of ACM

Estimated Quantity in EIA

Estimated Volume, m3

Type 1

Flue guide plates (flue guides on platforms 1 to 7, chimney)* (< 3m3)

3m3

3

Floor tile (Thickness = 2mm)

- Conference Room, Office Block (6m x 6m)

- Plant Manager Offices, Office Block (18m x 6m)

- Kitchen Office, Main Building Offices (3m x 6m)

- Laboratory, Main Building Offices (10m x 11m)

- Corridor, Main Building Offices (2m x 20m)

- Workshop Office, Main Building Offices (4m x 5m)

- Day Supervisors Office, Main Building Offices (6m x 12m)

 

36m2

108m2

18m2

110m2

40m2

20m2

72m2

 

Sub-total

404m2

0.8

Weather cladding (Main Building)

(Package method#:

Dimension of cladding sheet: 3m x 0.7m = 2.1m2,

10 sheets per pack per meter depth.

Each pack volume = 3m x 0.7m x >1m (thickness) = 2.1m3

No. of packs = 13,000m2/2.1m2/10 sheets = 619 packs Volume of cladding: 619 packs x 2.1m3 = 1,300m3)

13,000 m2 #

1,300

ACM waste (from cleaning, containment materials, wastewater, etc.) (Type 1)

<100m3

100

Type 1 Total

1,403.8

Type 2

Flexible joints (joint between remains of gas ducts on flues at ground level, base of chimney)*

Total < 20m3

20

Gasket (gas door seal on flues at ground level, base of chimney)*

Total < 2m3

2

Gasket (duct seal on ventilation above ground level, outside Kitchen)

Total < 0.2m3

0.2

Ribbon (Fuse box at the office block)

Total <0.1m3

0.1

ACM waste (from cleaning, containment materials, wastewater, etc.) (Type 2)

<30m3

30

Type 2 Total

52.3

Type 3

Gaskets (flues on platforms 1 and 2, chimney)*

Total < 3m3

3

Water pipe (fire water supply, ash bunker)

Total < 20m3

20

ACM waste (from cleaning, containment materials, wastewater, etc.) (Type 3)

<20m3

20

Type 3 Total

43

 

Total Volume = Type 1 + Type 2 + Type 3

Grand Total

1,499.1

*The abatement, treatment and disposal of any ACM within the KCIP Chimney shall be subject to later agreement with EPD and to be covered in a separate WMP for Chimney.

# There are the same estimation between onsite survey and estimated in the EIA stage and approved AAP. The proposed packing method is following the approved AAP section 5.1.3. The actual bulk volume of weather cladding depends on the shape and the Contractor will try the best to reduce the waste volume if applicable.

4.4.3              The tentative programme of the ACM generation would be from June 2008 to December 2008.

On-site Handling and Storage

4.4.4              All ACM will be removed prior to commencement of demolition works. Other than ACM located in chimney, ACM are located separately from DCM. Thus asbestos removal works will not be disturbed and cross contamination with DCM Details on the method statements, work sequence and procedure with regard to removal of ACM are included in Appendix D.

Package of Asbestos Wastes:

·            Type 1 asbestos wastes (approximately 3m3 of bulk material plus 13,404m2 of floor tile and claddings. It is estimated that the thickness of floor tiles is 2mm and removal of weather cladding will follow the approved AAP section 5.1.3, i.e. a total of 1,403.8m3 of type 1 asbestos waste including ACM waste generated during decontamination. Refers to Table 4-2 for details) (bonded asbestos wastes, other than blue or brown asbestos in good condition) will be packed with 2 individual layers of strong transparent plastic sheets of not less than 0.15 mm thickness and completely sealed with adhesive tapes. Type 1 waste will be packed in suitable sizes for easy handling. The height of each package will be around 1m.

·            Type 2 asbestos wastes (approximately 52.3m3 of bulk material including ACM waste generated during decontamination, refers to Table 4-2 for details) (any waste containing loose asbestos fibres (other than blue or brown asbestos)) must be contained, as soon as it is produced, in strong bags made from plastic or other containers approved by EPD. The bags should be goose-neck sealed by means of adhesive tapes. A bag filled with asbestos waste should be placed inside another plastic bag to provide additional protection. The colour of the inner bag should be white while the outer bag should be transparent to facilitate visual inspection.

·            The handling of Type 3 asbestos wastes (approximately 43m3 of bulk material including ACM waste generated during decontamination, refers to Table 4-2 for details) (all blue asbestos (crocidolite) and brown asbestos (amosite), whether in good condition or not, or any articles contaminated by blue or brown asbestos) should be similar to that of Type 2 except that the colour of the inner bags should be orange.

 Storage of Asbestos Wastes

4.4.5              All asbestos waste will be stored properly in a secure place isolated from other substances so as to prevent any possible release of asbestos fibres into the atmosphere and contamination of other substances.  Type 1 asbestos waste will not be stored together with Types 2 and 3 asbestos wastes so as to avoid damage to the plastic bags of Type 2 or 3 asbestos waste, unless the bags are packed in boxes or drums for additional protection. Bagged asbestos waste will not be stacked more than 3 bags high in order to avoid damage to the bottom bag. The storage area will be isolated from other working areas and bear warning panels to alert people of the presence of asbestos waste.

4.4.6              Location of temporary storage area of asbestos wastes is indicated in Figure 4-1.

 

Disposal Arrangement

4.4.7              Disposal of asbestos wastes will not commence before a designated notification has been given to EPD and confirmed. Before being transported for disposal, all the asbestos waste produced will be stored in a temporary storage area which complies with the requirements of Section 7 of the Code of Practice on the Handling, Transportation and Disposal of Asbestos Waste.

4.4.8              All asbestos wastes for disposal shall be transported by an asbestos waste collector - General Central Engineering Limited, licensed by EPD and in a designated barge equipped as stated in the Code of Practice and to be disposed of at the SENT Landfill Site or other areas as designated by EPD. For waste transportation arrangement for the delivery to and deposition at SENT Landfill Site, the Contractor will use CEDD’s pier at TKO Area 137 for unloading the materials to truck and then deliver to EPD’s landfill site. The self-explanatory letter of CEDD is shown in Appendix E. The asbestos wastes would be temporarily stored in 39 containers to be transported to the barge. It is estimated that each barge could accommodate 8 nos. containers and therefore totally 5 barge trips for the disposal of the waste to the landfill from June 2008 to December 2008 would be required.

4.4.9              Pursuant to S74(3) of the APCO, the proposed amendment to use marine vessel for transportation of asbestos waste was approved by EPD [Ref.: (10) in EPAC/A/15/000/918 Pt.VI dated 29 August 2007] on the condition that the marine vessels will be the approved ones listed in the list of licensed chemical waste collectors issued by EPD. Transportation route for disposal of ACM waste is indicated in Figure 4-2 and the generic method statement of ACM removal is attached in Appendix D.

4.5                   Dioxin / Furan Contaminated Wastes

Source of Wastes

4.5.1              According to Section 4.7.26 of the approved EIA Report (AEIAR-049/2002), ash waste containing a considerable amount of dioxin and in its untreated state would be classified as a chemical waste under the Waste Disposal (Chemical Waste) (General) Regulation.

4.5.2              Dioxin contaminated ash on the walls and floor near the ash bunker will be collected and stabilized with cement to meet landfill disposal criteria of EPD, e.g. TCLP tests as per Section 4.7.32 of the approved EIA Report (AEIAR-049/2002). The stabilized ash/ sediment will then be sealed in polythene-lined steel drums for landfill disposal.

4.5.3              Treatment and disposal of ash from the chimney of the KCIP shall be subject to later agreement with EPD and be documented in a separate WMP for approval.

4.5.4              Regarding the quantities and level of contamination of DCM in ash bunker and the KCIP chimney, please refer to the following section.


Estimated Quantities and Timing for Generation

4.5.5              The estimated quantity of dioxin/furans contaminated waste after detailed site investigation works carried out subsequent to the EIA stage is as follows:

Ø                  Ash and sediment in the area of the Ash bunker: 20m3 [Cement-stabilisation on-site, followed by disposal to landfill (disposal to CWTC will only be a fallback solution as per EP No. 121/2002)]

Ø                  Ash in the chimney flue: 7m3 (to be agreed with EPD in a separate WMP)

Ø                  Chimney flue sections: 1,100m3 (to be agreed with EPD in separate WMP)

 

Level of Contamination

Ash Bunker

4.5.6              The laboratory analysis results presented Table 4-3 below has verified the findings of the EIA Report with respect to dioxin contamination around the ash bunker.  Amongst the 12 samples collected around the ash bunker, PCDDs/PCDFs were detected in 11 samples, and 4 samples were found to have TEQ exceeding the USEPA criterion and EP no. EP-121/2002 Clause 2.13 requirements of 1ppb TEQ. The sampling location is given Figure 4-3 of Appendix A.

Table 43          PCDDs/ PCDFs Analysis Results for Samples Collected at the Ash Bunker

Sample ID

Type of Sample

Location

Total TEQ (ppb)*

D1

Ash

Surface sample from wall of ash bunker at 5m above ground level

4.6184

D2

Ash

Surface sample from wall of ash bunker at 7m above ground level

0.32281

D3

Ash

Surface sample from wall of ash bunker at 5m above ground level

3.06332

D4

Ash

Surface sample from wall of ash bunker at 7m above ground level

2.77459

D5

Ash

Surface sample from floor at 5m away from the ash bunker

0.02491

D6

Ash

Surface sample from floor at 5m away from the ash bunker

0.00301

D7

Sediment

Sediment sample from bottom of ash bunker

0.20995

D8

Sediment

Sediment sample from bottom of ash bunker

0.41922

D9

Water

Water sample taken from ash bunker

0

D10

Water

Water sample taken from ash bunker

0.00017

D11

Ash

Surface sample from floor at 5m away from the ash bunker

2.73043

D12

Ash

Surface sample from floor at 5m away from the ash bunker

0.01233

* Limited level = 1 part per billion (ppb)


4.5.7              Dioxin was found in ash deposits in the ash/sediment of the Ash Bunkers, the Main Hall Ash Bunker and wall above Ash Bunker of the KCIP site. As indicated in the approved EIA Report, remedial action is required to clean up these materials prior to demolition. The decontaminated structures, including the ash bunker, wall and floor would be dismantled as part of the overall demolition programme.  The dismantled structures should be disposed of as Construction and Demolition (C&D) Material.

4.5.8              Based on the laboratory testing results, it is considered that the ash material retained on the surface of the wall (D1, D3 & D4) and north side of upper floor beside the ash bunker (D11) are dioxin-contaminated (i.e. >1ppb TEQ with the range of 2.7 – 4.6 ppb TEQ).  Furthermore, the surface of the wall (D2), the ground floor nearby the ash bunker (D5, D6 & D12), accumulated water (D9 & D10) and sediment (D7 & D8) inside the ash bunker were found below 1ppb TEQ. The total quantity of ash and sediment material to be handled is estimated to be in the order of 20m3 (i.e., 13m3 of sediment at the bottom of the ash bunker and 7m3 of ash on surface of wall and floor around the bunker).

Timing for generation

4.5.9              The tentative programme for DCM generation around the ash bunker would be tentatively from August 2008 to December 2008.

On-Site Remediation Works

Ash Bunker (20 m3 of ash and sediment in the area of the ash bunker)

4.5.10           To prevent cross-contamination with the low concentration DCM, the treatment sequence is firstly for accumulated water in ash bunker; secondly for sediment and wall ash to be treated at the last.

4.5.11           There is about 2,000m3 water accumulated inside the ash bunker. From the laboratory results of the water samples (D9 & D10), it was found that the dioxin concentration is much lower than the criteria. To prevent extract the sediment prior to discharge, water will be pumped into the sediment tank with 5mm water filter, reassurance test will be carried out prior to discharge.

4.5.12           As the dioxin level of sediment (D7 & D8) and ground floor (D5, D6 & D12) were below 1ppb TEQ, sediment will be excavated and ground floor will be HEPA vacuumed cleaned. The collected sediment and ash will be mixed with 10% cement for solidification within the full containment. The treated sediment floor ash shall meet the TCLP test before be sealed into steel drums lined with plastic sheeting prior to disposal at designated area in landfill. In case of failure in the reassurance TCLP test, the mixing percentage will be increased to ensure passing the TCLP requirement. It is estimated that 13m3 ash and sediment to be collected and 14.3m3 treated ash and sediment to be disposed of.

4.5.13           The remediation strategies for contaminated material will be adopted where the level of dioxin contaminants exceeded the USEPA criterion of 1ppb. D2 is located on the wall of the ash bunker which closed to D1, as prudent approach to prevent cross-contamination during decontamination works, D2 will be treated together with D1, D3, D4 and D11. For the sampling locations vicinity to D1, D2, D3, D4 and D11, ash/rubble will be HEPA vacuumed and scrabbled. Cement stabilization/solidification will be carried out for the ash/rubble to meet landfill disposal criteria (TCLP test) of EPD, 1ppb TEQ and specified in Condition 2.13, Part C of the EP.  Pilot test will be carried out first to obtain the reasonable cement ratio for the ash/rubble. The confirmation test will be carried out. The flow diagram of cement solidification is given Appendix F1. It is estimated that 7m3 ash will be collected and estimated that 14m3 treated wall ash will be disposed of subjected to cement ratio obtained from pilot test.

Pilot Test for Dioxin/Furan Contaminated Soil/Ash Solidification

4.5.14           The ratio of contaminants / cement mixture must be predetermined as the effectiveness of the solidification process depends upon a number of factors including the concentration of contaminants, contaminants quality, moisture content, and quality of cement.

4.5.15           Given the time factor and as a conservative approach, the pilot test for the dioxin contaminated ash/rubble (i.e. ash collected near D1, D2, D3, D4 and D11) will commence with cement ratio of 50% to ensure passing the TCLP requirement of 1ppb TEQ. The ratio of cement will be increased in case of failed in the test to achieve the landfill disposal criteria (TCLP test) of 1ppb TEQ. The flow diagram of cement solidification is given Appendix F1. In accordance with the EP Condition 2.14, disposal at the Chemical Waste Treatment Centre, Tsing Yi, will be considered as a fall back option if the pilot test criteria cannot be met.

4.5.16           It is estimated that the cement mixing ratio of 300% could be achieved the disposal criteria, otherwise fall back option as stated in EP Condition 2.14 will be considered. All collected ash near D1, D2, D3, D4 and D11 will be sealed into steel drums lined with plastic sheeting prior to disposal at the Tsing Yi Chemical Waste Treatment Centre. Designated barge will deliver to the Chemical Waste Treatment Centre.

4.5.17           After granted the disposal license from EPD, the Contractor will carry out the reassurance test to satisfy the disposal licence requirements, if any. The ratio of cement to soil/ash will then be selected based on the results of the TCLP tests. The methodology of TCLP is given in Appendix F2.

On-site Handling and Storage

4.5.18           DCM decontamination works will be conducted within a full containment. Ash contaminated with dioxin will be treated by solidification / stabilisation with cement, and the treated ash shall meet the TCLP test before it is sealed into steel drums lined with plastic sheeting prior to disposal at designated areas in landfill. According to “A Guide to the Registration of Chemical Waste Producers” issued by the EPD, ash generated from incineration of wastes is classified as chemical waste.

4.5.19           As a prudent approach, all wastes generated from the decontamination and removal works will be considered as contaminated waste and will be properly handled and disposed of. Other waste such as polythene wrapping sheets, waste generated from the dismantlement of the containment and decontamination units, and cloth used in wet wrapping, etc. will also be classified as contaminated waste. It is estimated that 3m3 used materials will be generated and disposed of.

4.5.20           The storage, handling, transport and disposal of chemical waste will be in accordance with the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes issued by EPD.

4.5.21           A total of 31.3m3 of treated DCM and contaminated materials, subjected to cement ratio obtained from pilot test, will be generated from the decontamination works of ash bunker and will be either directly sealed in drums or be remediated followed by sealing in drums. These drums will be temporarily stored within the enclosed material storage building, prior to landfill disposal. Location of the temporary storage area is indicated in Figure 4-1.

Disposal Arrangement

4.5.22           All contaminated residual ash removed from the ash bunker will be solidified with cement and sent to designated landfill site for disposal after passing the TCLP test.

4.5.23           This waste stream will be disposed of at a designated landfill site under the surveillance of trip ticket system. A permit will be obtained from EPD prior to disposal.

4.5.24           All DCM wastes for disposal will be transported by licensed chemical waste collector approved by EPD and in a designated barge equipped as stated in the Code of Practice and to be disposed of. Barge will berth at the barging facilities of CEDD Mines Division at Tsuen Kwan O Area 137 and waste will be delivered to designated landfill by trucks or other disposal outlets as directed by the EPD / Engineer’s Representative.  Transportation route for disposal of DCM waste is indication in Figure 4-2.

4.6                   Chemical Wastes

Source of Wastes

4.6.1              The chemical wastes generated from the demolition works will primarily arise from the maintenance of plant and equipment. These wastes include spent lubricant oil, surplus paint and spent diesel.

4.6.2              For chemical waste produced from a process, as defined by Schedule 1 of the Waste Disposal (Chemical Waste) (General) Regulation, registration will be made with EPD as a Waste Producer.

Estimated Quantity and Timing for generation

4.6.3              The generation of chemical wastes from the maintenance of plant and equipment is anticipated throughout the demolition project based on the utilisation of plant and equipment. The maintenance of plants and equipments will be minimized conducted on site except emergency maintenance. It is estimated that the generation of chemical waste is 75L per month (approx. 64kg/month).

Control Measures

4.6.4              Preventive measures will be implemented for leakage and spillage of fuel and lubricating oil to avoid contamination of the construction site.

4.6.5              All plant and equipment will require regular maintenance. Their maintenance records will be kept in site office for future reference.

4.6.6              Good housekeeping practices will be adopted to deal with chemical waste include:

(i)  Generating less chemical waste through:

·           Delivering appropriate quantity of chemicals to the construction site.

·           Avoiding unnecessary wastage of chemicals by using the chemicals more sensible and in accordance with the manufacturer’s instructions.

·           Finishing one bottle/container of chemicals before opening the next one for use.

·           Collecting the remaining chemicals in suitable containers.

·           Removing the unused chemicals out of the construction site after completion of the project.

(ii) Preventing illegal discharge of chemicals or chemical wastes through staff of the project.

(iii) Minimising the volume of unused chemicals to be disposed of through:

·           Using the chemicals before the expiry date.

·           Ordering appropriate quantity of chemicals and avoiding unnecessary storage of excess chemicals.

On-site Handling and Storage

4.6.7              Chemical waste will be handled in accordance with the Code of Practice on the Packaging, Handling and Storage of Chemical Waste. The details are described as follows and the location of temporary storage area of chemical waste is indicated in Figure 4-1.

(i) Containers used for the storage of chemical waste will:

·           be suitable for the substance they are holding, resistant to corrosion, maintained in a good condition, and securely closed;

·           have a capacity of less than 450 litres unless the specification have been approved by EPD; and

·           display a label in English and Chinese in accordance with instruction prescribed in Schedule 2 of the Regulations.

(ii) The storage area for chemical waste will:

·           be clearly labelled and used solely for the storage of chemical waste;

·           be enclosed on at least three sides;

·           have an impermeable floor and bund, 110% capacity of the largest container or 20% of the storage capacity, whichever is the greatest;

·           have adequate ventilation;

·           be covered to prevent rainfall entering (water collected within the bund must be tested and disposed as chemical waste if necessary); and

·           be arranged so that incompatible materials are adequately separated.

Disposal Arrangement

4.6.8              Chemical waste will be disposed of:

·         via a licensed waste collector;

·         to a facility licensed to receive chemical waste, e.g. Chemical Waste Treatment Facility in Tsing Yi; or others

·         to a re-user of the waste, under the approval from the EPD.


5                        IMPLEMENTATION OF WASTE MANAGEMENT

5.1                   Waste Flow Table (WFT)

5.1.1              Waste Flow Tables will be used to record all waste removed off site each month.

5.1.2              The estimated and actual quantities of wastes that will be generated each year from the project will be reported, using the table “Yearly Summary Waste Flow Table”, which is attached in Appendix G of this WMP.

5.1.3              The actual quantities of wastes generated in each month will be recorded in a monthly basis, using the table “Monthly Summary Waste Flow Table”, which is attached in Appendix G of this WMP.

5.1.4              Site Agent will be responsible to update the Yearly and Monthly Summary Waste Flow Tables.

5.2                   Recycling Proposal

5.2.1              As outline in Sections 4, the Contractor will segregate, as far as practical, the recyclable materials (mainly metals), from the C&D waste stream and general waste, so that the recycling contractors can collect the materials on a regular basis for recycling or export. Waste sorting and segregation will be carried out in accordance with the following categories for recycling:

·         Plastic (i.e. plastic bag, plastic bottle, plastic packaging, etc.);

·         Rubber;

·         Paper;

·         Wood/ timber;

·         Glass;

·         Textile; and

·         Metal (i.e. aluminium can, steel metal, ferrous metal, and non-ferrous)

5.3                   Trip-ticket System

5.3.1              The disposal of C&D Material will be carried out in accordance with the ETWB TC(W) No. 31/2004.  The Contractor will produce a Construction and Demolition Material Disposal Delivery Form (the Form) for each and every vehicular trip transporting C&D material off site.  The Contractor will complete all relevant details on the Form in quadruplicate except for the Time of Departure. A sample of the Form is attached in Appendix H. All inert C&D material will be disposed of by marine transport to the public fill area or other areas as designated by EPD. Vessel chits forms should be used for C&D material disposal of at public fill area by barge.

5.3.2              Prior to the vehicle leaving the site, the Contractor will present to the ER the completed Form.  The ER will insert the Time of Departure and stamp the Form.  The ER will retain a copy of the Form and return the original to the Contractor.  The Form will be carried on board the vehicle at all times throughout the vehicular trip.

5.3.3              In case marine transportation is employed for disposal of inert C&D material, the Contractor follow the vessel trip-ticket system arrangement for all barges to deliver to designated public fill area. For disposal of ACM, the Contractor still needs to follow the aforesaid trip ticket arrangement for all trucks when materials are transferred from the barges to the trucks at existing barging point nearby the disposal site before the trucks are allowed to dispose of the collected materials at the designated sites.

5.3.4              The copies of the Form and the receipt will be maintained on site for future references.

5.3.5              For each trip of off-site disposal of chemical waste, trip tickets issued for every chemical waste collection made by the licensed waste collector will be copied to the ER with the original maintained on site for future references.

5.3.6              The Site Management Plan for Trip-Ticket System is attached for reference in Appendix H.

5.4                   Inspection Programme and Performance Monitoring

5.4.1              Auditing of each waste stream will be carried out periodically by the EM&A Team to determine if wastes are being managed in accordance with approved procedures. The audits will look at all aspects of waste management including waste generation, storage, recycling, treatment, transport, and disposal. An appropriate audit programme would be to undertake a first audit at the commencement of the demolition works, and then to audit quarterly thereafter.

5.4.2              The Waste Manager and the ET will be responsible for the monitoring and auditing of the waste management practice during his weekly site inspection in order to ensure that appropriate control measures are properly implemented. 

5.4.3              If deficiency of the waste control measures were identified during the site inspection and audit, the Waste Manager of the Contractor will discuss with the Site Agent for formulation of remedial measures and the Site Agent will implement the remedial measures promptly to rectify the situation.  If deficiency persists, alternative and/or additional control measures will be proposed to the satisfaction of the ER.

5.5                   Record Keeping and Reporting

5.5.1              The Contractor will keep adequate and proper records such as trip tickets, photographs and measurement records relating to the implementation of the WMP, and submit such records of each calendar month to the ER within the first week of the following calendar month for their onward submission to the Public Fill Committee for information.  The record will include the amount of wastes generated, recycled and disposed of (including the disposal sites). A sample of the Construction and Demolition Material Disposal Delivery Form is included in Appendix H for reference.

5.5.2              After the completion of the Contract, the Contractor will submit a report on the implementation of the WMP in the content to be agreed by the ER.  The report will include the following information and any other information as the ER may consider appropriate:

·         The quantities of different types of C&D material as estimated at the commencement of the Contract;

·         A statistics on the monthly quantities of different types of C&D material generated and their disposal method; and

·         Reasons for any significant differences between the estimated quantities at (a) and the actual quantities at (b).


6                        EMERGENCY RESPONSE

6.1                   Objective of the Emergency Response Procedure

6.1.1              The plan addresses emergencies related to the demolition, treatment, storage and transportation of contaminated materials. Such emergencies may include:

·         Fire in full containment for ACM / DCM decontamination;

·         Chemicals & chemical wastes spillages on land and sea;

·         Typhoon attack on chimney decontamination containment;

·         Overflow of contaminated surface run-off due to heavy rain storm attack;

·         On-site traffic accident; and

·         Power failure during ACM / DCM decontamination

6.1.2              The Project identifies three general groups of activities that have the potential to affect the public or the environment in the event of an emergency:

·         Demolition and decontamination of ACM / DCM; and

·         Storage and transportation of ACM / DCM.

6.2                   Definition of Emergency

6.2.1              An emergency is an existing or imminent event that presents a danger of major proportions to human health or the environment. An emergency requires prompt co-ordination of actions to protect the health, safety or welfare of people, and/or to limit damage to the environment or property and equipment.

6.3                   Emergency Response Team

6.3.1              An Emergency Response Team (ERT) has been formed and consists of the following personnel:

·         Safety Officer;

·         Safety Supervisor;

·         Site Agent;

·         General Foreman;

·         Site Engineer;

·         First Aider;

·         Electrician; and

·         Public Relation Officer.

6.3.2              The ERT members and the action of each stakeholder for tackling emergency situations are included in Table 6-1.

 

Table 61     ERT Member List

Name

Position

Emergency Team

Contact No.

Action, Roles and Responsibilities in Emergency Situations

Mr. Vincent LEUNG

Safety Officer

ERT Leader

9475 3666

l        Manage all resources on-site for the implementation of emergency.

l        Inform Project Manager / Site Agent

l        Responsible for all emergency arrangement on-site and develop appropriate handling procedures.

l        Advice on health and safety related issues.

Mr. Steven Ho

Site Agent

Deputy ERT Leader

6281 8608

l        Assist the ERT leader for carrying out his duties in case of emergency event.

l        Implement emergency procedures.

l        Oversee the emergency management and provide necessary support to ERT Leader.

l        Advise on clean-up procedure and co-ordination of resources.

Mr. Sai Ho CHAN

Safety Supervisor

ERT member

6909 6344

l        Assist the Safety Officer for carrying out his duties in case of emergency event.

Mr. Hon Wing WONG

General Foreman

ERT member

9076 1422

l        Assist in implementing emergency procedures.

Mr. Shao Chen NING

Site Engineer

ERT member

6692 2413

l        Notify relevant Government Department and Parties, where necessary.

Mr. Sai Ho CHAN

First Aider

ERT member

6909 6344

l        Provide necessary on-site first aid recovery as instructed by ERT Leader under safe environmental condition.

Mr. Kwan Yuen WU

Electrician

ERT member

9109 6231

l        Ensure electrical safety as instructed by ERT Leader under safe environmental condition.

Mr. Ivan KONG

Public Relation Officer

ERT member

8102 2699

l        Answer 24-hr Hotline.

l        Provide communication support and service.

l        Manage public communications in the event of issues, crisis and complaints.

24-hr Hotline

8102 2699


6.4                   Chain of Command

6.4.1              A person within the ERT will be appointed to be the ERT leader - a primary decision-maker in the event of an emergency. In the case that the ERT leader cannot be contacted, an alternative person will be available to conduct the duties of the ERT leader. The responsibilities of the ERT leader are as follows:

·         To understand the project emergency plan and rescue procedures.

·         To immediately notify the ERT members in the event of an emergency.

·         To arrange the whole operation of the emergency rescue and fire fighting.

·         To determine the seriousness of the cases and take appropriate actions to handle the emergency / fire;

·         To assign personnel in the ERT to assist the ERT leader to carry out the rescue procedures in case of fire / emergency.

·         Immediately notify the Site Engineer and Project Manager of the detail of any accident and rescue procedures in case of a serious accident.

·         Review and recommend changes if necessary, the emergency procedures periodically with other safety personnel and monitor the system and its implementation.

·         To arrange necessary fire fighting / rescue equipment in accordance with legislation requirements.

·         To re-organise the ERT members from time to time to ensure the effectiveness of the system and competency of the members.

·         To arrange practice drills for assessing the efficiency and effectiveness of the rescue team regularly.

6.4.2              In general, anyone that has discovered chemical leakage and spillage shall immediately report to the ERT leader, ET/ ET Leader, and the Waste Manager. ERT leader shall take into account the safety and environmental advises from Environmental Officer and Safety Officer once the chemical leakage and spillage incident is observed/ reported.

6.5                   Internal Communications

6.5.1              Telephones and direct face-to-face communication will form the basis of communications within the site. The site office will be equipped with telephones. Cellular phones will allow for communication among field personnel, truck drivers and the site office.

6.6                   Communications with the Public

6.6.1              All community enquiries or complaints in relation to activities described in this emergency section should be directed to the project 24-hr Hotline and the project representatives identified in the ERT member list. A separate Public Relation (PR) Plan has been prepared by the Public Relation Officer detailing the communication channel with the public. (Contract Clause PSA 2.4)

 

6.6.2              Communication between the public and project personnel will only be required in the event of issues, crisis and complaints where the situation is to be handled within the project site. However, depending on the nature of an emergency, in the event where the situation has been handed to the Police or FSD, Police or FSD will be the overall commander and communication with government agencies, medical service providers, external experts and the public. The ERT leader will maintain close liaison with the Police or FSD representative on site.

6.7                   Emergency Call List

6.7.1              An up-to-date emergency call-out list including major ERT members will be displayed on a prominent position in the site office. This list shall be a dynamic document and be continuously updated as necessary. This list is currently based on normal working hours but will be updated if required by an increase in operational hours.

6.7.2              In addition to the above contacts, other organisations that may need to be contacted in the event of an emergency include:

Kwai Chung Fire Station                           2426-5694

Tsuen Wan Fire Station                              2499-5044

Water Supplies Department                        2824-5000

Police Emergency Call                               999

HKPF – Duty Officer, Kwai Tsing District 2410 2205

Drainage Services Department                  2300-1110

Hong Kong Observatory                            2926-8200

The Hong Kong and China Gas Company 2880-6999

CLP Power Hong Kong Limited                 2678 2678 Customer Service (24-hour)   

(Emergency Reporting)                              2728 8333 (24-hour)

(Engineering)                                             2678 7900

6.8                   Training

6.8.1              An emergency often creates unfamiliar circumstances and a hostile working environment for people required to respond to the emergency. In addition, time is usually a very important factor in determining the most appropriate response to an emergency. Training and experience can significantly improve the effectiveness of the responders and decision-makers. Training is therefore a vital part of the implementation of an Emergency Response Procedure (ERP).

6.8.2              The specialist personnel identified in this procedure will be trained and qualified in their respective roles as identified in this procedure. For example, it will be ensured that all First Aiders hold valid First Aid Certificates.

6.8.3              All workers will be briefed of the emergency response process in the site induction, and all workers identified in this section will be trained in its content in the language that the worker understands.

 

 

6.9                   The Contractor and Employees

6.9.1              All employees of the Contractor shall be thoroughly familiar with company policies and procedures for responding to emergencies. He/she will be knowledgeable in the contents under this section of the plan, and be actively involved in the training of other personnel identified under this section.

6.9.2              All personnel at the site will be made familiar with the Chain of Command with respect to reporting emergencies and subsequently taking directions from identified personnel. Every person is a potential resource in the early detection of problems, which if not reported and not addressed could lead to emergency situations.

6.9.3              The frequency of the training necessarily depends on the personnel and the circumstances at the site. New personnel should be trained systematically. Changes in the roles of individual personnel would warrant new training.

6.10               Sub-Contractors and Others

6.10.1           Sub-contractors and all other personnel working at the site shall be made familiar with the chain of command with respect to reporting emergencies and subsequently taking directions from site personnel.

6.11               Emergency Response Procedures

Response to General Emergency

6.11.1           Where the ERT leader deems an emergency situation, he will contact the necessary personnel identified in the ERT. The Safety Officer will go to the site of the incident and relay all details to the other ERT members who will gather at the contractor site office. The Safety Office will advise the ERT of all necessary equipment/PPE requirements/first aid treatment needed at the accident site. The ERT and associated team members will then co-ordinate all items require by the Safety Officer.

6.11.2           Upon clearing the accident site, a post-mortem report will be completed which details all occurrences prior to, during and following the incident. Applicable workers will be briefed on the contents of the incident report following its completion.

Fire in Full Containment for ACM / DCM Decontamination

6.11.3           In the event of fire in full containment for ACM / DCM decontamination, the Fire Services Department will be immediately notified and all personnel working within the containment or in the vicinity of the work site area evacuated. All personnel working within the containment shall:

·         Stop all work and if necessary remove worker(s) to a safe area;

·         If a worker has collapsed remove face mask (in all other cases the face mask should be left in place), carry out normal emergency first aid procedures and arrange to transfer the worker to hospital.  Personal decontamination should be carried out if possible;

·         Where it is impossible to carry out decontamination procedures on the worker, inform the medical team to enable them to take the appropriate safety measures; 

·         Bag all loose ACM / DCM debris present in the ACM / DCM removal work area and remove to a secure store.  Wipe clean and vacuum all surfaces and any adjoining area contaminated during the emergency;

·         Spray all surfaces and debris within the ACM / DCM removal work area with amended water in a fine mist spray, using airless spray equipment once the fire has been extinguished and the Site is safe for re-entry;

·         Prepare the Site for inspection by the Registered Asbestos Consultant; and

·         Carry out air testing prior to recommencing removal work.

Chemicals & Chemical Wastes Spillages on Land and Sea

6.11.4           Transportation of chemical waste including ACM / DCM and other chemicals shall be carried out by barge, loss of ACM / DCM and other chemical waste on roads are not anticipated.

6.11.5           Transportation of chemical waste including ACM / DCM and other chemicals shall be carried out by licensed waste collector, and be contained either in steel drums lined with plastic sheeting or by use of safety and suitable labelled containers.

6.11.6           Spillages or dropping into the sea while marine transportation shall be recoverable. Detail of the Works Execution Plan for transportation by vessels is included in Appendix H for reference.

6.11.7           While ACM / DCM are being loaded onto and off between barging point and the barge for marine transport, net carrier shall be used to prevent damages and dropping on land and sea.

Typhoon Attack on Decontamination Containment

6.11.8           In order to prevent water retention on the site (in particular, during decontamination of ACM), all storm and surface water drains, ditches and out-falls will be regularly checked and if necessary cleared of debris, soil and litter. Frequency of checking and clearing will increase during the typically wet months (June to August). Additionally, the drains, ditches and out-falls will be checked when heavy rainfall events are forecasted (including when an Amber Rainstorm Warning is hoisted) to confirm that these surface water management features are not obstructed.

6.11.9           After intense rainfall events such as Red or Black Rainstorm Warning or Typhoons, inspections and necessary actions (such as maintenance or repair of damaged drainage items) will be carried out.

6.11.10       The transportation of ACM / DCM will cease when warnings for a Black rainstorm and/or Typhoon signal No. 8 are given.

6.11.11       When warnings for a Black rainstorm and/or Typhoon signal No. 8 are given, the Contractor shall:

·         Stop all processes which may result in the production of ACM / DCM dust;

·         Spray all surfaces and debris within the ACM / DCM removal work area with amended water in a fine mist spray, using airless spray equipment;

·         Bag all loose ACM / DCM debris present in the ACM / DCM removal work area and remove to a secure store.  Wipe clean and vacuum all surfaces;

·         Cut off all power and water supplies and secure all loose equipment against typhoon damage;

·         Arrange a revised inspection by the Site Agent and Site Engineer before the workers leave Site;

·         Recommence the ACM / DCM removal works once the No. 8 typhoon signal has been lowered, the necessary cleaning up work and repairs to containment have been completed and permission has been given by the Site Engineer.

6.11.12       If during the course of abatement work, a worker collapses or some other accidents occur, the victim should follow normal decontamination procedures with assistance from fellow workers before exiting the work area. For life-threatening situation, however, decontamination should take a lower priority and every effort should be made to ensure the victim receives immediate medical treatment. Any area contaminated during the emergency should be thoroughly cleaned by wet wiping and HEPA vacuuming at the earliest opportunity, and verified by the registered asbestos supervisor and approved by the registered asbestos consultant before work is allowed to continue. 

6.11.13       In addition, the construction of containment is governed by the “Code of Practice on Asbestos Control, Asbestos Work Using Full Containment or Mini Containment Method”, Section 6 – Construction of Containment. Under which, the registered asbestos consultant is also responsible for the structural safety of the containment, and for the provision of safe means of access as well as alternative escape route for emergency situations. Sections extracted from the “Code of Practice on Asbestos Control, Asbestos Work Using Full Containment or Mini Containment Method” with regard to the construction, maintenance and emergency procedures for use of the containment approach are included in Annex V of Appendix D for reference.

Overflow of Contaminated Surface Run-off Due to Heavy Rain Storm Attack

6.11.14       As mention in Section 6.9.5, in order to prevent water retention on the site, all storm and surface water drains, ditches and out-falls will be regularly checked and if necessary cleared of debris, soil and litter. Owing to the nature of the Project, removal of ACM / DCM, solidification pilot test, and the actual cement solidification process shall be carried out under “full containment” approach.

6.11.15       Treatment and storage for the ACM / DCM removed shall strictly follow the Asbestos Abatement Report (Appendix 25 to the PS). As such, none of the removed ACM / DCM will be exposed to the surface run-off due to heavy rain storm in its untreated stated, overflow of contaminated surfaces of the ACM / DCM is not anticipated.

On-site Traffic Accident

6.11.16       On-site traffic accident will be minimised by speed control limit for all vehicle to 5 km/hr. In additional, all storage area of ACM / DCM shall form within a fenced / protected area and/or are inside existing buildings of the project site.          

6.11.17       All vehicles shall only be driven by personnel who have been trained in the Emergency Response Procedure and hold a valid Hong Kong driving licence for the class of vehicle operated.

Power Failure during ACM / DCM Decontamination

6.11.18       In the event of loss of power, back-up power will be available from portable generators. These units are readily available in the event of a disruption to the power supply.

6.11.19       Appropriate back-up facilities will be supplied in order to ensure the effective operation of the site and associated ACM / DCM decontamination containment when the standard facilities are out of action due to power failure.

6.12               Post-Emergency Procedures

6.12.1           An investigation will be carried out immediately after incident occurred. It aims to find out the causes of such incident. Base on this information, adequate preventive measures as well as toolbox training to relevant staffs will be provided in order to minimize the probability of recurrence. A post-mortem report of emergency incident including mitigation and preventive measures shall be submitted to the authorities.


7                        Training

7.1.1              The Contractor shall arrange and provide training on waste management in the site-specific induction and its refresher training for all employee and subcontractors involved in the works.  The content of the training will include the following:

·         Concepts of Site cleanliness.

·         The steps/requirements of the WMP stipulated in the Contract.

·         Classification of different waste types in accordance with the WMP.

·         Proper segregation, handling and storage of different types of waste in accordance with the WMP.

·         Procedures and measures for waste minimisation, reuse and recycling.

·         Locations of designated storage areas for different waste types in accordance with the WMP.

·         Handling of the ACM / DCM, including the appropriate PPE requirements.

·         Procedures for handling ACM / DCM; and

·         Emergency Response Procedure and mitigation measures.

7.1.2              An auditable record will be maintained for all environmental training undertaken.


APPENDICES

 

 

List of Appendices

Appendix A1  Figure 1-1         Location Plan of the Project Site

Appendix A2  Figure 4-1         Location of Temporary Storage Area

Appendix A3  Figure 4-2         Transportation Route for Different Type of Waste

Appendix A4  Figure 4-3         Dioxin Sampling Locations at Ash Bunker

Appendix B1   Master Works Programme

Appendix B2   General Demolition Procedure

Appendix C    Project Organization Chart

Appendix D    Generic Method Statement and Work Sequence of ACM Removal

Appendix E     Memo from Mines Division of CEDD for the use of TKO Area 137 Pier

Appendix F     Methodology of TCLP Test

Appendix G1   Waste Disposal Delivery Schedule to Landfill Site

Appendix G2   Yearly Summary Waste Flow Table

Appendix G3   Monthly Summary Waste Flow Table

Appendix H    Site Management Plan for Trip-ticket System


 

Appendix A

 

Figure 1-1                                    Location Plan of the Project Site

Figure 4-1                             Location of Temporary Storage Area

Figure 4-2     Transportation Route for Different Type of Waste

Figure 4-3                 Dioxin Sampling Locations at Ash Bunker


Appendix B

 

B1 – Master Construction Programme

 

B2 – General Demolition Procedure
Appendix C

 

Project Organization Chart


 


 


Appendix D

 

Generic Method Statement and

Work Sequence of ACM Removal

 

 


Appendix E

 

 Memo from Mines Division of CEDD for

the Use of TKO Area 137 Pier


Appendix F

 

F1 –      Flow Diagram of Cement Solidification

F2 –                            Methodology of TCLP Test


 

Appendix G

 

G1 – Waste Disposal Delivery Scheulde to Landfill Site

G2 – Yearly Summary Waste Flow Table

G3 – Monthly Summary Waste Flow Table


 

 

Appendix H

 

Site Management Plan for Trip-ticket System

 

 

 

List of Appendices of Appendix H

Appendix 1     Management Structure for TTS

Appendix 2     Yearly Summary Waste Flow Table

Appendix 3     Monthly Summary Waste Flow Table

Appendix 4     Site procedure s to ensure each truckload of C&D material leaving the Site will bear a duly completed DDF

Appendix 5     Proposed Mechanism to ensure timely retrieval of DDF

Appendix 6     Register of the DDF issued

Appendix 7     Control Measures to track internal movement of materials

Appendix 8     Sample Format of the Construction and Demolition Material Disposal Delivery Form

Appendix 9    Works Execution Plan by Chun Ming Machinery Engineering Ltd. for Chun Ming Vessel No. 23, 33, 68, 78

Appendix 10   Written Instruction to Barge Operator & Truck Drivers

Appendix 11   Site Layout Plan Showing Outlets