Improvements to
San Tin Interchange (Contract No. HY/2004/09)
Monthly
Environmental Monitoring & Audit Report
Report No. 1528
August September 2007
TABLE OF CONTENTS
1.1 Works undertaken during the Reporting Period
1.2 Environmental Permit and Licences
1.3 Environmental
Document Submissions to EPD
1.4 Environmental
Monitoring Locations
2 Environmental Measures and Implementation Status
3.3 Landscape and
Visual Resources
3.4 Ad-hoc Air
Quality Monitoring
4.3 Environmental
Non-compliance
4.4 Environmental Complaint and Prosecution
5.1 Key Issues for the Coming Months
5.2 Monitoring Schedules for the Next Month
List of Annexes
Annex A Contractor’s Works Programme
Annex B Mitigation Measures Checklist
Annex C Calibration Certificates
Annex D Noise Monitoring Results
Annex E Water Quality Visual Inspection Reports
Annex F Landscape & Visual Resources Inspection Reports
Annex G Weekly Site Inspection Reports
and
Non-Compliance FormsAnnex H Action
and Limit Levels
Annex I Cumulative Statistics on Complaints, Notifications of Summons and Successful Prosecutions
List
of Tables
Table 1.1 Details of Permits and Licenses issued in September 2007
Table 1.2 Summary of Environmental Submissions to EPD in September 2007
Table 1.3 Noise Monitoring Stations
Table 3.1 Summary of Noise Monitoring Results during Normal Working Hours
Table 3.2 Summary of Waste Disposal for September 2007
Table 5.1 Proposed Noise Monitoring Schedule for October 2007
List
of Figures
Figure 1 Site Plan & Locations of Noise and Air Quality Monitoring Stations
Executive Summary
Atkins
China Limited (ACL) has been appointed by Chun Wo Construction &
Engineering Co., Ltd. to implement the Environmental Monitoring and Audit
(EM&A) programme for the construction works under Contract No. HY/2004/09
Improvements to San Tin Interchange (hereinafter, the Project).
The
construction of the Project commenced since 21st June 2005. This report is the fourteenth fiftwenty
eighth monthly
EM&A report for the Project which summarises the monitoring results and
audit findings during the reporting period from 1st September 2007
to 330th
1st AugustSeptember
2007.
Environmental
Monitoring and Audit Progress
The
monthly EM&A programme was undertaken in accordance with the EM&A Manual. A summary of the monitoring activities
in this reporting period is listed below:
·
Weekly
site inspections were undertaken jointly with the Contractor and Engineer’s
Representative (ER) on 50th,
12th, 19th and 25th SeptemberAugust
2007. The Independent Environmental Checker (IEC) joined the site
inspection on 25th September 2007.
·
Noise
monitoring at three designated monitoring stations was undertaken on 3rd1st,
10th, 181th, 24th 17th, 23rdand
30th 28th
August
September
2007 during normal working hours. Also, o One ad-hoc monitoring was
undertaken on 12th August 2006 in response to
following
an exceedance of lLimit lLevel recorded on 11th August
2006.
·
Visual
site surveillance for water quality was undertaken three times a week.
·
Site
inspections for landscape and visual resources were undertaken on 148th and 30288th
August September 2007.
Breaches
of Action and Limit Levels
There was seven no environmental
exceedance recorded during this the reporting period, of which six were recorded
during reporting period.
Environmental
Non-Compliance
No environmental non-compliances were received during this reporting period.
There was
one The environmental
exceedance recorded during and one
non-compliance regarding to the normal working hours noise monitoring was due to
the measured Leq (30min) at on Monitoring Station CM1
was found to exceeding the Limit Level of
75dB(A), which was not in compliance with the requirements mentioned in EIA
Report and EM&A Manual. During the measurement period, concrete breaking
using a breaker was being undertaken at the Slip Road
A works area at side of San Tin Highway. The Contractor was advised to stop the
concrete breaking works in the concerned area immediately to avoid further
exceedances. Following the Event and Action Plan for
construction noise, additional noise measurement was conducted on the following
day (12th August 2006) during which no concrete breaking activity
was being undertaken. The measured Leq (30min) noise level was found to be
67dB(A). Thus, the Contractor was advised to provide mitigation measures as necessary such as and
reminded that movable noise barriers should be provided to avoid exceedances caused
by prior to any further site concrete breaking works in
the concerned area following the recommendations in Section 3.47 and Figure 3.5
of the Project EIA Report. Further to discussion with the Contractor, no
further concrete breaking activities will be required in the concerned area.
Following the Event and Action Plan for construction noise, additional noise
measurement was conducted on the following day (12th August
2006) in which no concrete breaking activity was being undertaken. The measured
Leq (30min) noise level was found to be 67dB(A).
Complaint
Log
No
environmental complaints were received during this reporting period.
Notifications
of Summons and Prosecutions
There
were no notifications of summons or prosecutions received during this reporting
period.
Reporting
Changes
This
report has been developed in compliance with the reporting requirements for the
subsequent monthly EM&A reports as required by the Project EM&A Manual.
Future
Key Issues
The
key issues with respect to the works in the forthcoming 2 months include:
· Laying of drainage pipes;
· Road widening works;
· Trench works;
· Landscaping works;
· Road paving; and
· Installation
of railings.
1.1
Works undertaken during the Reporting
Period
The
major construction activities undertaken during this reporting period are
summarised below:
·
Bored piling;
·
Laying
of drainage pipes;
· Road widening works;
· Trench works;
· Landscaping works;
· Road paving; and
·
Installation of railings.
The
site plan of the Project is shown in Figure 1. The Contractor’s works programme is provided in Annex A.
1.2
Environmental Permit and Licences
There were no changes or clarification to the Environmental Permit (EP-190/2004) during the reporting period.
Seven One Construction Noise
Permits (CNP) was issued in September 2007. Details of the CNPs are summarised in Table 1.1. One
CNP (Permit No. PP-RN0026-06)
for carrying out percussive piling works from 15th August 2006 to 13th November 2006 was issued on 31st July 2006 and
received by the Contractor in August 2006.
Table 1.1 Details of Permits and Licenses issued in August September 2007
Permit
/ License |
Reference No. |
Issue Date |
Expiry Date |
CNP for general construction work |
GW-RN0407-07 |
21st
September 2007 |
24th
November 2007 |
1.3
Environmental
Document Submissions to EPD
A
summary of the status of the submissions to EPD as provided during the month of
August
September
2007 is presented in Table 1.2.
Table 1.2 Summary of Environmental Submissions to EPD in August September 2007
Item No. |
Document
Title |
Date of Submission |
1 |
Monthly
EM&A Report No. 27 for August 2007 |
13th September 2007 |
1.4
Environmental Monitoring Locations
Noise monitoring was undertaken at three monitoring stations CM1, CM2 and CM3. The locations are shown on Figure 1. Description of these monitoring stations is provided in Table 1.3.
Table 1.3 Noise Monitoring Stations
Monitoring
Station ID |
Description |
Easting |
Northing |
CM1 |
Village house near San Tin
Highway |
826133 |
839839 |
CM2 |
Village house near San Tin
Highway |
826291 |
839918 |
CM3 |
Village house near Kwu Tung
Road |
826605 |
840076 |
The
mitigation measures listed in the Project EIA Report, EM&A Manual and
Environmental Permit and the implementation status are provided in Annex B.
In this reporting
period, tree planting at the slope of Fanling Highway near the South Division,
as part of the landscape works was commenced.
Based on site inspection findings, the
Contractor has implemented the required mitigation measures during construction works to date in general.
3.1.1 Noise Monitoring Equipment
Details
of the noise monitoring equipment are listed below and the calibration
certificates are presented in Annex C:
· Sound level meter ONO-SOKKI LA-5110
· Acoustical calibrator ONO-SOKKI SC-2110
· Hand-held anemometer
3.1.2 Noise Monitoring Methodology
The
sound level meter was calibrated with an acoustical calibrator prior to each
measurement. It was set on a
tripod at 1.2 m above local ground level at the monitoring station. Measurement of the A-weighted Leq(30
minutes) noise level for normal daytime hours was undertaken. Three consecutive A-weighted Leq(5
minutes) noise levels were measured for restricted hours monitoring. Wind speed was checked during the
monitoring period using the hand-held anemometer to ensure steady wind speed
did not exceed 5 m/s, or gusts did not exceed 10 m/s. After the noise measurement the sound level meter was
re-calibrated using the acoustical calibrator.
3.1.3 Noise Monitoring Results
Noise monitoring was
undertaken on a weekly basis when noise generating activities were
underway. The noise monitoring
results obtained in August September 2007, during the
normal working hours and restricted hours from 2300 to 0700 hours of
next day are summarised in Table 3.13. No noise monitoring was carried out
during the restricted hours as there were no construction activities during these
time periods.
There was were no environmental
exceedances of the Actione and Limit Levels for environmental exceedance of
the Action and Limit Levels for noise monitoring recorded during
the normal daytime hours within the reporting period.and
Details of the monitoring time period and weather condition during the monitoring period and the graphical presentation of the noise monitoring results are provided in Annex D.
Table 3.1 Summary of Noise Monitoring Results during Normal Working Hours
Date
of Monitoring |
Normal Hours. Noise Monitoring
Results Leq(30 minutes) dB(A) |
||
CM1 |
CM2 |
CM3 |
|
3rd September 2007 |
65 |
73 |
55 |
10th September 2007 |
65 |
73 |
57 |
18th September 2007 |
63 |
73 |
56 |
24th September 2007 |
63 |
- |
- |
28th September 2007 |
- |
73 |
57 |
Remark:
(1) CM2
is a non-façade measurement location.
A positive correction of 3dB(A) has been applied to the measured noise
level at CM2 according to EPD’s guideline.
(2)
Noise monitoring at CM2 and CM3 was cancelled on 24th
September 2007 due to raining condition and re-scheduled on 28th
September 2007.
|
|
||
|
|
|
|
|
|
|
|
|
|
|
|
(1)
CM2 is a non-façade measurement location. A
positive correction of 3dB(A) has been applied to the measured noise level at
CM2 according to EPD’s guideline.
(1)
Underlined figure indicates exceedance of the Limit
Level of 50dB(A).
(1)
Time of
measurement at CM3 started after 23:59 hours (midnight) of Tthe “Date of
Monitoring” stated in the table. Therefore, the “Date of Monitoring” for CM3 refers to 18th and 1st September 2006,
respectively refers to the date of which nighttime noise monitoring
started.
Visual site surveillances for water quality were undertaken three times a week. Based on the visual inspection results, the Contractor has followed all necessary site practices for the maintenance of the site drainage system, including:
· removal of stagnant water pools;
· reconnecting the pipe (connected to pump) to the sedimentation tank immediately after the temporary works;
· removal of litters and deposited silts in the U-channel;
The details of the water quality visual inspection
reports are provided in Annex E.
3.3
Landscape and
Visual Resources
Two site inspections on the
landscape and visual resources were undertaken in August September 2007.
During the inspections,
defective tree identification labels were found in both N1 and N2 Divisions.
The Contractor was reminded again to replace them. Overgrown weeds were found
inside the transplantation nurseries in both N1 and N2 Divisions. The
Contractor was reminded to remove the weeds regularly as proper maintenance. Also, the Contractor was reminded to
straighten up the leaning trees found inside transplantation nursery in N2
Division during the previous month and provide support for the tree
trunks. Tree planting was commenced
at the slope of Fanling Highway near the South Division.
Sandbags barrier encircling
the transplantation nursery in the N1 Division area was seen to have been
damaged. Some construction materials were seen to have accumulated on top of
the soil surface inside the nursery. The Contractor was reminded to clear up
the construction materials and place them in an appropriate storage area.
Damaged sandbags should be replaced by new ones to contain the soil
inside the nursery and prevent soil erosion.
Several trees inside the transplantation nursery in
the N2 Division aArea were
found to have fallen down during the inspection on 15th September 2006 due to the
typhoon event in early August 2006 and mid-September 2006. The
Contractor was reminded to replant these trees in the nursery to ensure their
survival. The fallen
trees were observed to have been
replanted during inspection on 27th September 2006.
The details of the landscape
and visual resources inspection reports are provided in Annex F.
3.4
Ad-hoc Air
Quality Monitoring
No ad-hoc air
quality monitoring was required during the reporting period.
The Contractor has
adopted a trip ticket system for the disposal of construction wastes. According to the records provided by
the Contractor, the disposal of construction waste within the reporting period
is summarised in Table 3.3Table 3.4Table 3.4Table 3.2.
Table 3.3442 Summary of Waste Disposal for SeptemberAugust 2007
Waste Type |
Destination |
No.
of Trips |
Quantity |
C&D Waste |
NENT Landfill |
19 |
95 m3 |
C&D Waste |
WENT Landfill |
5 |
25 m3 |
Building debris |
CEDD’s Tuen Mun
Area 38 Fill Bank |
421 |
2,105 m3 |
Sewage Holding
Tank Waste |
Collected by
Waylung Waste Services Ltd. |
13 |
- |
Site inspections were undertaken
on 50th,
12th, 19th and 25th SeptemberAugust
2007. The Independent
Environmental Checker (IEC) undertook the site inspection on 25th September 2007.
Specific locations within the site were
identified during the inspection for improvements in proper implementation of
the environmental mitigation measures.
These include:
· Replacement of damaged tarpaulin sheet to cover stockpile of soil and exposed slope surface to prevent dust emissions and soil being washed down by rain;
· Removal of the stagnant water pool to prevent mosquito breeding;
· Removal of the litters in the U-channel and maintain the drainage system properly.
· Well coverage of idle containers to prevent accumulation of stagnant water
· Removal of an oil leaking filter, and disposal of the contaminated soil as chemical waste with proper procedures.
The
record of the weekly site inspection findings is provided in Annex G.
4.2
Environmental Exceedance
There was seven no
record of environmental
exceedance during this reporting period.
The
Action and Limit Levels for impact monitoring are provided in Annex H.
4.3
Environmental
Non-compliance
During
the reporting period, no environmental non-compliance was recorded.
4.4
Environmental Complaint and Prosecution
During
the reporting period, no environmental complaints, prosecutions or summons were
received. Cumulative statistics on complaints,
notifications of summons and successful prosecutions for the Project are
provided in Annex I.
5.1
Key Issues for the Coming Months
The
key issues with respect to the works in the forthcoming 2 months include:
· Road widening works;
· Trench works;
· Landscaping works;
· Road paving; and
·
Installation of railings.
5.2
Monitoring Schedules for the Next
Month
The
proposed schedule for noise monitoring in September October 2007 is provided in Table 5.1.
Table 5.1 Proposed Noise Monitoring Schedule for September
October 2007
Date |
Noise
Monitoring Station |
4th
|
CM1, CM2 and CM3 |
9th
October 2007 (Tuesday) |
CM1, CM2 and CM3 |
15th
October 2007 (Monday) |
CM1, CM2 and CM3 |
|
CM1, CM2 and CM3 |
30th
October 2007 (Tuesday) |
CM1, CM2 and CM3 |
There
was no environmental non-compliance attributable to the Project works during
reporting period.
There
was six
no exceedance
recorded during the reporting period.
There was one exceedance
non-compliance
of the Limit Level recorded during the normal hours
noise monitoring due to concrete breaking activities in project works area
during the reporting period.
No
environmental complaints, prosecutions or summons was received during the
reporting period.