Improvements to
San Tin Interchange (Contract No. HY/2004/09)
Monthly
Environmental Monitoring & Audit Report
Report No. 1529
August October 2007
1.1 Works undertaken during the Reporting Period
1.2 Environmental Permit and Licences
1.3 Environmental
Document Submissions to EPD
1.4 Environmental
Monitoring Locations
2 Environmental Measures and Implementation Status
3.3 Landscape and
Visual Resources
3.4 Ad-hoc Air
Quality Monitoring
4.3 Environmental
Non-compliance
4.4 Environmental Complaint and Prosecution
5.1 Key Issues for the Coming Months
5.2 Monitoring Schedules for the Next Month
List of Annexes
Annex A Contractor’s Works Programme
Annex B Mitigation Measures Checklist
Annex C Calibration Certificates
Annex D Noise Monitoring Results
Annex E Water Quality Visual Inspection Reports
Annex F Landscape & Visual Resources Inspection Reports
Annex G Weekly Site Inspection Reports
and
Non-Compliance FormsAnnex H Action
and Limit Levels
Annex I Cumulative Statistics on Complaints, Notifications of Summons and Successful Prosecutions
List
of Tables
Table 1.1 Details of Permits and Licenses issued in October 2007
Table 1.2 Summary of Environmental Submissions to EPD in October 2007
Table 1.3 Noise Monitoring Stations
Table 3.1 Summary of Noise Monitoring Results during Normal Working Hours
Table 3.2 Summary of Waste Disposal for October 2007
Table 5.1 Proposed Noise Monitoring Schedule for November 2007
List
of Figures
Figure 1 Site Plan & Locations of Noise and Air Quality Monitoring Stations
Executive Summary
Atkins
China Limited (ACL) has been appointed by Chun Wo Construction &
Engineering Co., Ltd. to implement the Environmental Monitoring and Audit
(EM&A) programme for the construction works under Contract No. HY/2004/09
Improvements to San Tin Interchange (hereinafter, the Project).
The
construction of the Project commenced since 21st June 2005. This report is the fourteenth fiftwenty
ninth monthly
EM&A report for the Project which summarises the monitoring results and audit
findings during the reporting period from 1st October 2007 to 331st
1st AugustOctober
2007.
Environmental
Monitoring and Audit Progress
The
monthly EM&A programme was undertaken in accordance with the EM&A Manual. A summary of the monitoring activities
in this reporting period is listed below:
·
Weekly
site inspections were undertaken jointly with the Contractor and Engineer’s
Representative (ER) on 3rd, 10th, 17th, 24th and 31st
OctoberAugust 2007. The Independent
Environmental Checker (IEC) undertook the site inspection on 24th October 2007.
·
Noise
monitoring at three designated monitoring stations was undertaken on 4th1st,
5th, 9th, 151th, 22nd 17th, 23rdand
30th 30th
August
October 2007
during normal working hours. Also, o One ad-hoc
monitoring was undertaken on 12th August
2006 in response to following an exceedance of lLimit lLevel recorded on 11th August
2006.
·
Visual
site surveillance for water quality was undertaken three times a week.
·
Site
inspections for landscape and visual resources were undertaken on 178th and 3031st
August October 2007.
Breaches
of Action and Limit Levels
There was seven no environmental
exceedance recorded during this the reporting period, of which six were recorded
during reporting period.
Environmental
Non-Compliance
No environmental non-compliances were received during this reporting period.
There was
one The environmental
exceedance recorded during and one
non-compliance regarding to the normal working hours noise monitoring was due to
the measured Leq (30min) at on Monitoring Station CM1
was found to exceeding the Limit Level of
75dB(A), which was not in compliance with the requirements mentioned in EIA
Report and EM&A Manual. During the measurement period, concrete breaking
using a breaker was being undertaken at the Slip Road
A works area at side of San Tin Highway. The Contractor was advised to stop the
concrete breaking works in the concerned area immediately to avoid further
exceedances. Following the Event and Action Plan for
construction noise, additional noise measurement was conducted on the following
day (12th August 2006) during which no concrete breaking activity
was being undertaken. The measured Leq (30min) noise level was found to be
67dB(A). Thus, the Contractor was advised to provide mitigation measures as necessary such as and
reminded that movable noise barriers should be provided to avoid exceedances caused
by prior to any further site concrete breaking works in
the concerned area following the recommendations in Section 3.47 and Figure 3.5
of the Project EIA Report. Further to discussion with the Contractor, no
further concrete breaking activities will be required in the concerned area.
Following the Event and Action Plan for construction noise, additional noise
measurement was conducted on the following day (12th August
2006) in which no concrete breaking activity was being undertaken. The measured
Leq (30min) noise level was found to be 67dB(A).
Complaint
Log
No
environmental complaints were received during this reporting period.
Notifications
of Summons and Prosecutions
There
were no notifications of summons or prosecutions received during this reporting
period.
Reporting
Changes
This
report has been developed in compliance with the reporting requirements for the
subsequent monthly EM&A reports as required by the Project EM&A Manual.
Future
Key Issues
The key issues with respect to
the works in the forthcoming 2 months include:
· Road widening works;
· Landscaping works;
· Road paving; and
· Installation of railings.
1.1
Works undertaken during the Reporting
Period
The
major construction activities undertaken during this reporting period are
summarised below:
·
Bored piling;
·
Laying
of drainage pipes;
· Road widening works;
· Trench works;
· Landscaping works;
· Road paving; and
·
Installation of railings.
The
site plan of the Project is shown in Figure 1. The Contractor’s works programme is provided in Annex A.
1.2
Environmental Permit and Licences
There were no changes or clarification to the Environmental Permit (EP-190/2004) during the reporting period.
Seven One Construction Noise
Permits (CNP) was issued in October 2007.
Details of the CNPs are summarised in Table
1.1. One
CNP (Permit No. PP-RN0026-06)
for carrying out percussive piling works from 15th August 2006 to 13th November 2006 was issued on 31st July 2006 and
received by the Contractor in August 2006.
Table 1.1 Details of Permits and Licenses issued in August October 2007
Permit
/ License |
Reference No. |
Issue Date |
Expiry Date |
CNP for general construction work |
11th
October 2007 |
7th
January 2008 |
Seven One CNP (Permit
No. PP-RN0026-06) for carrying out percussive piling works from 15th August 2006 to 13th November 2006 was issued on 31st July 2006 and
received by the Contractor in August 2006.
1.3
Environmental
Document Submissions to EPD
A
summary of the status of the submissions to EPD as provided during the month of
August
October 2007
is presented in Table 1.2.
Table 1.2 Summary of Environmental Submissions to EPD in August October 2007
Item No. |
Document
Title |
Date of Submission |
1 |
Monthly
EM&A Report No. 28 for September 2007 |
12th October 2007 |
2 |
Certification
Sheet No. 047 - Reduced EM&A Frequency |
25th October 2007 |
1.4
Environmental Monitoring Locations
Noise monitoring was undertaken at three monitoring stations CM1, CM2 and CM3. The locations are shown on Figure 1. Description of these monitoring stations is provided in Table 1.3.
Table 1.3 Noise Monitoring Stations
Monitoring
Station ID |
Description |
Easting |
Northing |
CM1 |
Village house near San Tin
Highway |
826133 |
839839 |
CM2 |
Village house near San Tin
Highway |
826291 |
839918 |
CM3 |
Village house near Kwu Tung
Road |
826605 |
840076 |
The
mitigation measures listed in the Project EIA Report, EM&A Manual and
Environmental Permit and the implementation status are provided in Annex B.
In
this reporting period, tree planting at South Division (M6 and M2 works area)
was commenced.
Based on site inspection findings, the
Contractor has implemented the required mitigation measures during construction works to date in general.
3.1.1 Noise Monitoring Equipment
Details
of the noise monitoring equipment are listed below and the calibration
certificates are presented in Annex C:
· Sound level meter ONO-SOKKI LA-5110
· Acoustical calibrator ONO-SOKKI SC-2110
· Hand-held anemometer
3.1.2 Noise Monitoring Methodology
The
sound level meter was calibrated with an acoustical calibrator prior to each
measurement. It was set on a
tripod at 1.2 m above local ground level at the monitoring station. Measurement of the A-weighted Leq(30
minutes) noise level for normal daytime hours was undertaken. Three consecutive A-weighted Leq(5
minutes) noise levels were measured for restricted hours monitoring. Wind speed was checked during the
monitoring period using the hand-held anemometer to ensure steady wind speed
did not exceed 5 m/s, or gusts did not exceed 10 m/s. After the noise measurement the sound level meter was
re-calibrated using the acoustical calibrator.
3.1.3 Noise Monitoring Results
Noise monitoring was
undertaken on a weekly basis when noise generating activities were
underway. On 4th
October 2007, the noise monitoring was carried out at CM1 and CM2 only and
cancelled at CM3 due to scattered shower. Noise Monitoring at CM3 was
rearranged on 5th October 2007. The noise monitoring results obtained in August October 2007, during the
normal working hours and restricted hours from 2300 to 0700 hours of
next day are summarised in Table 3.1. No noise monitoring was carried out during the restricted
hours as there were no construction activities during these time periods
according to the Contractor’s information.
There was were no environmental exceedances of the Actione and Limit Levels for environmental exceedance of
the Action and Limit Levels for noise monitoring recorded during
the normal daytime hours within the reporting period.and
Details of the monitoring time period and weather condition during the monitoring period and the graphical presentation of the noise monitoring results are provided in Annex D.
Table 3.1 Summary of Noise Monitoring Results during Normal Working Hours
Date
of Monitoring |
Normal Hours. Noise Monitoring
Results Leq(30 minutes) dB(A) |
||
CM1 |
CM2 |
CM3 |
|
4th October2007 |
65 |
73 |
- |
5th October 2007 |
- |
- |
56 |
9th October 2007 |
64 |
73 |
59 |
15th October 2007 |
65 |
73 |
57 |
22nd October 2007 |
64 |
73 |
57 |
30th October 2007 |
64 |
73 |
55 |
Remark:
(1) CM2
is a non-façade measurement location.
A positive correction of 3dB(A) has been applied to the measured noise
level at CM2 according to EPD’s guideline.
(2) Noise Monitoring at CM3 was rearranged to 5th
October 2007 due to scattered shower on 4th October.
|
|
||
|
|
|
|
|
|
|
|
|
|
|
|
(1)
CM2 is a non-façade measurement location. A
positive correction of 3dB(A) has been applied to the measured noise level at
CM2 according to EPD’s guideline.
(1)
Underlined figure indicates exceedance of the Limit
Level of 50dB(A).
(1)
Time of
measurement at CM3 started after 23:59 hours (midnight) of Tthe “Date of
Monitoring” stated in the table. Therefore, the “Date of Monitoring” for CM3 refers to 18th and 1st September 2006,
respectively refers to the date of which nighttime noise
monitoring started.
Visual site surveillances for water quality were undertaken three times a week. Based on the visual inspection results, the Contractor has followed necessary site practices for the maintenance of the site drainage system, including:
· removal of litters and silts in U-channel;
The details of the water quality visual inspection
reports are provided in Annex E.
3.3
Landscape and
Visual Resources
During the inspections,
defective tree identification labels were found in both N1 and N2
Divisions. The Contractor was
reminded again to replace them. Overgrown weeds were found inside the
transplantation nurseries in N2 Division.
The Contractor was reminded to remove the weeds regularly as proper maintenance. Also, the Contractor was reminded to
provide support for the tree trunk inside transplantation nursery in N2
Division. Temporary protective
fencings for the transplantation nursery in N2 Division were found broken. The contractor was reminded to replace
the broken fencing to properly fence off the transplantation nursery.
Tree planting (at M2 and M6
works areas) and transplantation (near the site office and at M2 and M6 works
areas) have been commenced. 6
newly planted tree at the slope near Fanling Highway in South Division appeared
to be in poor condition. The
contractor was reminded to ensure the condition of planted trees is healthy.
Sandbags barrier encircling
the transplantation nursery in the N1 Division area was seen to have been damaged.
Some construction materials were seen to have accumulated on top of the soil
surface inside the nursery. The Contractor was reminded to clear up the
construction materials and place them in an appropriate storage area. Damaged
sandbags should be replaced by new ones to contain the soil
inside the nursery and prevent soil erosion.
Several trees inside the transplantation nursery in
the N2 Division aArea were
found to have fallen down during the inspection on 15th September 2006 due to the
typhoon event in early August 2006 and mid-September 2006. The
Contractor was reminded to replant these trees in the nursery to ensure their
survival. The fallen
trees were observed to have been
replanted during inspection on 27th September 2006.
The details of the landscape
and visual resources inspection reports are provided in Annex F.
3.4
Ad-hoc Air
Quality Monitoring
No ad-hoc air
quality monitoring was required during the reporting period.
The Contractor has
adopted a trip ticket system for the disposal of construction wastes. According to the records provided by
the Contractor, the disposal of construction waste within the reporting period
is summarised in Table 3.3Table 3.4Table 3.4Table 3.2.
Table 3.3442 Summary of Waste Disposal for OctoberAugust 2007
Waste Type |
Destination |
No.
of Trips |
Quantity |
C&D Waste |
NENT Landfill |
44 |
220 m3 |
C&D Waste |
WENT Landfill |
2 |
10 m3 |
Building debris |
CEDD’s Tuen Mun
Area 38 Fill Bank |
332 |
1,660 m3 |
Sewage Holding
Tank Waste |
Collected by
Waylung Waste Services Ltd. |
13 |
- |
Chemical Waste |
Collected by
Dunwell Enviro-Tech (Holdings) Ltd. |
1 |
1,000 L |
Site inspections were undertaken
on 3rd, 10th, 17th, 24th and 31st
OctoberAugust 2007. The Independent Environmental Checker (IEC) undertook the
site inspection on 24th October 2007. Specific
locations within the site were identified during the inspection for
improvements in proper implementation of the environmental mitigation
measures. These include:
· Removal of stagnant water pool to prevent mosquito breeding.
· Removal of litters in the U-channel as proper maintenance of the site drainage system.
· Removal of litters within the site area.
· Watering regularly in the unpaved works areas.
· Provision of drip trays for temporary storage of lubricant oil cans, and disposal of contaminated soil as chemical waste with proper procedures.
The
record of the weekly site inspection findings is provided in Annex G.
4.2
Environmental Exceedance
During the reporting
period, there was seven no recorded of exceedance during
this reporting period.
The
Action and Limit Levels for impact monitoring are provided in Annex H.
4.3
Environmental
Non-compliance
During
the reporting period, no environmental non-compliance was recorded.
4.4
Environmental Complaint and Prosecution
During
the reporting period, no environmental complaints, prosecutions or summons were
received. Cumulative
statistics on complaints, notifications of summons and successful prosecutions
for the Project are provided in Annex I.
5.1
Key Issues for the Coming Months
The
key issues with respect to the works in the forthcoming 2 months include:
· Landscaping works;
· Road paving; and
·
Installation of railings.
5.2
Monitoring Schedules for the Next
Month
The
construction works have been substantially completed. Accordingly, a reduction in the environmental monitoring and
audit frequency has been proposed.
The updated EM&A programme, which has been certified by the ETL,
reviewed and verified by IEC, and accepted by EPD, is described below:
· Site inspection & audit – twice a month
· Noise monitoring (normal working hour) – twice a month
· Visual site surveillance for water quality – 4 times a month
· Landscape and visual resources site inspection – once a month
The
proposed schedule for noise monitoring in September November 2007 is provided in Table 5.1.
Table 5.1 Proposed Noise Monitoring Schedule for September
November 2007
Date |
Noise
Monitoring Station |
13th
November |
CM1, CM2 and CM3 |
27th
November 2007 (Tuesday) |
CM1, CM2 and CM3 |
There
was no environmental non-compliance attributable to the Project works during
reporting period.
There
was six
no exceedance
recorded during the reporting period.
There was one exceedance
non-compliance
of the Limit Level recorded during the normal hours
noise monitoring due to concrete breaking activities in project works area
during the reporting period.
No
environmental complaints, prosecutions or summons was received during the
reporting period.