Improvements to

San Tin Interchange (Contract No. HY/2004/09)

 

 

Monthly Environmental Monitoring & Audit Report

Report No. 1531

 

 

August December 2007

 

 

 

 

 

 

 

 

 

 

 

 

 

 


 

1            Environmental Status. 1

1.1         Works undertaken during the Reporting Period. 1

1.2         Environmental Permit and Licences. 1

1.3         Environmental Document Submissions to EPD.. 1

1.4         Environmental Monitoring Locations. 1

2            Environmental Measures and Implementation Status. 2

3            Monitoring Results. 2

3.1         Noise Monitoring. 2

3.2         Water Quality Monitoring. 3

3.3         Landscape and Visual Resources. 3

3.4         Ad-hoc Air Quality Monitoring. 3

3.5         Waste Management 3

4            Environmental Audits. 4

4.1         Site Inspection and Audit 4

4.2         Environmental Exceedance. 4

4.3         Environmental Non-compliance. 4

4.4         Environmental Complaint and Prosecution. 4

5            Forecast and Schedule. 4

5.1         Key Issues for the Coming Months. 4

5.2         Monitoring Schedules for the Next Month. 5

6            Conclusion. 5


List of Annexes

Annex A               Contractor’s Works Programme

Annex B               Mitigation Measures Checklist

Annex C               Calibration Certificates

Annex D               Noise Monitoring Results

Annex E               Water Quality Visual Inspection Reports

Annex F               Landscape & Visual Resources Inspection Reports

Annex G               Site Inspection Reports

Annex H               Cumulative Statistics on Complaints, Notifications of Summons and Successful Prosecutions

 

List of Tables

Table 1.1             Details of Permits and Licenses issued in December 2007

Table 1.2             Summary of Environmental Submissions to EPD in December 2007

Table 1.3             Noise Monitoring Stations

Table 3.1             Summary of Noise Monitoring Results during Normal Working Hours

Table 3.2             Summary of Waste Disposal for December 2007

Table 5.1             Proposed Noise Monitoring Schedule for January 2008

 

List of Figures

Figure 1               Site Plan & Locations of Noise and Air Quality Monitoring Stations

 


Executive Summary

Atkins China Limited (ACL) has been appointed by Chun Wo Construction & Engineering Co., Ltd. to implement the Environmental Monitoring and Audit (EM&A) programme for the construction works under Contract No. HY/2004/09 Improvements to San Tin Interchange (hereinafter, the Project).

The construction of the Project commenced since 21st June 2005.  This report is the fourteenth fifthirty-first monthly EM&A report for the Project which summarises the monitoring results and audit findings during the reporting period from 1st to 331st 1st AugustDecember 2007.

Environmental Monitoring and Audit Progress

The monthly EM&A programme was undertaken in accordance with the EM&A Manual.  A summary of the monitoring activities in this reporting period is listed below:

·         Site inspections were undertaken jointly with the Contractor and Engineer’s Representative (ER) on 5th and 19th DecemberAugust 2007.  The Independent Environmental Checker (IEC) undertook the site inspection on 19th DecemberAugust 2007.

·         Noise monitoring at three designated monitoring stations was undertaken on 11th and 28th December 2007 during normal working hours. Also, o  One ad-hoc monitoring was undertaken on 12th August 2006 in response to following an exceedance of lLimit lLevel recorded on 11th August 2006.

·         Visual site surveillance for water quality was undertaken on 5th, 11th, 19th and 28th December 2007.

·         Site inspection for landscape and visual resources was undertaken on 21st December 2007.

Breaches of Action and Limit Levels

There was seven no environmental exceedance recorded during this the reporting period, of which six were recorded during reporting period.

Environmental Non-Compliance

No environmental non-compliances were received during this reporting period.

There was one The environmental exceedance recorded during and one non-compliance regarding to the normal working hours noise monitoring was due to the measured Leq (30min) at on Monitoring Station CM1 was found to exceeding the Limit Level of 75dB(A), which was not in compliance with the requirements mentioned in EIA Report and EM&A Manual. During the measurement period, concrete breaking using a breaker was being undertaken at the Slip Road A works area at side of San Tin Highway. The Contractor was advised to stop the concrete breaking works in the concerned area immediately to avoid further exceedances.  Following the Event and Action Plan for construction noise, additional noise measurement was conducted on the following day (12th August 2006) during which no concrete breaking activity was being undertaken. The measured Leq (30min) noise level was found to be 67dB(A).  Thus, the Contractor was advised to provide mitigation measures as necessary such as and reminded that movable noise barriers should be provided to avoid exceedances caused by prior to any further site concrete breaking works in the concerned area following the recommendations in Section 3.47 and Figure 3.5 of the Project EIA Report. Further to discussion with the Contractor, no further concrete breaking activities will be required in the concerned area. Following the Event and Action Plan for construction noise, additional noise measurement was conducted on the following day (12th August 2006) in which no concrete breaking activity was being undertaken. The measured Leq (30min) noise level was found to be 67dB(A).

Complaint Log

No environmental complaints were received during this reporting period.

Notifications of Summons and Prosecutions

There were no notifications of summons or prosecutions received during this reporting period.

Reporting Changes

This report has been developed in compliance with the reporting requirements for the subsequent monthly EM&A reports as required by the Project EM&A Manual.

Future Key Issues

The key issues with respect to the works in the forthcoming 2 months include landscaping works and road paving.

 


1                     Environmental Status

1.1               Works undertaken during the Reporting Period

The major construction activities undertaken during this reporting period are summarised below:

·      Bored piling;

·      Road widening works;

·      Landscaping works;

·      Road paving; and

·      Installation of railings.

The site plan of the Project is shown in Figure 1.  The Contractor’s works programme is provided in Annex A.

1.2               Environmental Permit and Licences

There were no changes or clarification to the Environmental Permit (EP-190/2004) during the reporting period.

Seven Two Construction Noise Permits (CNP) were issued in December 2007.  Details of the CNPs are summarised in Table 1.1.  One CNP (Permit No. PP-RN0026-06) for carrying out percussive piling works from 15th August 2006 to 13th November 2006 was issued on 31st July 2006 and received by the Contractor in August 2006.

Table 1.1   Details of Permits and Licenses issued in August December 2007

Permit / License

Reference No.

Issue Date

Expiry Date

CNP for general construction work

GW-RN0524-07

7th December 2007

12th March 2008

CNP for Erection of Sign Gantry

GW-RN0546-07

24th December 2007

7th April 2008

 

Construction Noise Permit for general construction work

GW-RN0427-06

22nd August 2006

3rd March 2007

Construction Noise Permit for general construction work

GW-RN0428-06

23rd August 2006

10th March 2007

Construction Noise Permit for general construction work

GW-RN0431-06

24th August 2006

7th September 2006

Construction Noise Permit for general construction work

GW-RN0435-06

29th August 2006

30th September 2006

Construction Noise Permit for general construction work

GW-RN0436-06

29th August 2006

11th October 2006

 

1.3               Environmental Document Submissions to EPD

A summary of the status of the submissions to EPD as provided during the month of August December 2007 is presented in Table 1.2.

 

Table 1.2   Summary of Environmental Submissions to EPD in August December 2007

Item No.

Document Title

Date of Submission

1

Monthly EM&A Report No. 30 for November 2007

14th December 2007

2

Quarterly EM&A Summary Report No. 10 (September 2007 to November 2007)

19th December 2007

1.4               Environmental Monitoring Locations

Noise monitoring was undertaken at three monitoring stations CM1, CM2 and CM3. The locations are shown on Figure 1.  Description of these monitoring stations is provided in Table 1.3.

 

Table 1.3   Noise Monitoring Stations

Monitoring Station ID

Description

Easting

Northing

CM1

Village house near San Tin Highway

826133

839839

CM2

Village house near San Tin Highway

826291

839918

CM3

Village house near Kwu Tung Road

826605

840076

 

2                     Environmental Measures and Implementation Status

The mitigation measures listed in the Project EIA Report, EM&A Manual and Environmental Permit and the implementation status are provided in Annex B.

In this reporting period, the trees planting were progressing at the area in South Division (M6 and M2 works area).  Landscape works were progressing at the N1 Division (near the site office) and South Division (M6 and M2 works area).

Based on site inspection findings, the Contractor has implemented the required mitigation measures during construction works to date in general.

3                     Monitoring Results

3.1               Noise Monitoring

3.1.1        Noise Monitoring Equipment

Details of the noise monitoring equipment are listed below and the calibration certificates are presented in Annex C:

·      Sound level meter ONO-SOKKI LA-5110

·      Acoustical calibrator ONO-SOKKI SC-2110

·      Hand-held anemometer

3.1.2        Noise Monitoring Methodology

The sound level meter was calibrated with an acoustical calibrator prior to each measurement.  It was set on a tripod at 1.2 m above local ground level at the monitoring station.  Measurement of the A-weighted Leq(30 minutes) noise level for normal daytime hours was undertaken.  Three consecutive A-weighted Leq(5 minutes) noise levels were measured for restricted hours monitoring.  Wind speed was checked during the monitoring period using the hand-held anemometer to ensure steady wind speed did not exceed 5 m/s, or gusts did not exceed 10 m/s.  After the noise measurement the sound level meter was re-calibrated using the acoustical calibrator.

3.1.3        Noise Monitoring Results

Noise monitoring was undertaken on a biweekly basis when noise generating activities were underway.  The noise monitoring results obtained in August December 2007, during the normal working hours and restricted hours from 2300 to 0700 hours of next day are summarised in Table 3.1.  No noise monitoring was carried out during the restricted hours as there were no construction activities during these time periods.

 

There was were no environmental exceedances of the Actione and Limit  Levels for environmental exceedance of the Action and Limit Levels for noise monitoring recorded during the normal daytime hours within the reporting period.and  

Details of the monitoring time period and weather condition during the monitoring period and the graphical presentation of the noise monitoring results are provided in Annex D.

Table 3.1   Summary of Noise Monitoring Results during Normal Working Hours

Date of Monitoring

Normal Hours Noise Monitoring Results Leq(30 minutes) dB(A)

CM1

CM2

CM3

11th December 2007

64

73

58

28th December 2007

64

74

56

Remark:   

(1)     CM2 is a non-façade measurement location.  A positive correction of 3 dB(A) has been applied to the measured noise level at CM2 according to EPD’s guideline.

 

 

 

 

 

 

Date of Monitoring

Restricted Hours Noise Monitoring Results Leq(15 minutes) dB(A)

CM1

CM2

CM3

17th August 2006

65

69

59

(18th August 2006)

31st August 2006

65

6970

5955

(1st September 2006)

 

Remark:       

(1)               CM2 is a non-façade measurement location. A positive correction of 3dB(A) has been applied to the measured noise level at CM2 according to EPD’s guideline.

(1)               Underlined figure indicates exceedance of the Limit Level of 50dB(A).

(1)               Time of measurement at CM3 started after 23:59 hours (midnight) of Tthe Date of Monitoring” stated in the table.  Therefore, the “Date of Monitoring” for CM3 refers to 18th  and 1st   September 2006, respectively refers to the date of which nighttime noise monitoring started.

3.2               Water Quality Monitoring

Visual site surveillances for water quality were undertaken on 5th, 11th, 19th and 28th December 2007.  Based on the visual inspection results, the Contractor has followed all necessary site practices for the maintenance of the site drainage system, included:

·       removal of debris at the existing outfall near M6 to maintain water free flow.

The details of the water quality visual inspection reports are provided in Annex E.

3.3               Landscape and Visual Resources

One site inspection on the landscape and visual resources was undertaken in August December 2007.

During the inspections, transplanted trees at N1 Division (near the site office) and South Division (near M2 and M6 works area) were found to be in poor condition.  The contractor is reminded to closely monitor these trees (with regular watering) to ensure their survival.  Trees planting were progressing in N1 Division and South Division (M2 and M6 works areas).

Sandbags barrier encircling the transplantation nursery in the N1 Division area was seen to have been damaged. Some construction materials were seen to have accumulated on top of the soil surface inside the nursery. The Contractor was reminded to clear up the construction materials and place them in an appropriate storage area. Damaged sandbags should be replaced by new ones to contain the soil inside the nursery and prevent soil erosion.

Several trees inside the transplantation nursery in the N2 Division aArea were found to have fallen down during the inspection on 15th September 2006 due to the typhoon event in early August 2006 and mid-September 2006. The Contractor was reminded to replant these trees in the nursery to ensure their survival. The fallen trees were observed to have been replanted during inspection on 27th September 2006.

The details of the landscape and visual resources inspection reports are provided in Annex F.

3.4               Ad-hoc Air Quality Monitoring

No ad-hoc air quality monitoring was required during the reporting period.

3.5               Waste Management

The Contractor has adopted a trip ticket system for the disposal of construction wastes.  According to the records provided by the Contractor, the disposal of construction waste within the reporting period is summarised in Table 3.3Table 3.4Table 3.4Table 3.2.

 

 

Table 3.2   Summary of Waste Disposal for DecemberAugust  2007

Waste Type

Destination

No. of Trips

Quantity

C&D Waste

NENT Landfill

17

85 m3

C&D Waste

WENT Landfill

1

5 m3

Building debris

CEDD’s Tuen Mun Area 38 Fill Bank

147

735 m3

Sewage Holding Tank Waste

Collected by Waylung Waste Services Ltd.

13

-

Chemical Waste

Collected by Dunwell Enviro-Tech (Holdings) Ltd.

1

1,100 litre

 

4                     Environmental Audits

4.1               Site Inspection and Audit

Site inspections were undertaken on 5th and 19th December 2007.  The Independent Environmental Checker (IEC) undertook the site inspection on 19th December 2007.  Specific locations within the site were identified during the inspection for improvements in proper implementation of the environmental mitigation measures.  These include:

·      Removal of debris and sediment at the existing outfall at M6 as proper maintenance.

·      Cleaning the tracks of sand and silt on the public road near the site exit and ensure all vehicles’ wheels have been washed before leaving the site.

The record of the site inspection findings is provided in Annex G.

4.2               Environmental Exceedance

During the reporting period, seven no environmental exceedance was recorded.

4.3               Environmental Non-compliance

During the reporting period, no environmental non-compliance was recorded.

4.4               Environmental Complaint and Prosecution

During the reporting period, no environmental complaints, prosecutions or summons were received.  Cumulative statistics on complaints, notifications of summons and successful prosecutions for the Project are provided in Annex H.

5                     Forecast and Schedule

5.1               Key Issues for the Coming Months

The key issues with respect to the works in the forthcoming 2 months include landscaping works and road paving.

 

5.2               Monitoring Schedules for the Next Month

The proposed schedule for noise monitoring in September January 2008 is provided in Table 5.1.

Table 5.1   Proposed Noise Monitoring Schedule for September January 2008

Date

Noise Monitoring Station

15th 5th SeptemJanuary 2008 (Tuesday)

CM1, CM2 and CM3

29th January 2008 (Tuesday)

CM1, CM2 and CM3

 

6                     Conclusion

There was no environmental non-compliance attributable to the Project works during reporting period.

There was six no exceedance recorded during the reporting period.

There was one exceedance non-compliance of the Limit Level recorded during the normal hours noise monitoring due to concrete breaking activities in project works area during the reporting period.

No environmental complaints, prosecutions or summons was received during the reporting period.