Improvements to
San Tin Interchange (Contract No. HY/2004/09)
Monthly
Environmental Monitoring & Audit Report
Report
No. 39
August
2008
Table of Content
1.1 Works undertaken during the Reporting Period
1.2 Environmental Permit and Licences
1.3 Environmental
Document Submissions to EPD
1.4 Environmental
Monitoring Locations
2 Environmental Measures and Implementation Status
3.3 Landscape and
Visual Resources
3.4 Ad-hoc Air
Quality Monitoring
4.3 Environmental
Non-compliance
4.4 Environmental Complaint and Prosecution
5.1 Key Issues for the Coming Months
5.2 Monitoring Schedules for the Next Month
List of Annexes
Annex A Contractor’s
Works Programme
Annex B Mitigation
Measures Checklist
Annex C Calibration
Certificates
Annex D Noise
Monitoring Results
Annex E Water
Quality Visual Inspection Reports
Annex F Landscape
& Visual Resources Inspection Reports
Annex G Site
Inspection Reports
Annex H Action
and Limit Levels
Annex I Cumulative
Statistics on Complaints, Notifications of Summons and Successful Prosecutions
List
of Tables
Table 1.1 Summary of Environmental Submissions to EPD in August 2008
Table 1.2 Noise Monitoring Stations
Table 3.1 Summary of Noise Monitoring Results during Normal Working Hours
Table 3.2 Summary
of Waste Disposal for August 2008
Table 5.1 Proposed Noise Monitoring Schedule for August 2008
List
of Figures
Figure 1 Site Plan & Locations of Noise and Air Quality Monitoring Stations
Executive Summary
Atkins
China Limited (ACL) has been appointed by Chun Wo Construction &
Engineering Co., Ltd. to implement the Environmental Monitoring and Audit
(EM&A) programme for the construction works under Contract No. HY/2004/09 Improvements
to San Tin Interchange (hereinafter, the Project).
The
construction of the Project commenced since 21st June 2005. This report is the thirty-ninth monthly
EM&A report for the Project which summarises the monitoring results and
audit findings during the reporting period from 1st August 2008 to
31st August 2008.
Environmental
Monitoring and Audit Progress
The
monthly EM&A programme was undertaken in accordance with the EM&A
Manual. A summary of the monitoring
activities in this reporting period is listed below:
· Site inspections were undertaken jointly with the Contractor and Engineer’s Representative (ER) on 12th and 27th August 2008. The Independent Environmental Checker (IEC) undertook the site inspection on 27th August 2008.
·
Noise
monitoring at the designated monitoring stations was undertaken on 18th
and 29th August 2008 during normal working hours.
·
Visual
site surveillance for water quality was undertaken on 8th, 12th,
18th and 27th August 2008.
·
Site
inspection for landscape and visual resources was undertaken on 26th
August 2008.
Breaches of Action and Limit
Levels
There were no environmental
exceedances recorded during this reporting period.
Environmental
Non-Compliance
No environmental non-compliances were received during this reporting period.
Complaint Log
No
environmental complaints were received during this reporting period.
Notifications of Summons and
Prosecutions
No
notifications of summons or prosecutions were recorded during this reporting
period.
Reporting Changes
This
report has been developed in compliance with the reporting requirements for the
subsequent monthly EM&A reports as required by the Project EM&A Manual.
Future Key Issues
The key works in the forthcoming 2 months include road paving and landscaping works.
1.1
Works undertaken
during the Reporting Period
The
major construction activities undertaken during this reporting period are
summarised below:
· Landscaping works; and
· Road paving.
The site
plan of the Project is shown in Figure 1.
The Contractor’s works programme is provided in Annex A.
1.2
Environmental
Permit and Licences
There were no changes or clarification to the Environmental Permit (EP-190/2004) during the reporting period.
No Construction Noise Permits (CNP) was issued in August 2008.
1.3
Environmental Document Submissions to EPD
Table 1.1 Summary of Environmental Submissions to EPD in August 2008
Item No. |
Document
Title |
Date of Submission |
1 |
Monthly
EM&A Report No. 38 for July
2008 |
18th August 2008 |
1.4
Environmental Monitoring Locations
Noise monitoring was undertaken at three monitoring stations CM1, CM2 and CM3. The locations are shown on Figure 1. Description of these monitoring stations is provided in Table 1.2.
Table 1.2 Noise Monitoring Stations
Monitoring
Station ID |
Description |
Easting |
Northing |
CM1 |
Village house near San Tin
Highway |
826133 |
839839 |
CM2 |
Village house near San Tin
Highway |
826291 |
839918 |
CM3 |
Village house near Kwu Tung
Road |
826605 |
840076 |
The
mitigation measures listed in the Project EIA Report, EM&A Manual and
Environmental Permit and the implementation status are provided in Annex B.
During this reporting period, the tree planting was progressing in the open laydown area in North Division.
Based on site inspection findings, the Contractor has
implemented the required mitigation measures during construction works to date
in general.
3.1.1 Noise Monitoring Equipment
Details
of the noise monitoring equipment are listed below and the calibration
certificates are presented in Annex C:
· Sound level meter ONO-SOKKI LA-5110
· Acoustical calibrator ONO-SOKKI SC-2110
· Hand-held anemometer
3.1.2 Noise Monitoring Methodology
The
sound level meter was calibrated with an acoustical calibrator prior to each
measurement. It was set on a tripod
at 1.2 m above local ground level at the monitoring station. Measurement of the A-weighted Leq(30
minutes) noise level for normal daytime hours was undertaken. Three consecutive A-weighted Leq(5
minutes) noise levels were measured for restricted hours monitoring. Wind speed was checked during the
monitoring period using the hand-held anemometer to ensure steady wind speed
did not exceed 5 m/s, or gusts did not exceed 10 m/s. After the noise measurement the sound
level meter was re-calibrated using the acoustical calibrator.
3.1.3 Noise Monitoring Results
Noise monitoring was undertaken on a biweekly basis when noise generating activities were underway. The noise monitoring results obtained in August 2008, during the normal working is summarised in Table 3.1. There were no construction activities during restricted hours from 1900 to 2300 hours on normal working days and all day on general holidays within this reporting period.
There were no environmental exceedances of the Action and Limit Levels for noise monitoring recorded during the normal daytime hours within the reporting period. Details of the monitoring time period and weather condition during the monitoring period and the graphical presentation of the noise monitoring results are provided in Annex D.
Table 3.1 Summary of Noise Monitoring Results during Normal Working Hours
Date
of Monitoring |
Measured Noise Level Leq(30
minutes) dB(A) |
||
CM1 |
CM2 |
CM3 |
|
18th
August 2008 |
65 |
73 |
56 |
29th
August
2008 |
65 |
73 |
55 |
Remark:
(1) CM2 is a non-façade measurement location. A positive correction of 3 dB(A) has
been applied to the measured noise level at CM2 according to EPD’s guideline.
Visual site surveillances for water quality were undertaken on 8th, 12th, 18th and 27th August 2008. The key observations from the visual inspection include:
· Deposited sands and silts were accumulated in the sand
trap and U-channels near site office due to the landscape work. The Contractor was reminded to ensure the drainage system is free of debris
for water flow.
· Stagnant
water pool was seen in the works area near Castle Peak Road and sand trap in works area
near San Tin Highway. The
Contractor was reminded to clear the stagnant water promptly.
· Landscape
materials were scattered in the U-channel in the Road Island amongst Roads
D200, D100 and G100. The Contractor was reminded to remove the landscape
materials to maintain site tidiness.
The details of the water quality visual inspection reports are provided in Annex E.
3.3
Landscape and Visual Resources
One site inspection
on the landscape and visual resources was undertaken on
26th August 2008.
During the inspection, some transplanted trees at M2 in South Division were seen to be in very poor condition. The Contractor was reminded to closely monitor the transplanted tress and to ensure the trees proper growth.
The details of the
landscape and visual resources inspection report are provided in Annex F.
3.4
Ad-hoc Air Quality Monitoring
No ad-hoc air
quality monitoring was required during the reporting period.
The Contractor has adopted a trip ticket system for the disposal of construction wastes. According to the records provided by the Contractor, the disposal of construction waste within the reporting period is summarised in Table 3.2.
Table 3.2 Summary
of Waste Disposal for August 2008
Waste Type |
Destination |
No. of Trips |
Quantity |
C&D
Waste |
NENT
Landfill |
20 |
|
Building debris |
CEDD’s Tuen Mun Area 38 Fill Bank |
30 |
|
Sewage Holding Tank Waste |
Collected by Waylung Waste Services Ltd. |
15 |
- |
Chemical Waste |
Collected by Dunwell Enviro-Tech (Holdings) Ltd. |
1 |
1,000 litre |
Site inspections were undertaken on 12th and 27th August 2008. The Independent Environmental Checker (IEC) undertook the site inspection on 27th August 2008. Specific locations within the site were identified during the inspection for improvements in proper implementation of the environmental mitigation measures. These include:
· Removing the landscape materials in U-channel in the Road Island amongst D200, D100 and G100.;
· Removing the deposited sands and silts in the U-channel of the site drainage regularly;
· Removing stagnant water promptly;
· Keeping the chemical waste storage area door closed and locked.
The
record of the site inspection findings is provided in Annex G.
4.2
Environmental Exceedance
There was no record of exceedance during this reporting period.
The Action and Limit Levels
for impact monitoring are provided in Annex H.
4.3
Environmental Non-compliance
During
the reporting period, no environmental non-compliance was recorded.
4.4
Environmental
Complaint and Prosecution
During
the reporting period, no environmental complaints, prosecutions or summons were
received. The cumulative statistics on complaints, notifications of summons and
successful prosecutions for the Project are provided in Annex I.
5.1
Key Issues for
the Coming Months
The
key issues with respect to the works in the forthcoming 2 months include:
· Road paving.
5.2
Monitoring
Schedules for the Next Month
The proposed schedule
for noise monitoring in September 2008 is provided in Table 5.1.
Table 5.1 Proposed Noise Monitoring Schedule for September 2008
Date |
Noise
Monitoring Station |
17th September 2008
(Wednesday) |
CM1, CM2 and CM3 |
29th September 2008 (Mondayy) |
CM1,
CM2 and CM3 |
There
was no environmental non-compliance attributable to the Project works during
reporting period.
There were no exceedances of the noise Limit Level during the reporting period.
No
environmental complaints, prosecutions or summons was received during the
reporting period.