Improvements to
San Tin Interchange (Contract No. HY/2004/09)
Monthly
Environmental Monitoring & Audit Report
Report No. 41
October 2008
Table of Content
1.1 Works undertaken during the Reporting Period
1.2 Environmental Permit and Licences
1.3 Environmental
Document Submissions to EPD
1.4 Environmental
Monitoring Locations
2 Environmental Measures and Implementation Status
3.3 Landscape and
Visual Resources
3.4 Ad-hoc Air
Quality Monitoring
4.3 Environmental
Non-compliance
4.4 Environmental Complaint and Prosecution
5.1 Key Issues for the Coming Months
5.2 Monitoring Schedules for the Next Month
List of Annexes
Annex A Contractor’s Works Programme
Annex B Mitigation Measures Checklist
Annex C Calibration Certificates
Annex D Noise Monitoring Results
Annex E Water Quality Visual Inspection Reports
Annex F Landscape & Visual Resources Inspection Reports
Annex G Site Inspection Reports
Annex H Notification
of Environmental Exceedances and Non-Compliance Forms
Annex I Action and Limit Levels
Annex J Cumulative Statistics on Complaints, Notifications of Summons and Successful Prosecutions
List
of Tables
Table 1.1 Summary of Environmental Submissions to EPD in October 2008
Table 1.2 Noise Monitoring Stations
Table 3.1 Summary
of Noise Monitoring Results during
Table 3.2 Summary of Noise Monitoring Results during Restricted Hours
Table 3.3 Summary
of Waste Disposal for October 2008
Table 5.1 Proposed Noise Monitoring Schedule for November 2008
List
of Figures
Figure 1 Site Plan & Locations of Noise and Air Quality Monitoring Stations
Executive Summary
Atkins
China Limited (ACL) has been appointed by Chun Wo Construction &
Engineering Co., Ltd. to implement the Environmental Monitoring and Audit
(EM&A) programme for the construction works under Contract No. HY/2004/09
Improvements to San Tin Interchange (hereinafter, the Project).
The
construction of the Project commenced since
Environmental
Monitoring and Audit Progress
The
monthly EM&A programme was undertaken in accordance with the EM&A Manual. A summary of the monitoring activities
in this reporting period is listed below:
·
Site
inspections were undertaken jointly with the Contractor and Engineer’s
Representative (ER) on 16th and
·
Noise
monitoring at the designated monitoring stations was undertaken on 10th
and
·
Visual
site surveillance for water quality was undertaken on 10th, 16th,
22nd and 29th October 2008.
·
Site
inspection for landscape and visual resources was undertaken on
Breaches of Action and Limit
Levels
There was one environmental
exceedance during the restricted hours noise monitoring on
Environmental Non-Compliance
No environmental non-compliances were received during this reporting period.
Complaint Log
No
environmental complaints were received during this reporting period.
Notifications of Summons and
Prosecutions
No
notifications of summons or prosecutions were recorded during this reporting
period.
Reporting Changes
This
report has been developed in compliance with the reporting requirements for the
subsequent monthly EM&A reports as required by the Project EM&A Manual.
Future Key Issues
The key works in the forthcoming 2 months include landscaping works and maintenance works.
1.1
Works undertaken
during the Reporting Period
The
major construction activities undertaken during this reporting period are summarised
below:
· Landscaping works; and
· Road paving.
The site
plan of the Project is shown in Figure 1.
The Contractor’s works programme is provided in Annex A.
1.2
Environmental
Permit and Licences
There were no changes or clarification to the Environmental Permit (EP-190/2004) during the reporting period.
No Construction Noise Permit (CNP) was issued in October 2008.
1.3
Environmental Document Submissions to EPD
Table 1.1 Summary of Environmental Submissions to EPD in October 2008
Item No. |
Document
Title |
Date of Submission |
1 |
Monthly
EM&A Report No. 40 for September 2008 |
|
1.4
Environmental Monitoring Locations
Noise monitoring was undertaken at three monitoring stations CM1, CM2 and CM3. The locations are shown on Figure 1. Details of these monitoring stations are provided in Table 1.2.
Table 1.2 Noise Monitoring Stations
Monitoring
Station ID |
Description |
Easting |
Northing |
CM1 |
Village house near |
826133 |
839839 |
CM2 |
Village house near |
826291 |
839918 |
CM3 |
Village house near |
826605 |
840076 |
The
mitigation measures listed in the Project EIA Report, EM&A Manual and
Environmental Permit and the implementation status are provided in Annex B.
During this reporting period, the landscape works were progressing in the open laydown area in North Division.
Based on site inspection findings, the Contractor has implemented the
required mitigation measures during construction works to date in general.
3.1.1 Noise Monitoring Equipment
Details
of the noise monitoring equipment are listed below and the calibration
certificates are presented in Annex C:
· Sound level meter ONO-SOKKI LA-5110
· Acoustical calibrator ONO-SOKKI SC-2110
· Hand-held anemometer
3.1.2 Noise Monitoring Methodology
The
sound level meter was calibrated with an acoustical calibrator prior to each
measurement. It was set on a tripod
at 1.2 m above local ground level at the monitoring station. Measurement of the A-weighted Leq(30
minutes) noise level for normal daytime hours was undertaken. Three consecutive A-weighted Leq(5
minutes) noise levels were measured for restricted hours monitoring. Wind speed was checked during the
monitoring period using the hand-held anemometer to ensure steady wind speed
did not exceed 5 m/s, or gusts did not exceed 10 m/s. After the noise measurement the sound
level meter was re-calibrated using the acoustical calibrator.
3.1.3 Noise Monitoring Results
Noise monitoring was undertaken on a biweekly basis when noise generating activities were underway. The noise monitoring results obtained in October 2008, during the normal working and restricted hours are summarised in Table 3.1and Table 3.2.
There was were no environmental
exceedances of the Actione and
Limit Levels
for environmental exceedance of the Action and Limit
Levels for noise monitoring recorded during the normal daytime
hours within the reporting period but onesix notification of exceedance
during the rrestricted
hours were reported.
Details of the monitoring time period during the monitoring period and the graphical presentation of the noise monitoring results are provided in Annex D.
Table 3.1 Summary of Noise Monitoring Results during
Date
of Monitoring |
Measured Noise Level Leq(30
minutes) dB(A) |
||
CM1 |
CM2 |
CM3 |
|
10th
October 2008 |
67 |
72 |
53 |
16th
October 2008 |
64 |
73 |
56 |
Remark:
(1) CM2
is a non-façade measurement location.
A positive correction of 3 dB(A) has been applied to the measured noise
level at CM2 according to EPD’s guideline.
Table 3.2 Summary
of Noise Monitoring Results during Restricted Hours – All Days during Night-time (2300-0700 hours)
Date
of Monitoring |
Measured Noise Level Leq(15
minutes) dB(A) |
||
CM1 |
CM2 |
CM3 |
|
|
* |
71 |
48 |
Remark:
(1) CM2
is a non-façade measurement location.
A positive correction of 3 dB(A) has been applied to the measured noise
level at CM2 according to EPD’s guideline.
(2) Underlined
figure indicates an exceedance of the Limit Level of 50 dB(A).
(3) *
Noise measurement at CM1 was cancelled due to the unsafe condition at the time
(stray dogs constantly barking at the monitoring location, and staff could be
attacked).
Visual site surveillances for water quality were undertaken on 10th, 16th, 22nd and 29th October 2008. The key observations from the visual inspection include:
· Sand and silt were
accumulated in the sand tap and U-cannel in the works area of
· Dead
vegetations and general refuses were accumulated in Headwall No.7 Area. The Contractor
was reminded to collect and dispose of the rubbish and dead vegetations
regularly.
The details of the water quality visual inspection reports are provided in Annex E.
3.3
Landscape and
Visual Resources
One site inspection on the
landscape and visual resources was undertaken on
During the inspection, some
transplant trees at M6 in South Division were seen dead. The Contractor was
reminded to replace the dead trees with new trees of the same species and size
as compensatory measures.
The details of the landscape
and visual resources inspection report are provided in Annex F.
3.4
Ad-hoc Air
Quality Monitoring
No ad-hoc air
quality monitoring was required during the reporting period.
The Contractor has adopted a trip ticket system for the disposal of construction wastes. According to the records provided by the Contractor, the disposal of construction waste within the reporting period is summarised in Table 3.2.
Table 3.3 Summary of Waste Disposal for October 2008
Waste Type |
Destination |
No. of Trips |
Quantity |
Building debris |
CEDD’s Tuen Mun Area 38 Fill Bank |
20 |
100
m3 |
Sewage Holding Tank Waste |
Collected by Waylung Waste Services Ltd. |
15 |
- |
Chemical Waste |
Collected by Dunwell Enviro-Tech (Holdings) Ltd. |
1 |
1,000 litre |
Site inspections were undertaken
on 16th and
· Keeping the site tidy;
· Removing leaves and rubbish in the U-channel;
· Removing the deposited sands and silts in the catchpits of the site drainage regularly.
The
record of the site inspection findings is provided in Annex G.
4.2
Environmental Exceedance
During
the reporting period, there was one exceedance of the Limit Level. Six of
which were noise exceedances of the lLimit lLevel
during restricted hours noise monitoring at CM2 on
Further to discussion with the Contractor, the major construction
activity during the time of measurement was planting signal at San Tin Highway
which was far away (both more than 300 m) from CM2. The exceedances were due to
the high ambient background noise caused by road traffic on the Contractor, no further concrete breaking
activities will be required in the Slip Road A works area. Nonetheless, the
Contractor was advised to implement necessary noise mitigation measures such as
and reminded that movable noise barriers (as
recommended in the Project EIA Report) of 3 to
5m high with skid footing should be provided to avoid further
exceedances that would be caused by potential noisy prior
to any further site works in the concerned area
following the recommendations in Section 3.47 and Figure 3.5 of the Project EIA
Report. Further to discussion with the Contractor, no further concrete breaking
activities will be required in the concerned area.
Records of the notification
of environmental exceedances and the non-compliance forms are
provided in Annex H. The Action and Limit Levels for impact monitoring are
provided in Annex I.
4.3
Environmental
Non-compliance
During
the reporting period, no environmental non-compliance was recorded.
4.4
Environmental
Complaint and Prosecution
During
the reporting period, no environmental complaints, prosecutions or summons were
received. The cumulative statistics on complaints, notifications of summons and
successful prosecutions for the Project are provided in Annex J.
5.1
Key Issues for
the Coming Months
All the major construction works have been completed substantially. The key works in the forthcoming 2 months include landscaping works and maintenance works.
5.2
Monitoring
Schedules for the Next Month
The proposed schedule
for noise monitoring in November 2008 is provided in Table 5.1.
Table 5.1 Proposed Noise Monitoring Schedule for November 2008
Date |
Noise
Monitoring Station |
|
CM1, CM2 and CM3 |
|
CM1, CM2 and
CM3 |
There
was no environmental non-compliance attributable to the Project works during
reporting period.
There
was onesix exceedances of the noise Limit Level
during the reporting period. However, it was not attributable
to the Project works.
There was one exceedance
non-compliance of the Limit
Level recorded during the normal hours noise monitoring due to concrete
breaking activities in project works area during the reporting period.
No
environmental complaints, prosecutions or summons was received during the
reporting period.