Environmental Mitigation Implementation Schedule
Environmental Protection
Measures |
Location |
Implementation Status |
||
Apr 06 |
May 06 |
Jun 06 |
||
Air Quality |
||||
Sufficient watering |
All unpaved haul roads, stockpiled material,
exposed site areas, barging point |
@ |
@ |
b |
Truck speed below 10 km/hr |
All areas |
b |
b |
b |
Watering for truck loads after removal of tarpaulin
cover |
Site egress |
b |
b |
b |
Provision of vehicle washing facilities |
Site egress |
b |
b |
b |
Provision of road sweeper |
Public road near site egress |
b |
b |
b |
A
buffer zone, where any dusty materials stockpiled, loading / unloading
avoided, of at least 20 m should be maintained |
Between
the edge of the public fill stockpiling area of the fill bank and the nearest
air sensitive receivers at River Trade Terminal |
b |
b |
b |
A
"truckload control zone" of an area 100 m x 100 m established,
where no more than 64 vehicle-trip per hour and 704 vehicle-trip per day
shall be allowed to travel to the control zone |
The
north-eastern corner |
b |
b |
b |
Noise |
||||
Noisy equipment and activities should be sited by
the Contractor as far away from sensitive receivers as is practical |
All areas |
b |
b |
b |
Replace noisy plant with quieter alternatives |
All areas |
b |
b |
b |
Idle equipment should be turned off or throttled
down |
All areas |
b |
b |
b |
Quieten power units of stationary and earth moving
plant with partial or full enclosures or vibratory isolation |
All areas |
b |
b |
b |
Properly maintain powered mechanical equipment |
All areas |
b |
b |
b |
Schedule noisy activities to reduce duration and
severity of noise |
All areas |
b |
b |
b |
Include contract clauses for environmental
protection |
All areas |
b |
b |
b |
Water Quality |
||||
Tipping halls enclosed with top and 3-sides to
prevent spillage of material into marine water |
Seafront |
b |
b |
b |
Obtain discharge license |
Site offices |
@ |
b |
b |
Provide
proper sewage treatment and disposal facilities in the form of chemical
toilets for site workers |
All areas |
b |
b |
b |
Include
contract specifications for environmental protection |
All areas |
b |
b |
b |
Provide
proper drainage for collection of surface runoff |
All areas |
b |
b |
b |
Provision
of buffer distance of at least 50m between stockpiles and the seafront |
Along the seafront |
b |
b |
b |
Sand
and silt removal facility provided for stormwater to be treated before
discharge |
All areas |
b |
b |
b |
Construction
of open channel |
Perimeter of Fill Bank |
b |
b |
b |
Regular
removal of sand and silt |
All channels |
@ |
@ |
@ |
Construction Waste |
||||
Segregate
different categories of waste |
All areas |
b |
b |
b |
Register
chemical and maintenance wastes |
All areas |
b |
b |
b |
Bund
chemical material storage areas to 110% capacity |
All areas |
b |
b |
b |
Do
not connect chemical material storage areas to the foul or stormwater
drainage system |
All areas |
b |
b |
b |
Store
and label dangerous goods |
All areas |
b |
b |
b |
Prevent
disposal of hazardous materials to air, soil, water bodies |
All areas |
@ |
@ |
b |
Provide
refuse containers at all work areas |
All areas |
b |
b |
b |
Human
waste discharged into septic tanks or tankered away |
All areas |
b |
b |
b |
Landscape and Visual |
||||
Hydroseeding
or coloured geo-textile matting (dark green / brown) provided on the slopes
of the fill bank as the slopes of each layer of platform are formed |
Along
the eastern, northern and western sides of the fill bank |
b |
b |
b |
A
buffer tree planting strip consists of row of at least 3 m high native
evergreen trees species with a tall habit when fully grow (e.g. Casuarina
equisetifolia) planted prior to operational phase of the project |
Along
the site boundary facing |
b |
b |
b |
The
surface colour of structures at fill bank an earthy tone with strong natural
qualities in green, grey or brown colour and the use of bold colour schemes
avoided |
All areas |
b |
b |
b |
Maximum
stockpiling height at the fill bank limited to a maximum of +40mPD |
All areas |
b |
b |
b |