8.1
Environmental impact monitoring was performed in June 2006. All monitoring
results in the reporting month were checked and reviewed.
8.2
All measured 1-hour and 24-hour TSP concentrations in the reporting
month were below the AL Levels.
8.3
For water quality monitoring, sixteen
exceedances (twelve Action and four Limit Level) were recorded during the
reporting month. All
exceedances were concluded not due to the Project’s works.
8.4
No complaint, summons or prosecution related to environmental issues was
made against the Project in the reporting period.
8.5
According to the environmental audits performed and the tentative
construction programme in the reporting month, the following recommendations
are made:
Dust Impact
·
To prohibit any open burning on site.
·
To water all haul roads, exposed area and stockpiles.
Noise Impact
·
To regularly maintain the machinery and vehicles on site.
Water Impact
·
To minimise water discharge and surface runoff into nearby water body.
·
To minimise soil loss to nearby water body.
Waste/Chemical
Management
·
To check for any accumulation of waste materials or rubbish on site.
·
To avoid any discharge of chemical waste or oil directly from the site.