EXECUTIVE SUMMARY

 

This is the sixth monthly Environmental Monitoring and Audit (EM&A) report prepared by Maunsell Environmental Management Consultants Limited (MEMCL), the designated Environmental Team (ET), for the Project “Operation of Public Fill Reception Facility at Tuen Mun Area 38”. This report presents the results of EM&A works conducted in the period from 1 to 30 June 2006.

 

As advised by the Contractor, the construction activities carried out in the reporting month are:

 

l             Management and operation of facilities in Tuen Mun Area 38 Fill Bank;

l             Partial removal of the Public Fill stockpiled at Tuen Mun Area 38 Fill Bank including feeding of suitable public fill to the PBR2’s Sorting Facilities;

l             Operation of Tipping halls;

l             Provision and operation of a Crushing Plant; and

l             Landscaping works.

 

Monitoring of 1-hour Total Suspended Particulates (TSP) and 24-hour TSP at two designated monitoring stations and water quality at four designated monitoring stations were performed. The monitoring results were checked and reviewed. Site inspections were conducted on weekly basis. The implementation of the environmental mitigation measures, Event and Action Plans and environmental complaint handling procedures were also implemented.

 

Environmental Monitoring Works

 

Air Quality

All measured 1-hour and 24-hour TSP concentrations in the reporting month were below the Action and Limit (AL) Levels.

 

Water Quality

For water quality monitoring, sixteen exceedances (twelve Action and four Limit Levels) were recorded in the reporting month. All exceedances were concluded not related to the Project-works.

 

Implementation Status of Environmental Mitigation Measures

The following key observations were made during site inspection with regards to the implementation status of environmental mitigation measures:

 

·         The Contractor was reminded to provide adequate watering to haul roads and dusty operations more frequently;

·         Silty material inside drainage channel should be cleared regularly;

·         Water pondings should be removed regularly during wet season;

·         All stockpiles should be covered or sprayed with water; and

·         Drip trays should be provided to all chemicals drums.

 

Environmental Complaints and Prosecution

No complaint, summons or prosecution related to environmental issues was made against the Project in the reporting period.

 

Future Key Issues

Key issues to be considered in the coming month include:

 

·         Dust generation from activities on-site, such as vehicular movements along unpaved area and rock crushing activities.

·         Noise impact from operating equipment and machinery on-site.

·         Uncontrolled wastewater and surface runoff from the construction site discharge into nearby water body.

·         Storage and using of chemicals/fuel and chemical waste/waste oil on site.