Key Issues for the Coming Month
7.1
Key issues to be considered in the coming month include:
·
Dust generation from activities on-site, such as vehicular movements
along unpaved area.
·
Noise impact from operating equipment and machinery on-site.
·
Uncontrolled wastewater and surface runoff from the construction site
discharge into nearby water body.
·
Storage and usage of chemicals/fuel and chemical waste/waste oil on
site.
7.2
To mitigate against the predicted impact arising from the scheduled
works activities, the following mitigation measures are proposed:
·
Regularly water of haul roads, exposed area and stockpiles.
·
Properly maintain all equipment at good working condition.
·
Avoid stockpiling fill materials near the seafront.
· Store all chemical waste at designated chemical waste store.
Environmental Monitoring Program for the Next Three Months
7.3 Tentative dust and water monitoring and site inspection schedule for the coming three months is shown in Appendix B.