Maeda Corporation |
|||||||||
|
|||||||||
Upgrading of Ting Kok Road Pumping Station No. 5 |
|||||||||
|
Monthly
EM&A Report No. 7 for
July 2006 August 2006 Report no: 01284R0221 |
||||||||
Hyder Consulting Ltd Incorporated in Hong Kong with limited liability—COI Number 126012 47th Floor, Hopewell Centre, 183 Queens Road East, Wanchai, Hong Kong Tel: +852
2911 2233 Fax: +852
2805 5028 www.hyderconsulting.com
|
|
||||||||
Maeda Corporation |
|||||||||
|
|||||||||
Upgrading of Ting Kok Road Pumping Station No. 5 |
|||||||||
Monthly EM&A Report No. 7 for July 2006 |
|||||||||
Author: |
Alexi Bhanja |
|
|||||||
Checker: |
Sharifah Or |
|
|||||||
Approver: |
Guiyi Li |
|
|||||||
|
|||||||||
Report no: |
EA01284R0221 |
|
|
Date: |
August 2006 |
||||
|
|||||||||
Certified by Landfill Gas Team Leader Alexi
Bhanja |
|
||||||||
Contents
5 Implementation
Status of LFG Control Measures................................................... 6
List of Tables
Table 2-1 Contact
Details for Key Project Personnel 3
Table 3-2 Fixed Monitoring Locations
for LFG EM&A 4
Table 4-3 Equipment List for LFG
Monitoring 5
Table 4-4 Action and Limit Levels and
Action Plan for Landfill Gas 5
Table 6-5 Monitoring Results at M1 6
Table 6-6 Monitoring Results at M3 6
List of Appendices
Appendix 1 Project Organisation
Appendix 2 Construction Programme
Appendix 3 Location of Works and Project Area
Appendix 4 Fixed Monitoring Locations
Appendix 5 Updated Implementation Schedule
Appendix 6 Calibration Records
Appendix 7 Field Measurement Recording Sheets
Drainage Services Department (DSD) awarded the contract for the Upgrading of Ting Kok Road Pumping Station No. 5 to Maeda Corporation in September 2005. Maeda appointed Hyder Consulting Limited as the Contractor’s Landfill Gas (LFG) Team during the construction period. The construction contract commenced in September 2005 and the total construction period is approximately 28 months.
This report recorded the results and findings of the required EM&A works undertaken during July 2006. All relevant mitigation measures and requirements were implemented. There have been no exceedances in Action/Limit (A/L) Levels at any of the locations monitored under the EM&A programme.
An 11m-deep borehole, designated “M1”, was installed by the Contractor to provide an “early warning” of potential LFG problems that could affect surface trenches, but does not form part of the EM&A programme. The Contractor has noted the monitoring results from M1 and will take them into consideration when planning surface trench works in the vicinity.
Manhole M2 was dismantled during the reporting month because of planned works and therefore monitoring at M2 was terminated. However, LFG has never been detected at M2 and so it is not considered that termination of monitoring at this location will have any significant impact on the overall effectiveness of the environmental monitoring programme, as monitoring at manhole M3 will continue.
Environmental Protection Department (EPD) has not conducted any site visit in the reporting period.
Event and Action Levels
The baseline monitoring results documented in the baseline monitoring report for the Project (our report ref.: EA01284R0022) provided the A/L Levels for LFG impact monitoring and also the Action Plan. For methane, A/L Levels are 0.5%/1.0%; for carbon dioxide, A/L Levels are 0.5%/1.5%; and for oxygen, A/L Levels are 19.0%/18.0%.
Complaint Log
There were no non-compliances in terms of the EM&A programme during the reporting period and no complaints regarding LFG were received.
Reporting Changes
There have been no reporting changes during the reporting period.
Future Key Issues
Based on anticipated construction activities for next month, on the construction programme and on the review of relevant Contractor’s method statements by the LGT, no significant future key issues in terms of LFG have been identified at this time.
Upgrading of Ting Kok
Road Pumping Station No. 5 (TKRPS) under North District and Tolo Harbour
Sewerage, Sewage Treatment and Disposal – High Priority Works is implemented
based on the findings of the Study Review
of North District and Tolo Harbour Sewerage Master Plan.
The purpose of the
Project is to upgrade the existing TKRPS to cope with the sewerage needs
of both existing and future developments along Ting Kok Road up to Tai Mei Tuk.
The design pumping capacity of TKRPS has to be increased from 2,888m3/day
to 11,520m3/day in order to serve the increasing sewage flow along
Ting Kok Road. The Project is of high priority and needs to commence as soon as
possible because full commissioning of the upstream sewerage facilities along
Ting Kok Road is dependent on the completion of this Project.
The proposed scope of
works includes construction of a new pumping station, laying of about 350m long
twin 450mm diameter rising mains and 250m long 600mm diameter gravity sewer,
and demolition of the existing pump pit. The main pumping station, transformer
room, gravity sewers, manholes and boundary wall (except the twin rising mains)
will be located outside the existing passive vent trench of Shuen Wan Landfill
and the three existing Landfill Gas (LFG) monitoring probes within the Project
site will not be affected by the works.
Six village houses are located about 60m away from the boundary of the proposed pumping station. The proposed pumping station upgrading works therefore constitute a Designated Project under type F.3(b)(i) in Schedule 2 of the Environmental Impact Assessment Ordinance. A Project Profile (PP) for direct application of the Environmental Permit (EP) (Application No.DIR-115/2005) was approved by the Environmental Protection Department (EPD) in March 2005 and an EP (EP-212/2005) was granted in April 2005, prior to the commencement of the upgrading works.
Drainage Services Department (DSD) awarded the contract for the upgrading of TKRPS to Maeda Corporation in September 2005. Maeda appointed Hyder Consulting Limited as the Contractor’s Landfill Gas Team (LGT) during the construction period. CH2M HILL Hong Kong Limited is the Independent Checker (Landfill Gas) (IC(LG)) of the project. The construction contract commenced in September 2005 and the total construction period is approximately 28 months.
Close proximity of the Project to Shuen Wan Landfill (within the 250m Consultation Zone of Shuen Wan Landfill) may also suggest the possibility of landfill gas being released during excavation works for substructure of pumping station, transformer room and associated rising mains and gravity sewers. As such, a Report on Landfill Gas Hazard Assessment has been prepared previously (as Appendix E to the PP) in accordance with EPD’s Landfill Gas Hazard Assessment Guidance Note and the Practice Note for Professional Persons – Landfill Gas Hazard Assessment for Development Adjacent to Landfills.
2.2 Management Structure and Project Organisation
The Engineer (DSD) is responsible for overseeing the construction works and ensuring that they are undertaken by the Contractor (Maeda) in accordance with the specification and contractual requirements. The Contractor shall report to the Engineer. The LGT is employed by the Contractor and responsible for conducting the EM&A programme. The IC(LG) shall advise the Engineer on LFG issues related to the Project.
The key personnel contact names and telephone number are summarised in Table 2-1. The project organisation is shown in Appendix 1.
Party |
Position |
Name: |
Tel. No.: |
Project Proponent and Engineer – DSD |
Project Manager |
Raymond LEE |
2594 7457 |
Engineer’s Representative |
Tim TSOI |
2594 7460 |
|
Contractor – Maeda |
Site Agent |
George CHEUNG |
9268 1918 |
LGT – Hyder Consulting |
LGT Leader |
Alexi BHANJA |
2911 2916 |
IC(LG) – CH2M HILL |
IC(LG) |
Aldex LEE |
2507 2203 |
Table 2-1 Contact Details for Key Project Personnel
Construction programme of the Project is attached in Appendix 2. As can be seen, all works carried out during the reporting period have been carried out with the required LFG control measures in place (e.g. LFG monitoring for “hot works”).
2.4 Works Undertaken during the Month
Works undertaken during the reporting period included:
§
Sheet piling work and temporary work for trenchless method
§
Construction of gravity sewer and rising main
§
Excavation
3.1
Works Undertaken during the Month with
Illustrations
Works undertaken during the reporting period
are identified in Section 2.4. Illustrations of these works, such as location
of works, etc., are provided in Appendix 3.
3.2 Project Area and Monitoring Locations
The site is located at Ting Kok Road in Tai Po, and the major items to be constructed are located outside the existing passive vent trench of the adjacent Shuen Wan Landfill, which has been restored and is currently being monitored.
The impact monitoring locations specified in the Report on Landfill Gas Hazard Assessment comprise “utilities’ manholes and chambers” (i.e. fixed locations for purposes of environmental protection) and at excavations of 1m depth or more (i.e. variable locations for purposes of worker safety).
An 11m-deep borehole, designated “M1”, was installed by the Contractor (in addition to contract requirements) to provide an “early warning” of potential LFG problems that could affect surface trenches. It is not intended that M1 forms part of the EM&A programme, since conditions deep below the surface do not fall within the scope of the EM&A programme (i.e. manholes and excavations >1m).
In terms of fixed monitoring locations, the
Baseline Report identified two existing manholes (M2 and M3). Manhole M2,
however, was dismantled during the reporting month because of planned works and
therefore monitoring at M2 was terminated. LFG has never been detected at M2
and so it is not considered that termination of monitoring at this location
will have any significant impact on the overall effectiveness of the
environmental monitoring programme, as monitoring at manhole M3 will continue.
There are no other suitable manholes within the site that can be monitored in
lieu of M2.
In terms of variable monitoring locations,
these vary from month to month, depending on site activities. The fixed monitoring location is shown in
Table 3-2:
Monitoring Station ID |
||
M3 |
Existing Manhole (2m deep) |
EM&A programme |
Table
3-2 Fixed Monitoring Locations for LFG EM&A
Project area is shown in Appendix 3 and the fixed monitoring location is shown in Appendix 4.
During the construction phase, impact monitoring of LFG is to be carried out in accordance with the Report on Landfill Gas Hazard Assessment at the selected locations. LFG parameters to be monitored comprise oxygen, methane and carbon dioxide. Temperature is also recorded but this is not a LFG parameter.
Table 4-3 shows the equipment list for LFG monitoring.
Equipment |
Manufacturer /
Serial Nos. |
Gas Analyser GA 2000 |
Geotechnical Instruments / GA 08277 |
Table 4-3 Equipment List for LFG Monitoring
4.3 Event and Action Levels/Plans
The baseline monitoring results documented in the baseline monitoring report for the Project (our report ref.: EA01284R0022) provided the Action and Limit (A/L) Levels for LFG impact monitoring and also the Action Plan. As per the Report on Landfill Gas Hazard Assessment, and in keeping with the standard presentation of LFG EM&A in other projects, both the A/L Levels and Action Plan are shown in the same table.
Table 4-4 shows the combined A/L Level and Action Plan for the Project, to be triggered if the LFG criteria are exceeded at fixed location M3, or at any of the variable locations:
Parameter |
A/L
Level |
Action Plan |
Oxygen |
<19% |
–
Ventilate to
restore oxygen to > 19% |
<18% |
–
Stop works –
Evacuate
personnel/prohibit entry –
Increase
ventilation to restore oxygen to >19% |
|
Methane |
>10% LEL (i.e. > 0.5 % by volume) |
–
Prohibit hot
works –
Ventilate to
restore methane to < 10% LEL |
> 20% LEL (i.e. > 1% by volume) |
–
Stop works –
Evacuate
personnel/prohibit entry –
Increase
ventilation to restore methane to < 10% LEL |
|
Carbon Dioxide |
>0.5% |
–
Ventilate to
restore carbon dioxide to <0.5% |
>1.5% |
–
Stop works –
Evacuate
personnel/prohibit entry –
Increase
ventilation to restore carbon dioxide to >0.5% |
Table 4-4 Action and Limit Levels and Action Plan for Landfill Gas
4.4 Mitigation Measures & Requirements in Contract Documents
Measures for mitigating LFG hazards during the construction works have been stated clearly in the Report on Landfill Gas Hazard Assessment, which forms part of the contract documents Specification. Relevant excerpts could be referred to the Project Profile for Upgrading of Ting Kok Road Pumping Station No. 5.
Section 5 and Appendix 5 summarise the mitigation measures and requirements as well as the implementation status.
The status of the mitigation measures implemented by the Contractor is listed in Appendix 5. All LFG hazard control measures have been implemented as stipulated in the contract documents and in the Report on Landfill Gas Hazard Assessment.
Calibration records for the equipment used for LFG monitoring are provided in Appendix 6. Original Field Measurement Recording Sheets are provided in Appendix 7.
During
the reporting period, LFG was monitored at M1 to give an “early warning” of
potential LFG problems. M1 is an 11m-deep borehole and the carbon dioxide and
methane concentrations may reflect possible influence of LFG at depth below the
site. Monitoring results are shown in Table 6-5, below. Location M1 is not
subject to EM&A and so A/L Levels are not applicable.
Monitoring
Station ID |
Date |
Gas
Concentration (%) |
Temperature
(OC) |
||
Methane |
Carbon
Dioxide |
Oxygen |
|||
M1 |
4 July 06 |
0.1 |
0.1 |
20.3 |
32.7 |
Table 6-5 Monitoring Results at M1
Considering the location of M1 adjacent to a restored landfill, the recorded levels are within expected norms and are not cause for concern. Notwithstanding, the Contractor has noted these concentrations and will take them into consideration when planning surface trench works in the vicinity.
During the
reporting period, LFG was monitored at the fixed location M3 for purposes of
environmental protection. This is shown in Table 6-6, below:
Monitoring
Station ID |
Date |
Gas
Concentration (%) |
Temperature
(OC) |
||
Methane |
Carbon
Dioxide |
Oxygen |
|||
M3 |
4 July 06 |
0.1 |
0.3 |
19.8 |
32.7 |
Note : bold indicates an exceedance of Action Level and bold
indicates exceedance of Limit Level
Table 6-6 Monitoring Results at M3
Appendix 4 shows
the position of each fixed monitoring station. There were no exceedances of A/L
Levels at the two fixed locations during the reporting period.
During the reporting period, LFG was also monitored at variable
locations (for purposes of worker safety). These locations were within Portions 4 to
7 as shown in Appendix 3. A total of 637 readings, each including carbon
dioxide, methane and oxygen, at variable locations were taken for
safety-related reasons, including excavation and hot works. There were no
exceedances for A/L Levels at any variable locations during the reporting
period.
LFG
monitoring results for variable locations are provided on the Field
Measurement Recording Sheets in Appendix 7.
EPD has not conducted any site visit in the reporting period.
There were no non-compliances during the reporting period and no complaints regarding LFG were received.
Construction activities for next month are anticipated to include:
§
Sheet piling work
§
Excavation
§
Diversion of existing sewer
§
Construction of gravity sewer and rising mains
§
Installation of pile head steel plate
§
Construction of sub-structure
§
Installation of steel plate for mini-piles
Based on the above, on the construction programme (shown in Appendix 2) and on the review of relevant Contractor’s method statements by the LGT, no significant future key issues in terms of LFG have been identified at this time.
LFG monitoring will be continued and the tentative monitoring schedule at fixed locations for the next three months is shown below:
§ 1 August 2006
§ 1 September 2006
§ 3 October 2006
8.2
Comments,
Recommendations and Conclusions
The LFG mitigation measures adopted by the Contractor during the reporting period are considered have been implemented in a satisfactory manner and there have been no exceedances in A/L Levels.
The EM&A programme is considered to have performed acceptably and there are no recommendations for improvements or modifications at this time.
In conclusion, there have been no significant issues relating to LFG hazard during the reporting period.
Appendix 1 |
Project Organisation |
Project Proponent Drainage Services Department Landfill Gas Team Hyder Consulting Limited Landfill Gas (Independent
Checker) CH2M HILL Environmental Protection
Department Line
of communication Line
of Authority
Appendix 2 |
Construction Programme |
Appendix 3 |
Location of Works and Project Area |
Appendix 4 |
Fixed Monitoring Locations |
Appendix 5 |
Updated Implementation Schedule |
Appendix 6 |
Calibration Records |
Appendix 7 |
Field Measurement Recording Sheets |