Maeda Corporation |
|||||||||
|
|||||||||
Upgrading of Ting Kok Road Pumping Station No. 5 |
|||||||||
|
Fourth
Quarterly EM&A Report (October
– December 2006) January 2007 Report no: 01284R0362 |
||||||||
Hyder Consulting Ltd Incorporated in Hong Kong with limited liability—COI Number 126012 47th Floor, Hopewell Centre, 183 Queens Road East, Wanchai, Hong Kong Tel: +852
2911 2233 Fax: +852
2805 5028 www.hyderconsulting.com
|
|
||||||||
Maeda Corporation |
|||||||||
|
|||||||||
Upgrading of Ting Kok Road Pumping Station No. 5 |
|||||||||
Fourth Quarterly EM&A Report (October – December 2006) |
|||||||||
Author: |
Alexi Bhanja |
|
|||||||
Checker: |
Sharifah Or |
|
|||||||
Approver: |
Guiyi Li |
|
|||||||
|
|||||||||
Report no: |
EA01284R0362 |
|
|
Date: |
January 2007 |
||||
|
|||||||||
Certified by Landfill Gas Team Leader Alexi
Bhanja |
|
||||||||
Contents
5 Implementation Status of LFG Control Measures................................................... 4
List of Tables
Table 2-1 Contact
Details for Key Project Personnel 2
Table 3-2 Fixed Monitoring Locations
for LFG EM&A 3
Table 4-3 Equipment List for LFG
Monitoring 4
Table 4-4 Action and Limit Levels and
Action Plan for Landfill Gas 4
Table 6-5 Monitoring Results at M1 5
Table 6-6 Monitoring Results at M3 5
List of Appendices
Appendix 1 Project
Organisation
Appendix 2 Construction Programme
Appendix 3 Location of Works and Project Area
Appendix 4 Fixed Monitoring Locations
Appendix 5 Updated Implementation Schedule
Appendix 6 Calibration Records
Appendix 7 Field Measurement Recording Sheets
Drainage Services Department awarded the contract for the Upgrading of Ting Kok Road Pumping Station No. 5 to Maeda Corporation in September 2005. Maeda appointed Hyder Consulting Limited as the Contractor’s Landfill Gas (LFG) Team during the construction period. The construction contract commenced in September 2005 and the total construction period is approximately 28 months.
This report recorded the results and findings of the required EM&A works undertaken during the period from October to December 2006. All relevant mitigation measures and requirements were implemented. There have been no exceedances in Action/Limit (A/L) Levels at of the locations monitored under the EM&A programme.
An 11m-deep borehole, designated “M1”, was installed by the Contractor to provide an “early warning” of potential LFG problems that could affect surface trenches, but does not form part of the EM&A programme. The Contractor has noted the monitoring results from M1 and will take them into consideration when planning surface trench works in the vicinity.
Manhole M2 was dismantled in July 2006 because of planned works and therefore monitoring at M2 has been terminated since July 2006. However, LFG has never been detected at M2 and so it is not considered that termination of monitoring at this location will have any significant impact on the overall effectiveness of the environmental monitoring programme, as monitoring at manhole M3 will continue.
Environmental Protection Department (EPD) conducted a site visit on 2 November 2006 and had no adverse comments.
Event and Action Levels
The baseline monitoring results documented in the baseline monitoring report for the Project (our report ref.: EA01284R0022) provided the Action and Limit (A/L) Levels for LFG impact monitoring and also the Action Plan. For methane, A/L Levels are 0.5%/1.0%; for carbon dioxide, A/L Levels are 0.5%/1.5%; and for oxygen, A/L Levels are 19.0%/18.0%.
Complaint Log
There were no non-compliances during the reporting period and no complaints regarding LFG were received.
Reporting Changes
There have been no reporting changes during the reporting period.
Future Key Issues
Based on anticipated construction activities for the next quarter, on the construction programme and on the review of relevant Contractor’s method statements by the LGT, no significant future key issues in terms of LFG have been identified at this time.
Upgrading of Ting Kok
Road Pumping Station No. 5 (TKRPS) under North District and Tolo Harbour
Sewerage, Sewage Treatment and Disposal – High Priority Works is implemented
based on the findings of the Study Review
of North District and Tolo Harbour Sewerage Master Plan.
The purpose of the
Project is to upgrade the existing TKRPS to cope with the sewerage needs
of both existing and future developments along Ting Kok Road up to Tai Mei Tuk.
The design pumping capacity of TKRPS has to be increased from 2,888m3/day
to 11,520m3/day in order to serve the increasing sewage flow along
Ting Kok Road. The Project is of high priority and needs to commence as soon as
possible because full commissioning of the upstream sewerage facilities along
Ting Kok Road is dependent on the completion of this Project.
The proposed scope of
works includes construction of a new pumping station, laying of about 350m long
twin 450mm diameter rising mains and 250m long 600mm diameter gravity sewer,
and demolition of the existing pump pit. The main pumping station, transformer
room, gravity sewers, manholes and boundary wall (except the twin rising mains)
will be located outside the existing passive vent trench of Shuen Wan Landfill
and the three existing Landfill Gas (LFG) monitoring probes within the Project
site will not be affected by the works.
There are six village houses located about 60m away from the boundary of the proposed pumping station. The proposed pumping station upgrading works therefore constitutes a Designated Project under type F.3(b)(i) in Schedule 2 of the Environmental Impact Assessment Ordinance. A Project Profile (PP) for direct application of the Environmental Permit (EP) (Application No.DIR-115/2005) was approved by the Environmental Protection Department (EPD) in March 2005 and an EP (EP-212/2005) was granted in April 2005, prior to the commencement of the upgrading works.
Drainage Services Department awarded the contract for the upgrading of TKRPS to Maeda Corporation in September 2005. Maeda appointed Hyder Consulting Limited as the Contractor’s Landfill Gas Team (LGT) during the construction period. The construction contract commenced in September 2005 and the total construction period is approximately 28 months.
Close proximity of the Project to Shuen Wan Landfill (within the 250m Consultation Zone of Shuen Wan Landfill) may also suggest the possibility of landfill gas being released during excavation works for substructure of pumping station, transformer room and associated rising mains and gravity sewers. As such, a Report on Landfill Gas Hazard Assessment has been prepared previously (as Appendix E to the PP) in accordance with EPD’s Landfill Gas Hazard Assessment Guidance Note and the Practice Note for Professional Persons – Landfill Gas Hazard Assessment for Development Adjacent to Landfills.
2.2 Management Structure and Project Organisation
The Engineer (DSD) is responsible for overseeing the construction works and ensuring that they are undertaken by the Contractor (Maeda) in accordance with the specification and contractual requirements. The Contractor shall report to the Engineer. The LGT is employed by the Contractor and responsible for conducting the EM&A programme. The IC(LG) shall advise the Engineer on LFG issues related to the Project.
The key personnel contact names and telephone number are summarised in Table 2-1. The project organisation is shown in Appendix 1.
Party |
Position |
Name: |
Tel. No.: |
Project Proponent – DSD |
Project Manager |
Raymond LEE |
2594 7457 |
Engineer’s Representative |
Tim TSOI |
2594 7460 |
|
Contractor – Maeda |
Site Agent |
George CHEUNG |
9268 1918 |
LGT – Hyder Consulting |
LGT Leader |
Alexi BHANJA |
2911 2916 |
IC(LG) –CH2M HILL |
IC(LG) |
Aldex LEE |
2507 2203 |
Table 2-1 Contact Details for Key Project Personnel
Construction programme of the Project is attached in Appendix 2. As can be seen, all works carried out during the reporting period have been carried out with the required LFG control measures (e.g. LFG monitoring for “hot works”).
2.4 Works Undertaken during the Quarter
Works undertaken during the reporting period included:
§
Construction of gravity sewer and rising main
§
Excavation and backfilling
§
Installation of waling and strut
§
Removal of waling and strut
§
Sheet piling work
§
Pile head cutting and installation of pile head steel plate
§
Construction of sub-structure
3.1
Works Undertaken during the Quarter with
Illustrations
Works
undertaken during the reporting period are identified in Section 2.4.
Illustrations of these works, such as location of works, etc., are provided in
Appendix 3.
3.2 Project Area and Monitoring Locations
The site is located at Ting Kok Road in Tai Po, and the major items to be constructed are located outside the existing passive vent trench of the adjacent Shuen Wan Landfill, which has been restored and is currently being monitored.
The impact monitoring locations specified in the Report on Landfill Gas Hazard Assessment comprise “utilities’ manholes and chambers” (i.e. fixed locations for purposes of environmental protection) and at excavations of 1m depth or more (i.e. variable locations for purposes of worker safety).
An 11m-deep borehole, designated “M1”, was installed by the Contractor (in addition to contract requirements) to provide an “early warning” of potential LFG problems that could affect surface trenches. It is not intended that M1 forms part of the EM&A programme, since conditions deep below the surface do not fall within the scope of the EM&A programme (i.e. manholes and excavations >1m).
In terms of fixed monitoring locations, the
Baseline Report identified two existing manholes (M2 and M3). Manhole M2,
however, was dismantled in July 2006 because of planned works and therefore
monitoring at M2 has been terminated since July 2006. LFG has never been detected at M2 and so it is not considered
that termination of monitoring at this location will have any significant
impact on the overall effectiveness of the environmental monitoring programme,
as monitoring at manhole M3 will continue. There are no other suitable manholes
within the site that can be monitored in lieu of M2.
In terms of variable monitoring locations,
these vary from month to month, depending on site activities. The fixed monitoring location is shown in
Table 3-2:
Monitoring Station ID |
||
M3 |
Existing Manhole (2m deep) |
EM&A programme |
Table 3-2 Fixed Monitoring Locations for LFG EM&A
Project area is shown in Appendix 3 and the fixed monitoring locations are shown in Appendix 4.
During the construction phase, impact monitoring of LFG is to be carried out in accordance with the Report on Landfill Gas Hazard Assessment at the selected locations. LFG parameters to be monitored comprise oxygen, methane and carbon dioxide. Temperature is also recorded but this is not a LFG parameter.
Table 4-3 shows the equipment list for LFG monitoring.
Equipment |
Manufacturer /
Serial Nos. |
Gas Analyser GA 2000 |
Geotechnical Instruments / GA 08277 |
Table 4-3 Equipment List for LFG Monitoring
4.3 Event and Action Levels/Plans
The baseline monitoring results documented in the baseline monitoring report for the Project (our report ref.: EA01284R0022) provided the Action and Limit (A/L) Levels for LFG impact monitoring and also the Action Plan. As per the Report on Landfill Gas Hazard Assessment, and in keeping with the standard presentation of LFG EM&A in other projects, both the A/L Levels and Action Plan are shown in the same table.
Table 4-4 shows the combined A/L Level and Action Plan for the Project, to be triggered if the LFG criteria are exceeded at fixed locations M2 or M3, or at any of the variable locations:
Table 4-4 Action and Limit Levels and Action Plan for Landfill Gas
4.4 Mitigation Measures & Requirements in Contract Documents
Measures for mitigating LFG hazards during the construction works have been stated clearly in the Report on Landfill Gas Hazard Assessment, which forms part of the contract documents Specification. Relevant excerpts could be referred to the Project Profile for Upgrading of Ting Kok Road Pumping Station No. 5.
Section 5 and Appendix 5 summarise the mitigation measures and requirements as well as the implementation status.
The status of the mitigation measures implemented by the Contractor is listed in Appendix 5. All LFG hazard control measures have been implemented as stipulated in the contract documents and in the Report on Landfill Gas Hazard Assessment.
Calibration records for the
equipment used for LFG monitoring are provided in Appendix 6. Original Field
Measurement Recording Sheets for both fixed locations and variable
locations are provided in Appendix 7.
During
the reporting period, LFG was monitored at M1 to give an “early warning” of potential
LFG problems. M1 is an 11m-deep borehole and the carbon dioxide and methane
concentrations may reflect possible influence of LFG at depth below the site.
Monitoring results are shown in Table 6-5, below. Location M1 is not subject to
EM&A and so A/L Levels are not applicable.
Monitoring Station ID |
Date |
Gas Concentration (%) |
Temperature (OC) |
||
Methane |
Carbon Dioxide |
Oxygen |
|||
M1 |
27 October 2006 |
0.1 |
0.5 |
19.8 |
26.5 |
27 November 2006 |
0.0 |
0.0 |
20.3 |
23.9 |
|
28 December 2006 |
0.0 |
0.0 |
20.4 |
21.9 |
Table 6-5 Monitoring Results at M1
Considering
the location of M1 adjacent to a restored landfill, the recorded levels are within
expected norms and are not cause for concern. Notwithstanding, the Contractor
has noted these concentrations and will take them into consideration when
planning surface trench works in the vicinity.
During the reporting
period, LFG was monitored at the fixed location M3 for purposes of
environmental protection. This is shown in Table 6-6, below:
Monitoring Station ID |
Date |
Gas Concentration (%) |
Temperature (OC) |
||
Methane |
Carbon Dioxide |
Oxygen |
|||
M3 |
27 October 2006 |
0.0 |
0.3 |
19.9 |
27.1 |
M3 |
27 November 2006 |
0.0 |
0.0 |
20.3 |
23.9 |
M3 |
28 December 2006 |
0.0 |
0.0 |
20.4 |
21.9 |
Note : bold indicates an exceedance of Action Level and bold
indicates exceedance of Limit Level
Table 6-6 Monitoring Results at M3
Appendix 4 shows
the position of each fixed monitoring station. There were no exceedances of A/L
Levels at the two fixed locations during the reporting period.
During the reporting period, LFG was monitored at variable locations (for purposes of worker safety) within Portions 4 to 7, as shown in Appendix 3. Readings were taken for safety-related reasons, including piling works, trench excavation, hot works, post-drilling work and the construction of the temporary drainage system.
A total of 465 nos. of readings were taken in October 2006,
670 nos. of readings in November 2006 and 732 no. readings in December 2006,
giving a total of 1867 for the reporting period. There were no exceedances of
A/L Levels at any variable locations during the reporting period. The LFG
monitoring results are provided on the Field Measurement Recording Sheets
in Appendix 7.
EPD has conducted site visit on 2 November, 7 and 23 December 2006 in the reporting month. EPD inspected the effluent discharge, the chemical waste storage area, measures on dust prevention and the permit display at site entrance on 2 November 2006. On 7 December 2006, EPD visited the site to have an understanding on site condition for the CNP application submitted on 5 December 2006. They also checked the site condition on 23 December 2006 in relation to the CNP granted.
EPD has no adverse comment. There were no non-compliances during the reporting period and no complaints regarding LFG were received.
Construction activities for next quarter are anticipated to include:
§
Excavation
and backfilling
§
Construction
of gravity sewer and rising main
§
Removal
of waling and strut
§
Construction
of sub-structure
Based on the above, on the construction programme (shown in Appendix 2) and on the review of relevant Contractor’s method statements by the LGT, no significant future key issues in terms of LFG have been identified at this time.
LFG monitoring will be continued and the monitoring schedule for the next three months is shown below:
§ 3 January 2007
§ 1 February 2007
§ 1 March 2007
8.2
Comments, Recommendations and Conclusions
The LFG mitigation measures adopted by the Contractor during the reporting period are considered to have been implemented in a satisfactory manner and there have been no exceedance of A/L Levels.
The EM&A programme is considered to have performed acceptably and there are no recommendations for improvements or modifications at this time.
In conclusion, there have been no significant issues relating to LFG hazard during the reporting period.
Appendix 1 |
Project Organisation |
Project Proponent Drainage Services Department Landfill Gas Team Hyder Consulting Limited Landfill Gas (Independent
Checker) CH2M-IDC Environmental Protection
Department Line
of communication Line of
Authority
Appendix 2 |
Construction Programme |
Appendix 3 |
Location of Works and Project Area |
Appendix 4 |
Fixed Monitoring Locations |
Appendix 5 |
Updated Implementation Schedule |
Appendix 6 |
Calibration Records |
Appendix 7 |
Field Measurement Recording Sheets |