|
|
|||||||||||
|
|
|||||||||||
|
Upgrading of
Ting Kok Road Pumping Station No. 5 |
|||||||||||
|
|
Ninth
Quarterly EM&A Report (January
– March 2008) April 2008 Report no: 01284R0761 |
||||||||||
|
47th Floor, Hopewell Centre, 183 Queens Road East, Wanchai, Hong Kong Tel: +852 2911 2233 Fax: +852 2805 5028 www.hyderconsulting.com
|
|
||||||||||
|
|
|||||||||||
|
|
|||||||||||
Upgrading of Ting Kok Road
Pumping Station No. 5 |
|
|||||||||||
Ninth Quarterly EM&A Report (January– March 2008) |
|
|||||||||||
Author: |
Amy Bowker |
|
|
|||||||||
Checker: |
Alexi Bhanja |
|
|
|||||||||
Approver: |
Guiyi Li |
|
|
|||||||||
|
|
|||||||||||
Report no: |
EA01284R0761 |
|
|
Date: |
April 2008 |
|
||||||
|
|
|||||||||||
Certified
by Landfill Gas Team Leader Alexi Bhanja |
|
|
||||||||||
Contents
5 Implementation
Status of LFG Control Measures................................................ 81
List of Tables
Table
2-1 Contact Details for Key Project Personnel 2
Table 3-2 Fixed Monitoring
Locations for LFG EM&A 3
Table 4-3 Equipment List
for LFG Monitoring 4
Table 4-4 Action and Limit
Levels and Action Plan for Landfill Gas 4
Table 6-5 Monitoring
Results at MH3 5
List of Appendices
Appendix 1 Project
Organisation
Appendix 2 Construction
Programme
Appendix 3 Location of Works and Project Area
Appendix 4 Fixed Monitoring Locations
Appendix 5 Updated Implementation Schedule
Appendix 6 Calibration Records
Appendix 7 Field Measurement Recording Sheets
Drainage Services Department awarded the contract for the Upgrading of Ting Kok Road Pumping Station No. 5 to Maeda Corporation in September 2005. Maeda appointed Hyder Consulting Limited as the Contractor’s Landfill Gas (LFG) Team during the construction period. The construction contract commenced in September 2005 and the total construction period is approximately 28 months.
This report recorded the results and findings of the January to March 2008. All relevant mitigation measures and requirements were implemented. There have been no exceedances in Action/Limit (A/L) Levels at of the locations monitored under the EM&A programme.
An 11m-deep borehole, designated “M1”, was installed by the Contractor to provide an “early warning” of potential LFG problems that could affect surface trenches, but does not form part of the EM&A programme. The Contractor has noted the monitoring results from M1 and will take them into consideration when planning surface trench works in the vicinity.
However, as works have progressed,
Borehole M1 now clashes with boundary wall construction and so was dismantled
on 30 August 2007. It is not proposed to replace Borehole M1 since its purpose
was only to provide an early warning of potential LFG problems for surface
trench works, which are now almost complete. Besides, as advised by the
Contractor, future construction will not involve excavation of more than 3
m. Therefore, monitoring at Manhole M3
will serve the purpose for dismantle of Borehole M1. As Borehole M1 did not
form part of the EM&A programme, there is no impact to the effectiveness of
the EM&A programme now that Borehole M1 has been dismantled.
Manhole M2 was dismantled in July 2006 because of planned works and
therefore monitoring at M2 has been terminated since July 2006. However, LFG has never been detected at M2
and so it is not considered that termination of monitoring at this location
will have any significant impact on the overall effectiveness of the
environmental monitoring programme, as monitoring at manhole M3 will continue.
As
works have progressed, connection of gravity sewer to the new pumping system is
completed in Ting Kok Road. As such,
the existing pump pit, together with the fixed monitoring location M3 was
demolished in December 2007. A manhole
MH3 (approximately 4m depth and 3m next to M3) of the new system has been
constructed to be the alternative monitoring station to serve the same purpose
of M3.
EPD conducted site inspection on 10 March 2007, no
inspections were carried out in January or February. General inspection on site
condition was conducted for the inspection. No adverse comment was given.
Event and Action Levels
The baseline monitoring results documented in the baseline monitoring report for the Project (our report ref.: EA01284R0022) provided the Action and Limit (A/L) Levels for LFG impact monitoring and also the Action Plan. For methane, A/L Levels are 0.5%/1.0%; for carbon dioxide, A/L Levels are 0.5%/1.5%; and for oxygen, A/L Levels are 19.0%/18.0%.
Complaint Log
There were no non-compliances during the reporting period and no complaints regarding LFG were received.
Reporting Changes
There have been no reporting changes during the reporting period.
Future Key Issues
Based on anticipated construction activities for the next quarter, on the construction programme and on the review of relevant Contractor’s method statements by the LGT, no significant future key issues in terms of LFG have been identified at this time.
Upgrading
of Ting Kok Road Pumping Station No. 5 (TKRPS) under North District and Tolo
Harbour Sewerage, Sewage Treatment and Disposal – High Priority Works is
implemented based on the findings of the Study Review of North District and Tolo Harbour Sewerage Master Plan.
The
purpose of the Project is to upgrade the existing TKRPS to cope
with the sewerage needs of both existing and future developments along Ting Kok
Road up to Tai Mei Tuk. The design pumping capacity of TKRPS has to be
increased from 2,888m3/day to 11,520m3/day in order to
serve the increasing sewage flow along Ting Kok Road. The Project is of high
priority and needs to commence as soon as possible because full commissioning
of the upstream sewerage facilities along Ting Kok Road is dependent on the
completion of this Project.
The
proposed scope of works includes construction of a new pumping station, laying
of about 350m long twin 450mm diameter rising mains and 250m long 600mm
diameter gravity sewer, and demolition of the existing pump pit. The main
pumping station, transformer room, gravity sewers, manholes and boundary wall
(except the twin rising mains) will be located outside the existing passive
vent trench of Shuen Wan Landfill and the three existing Landfill Gas (LFG)
monitoring probes within the Project site will not be affected by the works.
There are six village houses located about 60m away from the boundary of the proposed pumping station. The proposed pumping station upgrading works therefore constitutes a Designated Project under type F.3(b)(i) in Schedule 2 of the Environmental Impact Assessment Ordinance. A Project Profile (PP) for direct application of the Environmental Permit (EP) (Application No.DIR-115/2005) was approved by the Environmental Protection Department (EPD) in March 2005 and an EP (EP-212/2005) was granted in April 2005, prior to the commencement of the upgrading works.
Drainage Services Department awarded the contract for the upgrading of TKRPS to Maeda Corporation in September 2005. Maeda appointed Hyder Consulting Limited as the Contractor’s Landfill Gas Team (LGT) during the construction period. The construction contract commenced in September 2005 and the total construction period is approximately 28 months.
Close proximity of the Project to Shuen Wan Landfill (within the 250m Consultation Zone of Shuen Wan Landfill) may also suggest the possibility of landfill gas being released during excavation works for substructure of pumping station, transformer room and associated rising mains and gravity sewers. As such, a Report on Landfill Gas Hazard Assessment has been prepared previously (as Appendix E to the PP) in accordance with EPD’s Landfill Gas Hazard Assessment Guidance Note and the Practice Note for Professional Persons – Landfill Gas Hazard Assessment for Development Adjacent to Landfills.
2.2 Management Structure and Project Organisation
The Engineer (DSD) is responsible for overseeing the construction works and ensuring that they are undertaken by the Contractor (Maeda) in accordance with the specification and contractual requirements. The Contractor shall report to the Engineer. The LGT is employed by the Contractor and responsible for conducting the EM&A programme. The IC(LG) shall advise the Engineer on LFG issues related to the Project.
The key personnel contact names and telephone number are summarised in Table 2-1. The project organisation is shown in Appendix 1.
Party |
Position |
Name: |
Tel. No.: |
Project Proponent – DSD |
Project
Manager |
Raymond
LEE |
2594 7457 |
Engineer’s
Representative |
Tim TSOI |
2594 7460 |
|
Contractor – Maeda |
Site
Agent |
George
CHEUNG |
9268 1918 |
LGT – Hyder Consulting |
LGT
Leader |
Alexi
BHANJA |
2911 2916 |
IC(LG) –CH2M HILL |
IC(LG) |
Adlex LEE |
2507 2203 |
Table 2-1 Contact Details for Key Project Personnel
Construction programme of the Project is attached in Appendix 2. As can be seen, all works carried out during the reporting period have been carried out with the required LFG control measures (e.g. LFG monitoring for “hot works”).
2.4 Works Undertaken during the Quarter
Works undertaken during the reporting period included:
§
Concrete
carriageway;
§
Construction of
boundary wall;
§
Grouting of
existing disused pipes;
§
Demolition of
existing pump pit; and
§
Modification of
chequer plate.
3.1
Works Undertaken during the
Quarter with Illustrations
Works undertaken during the reporting period are identified in
Section 2.4. Illustrations of these works, such as location of works, etc., are
provided in Appendix 3.
3.2 Project Area and Monitoring Locations
The site is located at Ting Kok Road in Tai Po, and the major items to be constructed are located outside the existing passive vent trench of the adjacent Shuen Wan Landfill, which has been restored and is currently being monitored.
The impact monitoring locations specified in the Report on Landfill Gas Hazard Assessment comprise “utilities’ manholes and chambers” (i.e. fixed locations for purposes of environmental protection) and at excavations of 1m depth or more (i.e. variable locations for purposes of worker safety).
An 11m-deep borehole, designated
“M1”, was installed by the Contractor (in addition to contract requirements) to
provide an “early warning” of potential LFG problems that could affect surface
trenches. It is not intended that M1 forms part of the EM&A programme,
since conditions deep below the surface do not fall within the scope of the
EM&A programme (i.e. manholes and excavations >1m).
However, as works have progressed,
Borehole M1 now clashes with boundary wall construction and so was dismantled
on 30 August 2007. It is not proposed to replace Borehole M1 since its purpose
was only to provide an early warning of potential LFG problems for surface
trench works, which are now almost complete. Besides, as advised by the
Contractor, future construction will not involve excavation of more than 3
m. Therefore, monitoring at Manhole M3
will serve the purpose for dismantle of Borehole M1. As Borehole M1 did not
form part of the EM&A programme, there is no impact to the effectiveness of
the EM&A programme now that Borehole M1 has been dismantled.
In terms of fixed monitoring
locations, the Baseline Report identified two existing manholes (M2 and M3).
Manhole M2, however, was dismantled in July 2006 because of planned works and
therefore monitoring at M2 has been terminated since July 2006. LFG has never been detected at M2 and so it
is not considered that termination of monitoring at this location will have any
significant impact on the overall effectiveness of the environmental monitoring
programme, as monitoring at manhole M3 will continue. There are no other
suitable manholes within the site that can be monitored in lieu of M2.
As works have progressed,
connection of gravity sewer to the new pumping system is completed in Ting Kok
Road. As such, the existing pump pit,
together with the fixed monitoring location M3 was demolished in December
2007. A manhole MH3 (approximately 4m
depth and 3m next to M3) of the new system has been constructed to be the
alternative monitoring station to serve the same purpose of M3.
In terms of variable monitoring
locations, these vary from month to month, depending on
site activities. The
fixed monitoring location is shown in Table 3-2:
Monitoring Station ID |
||
M3 |
Existing Manhole (3m deep) |
EM&A programme |
MH3 |
Constructed Manhole (4m deep) |
EM&A programme |
Table 3-2 Fixed Monitoring Locations for LFG EM&A
Project area is shown in Appendix 3 and the fixed monitoring locations are shown in Appendix 4.
During the construction phase, impact monitoring of LFG is to be carried out in accordance with the Report on Landfill Gas Hazard Assessment at the selected locations. LFG parameters to be monitored comprise oxygen, methane and carbon dioxide. Temperature is also recorded but this is not a LFG parameter.
Table 4-3 shows the equipment list for LFG monitoring.
Equipment |
Manufacturer
/ Serial Nos. |
GFM410 |
GAS DATA LTD / 10239 |
Table 4-3 Equipment List for LFG Monitoring
4.3 Event and Action Levels/Plans
The baseline monitoring results documented in the baseline monitoring report for the Project (our report ref.: EA01284R0022) provided the Action and Limit (A/L) Levels for LFG impact monitoring and also the Action Plan. As per the Report on Landfill Gas Hazard Assessment, and in keeping with the standard presentation of LFG EM&A in other projects, both the A/L Levels and Action Plan are shown in the same table.
Table 4-4 shows the combined A/L Level and Action Plan for the Project, to be triggered if the LFG criteria are exceeded at fixed locations M2 or MH3, or at any of the variable locations:
Table 4-4 Action and Limit Levels and Action Plan for Landfill Gas
4.4 Mitigation Measures & Requirements in Contract Documents
Measures for mitigating LFG hazards during the construction works have been stated clearly in the Report on Landfill Gas Hazard Assessment, which forms part of the contract documents Specification. Relevant excerpts could be referred to the Project Profile for Upgrading of Ting Kok Road Pumping Station No. 5.
Section 5 and Appendix 5 summarise the mitigation measures and requirements as well as the implementation status.
The status of the mitigation measures implemented by the Contractor is listed in Appendix 5. All LFG hazard control measures have been implemented as stipulated in the contract documents and in the Report on Landfill Gas Hazard Assessment.
Calibration
records for the equipment used for LFG monitoring are provided in Appendix 6. Original
Field Measurement Recording Sheets for both fixed locations and variable
locations are provided in Appendix 7.
During
the reporting period, LFG was monitored at the fixed location MH3 for purposes
of environmental protection. This is shown in Table 6-5, below:
Monitoring Station ID |
Date |
Gas Concentration (%) |
Temperature (OC) |
||
Methane |
Carbon Dioxide |
Oxygen |
|||
MH3 |
29 January 2008 |
0.0 |
0.0 |
20.9 |
10.0 |
0.0 |
0.0 |
20.9 |
10.0 |
||
MH3 |
28 February 2008 |
0.0 |
0.0 |
20.6 |
11.0 |
0.0 |
0.0 |
20.6 |
11.5 |
||
MH3 |
27 March 2008 |
0.0 |
0.0 |
23.0 |
23.0 |
0.0 |
0.0 |
23.5 |
23.5 |
Note : bold indicates an exceedance of
Action Level and bold
indicates exceedance of Limit Level
Table 6-5 Monitoring Results at MH3
Appendix
4 shows the position of each fixed monitoring station. There were no exceedances
of A/L Levels at the two fixed locations during the reporting period.
During the reporting period, LFG was monitored at variable locations (for purposes of worker safety) within Portions 4 to 7, as shown in Appendix 3. Readings were taken for safety-related reasons, including piling works, trench excavation, hot works, post-drilling work and the construction of the temporary drainage system.
A total of 120 nos. of readings were taken in January 2008, 78 nos. of readings in February 2008 and 102
nos. of readings in March 2008, giving a total of 300 for the reporting
period. There were no exceedances of A/L Levels at any variable locations
during the reporting period. The LFG monitoring results are provided on the Field
Measurement Recording Sheets in Appendix 7.
EPD conducted a on 10 March 2008, there were
no site inspections carried out in January and February in the reporting
period. General inspection on site condition was conducted for the site
inspection. No adverse comment was given.
There were no non-compliances during the reporting period and no complaints regarding LFG were received.
Construction activities for next quarter are anticipated to include:
§
Landscaping;
§
Extension of Cat
ladder; and
§
Concrete carriageway.
Based on the above, on the construction programme (shown in Appendix 2) and on the review of relevant Contractor’s method statements by the LGT, no significant future key issues in terms of LFG have been identified at this time.
LFG monitoring will be continued and the monitoring schedule for the next three months is shown below:
§ 1 April 2008
§ 1 May 2008
§
1 June 2008
8.2
Comments, Recommendations and
Conclusions
The LFG mitigation measures adopted by the Contractor during the reporting period are considered to have been implemented in a satisfactory manner and there have been no exceedance of A/L Levels.
The EM&A programme is considered to have performed acceptably and there are no recommendations for improvements or modifications at this time.
In conclusion, there have been no significant issues relating to LFG hazard during the reporting period.
Appendix 1 |
Project Organisation |
Project Proponent Drainage Services Department Landfill Gas Team Hyder Consulting Limited Landfill Gas (Independent Checker) CH2M-HILL Environmental Protection Department Line of
communication Line of
Authority
Construction Programme |
Location of Works and Project Area |
Fixed Monitoring Locations |
Updated Implementation Schedule |
Calibration Records |
Field Measurement Recording Sheets |